Procurement of Works

Requirements

Contents

1. Scope of Works

2. Specification

3. Drawings

4. Supplementary Information
Scope of Works

CONTENTS

I. COMPLETE DESCRIPTION OF THE PROJECT


1. Line location
2. Current status
3. Route of the new OHTL
4. Scope of procurement
II. TECHNICAL SPECIFICATIONS
1. Technical specifications for Civil and Erection Works (CEWs)
1.1. Access and route approaches
1.2. Structure alignment and staking requirements
1.3. Excavations and foundations
1.4. Towers
1.4.1. Tower assembly and raising
1.5. Conductors, ground wires, fiber optic cable and optical connectivity
1.5.1. Conductors
1.5.2. Optic power ground wire (OPGW)
1.5.3. Steel ground wire
1.5.4. Fiber optic cable and optical connectivity
1.6. Line insulation
1.7. Fittings
1.7.1. Conductor fittings
1.7.2. Fittings for the steel ground wire
1.8. Surge protection and grounding
1.9. Signs and plates
2. Dismantling activities and reconstruction of existent OHTLs
2.1. 400 kV Vezhen OHTL
2.2. 110 kV Katunitsa OHTL
2.2.1. Current status
2.2.2. Design concept
2.2.3. Dismantling activities
3. Temporary civil works
4. Deadlines and completion sequence of CEWs
5. Plant and Materials specification
5.1. Towers
5.2. Concrete
5.3. Conductors and ground wires
5.3.1. Conductors
5.3.2. Hot-dip galvanized ground wire
5.3.3. Optic power ground wire (OPGW)
5.4. Requirements for optic underground cable (OPUG)
5.5. Insulator strings and fittings
5.5.1. Polymeric insulators
5.5.2. Fittings for insulator strings
5.5.3. Conductor fittings
5.5.4. Fittings for hot-dip galvanized steel wire
5.5.5. Fittings for OPGW
5.5.6. Protective fittings
5.6. Earth rods
5.7. Patch panel
5.8. Fiber optic distribution cabinet
5.9. Other Plant and Materials
6. Testing of delivered materials
6.1. Testing of towers
6.1.1. Type tests
6.1.2. FATs
6.1.2.1. Trial assembly
6.1.2.2. Mechanical and chemical tests of tower material
6.1.2.3. Testing of bolts and nuts
6.1.2.4. Hot-dip galvanized coating test
6.2. Conductor tests
6.3. Testing of hot-dip galvanized steel wire, size 11 mm
6.4. Testing of OPGW
6.4.1. Type tests
6.4.2. FATs
6.5. Testing of OPUG
6.6. Insulators
6.6.1. Design tests
6.6.2. Type tests
6.6.3. FATs
6.6.4. Routine test
6.7. Testing of complete string
6.8. Fittings
6.8.1. Fittings for insulator sting and ground wire
6.8.1.1. Type tests
6.8.1.2. FATs
6.8.2. Tension connections (span couplers) and tension clamps
6.8.2.1. Type tests
6.8.2.2. FATs
6.8.3. Suspension clamps
6.8.3.1. Type tests
6.8.3.2. FATs
6.8.4. Partially strained fittings
6.8.4.1. Type tests
6.8.4.2. FATs
6.8.5. Protective fittings for insulator strings
6.8.5.1. Type tests
6.8.5.2. FATs
6.8.6. Spacers (БДС ЕN 61854 or equivalent)
6.8.6.1. Type tests
6.8.6.2. FATs
6.8.7. Dampers (БДС ЕN 61897 or equivalent)
6.8.8. Testing of other materials
7. Documentation in the course of site construction and acceptance
I. COMPLETE DESCRIPTION OF THE PROJECT
1.Line location
The new 400 kV OHTL between Plovdiv s/s and Maritsa Iztok s/s will be built on an approved
route with effective Detailed Development Plan (DDP) according to Order No РД-02-15-
35/11.04.2017 issued by the Minister of Regional Development of Bulgaria. The new route
starts from tower 445A of existent 400 kV Vezhen double circuit OHTL and ends at the line
gantry tower of Maritsa Iztok s/s. Connectivity between both end substations will be provided
using the free conductor triad of 400 kV Vezhen double circuit OHTL in the section between
towers 445А and 453А (Plovdiv s/s). A layout of the new route is shown in drawings № D104-
01C1-01-0A#1 and #2,where benchmark 4(R4) corresponds to tower 445A.

2.Current status
The unoccupied conductor triad of 400 kV Vezhen double circuit OHTL in the section from
line gantry tower of Plovdiv s/s to tower 445A with a length of 1.925 km will be used for
construction of the new 400 kV OHTL. This section is built with towers designed for ACO-400
type conductor consisting of three wires per bundle. The suspension towers are of type НМ
for two 400 кV OHTLs and special type СЕН2, whereas the tension towers are two per stake
of the currently available types 20.N and 70.N. Outlines of the suspension towers are shown
in drawings № 099-TL1-05DD-01-0101A1-00_МС-1HM and № D104-01C4-02-0A. Sheet 1
and 2 of № D104-01C4-04-0A represent the tension towers in front view.
From tower 445A to line gantry tower of Maritsa Iztok s/s, the new 400 kV OHTL will run on
an entirely new route as described in chapter I.3 of these Technical Specifications.

3.Route of the new OHTL


The new 400kV OHTL will start from line gantry tower of Plovdiv s/s. Before it is tower 453А,
which is terminal for the existing Vezhen double circuit tower line where the second triad is
not installed. In the section between towers 453А and 445А is a triad of conductors, one
being installed on the side of the free triad to ensure optimal load distribution on the towers.
This 400 kV OHTL will take the place of the second triad. The new 400kV OHTL will thus
share the same route with 400 kV Vezhen OHTL to tower 445А. In the section from Plovdiv
s/s to the split from existent double circuit line, the route takes several bends as benchmarked
from R1 to R4 in drawing No D104-01C1-01-0A#1 attached hereto.
Between benchmarks R4 and R32 (line gantry tower of Maritsa Iztok s/s), the new 400 kV line
route is oriented to the East and crosses the municipal territories of Rodopi, Sadovo,
Asenovgrad, Parvomay, Dimitrovgrad, Opan, Galabovo, and Simeonovgrad.
The line length of the new 400 kV OHTL from Plovdiv s/s to Maritsa Iztok s/s is 92.985 km.
Line deployment layouts of both Plovdiv s/s and Maritsa Iztok s/s are correspondingly shown
in drawings No D104-01C1-02-0A and No D104-01C1-03-0A.

4. Scope of procurement
The scope of this procurement includes the following works:
- New tower route and midpoint staking;
- Foundation spotting;
- Excavations for foundation laying, installation and and leveling of tower foots according
to the stress-strain properties of the soil beneath each individual tower;
- Concrete delivery and casting and foundation laying for the new towers, including
formwork assembly and removal activities;
- Delivery and installation of earth rods on the new towers;
- Foundation backfilling and compacting;
- Delivery and assembly of the new towers, preparation and raising once the cast
concrete has stiffened to its design strength;
- Delivery and completion of suspension strings for conductors and ground wires with
roller supports and suspending them on the towers;
- Deployment of lead cables for each tension section and ensuring that the crossing
facilities are secured;
- Delivery, pulling, adjustment and installation of conductors and ground wires, including
installation of tension strings for conductors and ground wires;
- Delivery and installation of suspension clamps;
- Delivery and installation of conductor spacers in the spans according to attached
assembly diagrams;
- Installation of jumpers on all tension towers;
- Delivery and installation of HV warning signs and marking all towers of the 400 kV OHTL
with date and number;
- Measurement of contact joints and earth connections;
- Visual inspection of the new line, route clearing and finial works on the new tower sites.

II. TECHNICAL SPECIFICATIONS

1. Technical specifications for Civil and Erection Works (CEWs)


All works according to this documentation must be carried out in compliance with the
applicable regulations, including the provisions of the Ordinance on design of electrical
installations and power lines (OSEIPL) - 2004, Ordinance No 3/18.09.2007 on technical rules
and regulations for control and acceptance of electrical works, Ordinance No 14/15.06.2005
on technical rules and regulations for design, construction and use of sites and facilities for
production, transformation, transmission and distribution of electricity, and Ordinance No
2/31.07.2003 on commissioning of construction sites in the Republic of Bulgaria.
In addition to the documents as referred to above, all requirements stated in this
documentation and its annexes, detailed design, drawings and schemes must be respected.
The activities and quantities specified in this documentation are in full compliance and not in
conflict with the detailed design for construction of the new 400 kV OHTL and these
requirements complement the projects. Contractor shall provide and use the best and
established civil engineering practices and technologies for this type of construction sites
without conflicting with Employer’s requirements.
All assembly and dismantling activities shall be performed by Contractor's qualified personnel
having the needed certificates and authorizations to work on power equipment and facilities.
Contractor shall have the necessary personnel, machinery, special equipment and tools for
carrying out the assembly and dismantling activities in a volume no less than the minimum
requirements specified in the tender procedure.

1.1. Access and route approaches


During civil works, the towers shall be accessed using existent forest, field, municipal and
national road network as well as via the line route while strictly observing the Detailed
Development Plan (DDP) and the designated line easement areas. Terrain preparation must
be carried out in a way that prevents damage to both existing structures and those under
construction. All damages incurred are at Contractor's expense and the affected equipment
and/or materials shall be restored to their original state. Where necessary to build
embankments or spread gravel for access to the route or new towers, the earth mass or
fractions used shall be utilized to recover the terrain in its original form.
It will be Employer’s responsibility to preclean the necessary rights-of-way in forest areas
according to the established easement. Contractor shall be responsible for the subsequent
cleanup of any volunteer vegetation and upgrowth during construction of the new power lines.
In the bidding process, each candidate needs to know the route of the new 400 kV line and
shall envisage access to each new tower and those of the existing 400 kV Vezhen OHTL.
Those approaches shall be offered in a separate item of the bill of quantity as machine-shifts
for access and preparation of sites for the new towers.
At the construction phase, those approaches that are already defined by the selected
Contractor need to be agreed with an authorized representative of Employer and this
agreement shall then be reflected in bilateral protocols. Any damage to pre-agreed
approaches shall be at Employer’s expense. Any damage due to negligence or failure to use
pre-agreed approaches on the part of Contractor shall be be at its own expense.

1.2. Structure alignment and staking requirements


Line alignment shall be performed in tension sections or between two benchmarks, with the
towers then being aligned in separate straight sections. Aligned tower axes shall be within
accuracy tolerance of 5 cm in Bulgarian Geodetic System 2005 and Baltic Height System
(altitudes from GPS shall not be used without applying gravimetric measurements).
Once the midpoints or staking point of the new towers are identified, with two towers per
stake, a surveyor’s transit instrument (theodolite or total station) shall be positioned at one of
the tower midpoints to check whether all aligned tower axes lay on the corresponding straight
line and make corrections if any deviation is detected.
For each tower or stake, once the midpoint is aligned, checked and adjusted, it shall be
proceeded to spot the tower legs by first determining their orientation and making a cord
scaffold in two perpendicular directions to preserve their center and orientation. Having
determined tower midpoint and main leg axes, the tower legs shall be spotted by means of a
tape rule or other instrument and then a cord scaffold shall be built to spot the legs. After the
tower legs are aligned, it shall be verified that their directions are perpendicular to each other
by measuring both diagonals (they must be equal).
Coordinates of the new tower legs are attached to the detailed design for this project.

1.3. Excavations and foundations


The soil conditions for foundation laying of each individual tower have been determined based
on geological surveys and related reports. Prior to excavation works, the construction site
shall be cleaned up and secured with fencing and safety facilities. Foundations for the new
towers shall be excavated by special machinery and, where necessary, finished by hand
under strict observance of the established staking and spotting points. Excavations with
vertical walls are only allowed in moderately humid soil without ground waters. Possible
excavation depths are up to 1 m in sandy soil, 1.25 m in clay soil and 2 m in highly compact
soil. These are admissible dimensions provided that foundations are cast within 2-3 days after
excavation.
When doing earthworks for tension and special towers whose foundations are deeper, it is
necessary to either reinforce or align the excavation walls with the natural slope of the
particular soil type. In case of weak soils, the excavation walls shall be tightly reinforced
depending on the soil properties. Excavated earth shall be deposited not less than 0.5 m
away from the edge of excavation to prevent the walls from being overloaded. Excavated
material shall be left aside and subsequently used to backfill and reinforce the tower
foundations; any excess material shall be evenly spread around the site. When doing
earthworks on arable terrain, the upper soil layer must be removed and put aside from the
excavated material to spread it back on top upon backfilling once the concrete foundations
are cast. Spoil shall be deposited so that in does not interfere with the subsequent works
(installation, leveling and concrete lining of the foundations). Storage of tower parts and
movement of machinery around excavations are allowed outside the edges of natural terrain
slope.
To increase the service life of foundations, they shall be cast in place with the necessary
smoothness and surface gradients, without additional cement lining, and must be compressed
by vibration method. Once the concrete is cast, it shall be left for the rated setting time to
gather its design strength. To drain precipitation water away from the structure foundations,
their backfilling must be compacted by ramming. Next, the sites around the structures shall be
finished with inclinations away from the towers and trenches to drain surface waters.
Backfilling shall be carried out layer by layer and rammed to the rated volumetric density.
Using stones and construction waste for backfilling purposes is not allowed.
The foundation laying conditions are specified in the Construction Design, Geology and
Occupational Health and Safety Plan (OHSP) sections of the detailed design, the required
quantities being stated in Appendix 1.
Each of the four available foundations of existent tower 445А from 400 kV Vezhen OHTL will
be reinforced with additional steel concrete. The technology of implementation, how to bind a
new concrete to old concrete, and the location of steel reinforcement in the foundations are
described in the Construction Design section. The required quantities are specified in the bill
of quantity for this construction project. The reinforcement is shown in drawing No D104-
01F6-02-0A.

1.4. Towers
The new towers to be used for construction of the 400 kV line are designed for АСО-400 type
conductors consisting of three single wires per bundle, bolted design with hot‐dip galvanized
coating for anticorrosive protection in accordance with БДС EN ISO 1461:2009 or equivalent.
Steel grades S355J0 and S235J0 as per БДС EN 10025-2 are used for different details of the
new towers to enable structural optimization. The following tower structures are used:
− СНД1 – suspension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and two ground wires С-70). It is used for normal weight
and wind conditions and its outline is shown in drawing № D104-01F1-01-0A;
− СНД2 – suspension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and two ground wires С-70). This is a more heavy-duty
tower compared to СНД1 and its outline is shown in drawing № D104-01F2-01-0A;
− СЕН1,2 – suspension tower for one or two bundle conductors АСО-400. It ensures
the necessary vertical clearances to crossing infrastructure where a suspension point
higher than 32 m is required. Its outline is shown in drawing № D104-01F5-01-0A;
− 20.NN – angle tension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and two ground wires С-70). Its outline is shown in №
D104-01F3-01-0A;
− 60.NN – angle tension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and two ground wires С-70). Its outline is shown in
drawing № D104-01F4-01-0A.
− In addition to the above structures, the existent towers of 400 кV Vezhen OHTL are
also used as follows:
− 70.NN - angle tension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and two ground wires С-70) with existent numeration
453А;
− 70.N - angle tension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and one ground wire С-70) with existent numeration
448А;
− 20.N - angle tension structure for conductors 1x3x3АСО400 + 2xC-70 (one triad of
bundle conductors АСО-400 and one ground wire С-70) with existent numeration
445А, 446А, 447А, and 451А;
− СЕН2 – suspension structure for two bundle conductors АСО-400 with existent
numeration 445А,В and 446А,В;
− 1Н.М - suspension tower for two triads of bundle conductors АСО-400 and two
ground wires С-70 with existent numeration 452.
The same will be reused and positions #311, 312 and 485 of tower 445A will be replaced
along with their bolted connections. These are shown in drawing № D104-01F6-01-0A. The
total weight of new structure profiles is 91.5 kg inclusive of fittings.
The weights of new structures to be used to build the line are specified in Appendix 2. The
weight of shaped steel elements and reinforcement fittings for tower 445А are specified in the
Bill of Quantity for the new 400 кV OHTL.
Appendix 3 indicates the new towers distribution on the line route.

1.4.1. Tower assembly and raising


The components of each tower shall be transported without being damaged. The main
structural components must be properly marked and sorted to facilitate their installation on a
particular tower.
Tower installation works shall be done on a prearranged site in immediate proximity to the
new foundations. It is not allowed to perform any structural modifications such as drilling and
expanding holes as well as any welding operations. No bending of profile components for
assembling purposes is allowed. All fittings must be hot-dip galvanized and compliant with the
standards referred to in the Construction Design.
The new towers may be raised after checking the dimensions of the already built ones. In
case of inadmissible grading deviations or horizontal displacements, the corresponding
design engineer shall be consulted for advice. The new towers shall be raised using a
suitable method depending on terrain conditions, access, cranes’ lifting capacity, and the
requirement to prevent any structural damage. They can be either installed section by section
after being partially assembled on the ground or raised as a whole structure or built up
position by position with a mounting frame. Pertaining to the most common suspension
structure СНД 1 and 2, there is a universal mounting frame whose use is absolutely
mandatory regardless of whether the tower is being raised in a fully assembled state or as an
assembled body with brackets!
Specific structure assembling and raising instructions are set out in the Electromechanical,
Construction Design and OHSP sections of the detailed design.

1.5. Conductors, ground wires, fiber optic cable and optical connectivity
1.5.1. Conductors
A triad of bundle АСО-400 with electromechanical properties according to БДС 1133-89 or
equivalent shall be installed. The required quantity is specified in Appendix 4.
Single subconductors in bundle shall be spaced at 400 mm from each other and in an
equilateral-triangle arrangement. Their equidistant positions in the span shall be ensured by
means of triple spacer dampers whose indicative distribution and number in a span are
shown in Appendix 5. Double spacer dumpers shall be used for jumper conductors.
The new line conductors shall be pulled using the mechanical stress method according to IEC
TR 61328 and IEC TR 62263-2005 or their equivalents. All machinery, equipment, facilities
and safety gear must conform to the above standards and enable flawless conductor
installation. It is not allowed to deploy conductors in a random tension section on the ground.
Conductor installation shall be carried out by running a lead cable through the entire tension
section and then pulling the bundle conductor attached to the end of lead cable. All three
subconductors in bundle shall be pulled simultaneously and applying the same tensile force.
A set of pulling machines designed to strain three or more conductors simultaneously shall be
used for this purpose. It is not allowed for a bundle to touch the ground or crossing
infrastructure while being pulled and strain adjusted as well as to exceed the rated tensile
force of its particular tension section. For precise adjustment of roller supports suspended on
towers, they shall be mounted at the same level as suspension and tension clamps to which
the conductor will be attached.
Redundant conductor that remains wound on the drum after installation shall be used to make
jumpers on tension structures instead of being installed in line sections.
Conductor adjustment shall be made as prescribed in the relevant straining tables for the
weather conditions specified in the longitudinal profile.
The phasing diagram of the new power line is shown in drawing № D104-01C3-12-0A.

1.5.2. Optic power ground wire (OPGW)


Surge protection of the new 400 кV OHTL will be provided by two ground wires, one of which
is type OPGW with properties specified in clause 5.3.3 of the Plant and Mmaterials
specification. Appendix 6 shows the tension sections for fiber optic cable installation with
corresponding allowances for sagging and attachment. Stockbridge dampers of quantity
specified in Appendix 7 will protect the fiber optic cable against vibrations. The specific
shipment of dampers as per selected fiber optic cable shall be delivered with an installation
manual to be approved by Employer.
The optic cable pulling and installation routine is similar to that for conductors, with additional
attention being paid to ensure that the contact surfaces of all installation gear and machinery
do not come into metal touch with the cable. They shall have appropriate silicone or other
insulation coating that shall be replaced in due course before it gets worn out and its
operational lifetime has elapsed. This requires that Contractor has and uses efficient devices
to earth the cable while being pulled.
During installation, no less than the minimum admissible bending radius specified by the
manufacturer shall be applied.
To verify that the optic fibers are left intact after installation, it is necessary to terminate the
optic cable at both end substations and measure the signal attenuation along the route from
both sides. Acceptable attenuations:
− 0.06 dB (average) and 0,15 dB (max) at junction box;
0
− 0.25 dB/km along the route @ 1550 nm, 20 C.
Individual fiber attenuations shall not differ by more than 0.02 dB/km.

1.5.3. Steel ground wire


The second ground wire is a steel one, with mechanical properties as specified in clause
5.3.2 of the Plant and Materials specification, and its conditional identification is С-70. The
pulling and installation routine is quite similar to that for conductors and the required
quantities are indicated in Appendix 8.

1.5.4. Fiber optic cable and optical connectivity


The fiber type (OPUG) shall be the same as that of OPGW. Optical connectivity of the ground
wire from its corresponding bay gantry tower of the new 400 kV OHTL to line equipment room
(LER) in the relevant substation shall be provided via fiber optic cable with properties as
described in clause 5.4. The ground wire shall be connected to the fiber optic cable through
an OPGW-OPUG junction box mounted 5.50-6.00 meters above terrain level on the column
next to the optic cable suspension. A 32-millimeter high density polyethylene (HDPE) flexible
protection pipe shall protect the entire fiber optic cable.
Drawing № D104-01C1-04-0A represents the optic cable routing layout in the 400 кV
switchyard of Plovdiv s/s. The corresponding layout in Maritsa Iztok s/s is given in drawing №
D104-01C1-05-0A. Specific routing requirements are described in the detailed design; the bill
of quantity specifies the necessary equipment for optical connectivity in terms of
nomenclature and quantities.

1.6. Line insulation


Line insulation shall be implemented using polymeric insulators with tensile strength of not
less than 160 kN. This applies to both suspension and tension strings. The complete set of
unit insulators in the strings is defined in accordance with rated safety factors for the relevant
sizing conditions. Rings and/or horns will be installed to distribute the magnetic field and lead
any discharge away from the string.
The applicable technical characteristics for unit insulators are set out in the Plant and
Materials specification.

1.7. Fittings
Given the type of tower structures used for the new power line, both new and existent
ones, the realized wind and weight spans and prescribed maximum normal stress in
conductors and ground wires, different indicative complete sets of tension and suspension
insulator strings are foreseen.
1.7.1. Conductor fittings
The following complete sets of insulator strings are used for the new 400 kV OHTL:
− Single suspension insulator string designed to bypass the conductors around the
body of tension towers, complete with 2х25 kg of weights. It is shown in drawing №
D104-01C3-04-0A;
− Single suspension insulator string for special suspension towers. This string is similar
to the above one but has no weights attached to it;
− V-suspension insulator string for suspension towers type СНД. It is shown in drawing
№ D104-01C3-03-0A;
− Single and double tension insulator string. This one is used for tension towers in
approaches to end substations. It is shown in drawing № D104-01C3-01-0A;
− Triple tension insulator strings for tension towers along the line route. It is shown in
drawing № D104-01C3-02-0A.
The required quantities per string type are specified in Appendix 9.
Pursuant to the approved and effective Environmental Impact Assessment Report (EIAR), it is
necessary to install bird (stork) guards above all suspension strings as well as bird diverters
along the steel ground wire.
The bird guard design is shown in drawing № D104-03C3-08-0A.
Bird diverters shall be installed on the steel ground wire at distances of 20 m along the spans
between towers 57 and 68.

1.7.2. Fittings for the steel ground wire


The following strings are used to complete the ground wire suspensions of the new 400 kV
OHTL:
− ЕН-C70 – standing single suspension string for ground wire С-70 with swing clamp
intended for suspension towers. This string is shown in drawing № D104-01C3-08-
0A;
− ЕО-C70 - single tension string for ground wire С-70. Its drawing is № D104-01C3-07-
0A;
− ЕО-OPGW - single tension string for optic power ground wire (OPGW). This string is
shown in drawing № D104-01C3-05-0A;
− ЕН-OPGW - single suspension string for OPGW with С-link. This string is shown in
drawing № D104-01C3-06-0A.
The required quantities per string type are specified in Appendix 9.

The requirements for complete string set fittings are described in clause 5.5 of these
Technical Specifications.

1.8. Surge protection and grounding


All new structures shall be grounded with earth rods as specified in the detailed design and
taking into account the geological surveys for foundation laying per tower. All components of
the earth rods shall be hot-dip galvanized and with welded underground connections whose
weldings are covered with protective primer in accordance with the detailed design. The joints
to towers shall be bolted-type and made through a pre-dilled mount hole in the mast.
OPGW shall be grounded through the string earth rod bolted to the tower top as shown in the
drawings of complete ground wire sets.
Two types of earth rod design are foreseen to ensure the rated contact resistance of the new
tower’s earth rods:
Vertical earth rod consisting of 40х4 mm horizontal hot-dip galvanized steel bars to which 1.5-
meter long vertical hot-dip galvanized steel profile rods (L63/63/6 mm) are attached. Its
diagram is shown in drawing № D104-01C3-13-0A, page 1;
Deep-driven earth rod made of 40х4 mm horizontal hot-dip galvanized steel bars. The
horizontal earth rods are installed 0.3m beneath the corresponding steel latticed tower
foundations. Its diagram is shown in drawing № D104-01C3-13-0A, page 2;

The required type of grounding devices for the new towers is specified in Appendix 11.

No new earth rods will be installed on the existing towers of 400 kV Vezhen OHTL to be used
for the new 400 кV line.
1.9. Signs and plates
Electric shock hazard signs shall be mounted on all new towers as well as on the existent
ones of 400 кV Vezhen OHTL. These shall be enameled and fixed to special mounting plates
bolted to the tower sections 3 meters above terrain level.
All towers shall be numbered, dated and labeled with dispatch name. Black font on yellow
background shall be used for the signs according to a sample agreed with Employer.

2. Dismantling activities and reconstruction of existent OHTLs

2.1. 400 kV Vezhen OHTL


The existent 400 кV Vezhen OHTL was commissioned on a double circuit line tower where
one bundle conductor is installed on the towers with index “А“. In order to preserve the
uniformity of fittings and insulation, i.e. to complete the new 400 kV OHTL with polymeric
insulators and keep the current equipment of 400kV Vezhen OHTL, the following works need
to be done:
For the section between towers 445 and 451, remove the conductor suspended on the south
towers between 445А and 451А and reinstall it on the northeast brackets on towers 445B to
451B;
For the section between towers 451 and 453, remove the conductor suspended on the south
towers between 451 and 453 and reinstall it on the north brackets; on tower 453B, it will
occupy the existing north phase. The latter shall be suspended on the south bracket of tower
453В;
For the section from tower 453 to the gantry tower of s/s Plovdiv, in view of preserving the
phasing diagram of s/s Plovdiv, is is necessary to switch the positions of conductors В and С.
The existent north conductor shall be suspended in the middle of the gantry tower but since it
is currently attached to the most northern point of the gantry tower, it will not be long enough
for that purpose. This is why a new conductor will be installed in the span. The conductor
which is now attached to tower body 453 will be shifted to the gantry tower of the most
northern suspension point. To this end, the press joints on the side of Plovdiv s/s shall be
made again after line adjustment.
Layout № D104-01C3-12-0A shows the new phasing diagram.
Existent ground wire С-70 in the section between towers 453В and 445А will be removed and
replaced by a new one of type OPGW.
The weather conditions along the existent section from the gantry tower of Plovdiv s/s to
tower 445А are described in the executive documentation of 400kV Vezhen OHTL.
Due to impossibility to meet the provisions set forth in Article 581 of OSEIPL, one additional
jumper bracket shall be installed between towers 453A and 453B to bypass tower 453В. This
bracket is similar to the additional one currently attached to the tower and holding the jumper
connection of the conductor suspended from its body. It will be installed at the level of the
existing one to hold the west conductor’s jumper connection. The latter will be made in
vertical direction above the tension string of this conductor. A separate section of the detailed
design shows the structural design of this bracket; the bill of quantity specifies how many of it
need to produced and describes the corresponding installation works.

2.2. 110 kV Katunitsa OHTL


The new 400kV OHTL in the span between towers 15 and 16, at kilometer 6+619, crosses
the existent 110kV Katunitsa OHTL in its span between towers 22 and 23. Given the small
crossing angle between these two lines and the structural design of the 110 kV Katunitsa
OHTL, the crossing line will be subject to reconstruction according to a separate detailed
design which has already been drafted.

2.2.1. Current status


The 110 кV Katunitsa OHTL is built for two triads of conductors in a barrel-shaped
arrangement and one ground wire, with one triad already installed on one circuit of the double
line between towers 19 and 23. In the section between towers 23 and 26, the line has
horizontal suspension towers type НХ. The conductors are АСО-400 and the ground wire is
С-70 / 2хС-50 depending on tension sections. The existing line crosses the new 400 кV
OHTL is span 22-23. A layout of this crossing is given in drawing № D104-03C1-01-0A.

2.2.2. Design concept


To provide the rated crossing clearances, suspension tower 22 type НБ and tension tower 23
type 30 will be replaced with tension structures type 30.ВВ suspending all conductors at the
level of the lower tower brackets. Doing so will ensure that the existing elevation levels of
conductors and, correspondingly, ground wire for which the free suspension for conductor to
tower body will be used, respect the required crossing clearances between both power lines.
The conductors will remain as they are. The ground wire in the new tension sections will be
as follows:
− Tower 19 - tower 22 – 1хС-70;
− Tower 22 - tower 23 – 1хС-70;
− Tower 23 - tower 26 – 2хС-50.
A longitudinal profile of the reconstructed section is shown in drawing № D104-03C2-01-0A
and the power line phasing diagram is in drawing № D104-03C3-01-0A.
The the new tension strings for conductors shall be completed according to drawing № D104-
03C3-02-0A and the new ones for ground wire shall correspond to drawing № D104-03C3-
05-0A. Bird guards as per drawing № D104-03C3-08-0A shall be installed over the
suspension strings that provide jumper clearances of the middle conductor suspended on
tower body.
New dampers shall be installed to protect the conductors between towers 22 and 24.
Tower foundations shall be designed for stiff soil.
The new towers will be grounded with hot-dip galvanized double earth rods as shown in
drawing № D104-03C3-06-0A.

2.2.3. Dismantling activities


Existent towers 22 type НБ and 23 type ЪБ 30 shall be dismantled. Their foundations shall be
exposed and removed transferring all concrete debris to a dump site specified by Employer.
Dismantled towers shall be packed by components and taken to Employer’s storage facility fit
for reuse. Glass insulator components will be reused when completing the new tension strings
and shall also be demounted without breaking their glass parts or bending their cores.
The requirements for reconstruction of 110 kV Katunitsa OHTL are similar to those for
building the new 400 кV OHTL as they are based on a uniform line infrastructure construction
methodology.
All deliveries, civil, dismantling and process measurement activities that are necessary in
order to reconstruct the crossing 110 kV OHTL are specified in the bill of quantity.

3. Temporary works
These activities include construction of temporary roads and approaches as well as
construction works (assembly and disassembly works on temporary gantry structures, 20 kV
OHTL, etc.) to secure the crossing locations (roads, railways, etc). The crossing infrastructure
is shown in Appendix 10. A separate safety notice is provided for each crossing location that
requires such notice; temporary traffic safety arrangements will be applied in all locations
where the new line crosses roads which are part of the national road network. These
arrangements are imperative to Contractor. It is incumbent on Contractor to bear all costs for
traffic coordination and/or stoppage on crossing roads, disconnection of MV and HV power
lines (incl. cabling were necessary), railway occupation and other similar measures. Those
crossing locations for with no safety notice is issued must be secured by Contractor with
temporary wooden gantry structures, bucket trucks, traffic signs, road marking, etc.

4. Deadlines and completion sequence of CEWs


The deadline for completion of the new 400 kV OHTL from Plovdiv s/s to Maritsa Iztok s/s is:
− 60 days – delivery of Plant and Materials, agreement of implementation time
schedules, approval of line disconnection orders, safety precautions, etc. This period
starts as from the signature date of Protocol (Standard Form 1). At this stage, the
Contractor of the relevant position shall produce and submit to Employer a detailed
implementation time schedule at least 30 prior to starting CEWs.
− 800 days - to complete CEWs as from the signature date of Protocol (Standard Form
2).
The sequence of work to build the new power line is described in section 3 of these technical
specifications. Before proceeding to CEWs, the existent 400 kV Vezhen and 110 kV Katunitsa
OHTLs need to be reconstructed and this shall be taken into account in the line
implementation schedules. The lines shall be disconnected for as short a time period as
possible to avoid system disturbance.
Contractor of CEWs shall issue instructions on how to carry out each type of activities related
to the construction of this new 400 kV OHTL.

5. Plant and Materials specification


All Plant and Materials necessary to build the new power line shall be provided by the
Contractor.
The latter shall only use materials (fittings, towers, conductors, insulators, hot-dip galvanized
steel ground wires, OPGW, OPUG, etc.) made by manufactures using quality management
system according to ISO 9001:2015. A proof of this shall be submitted in the form of
certificates covering the following scope:
Fittings –manufacture of fittings for high-voltage OHTLs;
Towers –manufacture of lattice steel towers/structures;
Conductors/ground wires –manufacture of conductors and/or ground wires;
Insulators –manufacture of insulators;
OPGW –manufacture of optic power ground wire;
OPUG –manufacture of fiber optic cables.

Delivered Plant and Materials shall be incorporated in accordance with Ordinance № РД-02-
20-1 of 5.02.2015 on rules and procedure for incorporation of building products at
construction sites in Bulgaria.
They shall have equal or superior parameters to those specified in the applicable
standards or their equivalents.
The delivered Plant and Materials shall conform to the applicable standards listed in Appendix
30.

5.1. Towers
Lattice steel towers for this construction site shall be ordered for manufacture and delivery
according to the detailed design documentation and sectional standards No 0151737-83 and
No 0179782-87. All design documentation will be provided to Contractor.
All size deviations in tower geometry and all tolerances for bolted connections must be within
the limits set in the above sectoral standards.
Towers will be made of square-shaped iron according to БДС EN 10056-1 or equivalent, U-
profiles according to DIN 10026 (or equivalent), and S235JR and S355JO structural steel for
profiles and plates according to БДС EN 10025 or equivalent. All structural components of
lattice steel towers shall be hot-dip galvanized in factory environment according to БДС EN
ISO –1461:2009 or equivalent.
Bolts shall be of resistance class and sizes corresponding to design documentation.
Their threaded section shall not enter into the bolted connection (the thread of a bolt shall not
enter into its load-bearing stem).
Steel grades and bolt types to be used per tower type are given in the following table:
Type of lattice Bolts, resistance
Structural steel for profiles and plates, grade
steel towers class
СНД1 S235JR and S355JO 8.8 and 5.6*
СНД2 S235JR and S355JO 8.8 and 5.6*
СЕН1 and S235JR 5.6
СЕН2
20.(16-28).NN S235JR and S355JO 8.8
60.(16-28).NN S235JR and S355JO 8.8
Note: Positions marked with * refer to tamper-proof bolts.

The manufacturer of lattice steel towers shall mark each of them with a unique serial number
consisting of an alphanumerical code that corresponds exactly with the design drawing
identifications for each individual component of a tower.
Position numbers on steel components shall be stamped by a press machine or other suitable
technique so that they remain clearly visible after being hot-dip galvanized. All bolts shall be
complete with 1 nut, 1 washer and 1 lock washer. All bolts, nuts and washers shall be hot-dip
galvanized.
All new towers shall have security bolts (theft-proof) installed up to 3 meters above
terrain level. Tamper-proof bolts shall be of size, resistance class and anticorrosive
protection according to design documentation.
Towers shall be transported, assembled and erected in a way that ensures minimum damage
to their anti-corrosive coating. The damage tolerance is 1.5% of the total tower area. Materials
to recover any damaged anticorrosive coating shall be foreseen and provided by Contractor.

5.2. Concrete
Concrete for foundation laying shall conform to БДС EN 206:2013+A1:2016/NA:2017 or
equivalent. It must not be mixed on site but should only be delivered from a concrete mixing
station. The concrete grade for foundation laying shall correspond to design specifications
stated in the drawings. Chemical admixtures, e.g. for setting acceleration, freeze-thaw
resistance and other purposes, may only be added to the concrete mixture upon agreement
with representatives of Employer and the company supervising the line construction process.
Concrete should only be transported using specialized mixer trucks to guarantee its
properties. It shall undergo tests according to БДС EN 12390-2:2009 or equivalent. The
concrete sampling method and interval shall be according to БДС EN 206 and БДС EN
206/NA or their equivalents. The concrete delivery shall be accompanied by certificates of
operational properties and performance. Test and transfer protocols shall be made available
to Employer or construction oversight representatives upon request for quality tracking
purposes.
5.3. Conductors and ground wires

5.3.1. Conductors
The main standard applicable to conductors delivered for this project is БДС 1133-89 (or
equivalent) (hereinafter referred to as “The Standard”).
New conductors shall be of type АСО-400 according to the above Standard. Their design
and technical specifications are given in Appendix 31.
Aluminum subconductors shall be made of rolled wire with characteristics as per БДС EN
1715-1:2008 or БДС EN 1715-2:2008 or their equivalents.
Hot-dip galvanized steel wires shall be in full conformity with БДС 5875-73 (or equivalent) for
grade МС, second group.
No intertwined, broken, flattened, kinked or scored subconductors are admissible. Conductor
layers shall be wound in opposite directions, with outer layer in clockwise direction. Their
bundled core shall be entirely covered with neutral grease whose start-dripping temperature is
not less than 65 °С.
Aluminum and steel wires shall be connected via butt-welded joint or cold welding. Welded
joints shall be at least 15 m apart. The welded joints of steel wire shall be covered with
anticorrosive material.
The electrical resistivity of conductors must not exceed the limits according to Appendix 1 of
the Standard.
The weight of complete conductor shall correspond with the rated weight according to table 1-
4 of Appendix 1of the Standard. The outer diameter of conductor shall be as defined in the
Standard, i.e. 27,24 mm.
Delivered conductors shall have service lifetime of not less than 45 years.
Their lengths shall be as prescribed in the Standard or its equivalent.
Conductors must be new, manufactured not more than two years prior to construction start
and in conformity with the technical specifications and testing methods, acceptance, marking,
packaging and transportation requirements of the Standard or its equivalent.
Recovery of damaged subconductors is only allowed using АСО 400 repair sleeves after
agreement with Employer and the construction oversight company.

5.3.2. Hot-dip galvanized ground wire


The main technical specifications for hot-dip galvanized ground wire are referred to in
Appendix 32.
A single, steel, clockwise wound, butt-welded ground wire will be used. It will have bundled
structure 1х19 with outer diameter of 11 mm.
The diameter of bundle wires, their size tolerance and minimum weight of protective coating
shall correspond with the rated values in table 2 of БДС EN 10264-2:2012 or equivalent.
Any deviation from the rated diameter of ground wire shall be within tolerance as specified in
the standard.
All bundles shall be evenly wound and properly arranged in a tight fit without any bends,
dents or bulges and without crossing each other. No kinked, flattened, torn or scored wires
are admissible. Bundle layers shall be wound in opposite directions, with outer layer in
clockwise direction.
The ground wire shall be with strength class ≤1570 and breakdown stress ≤99.9 кN (table
С2 of БДС EN 12385-10:2003+А1:2008 or equivalent).
Class A galvanized coating with 99.9 % zinc content shall protect the outer surface of the
ground wire.
Ground wires must be new, manufactured not more than two years prior to construction start
and in conformity with the technical specifications and testing methods, acceptance, marking,
packaging and transportation requirements of БДС 16750-88, БДС EN 10264:2012, БДС EN
12385-1:2002+A1:2009, БДС EN 12385-2:2002+A1:2008, БДС EN 12385-10:2002+A1:2009
or their equivalents.

5.3.3. Optic power ground wire (OPGW)


The new OPGW shall be designed to provide:
mechanical strength in all rated weather conditions;
single-phase short circuit thermal withstand;
lightning impulse thermal withstand;
optic performance within tolerance in all of the above cases or combination thereof.
The main technical specifications for OPGW are referred to in Appendix 33.
A single OPGW will be used consisting of one clockwise wound layer of round aluminized
steel wires with central fiber protection metal tube. It is Employer’s requirement that the fiber
protection tube be made of stainless steel with diameter not less than 3.2 mm.
The OPGW will consist of 24 optic fibers running to its fiber protection steel tube. These shall
be of Non Zero Dispersion Shifted Fiber type according to ITU-T.G655 specification. No
spliced fibers are allowed. The fibers shall be installed freely (with sufficient allowance) in one
protective tube made of stainless steel by technique that renders it air-tight. At lest 0.4% of
additional fiber length (allowance) shall be provided inside the tube.
That tube shall be filled with water-resistant, dielectric, homogeneous gel.
All aluminized steel wires that OPGW is composed of shall correspond to БДС EN
61232:2003 or equivalent.
OPGW shall meet the following criteria:
Its layer winding technique shall be in accordance with IEC 61089 or equivalent.
No grease shall be applied between the separate layers.
When the OPGW is not strained (on the drum), the wires in its individual layers shall be in
contact with each other.
Its outer (end) layer must be would clockwise.
Delivered OPGW must be new, manufactured two years prior to delivery date.

5.4 Requirements for optic underground cable (OPUG)


The main technical specifications for optic underground cable (OPUG) are referred to in
Appendix 34.
OPUG shall correspond to БДС EN 60794-1-1:2016 or equivalent, with the same type of
fibers as OPGW.
Main requirements for OPUG:
Hybrid type, fit to be pulled in a HDPE protective tube and for indoor installation;
Water resistance;
Flame retardancy;
The cable sheathing must not stiffen in the course of aging;
The cable data must be stamped on its outer sheath in a clear, durable and water-insoluble
manner.
Easily accessible optic fibers;
Standard color coding of the optic fibers;
Axial reinforcement;
Ambient temperature range for transportation and storage: -40 °С to +70 °С
Ambient temperature range for installation: -5°С to +40°С
Operating temperature: -40°С to +70°С.

5.5 Insulator strings and fittings


The new 400 kV OHTL shall be insulated with new polymeric insulators and fittings. All fittings
must conform to the quoted standards or their equivalents. The minimum breakdown stress
for each fitting component shall be determined in accordance with the particular tensile force
exerted on each separate string.
Fitting components of different insulator strings must be interchangeable. New fittings shall
correspond with the size and material of conductors and ground wires. All fitting joints shall be
wear-proof and dependable.
Fitting components shall include bolts, nuts, washers, lock pins and other fixtures to enable
assembly and installation without any special tools or aids. Lock pins for spherical and
coupled or tension elements must conform to БДС EN 60372:2006 or equivalent.
All bolted joints of a suspension/tension string shall provide the required mechanical strength
to the elements being joined and to the insulator sting.
Fittings or their parts made of steel (cast or malleable) shall be hot-dip galvanized according
to БДС EN ISO –1461:2009 or equivalent.
Clamps shall not allow any deformation of conductors or ground wires.
Metal parts shall be resistant to corrosion, premature wear-and-tear of contact surfaces or
electrolytic reaction between different metals. Contact surfaces shall thus provide good
electrical contact in operating conditions.
Aluminum parts attached to conductors made of aluminum or its alloy shall be with fineness of
at least 99.5% or composed of an equally anti-corrosive alloy.
Fitting components under stress shall have no sharp angles or edges that could potentially
lead to high electrostatic tensions during normal operating conditions. All surfaces, including
those of bolts and nuts, shall be rounded or spherical in order to minimize corona losses and
comply with the applicable requirements to RF interference.

5.5.1. Polymeric insulators:


The main technical specifications for polymeric insulators are described in Appendix 35.
Polymeric insulators shall meet the following criteria:
− The mechanical properties of an insulator depend on its core, which shall be made of
epoxy resin reinforced with fiber-glass of high axial strength; Both fiber glass and
epoxy resin shall have optimal performance in terms of mechanical strength, acid
resistance and water absorbency;
− E-CR glass fibers will be used for the core;
− Polymeric insulators shall be made of flame retardant and high temperature
vulcanized (HTV) rubber providing maximum water-repellency;
− Insulators shall be manufactured by direct molding of their body together with the
insulator sheds; Mold lines (trailings) shall not exceed 1 mm;
− The core’s silicone rubber sheathing shall be at least 3 mm thick;
− Good self-cleaning capability (aerodynamics); Insulator sheds shall have a smooth
surface without any process unevenness or edges. Their design must prevent any
occurrence of corona activity and partial shunting of an insulator due to dirt, rain,
snow or ice;
− Compatible fittings shall be used to complete the insulator string. Polymeric insulators
shall be fitted with socket tongues at their earthed end and ball-eyes at their live end,
their size being 20 as per БДС HD 474 S1:2004 (IEC 60120) or equivalent. Lock pins
must correspond to БДС EN 60372:2006 or equivalent;
− Insulators shall be equipped with field equalizing ring capacitors.
According to design concept, insulators will be fitted with ring capacitors and additionally with
arc protection fittings.
These arc protection fittings shall be easy to maintain and replace if necessary without having
to dismantle the insulator or individual components of suspension/tension strings.

5.5.2. Fittings for insulator strings


The drawings referred to in subsection II.1.7 and attached to this documentation show the
required complete sets of suspension/tension string. They also indicate the needed minimum
tensile forces that individual components must be able to withstand.
The main requirements for components (fitting elements) used to complete the strings are as
follows:
Socket tongue/socket tongue for horn –connection size as per assembly drawing of the
relevant string and conformity with БДС HD 474 S1:2004. These fittings shall be made of
malleable steel. When completing insulator strings, socket tongues for horn need to be used -
these are able to connect an accessory such as horn, ring, etc. The main technical
specifications for socket tongues are described in Appendices 36 and 37;
Ball-eye/ball-eye for horn –connection size as per assembly drawing of the corresponding
string and conformity with БДС HD 474 S1:2004. Ball-eyes shall be made of malleable steel.
Insulation strings shall be also be fitted with socket tongues for horn due to the same reasons
as described above. The main technical specifications for ball-eyes are described in
Appendices 38 and 39;
Clevis –connection size as per assembly drawing of the corresponding string. These fittings
connect strings to tower and must have connection sizes specified in the above tables. The
main technical specifications for clevis assemblies are described in Appendices 40 and 41.
U-bolt –connection size as per corresponding assembly drawings in the detailed design. U-
bolts shall be hot-dip galvanized and their threads shall therefore be cleaned up so that nuts
can be easily installed. The main technical specifications for U-bolts are described in
Appendix 42;
Swivel clamp –this type of fitting is used as necessary to rotate the plain of string elements
at 90 degrees. These fittings shall be made of malleable steel;
Yoke plate –used when completing suspension and tension strings to fix subconductors in
bundle at a distance of 400 mm from each other and distribute the tensile stress among
individual subconductors;
Shackle –provides a quick joint between two separate units of a string;
Link adjuster –provides mechanical connection and the required overall dimensions of a
suspension or tension string by stepwise adjustment of its length;
Turn buckle –used in a tension string to fine-tune the strain of conductors by length
adjustment;
Extension link –serves to achieve the required overall dimension of a string;
Mount joint –provides mechanical connection and enables easy mounting/dismantling of an
insulation string;
Other fittings for string completion: Any fittings not referred to above but used to complete
suspension/tension sections shall correspond with the general requirements for fittings. Their
connection sizes shall allow them to be installed with their belonging components while
respecting the desired mechanical performance for each corresponding string.

5.5.3. Conductor fittings


Lock and connection fittings for conductors shall be selected depending on the outer diameter
( 27.24 mm) of delivered conductor АСО-400.
The main requirements for conductor lock and connection fittings are as follows:
Tension clamps and span couplers shall be press-type to prevent any slipping or damage
of conductors under mechanical load. The mechanical strength of conductor-to-tension clamp
and conductor-to-conductor connection must be at least 95% of the conductor’s rated tensile
strength. While in normal operation, offered clamps and span couplers shall ensure that their
connection maintains stable electrical resistance and its temperature does not exceed that of
the connected conductor. The main technical specifications for tension clamps and span
couplers are described in Appendices 43. and 44, correspondingly;
Suspension clamps shall not cause conductor deformation or undbundling while in
operation. Their assembly may also include protective sleeves. Suspension clamps shall be
designed to enable optimal vibration damping. Their bodies and upper parts shall be made of
nonferrous material that minimizes magnetic losses. Sufficient contact surface shall be
provided to prevent potential damage in fault conditions. Suspension clamps shall be able to
swing freely in the vertical plane around their horizontal axis. As soon as a conductor has
reached 20% of its nominal tensile strength, the suspension clamp will let it slip through. If
overtightened, the thread turns of connection bolts must snap off before damaging the
clamp’s body or upper part with installed conductor. The clamp grooves must be smooth and
without any waves, corrugations or other roughness on their surface. The main technical
specifications for conductor suspension clamps are described in Appendix 45;
Jumper couplers shall ensure a reliable galvanic contact between the two coupled
conductors. When a coupler is live (current-carrying), its surface temperature shall not differ
from that of the conductor itself. The jumper connection shall maintain stable electrical
resistance while in operation.

5.5.4. Fittings for hot-dip galvanized steel wire


The drawings attached to this documentation show the complete set of suspension/tension
string for hot-dip galvanized steel wire. They also indicate the needed minimum tensile forces
that individual components must be able to withstand.
Tension string. Tension clamps shall be of spiral type and the wire-to-clamp connection shall
have mechanical strength of not less than 95% of the wire’s rated tensile strength. The main
technical specifications for hot-dip galvanized steel wire tension clamps are described in
Appendix 46;
Suspension string. Suspension clamps shall not damage ground wire or its galvanic coating,
nor shall it cause wire splitting while in operation. Suspension clamps shall be able to swing
freely in the vertical plane around their horizontal axis. As soon as a ground wire has reached
20% of its nominal tensile strength, the suspension clamp will let it slip though. If
overtightened, the thread turns of connection bolts must snap off before damaging the
clamp’s body or upper part with installed ground wire. The clamp grooves must be smooth
and without any waves, corrugations or other roughness on their surface. The main technical
specifications for hot-dip galvanized steel wire suspension clamps are described in Appendix
47;
Span couplers shall be of spiral type and the wire-to-wire connection shall have mechanical
strength of not less than 95% of the wire’s rated tensile strength. They have to ensure a
reliable connection while in service. The main technical specifications for hot-dip galvanized
steel wire span couplers are described in Appendix 48;
Current clamps shall ensure a reliable galvanic contact between the two coupled ground
wires. They shall be compatible with the material of the ground wire and its anticorrosive
coating to prevent electrochemical corrosion.

5.5.5. Fittings for OPGW


Fittings for installation of OPGW shall be designed according to its outer diameter and
winding direction as well as the method of their suspension from tower tops.
The drawings attached to this documentation show the complete set of suspension/tension
string for OPGW. They also indicate the needed minimum tensile forces that individual
components must be able to withstand.
Tension string. The fittings for completion of OPGW are shown in the drawings attached
thereto. Tension sleeve shall be provided as one set with protective sleeve and earth rod.
The main technical specifications for OPGW tension clamps are described in Appendix 49;
Suspension string. OPGW will be suspended by means of C-link. The main technical
specifications for OPGW suspension clamps are described in Appendix 50. C-links shall
meet the specifications described in Appendix 51;
Junction boxes will provide optical connectivity between two OPGWs. The main technical
specifications for junction boxes are described in Appendix 52. Outdoor junction boxes
delivered by Contractor shall be suitable for the types of cable/ground wire used in this power
line project. They shall be designed to accommodate and protect two/three cables, each
having 24 with optic fibers. The optic cable/wire bushings will be located on the bottom side.
In addition to being easily accessible for maintenance, the junction box, including its fittings,
shall be designed to seal and protect cable connections from dust, moisture and atmospheric
influence as specified in this specification. The recommended number of fibers per splicing
cassette is 12.
All junction boxes shall be made of stainless metal or alloy (with clean and polished surface),
capable of holding at least 3 meters of would optic fibers, and with easily accessible fittings.
Each junction box shall be equipped with all components, accessories and expendables
required for fiber installation, locking, arrangement and splicing. Junction boxes shall be
suable for installation on latticed steel structure and enable connection and termination of
optic fibers. They shall protected against damage and penetration of water, animals and
insects. Their fittings shall allow them to be attached to an L-profile of tower without drilling
any holes.
Holding clamps will be used to fix OPGW to tower structure next to its corresponding
junction box. These fittings shall be able to hold one as well as two OPGWs. Their installation
to tower structure shall be possible without having to drill any holes. Studs, bolts and nuts
shall be made of steel or hot-dip galvanized. The length of studs shall be ≤120 mm. The heel
shall be fixed independently from the stud.

5.5.6. Protective fittings


Conductor spacers shall conform to БДС EN 61854 or equivalent standard and ensure that
the subconductors in bundle are spaced at distance of 400 mm from each other. Triples
spacers will only be used in spans. Single spacers will be used for jumper connections. Both
types of spacers shall be bracket-type, damping, and with clamps according to the outer
diameter of subconductor.
They shall maintain the rated spacing of subconductors in all operating conditions except for
short-circuit. In case of short-circuit, the rated spacing has to be restored immediately.
Spacers shall cause no damage to subconductors while in operation. Shear stability shall
remain unaffected in subspan galloping conditions. Dampers will be replaceable and made of
wear-resistant materials. Spacer-to-subconductor joints shall be secured from becoming
loose. The main technical specifications for conductor spacers are described in Appendix 53.
Arc protection fittings shall be made of material which is wear-resistant in short-circuit
arcing conditions. Arc protection rings will be fixed to insulator string fittings by bolted
connection with one or two attachment points depending on the type of fittings. These arc
protection fittings shall be easy to maintain and replace if necessary without having to
dismantle the insulator or individual components of suspension/tension strings. All metal
components of arc protection rings shall be hot-dip galvanized in conformity with БДС EN ISO
1461:2009 or equivalent;
− Potential equalizer rings without arc protection function shall be made of aluminum
or its alloy. These shall ensure even distribution of the electric filed;
− Bird guards will protect suspension insulator strings from bird lime. They shall be
delivered and installed as instructed in the detailed design;
− Bird diverters will mark the ground wire to prevent bird impact. The Environmental
Impact Assessment Report (EIAR) recommends the use of protective (contact)
plates, spheres or sleeves made of fluorescent material.

Examples of devices (diverters) for bird impact prevention include:


Dampers. These shall be Stockbridge type according to БДС EN 61897:2003 or equivalent.
They shall be designed for optimal absorption of the energy generated by vibrations. Fittings
and metal parts used to install dampers on ground wires shall be secured from being
loosened or displaced due to vibrations and shall cause no damage. Lock clamps shall fit to
the outer diameter of OPGW and be made of aluminum or its alloy (nonferrous material). To
reduce corona effect, all details shall be without sharp edges or abrupt transition in form.
All damper components made of corrosive metal shall be hot-dip galvanized according to
БДС EN ISO –1461:2009 or equivalent.

5.6. Earth rods


The type of earth rods shall be as per detailed design drawings. They will be made of 40х4
mm galvanized steel bar and L63х63х6 mm hot-dip galvanized shaped steel with a length of
1.5 m. Deep-driven and vertical earth rods will be used. All underground connections shall
made by welding and treated against corrosion. The connections to towers shall be of bolted-
type.
All earth rod components shall be hot-dip galvanized in accordance with БДС EN ISO 1461 or
equivalent.

5.7. Patch panel


This panel used for termination of optic cables with 24 fibers. Protection rating: IP 30. Fit to be
installed in 19 ”mount panel with inlet ports for 24 adapters E-2000 0,1 dB and complete with
the following accessories:
− 24 adapters E-2000 APC Grade B;
− 3 splicing cassettes to lock the optic fibers;
− 24 heat shrinkable splice protectors.
− 24 pigtails E 2000 APC Grade B with a length ≥ 1,5m;

5.8. Fiber optic distribution cabinet


This cabinet shall have the following capabilities and include a modular system for installation
of 19 ”patch panels with fiber optic connectors:
− Possibility to install not less than five patch panels for termination of 24 optic fibers
per panel;
− Cable system enabling reliable storage of the main fiber optic cables and connectors
for optic equipment;
− Universal accessories for termination of the most common types of underground fiber
optic cables;
− Fully accessible cable interior and patch panels;
− Possibility for internal fastening of patch panels.

Design specifications:
− Transparent front door with safety glass;
− Openable front and rear door with locking systems;
− Removable side panels;
− Bottom and top cable inlets;
− Cable clamping buses;
− Cabinet earth point;
− Designed for 9” patch panels;
− External influence protection rating IP 31;
− Cable inlets/outlets with sealed bushings;

Overall dimensions of the cabinet:


− H ≥ 42 U;
− W 600 mm;
− D 600 mm.

The fiber optic distribution cabinet will provide:


− sufficient space to accommodate and protect all necessary connections;
− connectors type E 2000;
− possibility for installation of optic measurement devices.

5.9. Other Plant and Materials


These comprise Plant and Materials, including auxiliaries, to be installed or used during the
line construction process. This includes items specified in the detailed design but not in these
technical specifications as well as others (expendables) whose use is required in order to
complete main activities. All such items shall comply with the general requirements described
above in section 5.

6. Testing of delivered materials


Contractor shall prepare and submit FAT schedule(s) for a period of up to thirty (30) days as
from Contract signature. The testing period is included in the project completion deadline.
During the bid submission process, each tenderer shall submit their technical proposal also
including type tests and design tests in accordance with the specific requirements for each
type of product/material as described below. Before proceeding to shipment, Contractor shall
arrange FATs at their own expense with the participation of Employer’s representatives. The
scope of FATs for each material is described in the following sections and all tests will be
carried out according to the applicable standards.

6.1. Testing of towers

6.1.1. Type tests:


Lattice steel towers delivered as part of this procurement will not be subject to type (load)
tests.

6.1.2. FATs:
The following FATs with Employer ’participation will be conducted:

6.1.2.1. Trial assembly


Each tower intended for the new power line will be subject to trial assembly at the factory.
This will be carried out in the presence of Employer.
No force shall be applied while assembling tower components. If certain position turns out to
be off-tolerance or deformed, all elements of that position will be rejected and manufactured
again. Towers may only be transported to construction site after successful completion of
their trial assembly. A protocol of findings will be prepared to certify the successful trial
assembly.

6.1.2.2. Mechanical and chemical tests of tower material


The aim of these tests is to check the performance of the steel that is used to make profiles
and plates. Five (5) randomly selected steel samples shall be taken form the ready profiles
and plates of each type of tower under test. One tower of each type to be used in the project
will undergo such testing.

6.1.2.3. Testing of bolts and nuts


Random samples of the finished bolts and nuts shall be taken. The samples will be tested to
check their resistance class and conformity with the rated dimensions. Up to 10 fixture
elements per tower type will be tested.

6.1.2.4. Hot-dip galvanized coating test


This test will examine the zinc coating. It will be done on at least 5 structural components per
tower type. These components shall be selected at random.

6.2. Conductor tests


Conductors shall be tested in accordance with БДС 1133-89 or equivalent.
The bidder’s technical proposal shall be submitted with test protocols for conductors АСО-400
according to section 4 of БДС 1133-89 or equivalent.
The tests will include:
− Visual inspection as per clause 4.3
− Dimensional check as per clause 4.4
− Electrical resistivity test as per clause 4.5
− Breakdown stress test of finished conductor as per clause 4.6
− Conductor weight control as per clause 4.7
Finished conductors will be subject to FATs with the same scope. One conductor per each
300 metric tons of finished conductors will undergo FATs.
During the bid submission process, type test protocols for conductors АСО-400 shall be
provided according to clause 4 of БДС 1133-89 or equivalent. Any missing protocol will be
deemed as incomplete technical proposal.

6.3. Testing of hot-dip galvanized steel wire, size 11 mm


Hot-dip galvanized steel wires of size11 mm shall be tested in accordance with БДС EN
12385-1:2002+A1:2009 or equivalent.
During the bid submission process, each tenderer shall submit their technical proposal
supported by test protocols for finished hot-dip galvanized steel wire of size11 mm with the
following scope:
− Size tolerance check
− Tensile strength – index and tolerance
− Tensile strength – stress-strain test
− Tensile strength – variable bending test
− Tensile strength – torsion test
Zinc coating weight control

Finished hot-dip galvanized steel wires will be subject to FATs with the same scope as above.
One series of FATs will be performed.
Test protocols for wires of size 11 mm shall be provided along with the technical proposal.

6.4 Testing of OPGW

6.4.1. Type tests.


Each tenderer shall submit type test protocols for wire with similar deign. They shall be
conducted in accordance with БДС EN 60794 or equivalent in the following scope:
Tensile performance: БДС EN 60794-1-2, method Е1 or equivalent
Stress-strain: Appendix В of БДС EN 61089 or equivalent The length of the tested sample
shall be in accordance with БДС EN 61089 or equivalent.
Sheave: БДС EN 60794-1-2, method Е9 or equivalent
Repeated bending: БДС EN 60794-1-2, method Е6 or equivalent
Impact: БДС EN 60794-1-2, method Е4 or equivalent
Crush: БДС EN 60794-1-2, method Е3 or equivalent
Kink: БДС EN 60794-1-2, method Е10 or equivalent
Torsion: БДС EN 60794-1-2, method Е7 or equivalent
Temperature cycling: БДС EN 60794-1-2, method F1 or equivalent
Aaeolian vibration: БДС EN 60794-1-2, method Е19 or equivalent
Fault current: БДС EN 60794-1-2, method H1 or equivalent
Lightning: БДС EN 60794-1-2, method H2 or equivalent
Water penetration: БДС EN 60794-1-2, method F5B or equivalent
Attenuation: БДС EN 60794-1-40 or equivalent

6.4.2. FATs:
FATs will be carried out in the presence of Employer. They shall be conducted in accordance
with БДС EN 60794 or equivalent in the following scope:
− Optic fiber test: БДС EN 60793-1 or equivalent.
− Protective tube test (dimensions, tensile and elongation strength, electrical
resistance).
− Wires before stranding: БДС EN 61232:2003 or equivalent.
− Tensile performance: БДС EN 60794-1-2, method Е1 or equivalent
− Attenuation: БДС EN 60794-1-40 or equivalent

6.5. Testing of OPUG.


No type test protocols and no FATs are required for OPUG.

6.6. Insulators
Polymeric insulators delivered for this project shall be tested in accordance with БДС EN
61109:2008 or equivalent, БДС EN 62217:2013 or equivalent and related standards.
The technical proposal shall be submitted with design test and type test protocols for
insulators in the following scope:
6.6.1. Design tests:
Each tenderer shall support their technical proposal with a report of all conducted design tests
whose scope shall be according to Table 1 and Table 2 of БДС EN 61109:2008 as well as in
conformity with БДС EN 62217:2013 or equivalent;
6.6.2.Type tests:
Each tenderer shall support their proposal with a report of all conducted type tests whose
scope shall be according to Table 1 of БДС EN 61109:2008 or equivalent.

Before proceeding to shipment, Contractor shall arrange FATs with the participation of
Employer’s representatives. The type test shall include:
6.6.3. FATs:
These will be carried out in the presence of Employer’s representatives and with scope
according to section 12 of БДС EN 61109:2008 or equivalent.
6.6.4. Routine test:
Clause 13 of БДС EN 61109:2008 or equivalent. Employer’s representatives will be present
during the test of up to 2 % of the total quantity for delivery.

6.7. Testing of complete string:


One complete/assembled suspension string and one complete tension string will undergo
FATs according to БДС EN 60383-2 or equivalent. The type of suspension/tension strings
selected for testing will be agreed with Employer. The switching impulse, lightning impulse
and power-frequency withstand voltage test methods shall be in accordance with БДС EN
60060-1:2010 or equivalent. The strings under test must be complete with all fittings.
Employer’s representatives will attend the tests. The scope of these tests shall include as a
minimum:
− Lightning impulse (section 9 of БДС EN 60383-2 or equivalent);
− Wet breakdown voltage at power-frequency (clause10 of БДС EN 60383-2 or
equivalent);
− Switching-impulse breakdown voltage (clause 11 of БДС EN 60383-2 or equivalent);
− Radio-frequency interference test shall be performed in accordance with БДС ЕN
60437-2003. The tests shall be conducted following an approved procedure on
complete strings, with all fittings on, installed in a short length of the conductor and
recreating the real operational conditions as close as possible;
− AC high-voltage arc test according to БДС EN 61467:2008 or equivalent.

6.8. Fittings
Fittings delivered for this project shall be tested in accordance with БДС 6195 or БДС EN
61284 or their equivalents. Each tenderer shall support their technical proposal with type test
protocols for the following fittings and with a scope as listed below.

6.8.1. Fittings for insulator sting and ground wire.


The following tests apply to all fitting components for completion of conductor and ground wire
insulator strings.

6.8.1.1. Type tests:


- Visual inspection
- Dimensional check
- Mechanical (deformation and destruction)
- Corona discharge and RF interference (for insulator string fittings only)

6.8.1.2. FATs:
- Visual inspection
- Dimensional check
- Galvanization
- Mechanical (deformation and destruction)

6.8.2. Tension connections (span couplers) and tension clamps

6.8.2.1. Type tests:


- Visual inspection
- Dimensional check
- Mechanical (deformation and destruction, with х=1)
- Mechanical (bolted connections)
- Mechanical (deformation and destruction of suspension points)
- Temperature cycling (current-carrying fittings)

6.8.2.2. FATs:
- Visual inspection
- Dimensional check
- Galvanization (steel parts)
- Mechanical (bolted connections)
- Mechanical (stress-strain)

6.8.3. Suspension clamps


6.8.3.1. Type tests:
- Visual inspection
- Dimensional check
- Mechanical (deformation and destruction)
- Mechanical (slipping)
- Mechanical (bolted connections)
- Corona discharge and RF interference
- Magnetic loss (hysteresis)
6.8.3.2. FATs:
- Visual inspection
- Dimensional check
- Galvanization
- Mechanical (deformation and destruction)

6.8.4. Partially strained fittings


6.8.4.1. Type tests:
- Visual inspection
- Dimensional check
- Mechanical (stress-strain)
- Temperature cycling (current-carrying fittings)

6.8.4.2. FATs:
- Visual inspection
- Dimensional check
- Galvanization

6.8.5. Protective fittings for insulator strings:

6.8.5.1. Type tests:


- Visual inspection
- Dimensional check

6.8.5.2. FATs:
- Dimensional check
- Galvanization

6.8.6. Spacers (БДС ЕN 61854 or equivalent):

6.8.6.1. Type tests:


- Visual inspection
- Dimensional check
- Protective coating (if applicable)
- Mechanical (slipping)
- Mechanical (breaking point of bolts)
- Mechanical (bolt tightening)
- Mechanical (short-circuit simulation - tension and stress)
- Mechanical (resilience and damping)
- Mechanical (bending)
- Mechanical (material fatigue/wear-and-tear)
- Elastomer (if applicable)
- Electrical (corona discharge and RF interference)
- Electrical (resistance)
6.8.6.2. FATs:
- Visual inspection
- Dimensional check
- Protective coating (if applicable)
- Mechanical (breaking point of bolts)
- Mechanical (bolt tightening)

6.8.7. Dampers (БДС ЕN 61897 or equivalent):

6.8.7.1. Type tests:


- Visual inspection
- Dimensions, material and weight check
- Protective coating
- Slipping
- Breaking point of bolts
- Bolt tightening
- Suspension weight
- Clamp fastening
- Damper performance
- Material fatigue/wear-and-tear

6.8.7.2. FATs:
- Visual inspection
- Dimensions, material and weight check
- Protective coating
- Breaking point of bolts
- Bolt tightening
- Suspension weight
- Clamp fastening

The FATs applicable to clause 6.8 will be performed in the presence of Employer’s
representatives. They will focus on 10 randomly selected samples from each type of fittings.

6.8.8. Testing of other materials:


Tenderers are not required to present type test protocols in their technical proposals or to
perform FATs for materials other than those referred to above.

7. Documentation in the course of site construction and acceptance


During construction of the new 400 kV OHTL, the following documentation shall be prepared
and submitted to the acceptance committee:
Acts and protocols pursuant to the Spatial Development Act (SDA) - Ordinance No, prom. SG
72 of 15 August 2003 with amendments;
Support documentation of delivered materials, fittings and equipment according to Ordinance
№ РД-02-20-1/2015 on rules and procedure for incorporation of building products at
construction sites in Bulgaria (SG, 14/2015);
Protocols of findings and jointly agreed reports as required by this documentation, the tender
and the signed contract pertaining to any interruptions of activity, returned dismantled
material, approved milestones, etc.
Protocols and documentation pursuant to OSEIPL and Ordinance No 9/2004 on the operation
and maintenance of electrical power plants and networks :
Protocol(s) of earth rods contact resistance;
Press couplers and press tension clamps installation log and protocols on the contact
resistance of press couplers;
Sleeve couplers and clamps installation log;
Conductor and ground wire adjustment protocols for each tension section;
Protocols of measured clearances above/under crossing infrastructure (railway lines,
highways and first class national roads, ground-surface pipelines, and power lines with rated
voltage of 20 кV or higher). Employer may, at their own discretion, require additional
measurements of clearances to other infrastructure;
Protocol(s) on jointly measured attenuation at splice point and in fiber optic channel;
Other protocols substantiating the proper implementation of the projects and ToRs for
construction of the new 400 kV OHTL.

III. LIST OF APPENDICES AND DRAWINGS


All quoted drawings and Appendices are summarized and complete. They represent an
integral part of this documentation.
The selected Contractor will be provided with a copy of the approved Detailed Design and its
Appendices.
Specification

Table of Contents
1. PREAMBLE

2. SPECIFICATIONS

Appendix 30 - Applicable material standards

Appendix 31 - Main technical specifications of conductor type АСО-400

Appendix 32 - Main technical specifications of ground wire with outer dia Ø 11

Appendix 33 - Main technical specifications of OPGW

Appendix 34 - Main technical specifications of OPUG cable

Appendix 35 - Main technical specifications for polymeric insulator

Appendix 36 - Main technical specifications of socket tongue for insulator string

Appendix 37 - Main technical specifications of socket tongue for ground wire/OPGW

Appendix 38 - Main technical specifications of ball-eyes for insulator string

Appendix 39 - Main technical specifications of ball-eyes for ground wire/OPGW

Appendix 40 - Main technical specifications of clevis for insulator string

Appendix 41 - Main technical specifications of clevis for ground wire

Appendix 42 - Main technical specifications of U-bolt

Appendix 43 - Main technical specifications of tension clamp for conductor type АСО-400

Appendix 44 -Main technical specifications of span coupler for АСО-400

Appendix 45 -Main technical specifications of suspension clamp for conductor type АСО-400

Appendix 46 -Main technical specifications of tension clamp for ground wire

Appendix 47 - Main technical specifications of swing suspension clamp for ground wire

Appendix 48 - Main technical specifications of span coupler for ground wire

Appendix 49 - Main technical specifications of tension clamp for OPGW

Appendix 50 - Main technical specifications of suspension clamp for OPGW

Appendix 51 - Main technical specifications of C-link

Appendix 52 - Main technical specifications of OPGW/OPUG junction box

Appendix 53 -Main technical specifications of conductor spacers


1. PREAMBLE

The Tenderer shall complete all attached Specifications (Appendices from 30 to 53).
The Contract Works shall comply with the Specifications decribed in the Appendices from 30
to 53.

The Manufacturer’s quality system shall be in accordance with ISO 9001.


Type test certificates requested in the Tender Documents have to be issued by independent
certified laboratory or type test certificate from tests performed in certified factory laboratory
conducted and/or witnessed by independent experts.
2. SPECIFICATIONS

Appendix 30

Applicable material standards

# Type of material Conformity with standard (other) Tenderer’s offer

Ground wire type IEC 61089 (1991-06) or equivalent;


OPGW БДС EN 61232:2003 or equivalent;
БДС EN 60794 or equivalent;
IEEE Std 1138-2009 or equivalent;
БДС EN 60793-1 or equivalent

Optic cable type OPUG БДС EN 60794-1 or equivalent


Optic fibers БДС EN 60793-1 or equivalent;
Non-Zero Dispersion-Shifted Fiber, Rec
G655/ITU-T or equivalent;
EIA/TIA 598: Color Coding of Fiber
Optic Cables or equivalent
Slice box for optic cable БДС EN 60529:1991/AC:2016-12:2017
or equivalent;
HDPE tube БДС EN 12201-1:2011; БДС EN 12201-
2:2011 or equivalent
Fittings БДС EN 61284:2003 or equivalent;
БДС 6195-76 or equivalent
Polymeric insulator БДС EN 61109:2008 or equivalent;
БДС EN 62217:2013 or equivalent;
БДС HD 474 S1:2004 or equivalent;
БДС EN 60372:2006 or equivalent
Conductor БДС 1133-89 or equivalent;
БДС EN 1715-1:2008 or equivalent;
БДС EN 1715-2:2008 or equivalent;
БДС 5875-73 or equivalent
Steel ground wire БДС EN 12385 or equivalent;
БДС 16750:1988 or equivalent;
БДС EN 10264-1:2012 or equivalent;
БДС EN 10264-2:2012 or equivalent
Towers Sectoral standard Nº
0151737-83
0179782-87
БДС EN 10056:1999 or equivalent;
DIN 10026 or equivalent;
БДС EN 10025 or equivalent
Hot-dip galvanizing of БДС EN ISO 1461:2009 or equivalent;
metal structures БДС EN ISO 1461:2009/Revision
1:2014 or equivalent
Fittings (bolts, nuts, DIN 7990 or equivalent;
washers, and lock DIN 555 or equivalent;
washers) DIN1441 or equivalent;
DIN 127 or equivalent;
DIN 125 or equivalent
Concrete БДС EN 206:2013+A1:2016/NA:2017 or
equivalent;
БДС EN 12620:2002+A1:2008/NA:2017
or equivalent;
БДС EN 12390:2009 or equivalent
Spacers БДС EN 61854 or equivalent
Dampers БДС EN 61897:2003 or equivalent
HV Electric Shock Ordinance RD-07/8
Hazard sign

Note:
The materials must comply with the standards or their equivalents. It’s Tenderer’s
responsibility to provide a proof of equivalence, including compatibility with the requirements
of the specified standards.
Appendix 31

Main technical specifications of conductor type АСО-400


Employer’s Tenderer’s offer
#
Item requirement
2
1 Aluminum cross-section, mm = 391,95
2
2 Steel cross-section, mm = 49,48
2
3 Total cross-section , mm = 441,43

4 Conductor diameter, mm = 27,24

5 Steel diameter , mm = 9,00

6 Number of Al wires = 54

7 Diameter of Al wires, mm = 3.04

8 Number of steel wires =7

9 Diameter of steel wires , mm = 3.00


о
10 Resistance @ 20 С , Ω/кm ≤ 0,074

11 Breakdown stress, N ≥ 120,481

12 Weight, kg/km = 1,471

Notes:
Please complete the table with values according to БДС 1133-89 without referring to
tolerances.
Appendix 32

Main technical specifications of ground wire with outer dia Ø 11


# Item Employer’s Tenderer’s offer
requirement

1 Strength class of ground wire ≥ 1570


2 Outer diameter, mm = 11
3 Bundled (stranded) structure = 1x19
2
4 Rated cross-section of the metal part, mm = 70.7
2
5 Thickness of the zinc coating, g/m ≥ 230
6 Maximum breaking force, kN ≥ 99,9
7 Average weight, kg/100m = 58.7
Notes:
Please complete the table with values without referring to size tolerance.
Appendix 33
Main technical specifications of OPGW

# Item Unit Employer’s Tenderer’s offer


requirement
Diameter (max.) ≤ 11,4
mm
Material Aluminized
-
steel
Design:
- Central protection steel
tube pcs. =1
- Aluminized steel wires
=6
Weight (max.) ≤ 488
kg/km
Rated tensile strength (RTS) ≥ 77.7
kN
Ultimate pulling stress ≥ 33
kN
Young's modulus 2 ≥ 162
kN/mm
Linear expansion factor -6 0 ≤ 13
10 / K
Short-circuit current value for1 kA ≥ 5.5
0
s(20-200 C)
Linear DC resistance ≤ 1.247
Ω/km
Temperature limit 0 ≥ 200
C
Fiber type Non Zero Dispersion
Shifted Fiber, Rec
- G655/ITU-T or
equivalent

Optic fibers = 24
pcs.
Appendix 34
Main technical specifications of OPUG cable

# Item Unit Employer’s Tenderer’s


requirement offer

1 Outer diameter mm ≤ 15

2 Type of optic fiber - ITU-T G.655

3 Number of optic fibers pcs. 24

4 Hybrid type - Y

5 Central reinforcing element to allow pulling in - Y


HDPE tube

6 Water resistance - Y

7 Flame retardancy - Y

8 Cable sheath resistant to stiffening throughout - Y


its operational lifetime

9 Operating temperature °С -40 ÷ +70

10 Allowable pulling force N ≥ 1,500

11 Non-metal structure - Y
Appendix 35
Main technical specifications for polymeric insulator
Item Unit Employer’s Tenderer’s
#
requirements offer

1. - - -
Insulator materials:
1.1. - Epoxy reinforced with E-
- Core rod
CR fiber glass

1.2. - HTV silicone rubber


- Sheath, including sheds
1.3. - Elastomer (please specify)
- Seal (rubber-to-fitting interface)
2. kV ≥420
Maximum operating voltage
kN ≥160
Specified mechanical load (SML)
mm = 3200 ± 200
Overall length of insulator
- Y
Capacitive (corona) rings at both ends of
insulator (for field equalization)
mm = 2,950
Section length (distance between corona rings)

mm ≥10,500
Creepage distance
- Socket
Type of insulator-to-ground end fitting

- Ball
Type of insulator-to-current carrier fitting
mm = 20
Size of end fittings, БДС HD 474 S1:2004 (IEC
60120)
- HCR steel
Metal parts
- Hot-dip galvanized
- Galvanized
- Zinc coating thickness μm
≥80

кV ≥770
Power-frequency withstand voltage - wet
кV ≥1,425
Lightning impulse withstand voltage
with arc protection fittings

Arc protection rings - Hot-dip galvanized steel


Appendix 36
Main technical specifications of socket tongue for insulator string

# Item Unit Employer’s Tenderer’s offer


requirement

1 Connection size as per БДС HD 474 - = 20


S1:2004 (IEC 60120:1984 ) or
equivalent

2 Possibility to install an accessory - Yes


(horn, ring, etc.)

3 Clasping by lock pin as per БДС EN - W-20


60372:2006

4 Material - Malleable steel

5 Anticorrosive protection - Galvanization

6 Zinc coating thickness µm ≥ 80

7 Minimum tensile breaking strength kN ≥ 160

8 Short-time withstand current (for 1 кА ≥ 30


sec.)
Appendix 37

Main technical specifications of socket tongue for ground wire/OPGW

# Item Unit Employer’s Tenderer’s offer


requirement

1 Connection size as per БДС HD 474 - = 16


S1:2004 (IEC 60120:1984 ) or
equivalent

2 Possibility to install an accessory - No


(horn, ring, etc.)

3 Clasping by lock pin as per БДС EN - W-16


60372:2006

4 Material - Malleable steel

5 Anticorrosive protection - Galvanization

6 Zinc coating thickness µm ≥ 80

7 Minimum tensile breaking strength kN ≥ 120


Appendix 38

Main technical specifications of ball-eyes for insulator string

# Item Unit Employer’s Tenderer’s offer


requirement

1 Connection size as per БДС HD 474 - = 20


S1:2004 (IEC 60120:1984 ) or
equivalent

2 Possibility to install an accessory - Yes


(horn, ring, etc.)

3 Material - Malleable steel

4 Anticorrosive protection - Galvanization

5 Zinc coating thickness µm ≥ 80

6 Minimum tensile breaking strength kN ≥ 160

7 Short-time withstand current (for 1 кА ≥ 30


sec.)
Appendix 39

Main technical specifications of ball-eyes for ground wire/OPGW

# Item Unit Employer’s Tenderer’s offer


requirement

1 Connection size as per БДС HD 474 - = 16


S1:2004 (IEC 60120:1984 ) or
equivalent

2 Possibility to install an accessory - No


(horn, ring, etc.)

3 Material - Malleable steel

4 Anticorrosive protection - Galvanization

5 Zinc coating thickness µm ≥ 80

6 Minimum tensile breaking strength kN ≥ 120


Appendix 40

Main technical specifications of clevis for insulator string

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Steel

2 Anticorrosive protection - Galvanization

3 Zinc coating thickness µm ≥ 80

4 Minimum tensile breaking strength for kN ≥ 160


clevis of single tension string

5 Minimum tensile breaking strength for kN ≥ 480


clevis of triple tension string for angular
tower (type СЪЕВ)

6 Minimum tensile breaking strength for kN ≥ 160


clevis of triple tension string

7 Short-time withstand current (for 1 sec.) кА ≥ 30

Note:
Connection sizes of clevises are fixed and specified in the Specifications under section
“Fittings for insulator strings”.
Appendix 41

Main technical specifications of clevis for ground wire

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Steel

2 Anticorrosive protection - Galvanization

3 Zinc coating thickness µm ≥ 80

4 Minimum tensile breaking strength for kN ≥ 120


clevis of single tension string (ЕО1)

Note:
Connection sizes of clevises are fixed and specified in the Specifications under section
“Fittings for insulator strings”.
Appendix 42

Main technical specifications of U-bolt

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Steel

2 Anticorrosive protection - Galvanization

3 Zinc coating thickness µm ≥ 80

4 Minimum tensile breaking strength kN ≥ 160

5 Short-time withstand current (for 1 sec.) кА ≥ 30

Note:
U-bolt-to-tower connection sizes are fixed and specified in drawings № D104-01C3-04-0A
and № D104-01C3-03-0A.
Appendix 43

Main technical specifications of tension clamp for conductor type АСО-400

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - Press

2 Material - Al/Al alloy, steel

3 Anticorrosive protection of metal parts - Galvanization

4 Zinc coating thickness µm ≥ 80

5 Minimum tensile breaking strength kN ≥ 114.5

6 For conductor with outer diameter mm = 27.2

7. Number of bolt joints used to fasten pcs. ≥2


cable heads

8 Short-time withstand current (for 1 sec.) кА ≥ 30


Appendix 44

Main technical specifications of span coupler for АСО-400

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - Press

2 Material of core - Steel

3 Material of outer part - Aluminum

4 Minimum tensile breaking strength kN ≥ 114.5

5 For conductor with outer diameter mm = 27.2

6 Short-time withstand current (for 1 sec.) кА ≥ 30


Appendix 45

Main technical specifications of suspension clamp for conductor type АСО-400

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Aluminum/aluminu
m alloy, steel

2 Anticorrosive protection of metal parts - Galvanization

3 Zinc coating thickness µm ≥ 80

4 For conductor with outer diameter mm = 27.2

5 Minimum breakdown force kN ≥ 85

6 Conductor slippage force (20% of RTS) kN = 24

7 Short-time withstand current (for 1 sec.) кА ≥ 30


Appendix 46

Main technical specifications of tension clamp for ground wire

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - Sleeve

2 Anticorrosive protection of steel parts - Galvanization


(shackle)

3 Zinc coating thickness µm ≥ 80

4 Minimum tensile breaking strength kN ≥ 94.9

5 For ground wire with outer diameter mm = 11


Appendix 47

Main technical specifications of swing suspension clamp for ground wire

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Malleable steel

2 Anticorrosive protection of metal parts - Galvanization

3 Zinc coating thickness µm ≥ 80

4 For ground wire with outer diameter mm = 11

5 Minimum breakdown force kN ≥ 55

6 Ground wire slippage force (20% of kN = 20


RTS)

Note:
Connection sizes of swing suspension clamps are fixed and specified in detail drawing №
D104-01C3-08-0A.
Appendix 48

Main technical specifications of span coupler for ground wire

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - Sleeve

2 Minimum tensile breaking strength kN ≥ 94.9

3 For ground wire with outer diameter mm = 11


Appendix 49

Main technical specifications of tension clamp for OPGW

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - Sleeve clamp

2 Anticorrosive protection of steel parts - Galvanization


(shackle)

3 Zinc coating thickness µm ≥ 80

4 Minimum tensile breaking strength kN ≥ 73.8

5 For OPGW with outer diameter mm ≤ 11.4


Appendix 50

Main technical specifications of suspension clamp for OPGW

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of clamp - With neoprene pad


and holding sleeve

2 Anticorrosive protection of metal parts - Galvanization

3 Zinc coating thickness µm ≥ 80

4 Minimum breakdown stress for kN ≥ 55


suspension clamp

5 OPGW slippage force (20% of RTS) kN 15

6 For OPGW with outer diameter mm ≤ 11.4


Appendix 51

Main technical specifications of C-link

# Item Unit Employer’s Tenderer’s offer


requirement

1 Material - Steel / Cast-iron

2 Anticorrosive protection - Galvanization

3 Zinc coating thickness µm ≥ 80

4 Minimum axial load capacity* kN 20


kN
5 Minimum vertical load capacity* 50
kN
6 Minimum transversal load capacity* 30

Note:

1. Loads marked with “*“ are applied to the suspension-string-to-link attachment point.
2. Connection sizes of C-link are fixed and specified in the Technical Specifications
under section “Fittings for insulator strings”.
Appendix 52

Main technical specifications of OPGW/OPUG junction box

# Item Unit Employer’s Tenderer’s offer


requirement

1 Number of inputs pcs. ≥4

2 Number of fibers in 1 junction box pcs. ≥ 72

3 Material - Stainless steel/alloy

4 Protection rating - IP 56

0
5 Ambient temperature C - 40 ÷ + 70

6 Fastening - Without drilling


holes in tower

7 Cover - Cast, dome type


Appendix 53

Main technical specifications of conductor spacers

# Item Unit Employer’s Tenderer’s offer


requirement

1 Type of spacer - Damper

2 Fastening method - Bracket

3 Material - Al alloy, steel,


rubber

4 Anticorrosive protection of steel parts - Galvanization

5 Zinc coating thickness µm ≥ 80

6 Distance between subconductors mm 400

7 Outer diameter of spaced conductors mm 27.2

8 For number of subconductors in pcs. 3


bundle - for spacers in span

9 For number of conductors in bundle - pcs. 2


for spacers in jumper
Drawings

TABLE OF CONTENTS

Section 1: Information
Section 2: List of Drawings

Section 1: INFORMATION

1. INTRODUCTION

The route of the 400 kV Overhead Transmission Line between TPP Maritsa Iztok 2 (s/st MI)
and s/st Plovdiv–on the territory of the Republic of Bulgaria, has been determined by ESO
EAD in details and all tower sites have been marked. The total length of 400 кV OHTL is
92.985 km.

2. SHORT DESCRIPTION
2.1. TOWERS

The towers to be used for construction of the 400 kV line are designed for ACO-400 type
conductors consisting of three single wires per bundle, bolted design with hot-dip galvanized
coating for anticorrosive protection in accordance with БДС EN ISO 1461:2009 or equivalent.
Steel grades S355J0 and S235J0 as per БДС EN 10025-2 are used for different details of the
new towers to enable structural optimization. The following tower structures are used:
• CHД1 - suspension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and two ground wires C-70). It is used for normal weight and
wind conditions and its outline is shown in drawing № Dl04-01F1-01-0A;
• CHД2 - suspension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and two ground wires C-70). This is a more heavy-duty tower
compared to CHДl and its outline is shown in drawing № D104-01F2-01-0A;
• CEH1,2 - suspension tower for one or two bundle conductors ACO-400. It ensures
the necessary vertical clearances to crossing infrastructure where a suspension point higher
than 32 m is required. Its outline is shown in drawing № D104-01F5-01-0A;
• 20.NN - angle tension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and two ground wires C-70). Its outline is shown in №
D104- 0lF3-01-0A;
• 60.NN - angle tension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and two ground wires C-70). Its outline is shown in drawing №
D104-01F4-01-0A.
In addition to the above structures, the existent towers of 400 кV Vezhen OHTL are also used
as follows:
• 70.NN - angle tension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and two ground wires C-70) with existent numeration 453A;
• 70.N - angle tension structure for conductors 1x3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and one ground wire C-70) with existent numeration 448А;
• 20.N - angle tension structure for conductors lx3x3ACO 400 + 2xC-70 (one triad of
bundle conductors ACO-400 and one ground wire C-70) with existent numeration 445A,
446A, 447A, and 45lA;
• СЕН2 - suspension structure for two bundle conductors ACO-400 with existent
numeration 445 A,B and 446A,В;
• lH.M - suspension tower for two triads of bundle conductors ACO-400 and two ground
wires C-70 with existent numeration 452.
The same will be reused and positions #311,312 and 485 of tower 445A will be replaced
along with their bolted connections. These are shown in drawing № D104-01F6-01-0A. The
total weight of new structure profiles is 91.5 kg inclusive of fittings.
The weights of new structures to be used to build the line are specified in Appendix 2. The
weight of shaped steel elements and reinforcement fittings for tower 445A are specified in the
Bill of Quantity for the new 400 kV OHTL.
Appendix 3 indicates the new towers distribution on the line route.
All towers shall be corrosion protected, following the instructions of the Anticorrosion
protection system for new steel-lattice towers.

2.2. CONDUCTORS AND EARTH WIRES


2.2.1. Conductors
A triad of bundle ACO-400 with electromechanical properties according to EIC 1133-89 or
equivalent shall be installed. The required quantity is specified in Appendix 4.
Single sub conductors in bundle shall be spaced at 400 mm from each other and in an
equilateral triangle arrangement. Their equidistant positions in the span shall be ensured by
means of triple spacer dampers whose indicative distribution and number in a span are
shown in Appendix 5. Double spacer dumpers shall be used for jumper conductors.
The new line conductors shall be pulled using the mechanical stress method according to
IECTR 61328 and IEC TR 62263-2005 or their equivalents. All machinery, equipment,
facilities and safety gear must conform to the above standards and enable flawless conductor
installation. It is not allowed to deploy conductors in a random tension section on the ground.
Conductor installation shall be carried out by running a lead cable through the entire tension
section and then pulling the bundle conductor attached to the end of lead cable. All three sub
conductors in bundle shall be pulled simultaneously and applying the same tensile force. A
set of pulling machines designed to strain three or more conductors simultaneously shall be
used for this purpose. It is not allowed for a bundle to touch the ground or crossing
infrastructure while being pulled and strain adjusted as well as to exceed the rated tensile
force of its particular tension section. For precise adjustment of roller supports suspended on
towers, they shall be mounted at the same level as suspension and tension clamps to which
the conductor will be attached.
Redundant conductor that remains wound on the drum after installation shall be used to make
jumpers on tension structures instead of being installed in line sections.
Conductor adjustment shall be made as prescribed in the relevant straining tables for the
weather conditions specified in the longitudinal profile.
The phasing diagram of the new power line is shown in drawing № D104-01C3-I2-0A.

2.2.2. Optic power ground wire (OPGW)


Surge protection of the new 400 kV OHTL will be provided by two ground wires, one of which
is type OPGW with properties specified in clause 5.3.3 of the Plants and Materials
specification.
Appendix 6 shows the tension sections for fiber optic cable installation with corresponding
allowances for sagging and attachment. Stockbridge dampers of quantity specified in
Appendix 7 will protect the fiber optic cable against vibrations. The specific shipment of
dampers as per selected fiber optic cable shall be delivered with an installation manual to be
approved by Employer.
The optic cable pulling and installation routine is similar to that for conductors, with additional
attention being paid to ensure that the contact surfaces of all installation gear and machinery
do not come into metal touch with the cable. They shall have appropriate silicone or other
insulation coating that shall be replaced in due course before it gets worn out and its
operational lifetime has elapsed. This requires that Contractor has and uses efficient devices
to earth the cable while being pulled.
During installation, no less than the minimum admissible bending radius specified by the
manufacturer shall be applied.
To verify that the optic fibers are left intact after installation, it is necessary to terminate the
optic cable at both end substations and measure the signal attenuation along the route from
both sides.
Acceptable attenuations :
- 0.06 dB (average) and 0,15 dB (max) at junction box;
- 0.25 dB/km along the route @ 1550 nm, 200C.
Individual fiber attenuations shall not differ by more than 0.02 dB/km.

2.2.3. Steel ground wire


The second ground wire is a steel one, with mechanical properties as specified in clause
5.3.2 of the Plant and Materials specification, and its conditional identification is C-70. The
pulling and installation routine is quite similar to that for conductors and the required
quantities are indicated in Appendix 8.

2.2.4. Fiber optic cable and optical connectivity


The fiber type (OPUG) shall be the same as that of OPGW. Optical connectivity of the ground
wire from its corresponding bay gantry tower of the new 400 kV OHTL to line equipment room
(LER) in the relevant substation shall be provided via fiber optic cable with properties as
described in clause 5.4. The ground wire shall be connected to the fiber optic cable through
an OPGW-OPUG junction box mounted 5.50-6.00 meters above terrain level on the column
next to the optic cable suspension. A 32- millimeter high density polyethylene (HDPE) flexible
protection pipe shall protect the entire fiber optic cable.
Drawing № Dl04-01Cl-04-0A represents the optic cable routing layout in the 400 kV
switchyard of Plovdiv s/s. The corresponding layout in Maritsa Iztok s/s is given in drawing №
D104-01C1-05-0A.
Specific routing requirements are described in the detailed design; the bill of quantity specifies
the necessary equipment for optical connectivity in terms of nomenclature and quantities.

2.3. INSULATOR SETS AND LINE EQUIPMENT


Line insulation shall be implemented using polymeric insulators with tensile strength of not
less than 160 kN. This applies to both suspension and tension strings. The complete set of
unit insulators in the strings is defined in accordance with rated safety factors for the relevant
sizing conditions. Rings and/or horns will be installed to distribute the magnetic field and lead
any discharge away from the string.
The applicable technical characteristics for unit insulators are set out in the Plant and
Materials specification.
The following complete sets of insulator strings are used for the new 400 kV OHTL:
• Single suspension insulator string designed to bypass the conductors around the
body of tension towers, complete with 2x25 kg of weights. It is shown in drawing
D104-01C3-04-04;
• Single suspension insulator string for special suspension towers. This string is similar
to the above one but has no weights attached to it;
• V-suspension insulator string for suspension towers type CHД. It is shown in drawing
№ D104-01C3-03-0A;
• Single and double tension insulator string. This one is used for tension towers in
approaches to end substations. It is shown in drawing № D104-01C3-01-0A;
• Triple tension insulator strings for tension towers along the line route. It is shown in
drawing № D104-01C3-02-0A.
The required quantities per string type are specified in Appendix 9.

The fittings for the completion of the insulator sets will be in accordance with the approved
practice in Bulgaria:
• Suspension clamps for phase conductor and earthwire C-70 – of “dead line” type;
• Tension clamps and joints for phase conductors - of compression type
• Tension clamps and joints for earthwire C-70 - spiral type;
Tension clamps for earthwire OPGW type - spiral type;
Pursuant to the approved and effective Environmental Impact Assessment Report (EIAR), it is
necessary to install bird (stork) guards above all suspension strings as well as bird diverters
along the steel ground wire.
The bird guard design is shown in drawing № D104-03C3-08-0A.
Bird diverters shall be installed on the steel ground wire at distances of 20 m along the spans
between towers 57 and 68.

2.4. INFORMATIONS FOR TOWERS, FOUNDATIONS, EARTHING, CROSSINGS….

Those information’s are shown in the Аppendices listed below and are part of Tender
Documentation:
Appendix 1 - Quantity of Materials for New Tower Foundations
Appendix 2 - Quantity of steel and fittings for the new towers
Appendix 3 - Distribution of new towers on the line route
Appendix 4 - Quantity of Conductor ACO-400
Appendix 5 – Distribution of spacers in span
Appendix 6 - Quantity of OPGW
Appendix 7 - Quantity of Spacers for OPGW
Appendix 8 - Quantity of C-70
Appendix 9 - Quantity of Conductor and Ground Wire Fittings
Appendix 10 - Crossing infrastructure
Appendix 11 - Type of tower earthing system
Appendix 1

QUANTITY OF MATERIALS IN NEW TOWER FOUNDATION

foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
1 20.28.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
2 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
3 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
4 СНД1 Ф4 50% water uptake 1:0.3 36,20 120,00 10,00 84,00 36,00
5 СНД2+3 Ф6 50% water uptake 1:0.3 51,00 148,00 10,00 97,00 51,00
6 СНД1 Ф4 50% water uptake 1:0.3 36,20 120,00 10,00 84,00 36,00
7 20.22.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
8 СНД1-3 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
9 20.19.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
10А СЕН 1 +12 Ан Stiff soil 1:0.75 22,00 248,30 10,00 226,30 22,00
10B СЕН 2 +12 Ан Stiff soil 1:0.75 22,00 248,30 10,00 226,30 22,00
11 20.28.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
12 60.25.NN Ф3/Ф7 Stiff soil 1:0.3 49,10 211,00 10,00 162,00 49,00
13 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
14 20.25.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
15 СНД2+6 Ф3 Stiff soil 1:0.75 30,20 165,00 10,00 135,00 30,00
16 СНД2+6 Ф3 Stiff soil 1:0.75 30,20 165,00 10,00 135,00 30,00
17 СНД2+6 Ф3 Stiff soil 1:0.75 30,20 165,00 10,00 135,00 30,00
18 СНД2+3 Ф5 50% water uptake 1:0.75 43,00 193,00 10,00 150,00 43,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
19 СНД2+3 Ф5 50% water uptake 1:0.75 43,00 193,00 10,00 150,00 43,00
20 20.28.NN Ф2 50% water uptake Reinforcement 42,50 202,20 10,00 160,20 42,00
21 СНД2+6 Ф3 Stiff soil 1:0.75 30,20 165,00 10,00 135,00 30,00
22 20.22.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
23 СНД1-6 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
24 20.19.NN Ф1 Stiff soil 1:0.75 32,40 325,50 10,00 293,10 32,00
25 СНД2 +3 Ф3 Stiff soil 1:0.75 30,20 165,00 10,00 135,00 30,00
26 60.28.NN Ф1/Ф6 Stiff soil 1:0.75 24,00 240,00 10,00 216,00 24,00
27 СНД1-3 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
28 СНД1-3 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
29 60.19.NN Ф1/Ф6 Stiff soil 1:0.75 24,00 240,00 10,00 216,00 24,00
30 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
31 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
32 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
33 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
34 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
35 СНД2+3 Ф3 Stiff soil 1:0.75 30,20 139,00 10,00 119,00 30,00
36 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
37 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
38 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
39 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
40 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
41 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
42 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
43 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
44 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
45 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
46 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
47 СНД2+6 Ф6 50% water uptake Reinforcement 51,00 152,00 10,00 101,00 51,00
48 СНД2+6 Ф6 50% water uptake Reinforcement 51,00 152,00 10,00 101,00 51,00
49 20.25.NN Ф2 50% water uptake Reinforcement 42,50 202,20 10,00 160,20 42,00
50 СНД1 Ф3 50% water uptake Reinforcement 30,20 109,00 10,00 79,00 30,00
51 СНД1-3 Ф3 50% water uptake Reinforcement 30,20 109,00 10,00 79,00 30,00
52 СНД1 Ф3 50% water uptake Reinforcement 30,20 109,00 10,00 79,00 30,00
53 СНД1 Ф3 50% water uptake Reinforcement 30,20 109,00 10,00 79,00 30,00
54 СНД2+3 Ф6 50% water uptake Reinforcement 51,00 152,00 10,00 101,00 51,00
55 СНД1 Ф3 50% water uptake Reinforcement 30,20 137,00 10,00 94,00 30,00
56 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
57 СНД1-3 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
58 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
59 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
60 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 66,00 25,00
61 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 66,00 25,00
62 20.22.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
63 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
64 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
65 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
66 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
67 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
68 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
69 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
70 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
71 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
72 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
73 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
74 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
75 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
76 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
77 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
78 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
79 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
80 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
81 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
82 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
83 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
84 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
85 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
86 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
87 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
88 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
89 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
90 20.22.NN Ф3 Stiff soil 1:0.25 45,80 227,20 10,00 181,40 45,00
91 СНД1-6 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
92 СНД1-3 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
93 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
94 СНД1 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
95 СНД1-6 Ф1 Stiff soil 1:0.75 20,60 139,00 10,00 119,00 20,00
96 60.22.NN Ф2/Ф6 Stiff soil 1:0.25 32,70 158,00 10,00 126,00 32,00
97 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
98 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
99 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
100 СНД2+6 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
101 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
102 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
103 СНД2+3 Ф3 Stiff soil 1:0.25 30,20 102,00 10,00 72,00 30,00
104 20.25.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
105 СНД2+3 Ф3 Stiff soil 1:0.3 30,20 108,00 10,00 78,00 30,00
106 СНД1-3 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
107 СНД1-3 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
108 СНД1-3 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
109 20.28.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
110 СНД2+6 Ф3 Stiff soil 1:0.3 30,20 108,00 10,00 78,00 30,00
111 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
112 СНД2+3 Ф3 Stiff soil 1:0.3 30,20 108,00 10,00 78,00 30,00
113 СНД2+3 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
114 СНД2+6 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
115 СНД2+3 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
116 СНД2+3 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
117 СНД2+3 Ф3 Stiff soil 1:0.3 30,20 108,00 10,00 78,00 30,00
118 СНД2+3 Ф3 Stiff soil 1:0.3 30,20 108,00 10,00 78,00 30,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
119 20.25.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
120 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
121 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
122 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
123 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
124 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
125 СНД1 Ф1 Stiff soil 1:0.3 20,60 85,00 10,00 65,00 20,00
126 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
127 20.25.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
128 СНД1 Ф6 Stiff soil 1:0.3 51,00 148,00 10,00 97,00 51,00
129 СНД1 Ф6 Stiff soil 1:0.3 51,00 148,00 10,00 97,00 51,00
130 СНД1 Ф6 Stiff soil 1:0.3 51,00 148,00 10,00 97,00 51,00
131 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
132 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
133 СНД1 Ф6 Stiff soil 1:0.3 51,00 148,00 10,00 97,00 51,00
134 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
135 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
136 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
137 20.25.NN Ф2 Stiff soil 1:0.3 42,50 232,30 10,00 189,80 42,00
138 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
139 СНД1 Ф5 Stiff soil 1:0.3 43,00 134,00 10,00 91,00 43,00
140 СНД1 Ф5 Stiff soil 1:0.3 43,00 125,00 10,00 91,00 43,00
141 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
142 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
143 СНД1 Ф5 Stiff soil 1:0.3 51,00 134,00 10,00 91,00 51,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
144 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
145 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
146 СНД2+3 Ф7 Stiff soil 1:0.3 59,80 162,00 10,00 103,00 59,00
147 20.25.NN Ф6 Stiff soil 1:0.3 70,10 279,70 10,00 209,60 70,00
148 СНД2+6 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
149 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
150 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
151 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
152 СНД2+3 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
153 20.25.NN Ф3 Stiff soil 1:0.25 45,80 227,20 10,00 181,40 45,00
154 60.28.NN Ф3/Ф6 Stiff soil 1:0.3 45,50 203,00 10,00 158,00 45,00
155 60.25.NN Ф4/Ф7 Stiff soil 1:0.3 56,30 224,00 10,00 168,00 56,00
156 СНД2+6 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
157 СНД2+6 Ф4 Stiff soil 1:0.3 36,20 120,00 10,00 84,00 36,00
158 20.25.NN Ф2 50% water uptake Reinforcement 42,50 202,20 10,00 160,20 42,00
159 СНД1 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
160 СНД1-6 Ф2 Stiff soil 1:0.3 25,00 95,00 10,00 70,00 25,00
161 20.19.NN Ф4 50% water uptake Reinforcement 49,30 224,00 10,00 175,00 49,00
162 СНД1-3 Ф1 Stiff soil Reinforcement 20,60 84,00 10,00 64,00 20,00
163 20.22.NN Ф2 50% water uptake Reinforcement 42,50 202,20 10,00 160,20 42,00
164 СНД2+3 Ф3 Stiff soil Reinforcement 30,20 109,00 10,00 79,00 30,00
165 20.25.NN Ф2 50% water uptake Reinforcement 42,50 202,20 10,00 160,20 42,00
166 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
167 СНД1 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
168 СНД1-3 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
169 СНД1-3 Ф1 Stiff soil 1:0.25 20,60 80,00 10,00 60,00 20,00
170 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
171 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
172 СНД1-6 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
173 20.19.NN Ф4 Stiff soil 1:0.25 49,30 238,50 10,00 189,20 49,00
174 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
175 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
176 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
177 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
178 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
179 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
180 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
181 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
182 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
183 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
184 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
185 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
186 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
187 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
188 60.28.NN Ф3/Ф6 Stiff soil 1:0.25 45,50 191,00 10,00 146,00 45,00
189 20.28.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
190 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
191 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 66,00 25,00
192 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 66,00 25,00
193 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
194 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
195 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
196 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
197 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
198 20.22.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
199 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
200 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
201 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
202 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
203 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
204 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
205 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
206 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
207 20.25.NN Ф3 50% water uptake Reinforcement 45,80 213,00 10,00 168,00 45,00
208 СНД1-6 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
209 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
210 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
211 СНД1-6 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
212 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
213 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
214 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
215 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
216 20.19.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
217 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
218 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
219 СНД2 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
220 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
221 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
222 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
223 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
224 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
225 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
226 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
227 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
228 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
229 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
230 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
231 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
232 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
233 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
234 20.28.NN Ф3 Stiff soil 1:0.25 45,80 227,20 10,00 181,40 45,00
235 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
236 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
237 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
238A СЕН 1 +20 Aн Stiff soil 1:0.25 22,00 75,20 10,00 64,20 11,00
238B СЕН 2 +20 Aн Stiff soil 1:0.25 22,00 75,20 10,00 64,20 11,00
239 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
240 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
241 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
242 20.25.NN Ф2 Stiff soil 1:0.25 42,50 216,10 10,00 173,60 42,00
foundation pit,

spread./transp
3
Water uptake,

Backfilling, m
3
Slope grade
Foundation

Foundation
Tower type

concrete, m

2
plaster, m
Cement

3
Tower

ort, m
type

Soil
3
%
#

m
243 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
244 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
245 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
246 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
247 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 66,00 25,00
248 СНД1 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
249 СНД1-3 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
250 20.19.NN Ф3 Stiff soil 1:0.25 45,80 227,20 10,00 181,40 45,00
251 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
252 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
253 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
254 60.25.NN Ф4/Ф7 Stiff soil 1:0.25 56,30 217,00 10,00 161,00 56,00
255 СНД2+3 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
256 СНД2+6 Ф4 Stiff soil 1:0.25 36,20 115,00 10,00 79,00 36,00
257 СНД1-6 Ф2 Stiff soil 1:0.25 25,00 90,00 10,00 65,00 25,00
258 20.25.NN Ф5 Stiff soil 1:0.25 58,40 245,20 10,00 186,80 58,00
259A СЕН 1 +12 Вн 100% water uptake Reinforcement 32,20 161,70 10,00 129,50 32,20
259B СЕН 2 +12 Вн 100% water uptake Reinforcement 32,20 161,70 10,00 129,50 32,20
260 60.25.NN Ф4/Ф8 100% water uptake 1:0.25 67,00 243,00 10,00 176,00 67,00
TOTAL: 8 709,30 35 268,50 2 630,00 26 651,20 8 621,40
Appendix 2

QUANTITY OF STEEL AND FITTINGS FOR THE NEW TOWERS

Total weight,

Total weight,
single tower,

single tower,
foundations,

foundations,
Tower type

Tower type
Weight of

Weight of
Weight in

Weight in
Bolts,

Bolts,
pcs.

pcs.
kg

kg

kg

kg

kg

kg

kg

kg
#

#
1 20.19.NN 6 13 105,94 954,85 608,50 88 015,73 1 СНД1 93 9 392,12 314,50 265,70 927 425,76
2 20.22.NN 6 14 656,31 954,85 668,60 97 678,53 2 СНД1-3 18 8 583,12 314,50 246,50 164 594,12
3 20.25.NN 19 16 290,63 954,85 728,70 341 509,42 3 СНД1-6 8 8 138,61 314,50 234,30 69 499,26
4 20.28.NN 6 18 026,54 954,85 785,10 118 598,95 4 СНД2 9 10 054,30 366,80 266,80 96 191,11
5 60.19.NN 1 14 630,83 1 110,00 656,90 16 397,73 5 СНД2+3 61 10 706,19 366,80 286,50 692 928,89
6 60.22.NN 1 16 414,70 1 110,00 712,10 18 236,80 6 СНД2+6 22 11 524,10 366,80 300,80 268 217,33
7 60.25.NN 4 18 282,53 1 110,00 773,20 80 662,93 7 СЕН 1 +12 2 12 041,46 988,86 451,20 26 963,04
8 60.28.NN 3 20 257,49 1 110,00 826,50 66 581,96 8 СЕН 2 +12 2 12 496,31 988,86 470,40 27 911,15
TOTAL FOR TENSION TOWERS: 827 682,06 9 СЕН 1 +20 1 15 061,49 988,86 535,60 16 585,95
10 СЕН 2 +20 1 15 516,34 988,86 554,80 17 060,01
TOTAL FOR SUSPENSION TOWERS: 2 307 376,62

GRAND TOTAL
Total quantity of steel for suspension towers, kg: 2 307 376,62
Total quantity of steel for tension towers, kg: 827 682,06
Total quantity of steel for construction site, kg: 3 135 058,67
Appendix 3

DISTRIBUTION OF NEW TOWERS ON THE LINE ROUTE

# Tower type # Tower type # Tower type # Tower type # Tower type # Tower type # Tower type
1 20.28.NN 31 СНД1 61 СНД1 91 СНД1-6 121 СНД1 151 СНД1 181 СНД2+6
2 СНД1 32 СНД1 62 20.22.NN 92 СНД1-3 122 СНД1 152 СНД2+3 182 СНД2+6
3 СНД1 33 СНД1 63 СНД2+3 93 СНД1 123 СНД1 153 20.25.NN 183 20.25.NN
4 СНД1 34 СНД1 64 СНД1 94 СНД1 124 СНД1 154 60.28.NN 184 СНД1
5 СНД2+3 35 СНД2+3 65 СНД1 95 СНД1-6 125 СНД1 155 60.25.NN 185 СНД1
6 СНД1 36 СНД1 66 СНД1 96 60.22.NN 126 СНД1 156 СНД2+6 186 СНД1
7 20.22.NN 37 СНД1 67 СНД1 97 СНД2+3 127 20.25.NN 157 СНД2+6 187 СНД2
8 СНД1-3 38 20.25.NN 68 СНД1 98 СНД2+3 128 СНД1 158 20.25.NN 188 60.28.NN
9 20.19.NN 39 СНД1 69 СНД2+3 99 СНД1 129 СНД1 159 СНД1 189 20.28.NN
10A,
B СЕН 1, 2 +12 40 СНД2+3 70 СНД2 100 СНД2+6 130 СНД1 160 СНД1-6 190 СНД1
11 20.28.NN 41 СНД1 71 СНД1 101 СНД1 131 СНД2+3 161 20.19.NN 191 СНД1
12 60.25.NN 42 СНД2+3 72 20.25.NN 102 СНД2+3 132 СНД2+3 162 СНД1-3 192 СНД1
13 СНД1 43 СНД2+3 73 СНД2 103 СНД2+3 133 СНД1 163 20.22.NN 193 СНД2+3
14 20.25.NN 44 СНД2+3 74 СНД1 104 20.25.NN 134 СНД1 164 СНД2+3 194 СНД2
15 СНД2+6 45 СНД2+3 75 СНД1 105 СНД2+3 135 СНД1 165 20.25.NN 195 СНД2+3
16 СНД2+6 46 СНД1 76 СНД1 106 СНД1-3 136 СНД1 166 СНД1 196 СНД2+3
17 СНД2+6 47 СНД2+6 77 СНД1 107 СНД1-3 137 20.25.NN 167 СНД1 197 СНД1
18 СНД2+3 48 СНД2+6 78 СНД1 108 СНД1-3 138 СНД1 168 СНД1-3 198 20.22.NN
19 СНД2+3 49 20.25.NN 79 СНД2 109 20.28.NN 139 СНД1 169 СНД1-3 199 СНД1
20 20.28.NN 50 СНД1 80 СНД2 110 СНД2+6 140 СНД1 170 СНД1-3 200 СНД1

21 СНД2+6 51 СНД1-3 81 20.25.NN 111 СНД1 141 СНД2+3 171 СНД1 201 СНД1

22 20.22.NN 52 СНД1 82 СНД1 112 СНД2+3 142 СНД2+3 172 СНД1-6 202 СНД1

23 СНД1-6 53 СНД1 83 СНД1 113 СНД2+3 143 СНД1 173 20.19.NN 203 СНД2+3
24 20.19.NN 54 СНД2+3 84 СНД2+3 114 СНД2+6 144 СНД2+3 174 СНД1-3 204 СНД2+3
# Tower type # Tower type # Tower type # Tower type # Tower type # Tower type # Tower type
25 СНД2 +3 55 СНД1 85 СНД2 115 СНД2+3 145 СНД2+3 175 СНД1 205 СНД1
26 60.28.NN 56 СНД1 86 СНД1 116 СНД2+3 146 СНД2+3 176 СНД2+3 206 СНД1
27 СНД1-3 57 СНД1-3 87 СНД2 +3 117 СНД2+3 147 20.25.NN 177 СНД2+3 207 20.25.NN
28 СНД1-3 58 СНД1-3 88 СНД2+3 118 СНД2+3 148 СНД2+6 178 СНД2+6 208 СНД1-6
29 60.19.NN 59 20.25.NN 89 СНД2+3 119 20.25.NN 149 СНД1 179 СНД2+6 209 СНД1
30 СНД1 60 СНД1 90 20.22.NN 120 СНД1 150 СНД1 180 СНД1 210 СНД1

# Tower type # Tower type


211 СНД1-6 240 СНД2+3 Tension Suspension
212 СНД1 241 СНД2+3 Tower type pcs. Tower type pcs.
213 СНД1 242 20.25.NN 20.19.NN 6 СНД1 93
214 СНД2+3 243 СНД2+6 20.22.NN 6 СНД1-3 18
215 СНД1 244 СНД2+3 20.25.NN 19 СНД1-6 8
216 20.19.NN 245 СНД2+6 20.28.NN 6 СНД2 9
217 СНД1-3 246 СНД2+3 60.19.NN 1 СНД2+3 61
218 СНД2 247 СНД1-3 60.22.NN 1 СНД2+6 22
219 СНД2 248 СНД1 60.25.NN 4 СЕН 1 +12 2
220 СНД2+3 249 СНД1-3 60.28.NN 3 СЕН 2 +12 2
221 СНД1 250 20.19.NN СЕН 1 +20 1
222 СНД2+3 251 СНД2+3 СЕН 2 +20 1
223 СНД2+3 252 СНД2+3 Total tension towers: 46 Total suspension towers: 217
СНД1 253 СНД2+3
224 Total number of towers for the constriction site: 263
СНД1 254 60.25.NN
225
20.25.NN 255 СНД2+3
226
СНД1 256 СНД2+6
227
СНД2+6 257 СНД1-6
228
СНД2+3 258 20.25.NN
229
259A,
СНД2+3 B СЕН 1, 2 +12
230
# Tower type # Tower type # Tower type # Tower type # Tower type # Tower type # Tower type
231 СНД1 260 60.25.NN
232 СНД2+6
233 СНД2+3
234 20.28.NN
235 СНД2+3
236 СНД1
237 СНД2+3
238 СЕН 1, 2 +20
239 СНД2+6
Appendix 4

QUANTITY OF CONDUCTOR АСО-400

1. Conductor АСО-400
Length of OHTL from line gantry of Plovdiv s/s to Maritsa Iztok s/s 92 985 m
From tower 453В to line gantry of Plovdiv s/s 48 m
Total length: 93 033 m
Number of phase conductors per OHTL: 3 бр.
Number of subconductors in bundle per phase: 3 бр.
Percentage of the length for sags and jumpers 3%
Total length of single conductor ACO-400 to be delivered: 862 416 m
Appendix 5
DISTRIBUTION OF SPACERS IN SPAIN

SPACERS PER SPAN SPACERS PER JUMPER


Span, m Spacers, pcs. Length of jumper, m Spacers, pcs.
100 - 149 3 10.0 – 15.0 3
150 - 199 4 15.1 – 20.0 4
200 - 249 5 20.1 – 25.0 5
250 - 299 6 25.1 – 30.0 6
300 - 349 7 30.1 – 35.0 7
350 - 399 8 35.1 – 40.0 8
400 - 449 9 40.1 – 45.0 9
450 - 499 10 45.1 – 50.0 10
500 - 549 11
550 - 599 12
600 - 659 13
660 - 719 14
720 - 779 15
Appendix 6

QUANTITY OF OPGW
Wound
Tension
from Section 3% for Process Total length Type of Towers on which junction boxes
section to tower # Drum Nº
tower # length,m sag, m allowance length, m (on OPGW will be installed

drum), m
Gantry of
1 48 80
Plovdiv 453 50 130
2 453 451 204 220 150 370
3 451 448 709 740 150 890 Gantry of Plovdiv s/s
3 350 1
4 448 447 264 280 150 430 Tower 445А
5 447 446 398 410 150 560
6 446 445А 307 320 150 470
7 445A 1 335 350 150 500
8 1 7 2 265 2 340 150 2 490
9 7 9 630 650 150 800

ACS 68-5.5
4 200 2 Tower 12
10 9 11 422 440 150 590
11 11 12 158 170 150 320
12 12 14 327 340 150 490
13 14 20 2 185 2 260 150 2 410
4 500 3 Tower 24
14 20 22 795 820 150 970
15 22 24 459 480 150 630
16 24 26 718 740 150 890
2 040 4 Tower 29
17 26 29 963 1 000 150 1 150
18 29 38 3 409 3 520 150 3 670 3 670 5 Tower 38
19 38 49 4 458 4 600 150 4 750 4 750 6 Tower 49
20 49 59 3 692 3 810 150 3 960 4 110 7 Tower 59
21 59 62 1 130 1 170 150 1 320 1 470 8 Tower 62
Wound
Tension
from Section 3% for Process Total length Type of Towers on which junction boxes
section to tower # Drum Nº
tower # length,m sag, m allowance length, m (on OPGW will be installed

drum), m
22 62 72 3 832 3 950 150 4 100 4 100 9 Tower 72
23 72 81 3 479 3 590 150 3 740 3 740 10 Tower 81
24 81 90 3 436 3 540 150 3 690 3 690 11 Tower 90
25 90 96 1 876 1 940 150 2 090 2 090 12 Tower 96
26 96 104 2 898 2 990 150 3 140 3 140 13 Tower 104
27 104 109 1 548 1 600 150 1 750 1 750 14 Tower 109
28 109 119 3 685 3 800 150 3 950 3950 15 Tower 119
29 119 127 2 731 2 820 150 2 970 2 970 16 Tower 127
30 127 137 3 462 3 570 150 3 720 3 720 17 Tower 137
31 137 147 3 375 3 480 150 3 630 3 630 18 Tower 147
32 147 153 2 126 2 190 150 2 340
33 153 154 382 400 150 550
4 610 19 Tower 158
34 154 155 223 230 150 380
35 155 158 1 152 1 190 150 1 340
36 158 161 784 810 150 960
37 161 163 534 560 150 710 2 490 20 Tower 165
38 163 165 646 670 150 820

ACS 68-5.5
39 165 173 2 524 2 600 150 2 750 2 750 21 Tower 173
40 173 183 3 362 3 470 150 3 620 3 620 22 Tower 183
41 183 188 1 708 1 760 150 1 910 1 910 23 Tower 188
42 188 189 187 200 150 350
3 920 24 Tower 198
43 189 198 3 320 3 420 150 3 570
44 198 207 3 205 3 310 150 3 460 3 460 25 Tower 207
45 207 216 3 030 3 130 150 3 280 3 280 26 Tower 216
46 216 226 3 779 3 900 150 4 050 4 050 27 Tower 226
47 226 234 2 893 2 980 150 3 130 3 130 28 Tower 234
Wound
Tension
from Section 3% for Process Total length Type of Towers on which junction boxes
section to tower # Drum Nº
tower # length,m sag, m allowance length, m (on OPGW will be installed

drum), m
48 234 242 2 746 2 830 150 2 980 2 980 29 Tower 242
49 242 250 2 866 2 960 150 3 110 3 110 30 Tower 250
50 250 254 1 487 1 540 150 1 690

2 x ACS 68-
51 254 258 1 454 1 500 150 1 650
3 980 31 Gantry of ME s/s

5.5
52 258 260 340 360 150 510
Gantry of ME
53
260 s/s 44 50 80 130
Total length of OPGW type ACS 68-5.5, km 104 160 Total number of
junction boxes for 30 pcs
Total length of OPGW type ACS 68-5.5 without optic fibers, km 3,98 the construction site:
Appendix 7

QUANTITY OF DAMPERS FOR OPGW


Left span, Right span, Left span, Right span,
Tower Tower
pcs. pcs. pcs. pcs.
Switchyard Gantry 0 1 35 1
2 453 0 1 36 1
1 452 1 1 37 1
0 451 0 2 38 2
1 450 0 1 39 1
1 449 1 1 40 1
2 448 0 1 41 1
2 447 2 1 42 1
2 446 2 1 43 1
2 445 А 2 1 44 1
2 1 2 1 45 1
1 2 1 1 46 1
1 3 1 1 47 1
1 4 1 1 48 1
1 5 1 2 49 2
1 6 1 1 50 1
2 7 2 1 51 1
1 8 1 1 52 1
2 9 0 1 53 1
1 10 1 1 54 1
0 11 0 1 55 1
2 12 0 1 56 1
1 13 1 1 57 1
Left span, Right span, Left span, Right span,
Tower Tower
pcs. pcs. pcs. pcs.
0 14 2 1 58 1
1 15 0 2 59 2
1 16 1 1 60 1
1 17 1 1 61 1
1 18 1 2 62 2
1 19 1 1 63 1
0 20 2 1 64 1
1 21 1 1 65 1
2 22 0 1 66 1
1 23 1 1 67 1
0 24 2 1 68 1
1 25 1 1 69 1
2 26 2 1 70 1
1 27 1 1 71 1
1 28 1 2 72 2
2 29 2 1 73 1
1 30 1 1 74 1
1 31 1 1 75 1
1 32 1 1 76 1
1 33 1 1 77 1
1 34 1 1 78 1
1 79 1 1 123 1
1 80 1 1 124 1
2 81 2 1 125 1
1 82 1 1 126 1
1 83 1 2 127 2
1 84 1 1 128 1
1 85 1 1 129 1
Left span, Right span, Left span, Right span,
Tower Tower
pcs. pcs. pcs. pcs.
1 86 1 1 130 1
1 87 1 1 131 1
1 88 1 1 132 1
1 89 1 1 133 1
2 90 2 1 134 1
1 91 0 1 135 1
1 92 1 1 136 1
1 93 1 2 137 2
1 94 0 1 138 1
1 95 1 1 139 0
0 96 2 1 140 1
1 97 1 1 141 1
1 98 1 1 142 1
1 99 1 1 143 0
1 100 1 1 144 1
1 101 1 1 145 1
1 102 1 1 146 1
1 103 1 2 147 2
2 104 2 1 148 1
1 105 1 1 149 1
1 106 0 1 150 1
1 107 0 1 151 1
1 108 1 1 152 1
2 109 2 2 153 2
1 110 1 2 154 0
1 111 1 2 155 2
1 112 1 1 156 1
1 113 1 1 157 1
Left span, Right span, Left span, Right span,
Tower Tower
pcs. pcs. pcs. pcs.
1 114 1 2 158 2
1 115 1 1 159 0
1 116 1 1 160 1
1 117 1 0 161 0
1 118 1 1 162 1
2 119 2 0 163 2
1 120 1 1 164 1
1 121 1 0 165 2
1 122 1 1 166 1
1 167 1 1 211 1
1 168 1 1 212 1
1 169 1 1 213 1
1 170 1 1 214 1
1 171 1 1 215 1
1 172 1 0 216 0
0 173 0 1 217 1
1 174 0 1 218 1
1 175 1 1 219 1
1 176 1 1 220 1
1 177 0 1 221 1
1 178 1 1 222 1
1 179 1 1 223 1
1 180 1 1 224 1
1 181 1 1 225 1
1 182 1 2 226 2
2 183 2 1 227 1
1 184 1 1 228 1
1 185 0 1 229 1
1 186 1 1 230 1
Left span, Right span, Left span, Right span,
Tower Tower
pcs. pcs. pcs. pcs.
1 187 1 1 231 1
2 188 0 1 232 1
2 189 2 1 233 1
1 190 1 2 234 2
1 191 1 1 235 1
1 192 1 1 236 1
1 193 1 1 237 1
1 194 0 1 238 1
1 195 1 1 239 0
1 196 1 1 240 1
1 197 1 1 241 1
2 198 2 2 242 2
1 199 0 1 243 1
1 200 1 1 244 1
1 201 1 1 245 1
1 202 1 1 246 1
1 203 1 1 247 1
1 204 1 1 248 0
1 205 1 1 249 1
1 206 1 0 250 0
2 207 0 1 251 1
1 208 1 1 252 1
1 209 1 1 253 1
1 210 1 2 254 2
1 255 1 2 258 0
1 256 0 1 259 1
1 257 1 0 260 0
2 Gantry ME Switchyard
TOTAL: 569
Appendix 8

QUANTITY OF GROUND WIRE С-70

1. Ground wire С-70


Length of OHTL from tower 445А (of 400kV Vezhen OHTL) to tower 254 89 222 m
Total length: 89 222 m

Percentage of the length for sags and jumpers 3%


Total length of single C-70 to be delivered: 91 899 m
Appendix 9

QUANTITY OF CONDUCTOR AND GROUND WIRE FITTINGS

Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

1 20.28.NN 1 2 - - - 6 - - 2 2
2 СНД1 - - 3 - - - 1 1 - -
3 СНД1 - - 3 - - - 1 1 - -
4 СНД1 - - 3 - - - 1 1 - -
5 СНД2+3 - - 3 - - - 1 1 - -
6 СНД1 - - 3 - - - 1 1 - -
7 20.22.NN 1 2 - - - 6 - - 2 2
8 СНД1-3 - - 3 - - - 1 1 - -
9 20.19.NN 1 2 - - - 6 - - 2 2
10 СЕН 1, 2 +12 1 2 - - - - 1 1 - -
11 20.28.NN 1 2 - - - 6 - - 2 2
12 60.25.NN 1 3 - - - 6 - - 2 2
13 СНД1 - - 3 - - - 1 1 - -
14 20.25.NN 1 2 - - - 6 - - 2 2
15 СНД2+6 - - 3 - - - 1 1 - -
16 СНД2+6 - - 3 - - - 1 1 - -
17 СНД2+6 - - 3 - - - 1 1 - -
18 СНД2+3 - - 3 - - - 1 1 - -
19 СНД2+3 - - 3 - - - 1 1 - -
20 20.28.NN 1 2 - - - 6 - - 2 2
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

21 СНД2+6 - - 3 - - - 1 1 - -
22 20.22.NN 1 2 - - - 6 - - 2 2
23 СНД1-6 - - 3 - - - 1 1 - -
24 20.19.NN 1 2 - - - 6 - - 2 2
25 СНД2 +3 - - 3 - - - 1 1 - -
26 60.28.NN 1 3 - - - 6 - - 2 2
27 СНД1-3 - - 3 - - - 1 1 - -
28 СНД1-3 - - 3 - - - 1 1 - -
29 60.19.NN 1 3 - - - 6 - - 2 2
30 СНД1 - - 3 - - - 1 1 - -
31 СНД1 - - 3 - - - 1 1 - -
32 СНД1 - - 3 - - - 1 1 - -
33 СНД1 - - 3 - - - 1 1 - -
34 СНД1 - - 3 - - - 1 1 - -
35 СНД2+3 - - 3 - - - 1 1 - -
36 СНД1 - - 3 - - - 1 1 - -
37 СНД1 - - 3 - - - 1 1 - -
38 20.25.NN 1 2 - - - 6 - - 2 2
39 СНД1 - - 3 - - - 1 1 - -
40 СНД2+3 - - 3 - - - 1 1 - -
41 СНД1 - - 3 - - - 1 1 - -
42 СНД2+3 - - 3 - - - 1 1 - -
43 СНД2+3 - - 3 - - - 1 1 - -
44 СНД2+3 - - 3 - - - 1 1 - -
45 СНД2+3 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

46 СНД1 - - 3 - - - 1 1 - -
47 СНД2+6 - - 3 - - - 1 1 - -
48 СНД2+6 - - 3 - - - 1 1 - -
49 20.25.NN 1 2 - - - 6 - - 2 2
50 СНД1 - - 3 - - - 1 1 - -
51 СНД1-3 - - 3 - - - 1 1 - -
52 СНД1 - - 3 - - - 1 1 - -
53 СНД1 - - 3 - - - 1 1 - -
54 СНД2+3 - - 3 - - - 1 1 - -
55 СНД1 - - 3 - - - 1 1 - -
56 СНД1 - - 3 - - - 1 1 - -
57 СНД1-3 - - 3 - - - 1 1 - -
58 СНД1-3 - - 3 - - - 1 1 - -
59 20.25.NN 1 2 - - - 6 - - 2 2
60 СНД1 - - 3 - - - 1 1 - -
61 СНД1 - - 3 - - - 1 1 - -
62 20.22.NN 1 2 - - - 6 - - 2 2
63 СНД2+3 - - 3 - - - 1 1 - -
64 СНД1 - - 3 - - - 1 1 - -
65 СНД1 - - 3 - - - 1 1 - -
66 СНД1 - - 3 - - - 1 1 - -
67 СНД1 - - 3 - - - 1 1 - -
68 СНД1 - - 3 - - - 1 1 - -
69 СНД2+3 - - 3 - - - 1 1 - -
70 СНД2 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

71 СНД1 - - 3 - - - 1 1 - -
72 20.25.NN 1 2 - - - 6 - - 2 2
73 СНД2 - - 3 - - - 1 1 - -
74 СНД1 - - 3 - - - 1 1 - -
75 СНД1 - - 3 - - - 1 1 - -
76 СНД1 - - 3 - - - 1 1 - -
77 СНД1 - - 3 - - - 1 1 - -
78 СНД1 - - 3 - - - 1 1 - -
79 СНД2 - - 3 - - - 1 1 - -
80 СНД2 - - 3 - - - 1 1 - -
81 20.25.NN 1 2 - - - 6 - - 2 2
82 СНД1 - - 3 - - - 1 1 - -
83 СНД1 - - 3 - - - 1 1 - -
84 СНД2+3 - - 3 - - - 1 1 - -
85 СНД2 - - 3 - - - 1 1 - -
86 СНД1 - - 3 - - - 1 1 - -
87 СНД2 +3 - - 3 - - - 1 1 - -
88 СНД2+3 - - 3 - - - 1 1 - -
89 СНД2+3 - - 3 - - - 1 1 - -
90 20.22.NN 1 2 - - - 6 - - 2 2
91 СНД1-6 - - 3 - - - 1 1 - -
92 СНД1-3 - - 3 - - - 1 1 - -
93 СНД1 - - 3 - - - 1 1 - -
94 СНД1 - - 3 - - - 1 1 - -
95 СНД1-6 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

96 60.22.NN 1 3 - - - 6 - - 2 2
97 СНД2+3 - - 3 - - - 1 1 - -
98 СНД2+3 - - 3 - - - 1 1 - -
99 СНД1 - - 3 - - - 1 1 - -
100 СНД2+6 - - 3 - - - 1 1 - -
101 СНД1 - - 3 - - - 1 1 - -
102 СНД2+3 - - 3 - - - 1 1 - -
103 СНД2+3 - - 3 - - - 1 1 - -
104 20.25.NN 1 2 - - - 6 - - 2 2
105 СНД2+3 - - 3 - - - 1 1 - -
106 СНД1-3 - - 3 - - - 1 1 - -
107 СНД1-3 - - 3 - - - 1 1 - -
108 СНД1-3 - - 3 - - - 1 1 - -
109 20.28.NN 1 2 - - - 6 - - 2 2
110 СНД2+6 - - 3 - - - 1 1 - -
111 СНД1 - - 3 - - - 1 1 - -
112 СНД2+3 - - 3 - - - 1 1 - -
113 СНД2+3 - - 3 - - - 1 1 - -
114 СНД2+6 - - 3 - - - 1 1 - -
115 СНД2+3 - - 3 - - - 1 1 - -
116 СНД2+3 - - 3 - - - 1 1 - -
117 СНД2+3 - - 3 - - - 1 1 - -
118 СНД2+3 - - 3 - - - 1 1 - -
119 20.25.NN 1 2 - - - 6 - - 2 2
120 СНД1 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

121 СНД1 - - 3 - - - 1 1 - -
122 СНД1 - - 3 - - - 1 1 - -
123 СНД1 - - 3 - - - 1 1 - -
124 СНД1 - - 3 - - - 1 1 - -
125 СНД1 - - 3 - - - 1 1 - -
126 СНД1 - - 3 - - - 1 1 - -
127 20.25.NN 1 2 - - - 6 - - 2 2
128 СНД1 - - 3 - - - 1 1 - -
129 СНД1 - - 3 - - - 1 1 - -
130 СНД1 - - 3 - - - 1 1 - -
131 СНД2+3 - - 3 - - - 1 1 - -
132 СНД2+3 - - 3 - - - 1 1 - -
133 СНД1 - - 3 - - - 1 1 - -
134 СНД1 - - 3 - - - 1 1 - -
135 СНД1 - - 3 - - - 1 1 - -
136 СНД1 - - 3 - - - 1 1 - -
137 20.25.NN 1 2 - - - 6 - - 2 2
138 СНД1 - - 3 - - - 1 1 - -
139 СНД1 - - 3 - - - 1 1 - -
140 СНД1 - - 3 - - - 1 1 - -
141 СНД2+3 - - 3 - - - 1 1 - -
142 СНД2+3 - - 3 - - - 1 1 - -
143 СНД1 - - 3 - - - 1 1 - -
144 СНД2+3 - - 3 - - - 1 1 - -
145 СНД2+3 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

146 СНД2+3 - - 3 - - - 1 1 - -
147 20.25.NN 1 2 - - - 6 - - 2 2
148 СНД2+6 - - 3 - - - 1 1 - -
149 СНД1 - - 3 - - - 1 1 - -
150 СНД1 - - 3 - - - 1 1 - -
151 СНД1 - - 3 - - - 1 1 - -
152 СНД2+3 - - 3 - - - 1 1 - -
153 20.25.NN 1 2 - - - 6 - - 2 2
154 60.28.NN 1 3 - - - 6 - - 2 2
155 60.25.NN 1 3 - - - 6 - - 2 2
156 СНД2+6 - - 3 - - - 1 1 - -
157 СНД2+6 - - 3 - - - 1 1 - -
158 20.25.NN 1 2 - - - 6 - - 2 2
159 СНД1 - - 3 - - - 1 1 - -
160 СНД1-6 - - 3 - - - 1 1 - -
161 20.19.NN 1 2 - - - 6 - - 2 2
162 СНД1-3 - - 3 - - - 1 1 - -
163 20.22.NN 1 2 - - - 6 - - 2 2
164 СНД2+3 - - 3 - - - 1 1 - -
165 20.25.NN 1 2 - - - 6 - - 2 2
166 СНД1 - - 3 - - - 1 1 - -
167 СНД1 - - 3 - - - 1 1 - -
168 СНД1-3 - - 3 - - - 1 1 - -
169 СНД1-3 - - 3 - - - 1 1 - -
170 СНД1-3 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

171 СНД1 - - 3 - - - 1 1 - -
172 СНД1-6 - - 3 - - - 1 1 - -
173 20.19.NN 1 2 - - - 6 - - 2 2
174 СНД1-3 - - 3 - - - 1 1 - -
175 СНД1 - - 3 - - - 1 1 - -
176 СНД2+3 - - 3 - - - 1 1 - -
177 СНД2+3 - - 3 - - - 1 1 - -
178 СНД2+6 - - 3 - - - 1 1 - -
179 СНД2+6 - - 3 - - - 1 1 - -
180 СНД1 - - 3 - - - 1 1 - -
181 СНД2+6 - - 3 - - - 1 1 - -
182 СНД2+6 - - 3 - - - 1 1 - -
183 20.25.NN 1 2 - - - 6 - - 2 2
184 СНД1 - - 3 - - - 1 1 - -
185 СНД1 - - 3 - - - 1 1 - -
186 СНД1 - - 3 - - - 1 1 - -
187 СНД2 - - 3 - - - 1 1 - -
188 60.28.NN 1 3 - - - 6 - - 2 2
189 20.28.NN 1 2 - - - 6 - - 2 2
190 СНД1 - - 3 - - - 1 1 - -
191 СНД1 - - 3 - - - 1 1 - -
192 СНД1 - - 3 - - - 1 1 - -
193 СНД2+3 - - 3 - - - 1 1 - -
194 СНД2 - - 3 - - - 1 1 - -
195 СНД2+3 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

196 СНД2+3 - - 3 - - - 1 1 - -
197 СНД1 - - 3 - - - 1 1 - -
198 20.22.NN 1 2 - - - 6 - - 2 2
199 СНД1 - - 3 - - - 1 1 - -
200 СНД1 - - 3 - - - 1 1 - -
201 СНД1 - - 3 - - - 1 1 - -
202 СНД1 - - 3 - - - 1 1 - -
203 СНД2+3 - - 3 - - - 1 1 - -
204 СНД2+3 - - 3 - - - 1 1 - -
205 СНД1 - - 3 - - - 1 1 - -
206 СНД1 - - 3 - - - 1 1 - -
207 20.25.NN 1 2 - - - 6 - - 2 2
208 СНД1-6 - - 3 - - - 1 1 - -
209 СНД1 - - 3 - - - 1 1 - -
210 СНД1 - - 3 - - - 1 1 - -
211 СНД1-6 - - 3 - - - 1 1 - -
212 СНД1 - - 3 - - - 1 1 - -
213 СНД1 - - 3 - - - 1 1 - -
214 СНД2+3 - - 3 - - - 1 1 - -
215 СНД1 - - 3 - - - 1 1 - -
216 20.19.NN 1 2 - - - 6 - - 2 2
217 СНД1-3 - - 3 - - - 1 1 - -
218 СНД2 - - 3 - - - 1 1 - -
219 СНД2 - - 3 - - - 1 1 - -
220 СНД2+3 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

221 СНД1 - - 3 - - - 1 1 - -
222 СНД2+3 - - 3 - - - 1 1 - -
223 СНД2+3 - - 3 - - - 1 1 - -
224 СНД1 - - 3 - - - 1 1 - -
225 СНД1 - - 3 - - - 1 1 - -
226 20.25.NN 1 2 - - - 6 - - 2 2
227 СНД1 - - 3 - - - 1 1 - -
228 СНД2+6 - - 3 - - - 1 1 - -
229 СНД2+3 - - 3 - - - 1 1 - -
230 СНД2+3 - - 3 - - - 1 1 - -
231 СНД1 - - 3 - - - 1 1 - -
232 СНД2+6 - - 3 - - - 1 1 - -
233 СНД2+3 - - 3 - - - 1 1 - -
234 20.28.NN 1 2 - - - 6 - - 2 2
235 СНД2+3 - - 3 - - - 1 1 - -
236 СНД1 - - 3 - - - 1 1 - -
237 СНД2+3 - - 3 - - - 1 1 - -
238 СЕН 1, 2 +20 1 2 - - - - 1 1 - -
239 СНД2+6 - - 3 - - - 1 1 - -
240 СНД2+3 - - 3 - - - 1 1 - -
241 СНД2+3 - - 3 - - - 1 1 - -
242 20.25.NN 1 2 - - - 6 - - 2 2
243 СНД2+6 - - 3 - - - 1 1 - -
244 СНД2+3 - - 3 - - - 1 1 - -
245 СНД2+6 - - 3 - - - 1 1 - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

246 СНД2+3 - - 3 - - - 1 1 - -
247 СНД1-3 - - 3 - - - 1 1 - -
248 СНД1 - - 3 - - - 1 1 - -
249 СНД1-3 - - 3 - - - 1 1 - -
250 20.19.NN 1 2 - - - 6 - - 2 2
251 СНД2+3 - - 3 - - - 1 1 - -
252 СНД2+3 - - 3 - - - 1 1 - -
253 СНД2+3 - - 3 - - - 1 1 - -
254 60.25.NN 1 3 - - - 6 - - 2 2
255 СНД2+3 - - 3 - - - 1 1 - -
256 СНД2+6 - - 3 - - - 1 1 - -
257 СНД1-6 - - 3 - - - 1 1 - -
258 20.25.NN 1 2 - - 3 3 - - 2 2
259 СЕН 1, 2 +12 1 2 - - - - 1 1 - -
260 60.25.NN 1 3 - 3 3 - - - 2 2
Gantry ME s/s - - - 3 - - - - 1 1
Existing section
Gantry Plovdiv s/s - - - 3 - - - - 1 1
453А 70.25.NN - - - 3 3 - - - 2 2
452 1H.28.M 1 1 1 - - - - 1 - -
451A 20.22.N 1 3 - - 3 3 - - - 2
450A CEH2 +12 2 - - - - - - 1 - -
450B CEH2 +12 1 - - - - - - - - -
449A CEH2 +12 2 - - - - - - 1 - -
449B CEH2 +12 1 - - - - - - - - -
Ground
Single Single Ground wire
V-shape Single Double Triple Ground wire wire OPGW
suspension suspension C-70
Tower Nº Tower type suspension tension tension tension OPGW C-70 tension
for upper for lower swing
string string string string С block tension set
bracket bracket clamp
set

448A 70.19.N3 1 3 - - - 6 - - - 2
447A 20.28.N3 1 3 - - - 6 - - - 2
446A 20.25.N3 1 3 - - - 6 - - - 2
445A 20.28.N3 1 3 - - - 6 - - - 2
TOTAL: 61 123 634 12 12 294 214 217 96 106

Note:
The individual sting types and sets with fittings are given in the following drawings:
Single suspension string, upper and lower D104-01C3-04-0A Ground wire C-70 swing clamp D104-01C3-08-0A
V-shape suspension string D104-01C3-03-0A Ground wire OPGW С block D104-01C3-06-0A
Single tension string D104-01C3-01-0A Ground wire C-70 tension set D104-01C3-07-0A
Double tension string D104-01C3-01-0A OPGW tension set D104-01C3-05-0A
Triple tension string D104-01C3-02-0A

Ground
Single Single Ground wire Ground wire
V-shape Single Double Triple wire OPGW
suspension suspension C-70 OPGW
Tower Nº Tower type suspension tension tension tension C-70 tension
for upper for lower suspension suspension
string string string string tension set
bracket bracket set set
set

Gantry Plovdiv s/s - - - 2/2 - - - - - -


453А 70.25.NN - - - - - - - - - -
453B 70.25.NN - - - - - - - - - -
Ground
Single Single Ground wire Ground wire
V-shape Single Double Triple wire OPGW
suspension suspension C-70 OPGW
Tower Nº Tower type suspension tension tension tension C-70 tension
for upper for lower suspension suspension
string string string string tension set
bracket bracket set set
set

452 1H.28.M 1 1 1* - - - 1 - - -
451A 20.22.N - - - - 1 1 - - - -
451B 20.22.N - - - - 1 1 - - 2 -
450A CEH2 +12 - 1 - - - - - - - -
450B CEH2 +12 - - - - - - - - - -
450C CEH2 +12 - 1 - - - - 1 - - -
449A CEH2 +12 - 1 - - - - - - - -
449B CEH2 +12 - - - - - - - - - -
449C CEH2 +12 - 1 - - - - 1 - - -
448A 70.19.N3 - - - - - 2 - - - -
448B 70.19.N3 - - - - - 2 - - 1 -
447A 20.28.N3 - - - - - 2 - - -
447B 20.28.N3 - - - - - 2 - - 1 -
446A 20.25.N3 - - - - - 2 - - -
446B 20.25.N3 - - - - - 2 - - 1 -
445A 20.28.N3 - - - - - 2 - - -
445B 20.28.N3 - - - - - 2 - - 1 -
TOTAL to be dismantled: 1 2 2 1 9 3 0 6 0
TOTAL to be installed: 0 3 1* 2 1 9 0 0 0 0

* - An additional arm shall be delivered to complete the V-string.


Appendix 10

CROSING INFRASTRUCTURE

Span Crossing infrastructure Span Crossing infrastructure

453 452 Railway, off-grid 81 82 Dismantled 20 kV OHTL


453 452 220 kV OHTL Parvenets 81 82 Unpaved road
451 450 110 kV Lukovitsa 84 85 Unpaved road
451 450 110 kV Brezovo OHTL 85 86 Unpaved road
450 449 Yavorovo 110 kV OHTL 86 87 Unpaved road
450 449 110 kV OHTL 86 87 Unpaved road
450 449 110 kV OHTL 88 89 Unpaved road
450 449 110 kV OHTL 89 90 20 kV OHTL Debar
450 449 20 kV OHTL 92 93 Mechka river
448 447 20 kV OHTL 94 95 Double 20 kV Novakovo-Iskra OHTL
447 446 20 kV OHTL 94 95 Paved road III-667, km 14+225
447 446 Railway - electrified 97 98 Unpaved road
447 446 Paved road II-86, km 3 +250 100 101 Unpaved road
447 446 Gas pipeline 102 103 Paved road I-8 (E-80), km 268+528
447 446 Water pipeline 104 105 20 kV Dragoyna OHTL
446 445А Unpaved road 105 106 20 kV Dragoyna OHTL
446 445А Railway - electrified 106 107 Unpaved road

445А 1 Planned paved circular road of Plovdiv km 107 108 Unpaved road
101+873
2 3 Irrigation channel 109 110 20 kV Dragoyna OHTL
2 3 Gas pipeline 109 110 Paved road PDV 1213
2 3 Irrigation channel 110 111 Unpaved road
2 3 Unpaved road 111 112 Unpaved road
4 5 Irrigation channel 113 114 Unpaved road
5 6 Unpaved road 113 114 20 kV Dragoyna OHTL
Span Crossing infrastructure Span Crossing infrastructure

6 7 Unpaved road 114 115 20 kV Dragoyna OHTL


6 7 Unpaved road 114 115 Unpaved road
7 8 Unpaved road 115 116 Byala river
8 9 Unpaved road 124 125 Unpaved road
9 10 Irrigation channel 128 129 Unpaved road
10 11 400 kV Ivan Popov OHTL 130 131 Unpaved road

10 11 Double 20 kV Yagodovo-Separatsiya OHTL 132 133 20 kV Skobelevo OHTL

11 12 Orchard 132 133 Paved road III-807 km 2 +470


11 12 Paved road 134 135 Koyakliyka river
11 12 Pvovdiv-Svilengrad railway 141 142 Unpaved road
13 14 20 kV Separation OHTL 144 145 Unpaved road
14 15 Unpaved road 150 151 Paved road PDV 1210
15 16 110 kV Katunitsa OHTL for reconstruction 151 152 Ravine
15 16 Irrigation channel 152 153 20 kV Skobelevo OHTL
16 17 Katunitsa-Plovdiv Airport municipal road 154 155 20 kV Skobelevo OHTL
16 17 Gas pipeline 154 155 Sofia-Svilengrad railway

17 18 Double 20 kV Yagodovo-Separatsiya OHTL 155 156 Unpaved road

18 19 Unpaved road 156 157 Unpaved road


18 19 Chepelarska river 158 159 Municipal paved road
20 21 Irrigation channel 158 159 Maritsa highway km 26 + 247
20 21 Unpaved road 158 159 Draining facility
21 22 20 kV Dionisiy OHTL 159 160 20 kV Technical Waters OHTL
21 22 Unpaved road 163 164 Maritsa river
24 25 Unpaved road 163 164 20 kV Construction Products OHTL
26 27 Unpaved road 164 165 20 kV Construction Products OHTL
26 27 Water pipeline 165 166 Unpaved road
Span Crossing infrastructure Span Crossing infrastructure

28 29 Orchard 174 175 Orchard


29 30 Orchard 175 176 Paved road III-663 km 21 +860
31 32 Unpaved road 175 176 20 kV Merichleri OHTL
33 34 Unpaved road 176 177 Ravine
34 35 Paved road III-8006 km 6 +415 177 178 110 kV Kracholov OHTL
34 35 20 kV Mominsko OHTL 179 180 Unpaved road
35 36 Unpaved road 179 180 Unpaved road
36 37 Unpaved road 185 186 20 kV OHTL Stransko
37 38 Paved road III-8006 km 6 +416 187 188 Paved road III-663
37 38 Unpaved road 188 189 Merichreli-Dimitrovgrad railway
39 40 Irrigation channel 195 196 Paved road HKV1006
40 41 Afforestated area 200 201 Ravine
41 42 Unpaved road 205 206 Paved road I-5, km 267+790
42 43 Unpaved road 212 213 Unpaved road
42 43 Unpaved road 215 216 Unpaved road
43 44 Unpaved road 218 219 Unpaved road
45 46 Irrigation channel 228 229 Unpaved road
46 47 20 kV Bolyartsi OHTL 231 232 20 kV Vasil Levski OHTL
47 48 Paved road III-804 km 8+912 231 232 Paved road III-503 km 15 +500
47 48 Cherkezitsa river 236 237 Ravine

47 48 Sushitsa river 237 238 110 kV Strandzha OHTL

47 48 Unpaved road 237 238 Ravine

48 49 Irrigation channel 238 239 220 kV Sazliyka OHTL

50 51 Irrigation channel 238 239 Ravine

50 51 Irrigation channel 239 240 Ravine

51 52 20 kV Bolyartsi OHTL 241 242 Ravine


52 53 Unpaved road 245 246 Musachka river
54 55 Irrigation channel 253 254 Paved road III-554
Span Crossing infrastructure Span Crossing infrastructure

54 55 Unpaved road 253 254 20 kV Vasil Levski OHTL


59 60 Konush reservoir 258 259 110 kV Traction Station OHTL
60 61 Paved road PDV 1011 259 260 Double 110 kV Malevo-Pyasachevo OHTL
62 63 Unpaved road
63 64 Mound
68 69 Unpaved road
71 72 Unpaved road
74 75 Unpaved road
76 77 Unpaved road
79 80 Unpaved road
Appendix 11

TYPE OF EARTHING SYSTEM


Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
Gantry 4,04 ≤10 Existent 133 5,05 ≤10 Vertical
453 4,04 ≤10 Existent 134 5,05 ≤10 Vertical
452 4,04 ≤10 Existent 135 4,04 ≤10 Vertical
451 4,04 ≤10 Existent 136 5,05 ≤10 Vertical
450 4,04 ≤10 Existent 137 8,08 ≤10 Vertical
449 4,04 ≤10 Existent 138 8,08 ≤10 Vertical
448 4,04 ≤10 Existent 139 8,08 ≤10 Vertical
447 4,04 ≤10 Existent 140 8,08 ≤10 Vertical
446 4,04 ≤10 Existent 141 8,08 ≤10 Vertical
445 А 4,04 ≤10 Existent 142 8,08 ≤10 Vertical
1 4,04 ≤10 Vertical 143 8,08 ≤10 Vertical
2 4,04 ≤10 Vertical 144 8,08 ≤10 Vertical
3 4,04 ≤10 Vertical 145 8,08 ≤10 Vertical
4 4,04 ≤10 Vertical 146 8,08 ≤10 Vertical
5 4,04 ≤10 Vertical 147 8,08 ≤10 Vertical
6 13,06 ≤15 Deep-driven 148 8,08 ≤10 Vertical
7 13,06 ≤15 Deep-driven 149 8,08 ≤10 Vertical
8 13,06 ≤15 Deep-driven 150 8,08 ≤10 Vertical
9 13,06 ≤15 Deep-driven 151 4,04 ≤10 Vertical
10 13,06 ≤15 Deep-driven 152 4,04 ≤10 Vertical
11 13,06 ≤15 Deep-driven 153 4,04 ≤10 Vertical
12 13,06 ≤15 Deep-driven 154 4,04 ≤10 Vertical
13 13,06 ≤15 Deep-driven 155 4,04 ≤10 Vertical
Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
14 13,06 ≤15 Deep-driven 156 4,04 ≤10 Vertical
15 13,06 ≤15 Deep-driven 157 4,04 ≤10 Vertical
16 13,06 ≤15 Deep-driven 158 4,04 ≤10 Vertical
17 13,06 ≤15 Deep-driven 159 4,04 ≤10 Vertical
18 13,06 ≤15 Deep-driven 160 4,04 ≤10 Vertical
19 13,06 ≤15 Deep-driven 161 4,04 ≤10 Vertical
20 13,06 ≤15 Deep-driven 162 4,04 ≤10 Vertical
21 13,06 ≤15 Deep-driven 163 4,04 ≤10 Vertical
22 13,06 ≤15 Deep-driven 164 4,04 ≤10 Vertical
23 13,06 ≤15 Deep-driven 165 4,04 ≤10 Vertical
24 13,06 ≤15 Deep-driven 166 4,04 ≤10 Vertical
25 13,06 ≤15 Deep-driven 167 5,05 ≤10 Vertical
26 13,06 ≤15 Deep-driven 168 5,05 ≤10 Vertical
27 13,06 ≤15 Deep-driven 169 5,05 ≤10 Vertical
28 13,06 ≤15 Deep-driven 170 5,05 ≤10 Vertical
29 13,06 ≤15 Deep-driven 171 5,05 ≤10 Vertical
30 13,06 ≤15 Deep-driven 172 5,05 ≤10 Vertical
13,06 ≤15 Deep-driven 173 5,05 ≤10 Vertical
31
13,06 ≤15 Deep-driven 174 5,05 ≤10 Vertical
32
13,06 ≤15 Deep-driven 175 5,05 ≤10 Vertical
33
13,06 ≤15 Deep-driven 176 5,05 ≤10 Vertical
34
13,06 ≤15 Deep-driven 177 5,05 ≤10 Vertical
35
13,06 ≤15 Deep-driven 178 5,05 ≤10 Vertical
36
13,06 ≤15 Deep-driven 179 5,05 ≤10 Vertical
37
4,04 ≤10 Vertical 180 5,05 ≤10 Vertical
38
4,04 ≤10 Vertical 181 5,05 ≤10 Vertical
39
Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
40 4,04 ≤10 Vertical 182 5,05 ≤10 Vertical
41 4,04 ≤10 Vertical 183 5,05 ≤10 Vertical
42 4,04 ≤10 Vertical 184 5,05 ≤10 Vertical
43 4,04 ≤10 Vertical 185 5,05 ≤10 Vertical
44 4,04 ≤10 Vertical 186 5,05 ≤10 Vertical
45 4,04 ≤10 Vertical 187 5,05 ≤10 Vertical
46 4,04 ≤10 Vertical 188 5,05 ≤10 Vertical
47 4,04 ≤10 Vertical 189 4,04 ≤10 Vertical
48 4,04 ≤10 Vertical 190 4,04 ≤10 Vertical
49 4,04 ≤10 Vertical 191 5,05 ≤10 Vertical
50 4,04 ≤10 Vertical 192 5,05 ≤10 Vertical
51 4,04 ≤10 Vertical 193 5,05 ≤10 Vertical
52 4,04 ≤10 Vertical 194 5,05 ≤10 Vertical
53 4,04 ≤10 Vertical 195 5,05 ≤10 Vertical
54 4,04 ≤10 Vertical 196 5,05 ≤10 Vertical
55 4,04 ≤10 Vertical 197 5,05 ≤10 Vertical
56 5,05 ≤10 Vertical 198 5,05 ≤10 Vertical
57 5,05 ≤10 Vertical 199 5,05 ≤10 Vertical
58 5,05 ≤10 Vertical 200 5,05 ≤10 Vertical
5,05 ≤10 Vertical 201 5,05 ≤10 Vertical
59
5,05 ≤10 Vertical 202 5,05 ≤10 Vertical
60
5,05 ≤10 Vertical 203 5,05 ≤10 Vertical
61
5,05 ≤10 Vertical 204 5,05 ≤10 Vertical
62
5,05 ≤10 Vertical 205 5,05 ≤10 Vertical
63
5,05 ≤10 Vertical 206 4,04 ≤10 Vertical
64
5,05 ≤10 Vertical 207 4,04 ≤10 Vertical
65
Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
66 5,05 ≤10 Vertical 208 4,04 ≤10 Vertical
67 5,05 ≤10 Vertical 209 5,05 ≤10 Vertical
68 5,05 ≤10 Vertical 210 5,05 ≤10 Vertical
69 5,05 ≤10 Vertical 211 5,05 ≤10 Vertical
70 5,05 ≤10 Vertical 212 5,05 ≤10 Vertical
71 5,05 ≤10 Vertical 213 5,05 ≤10 Vertical
72 5,05 ≤10 Vertical 214 5,05 ≤10 Vertical
73 5,05 ≤10 Vertical 215 5,05 ≤10 Vertical
74 5,05 ≤10 Vertical 216 5,05 ≤10 Vertical
75 5,05 ≤10 Vertical 217 5,05 ≤10 Vertical
76 5,05 ≤10 Vertical 218 5,05 ≤10 Vertical
77 5,05 ≤10 Vertical 219 5,05 ≤10 Vertical
78 5,05 ≤10 Vertical 220 5,05 ≤10 Vertical
79 5,05 ≤10 Vertical 221 5,05 ≤10 Vertical
80 5,05 ≤10 Vertical 222 5,05 ≤10 Vertical
81 5,05 ≤10 Vertical 223 5,05 ≤10 Vertical
82 5,05 ≤10 Vertical 224 5,05 ≤10 Vertical
83 5,05 ≤10 Vertical 225 5,05 ≤10 Vertical
5,05 ≤10 Vertical 226 5,05 ≤10 Vertical
84
5,05 ≤10 Vertical 227 5,05 ≤10 Vertical
85
5,05 ≤10 Vertical 228 5,05 ≤10 Vertical
86
5,05 ≤10 Vertical 229 5,05 ≤10 Vertical
87
5,05 ≤10 Vertical 230 5,05 ≤10 Vertical
88
5,05 ≤10 Vertical 231 5,05 ≤10 Vertical
89
5,05 ≤10 Vertical 232 5,05 ≤10 Vertical
90
91 4,04 ≤10 Vertical 233 5,05 ≤10 Vertical
Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
92 4,04 ≤10 Vertical 234 5,05 ≤10 Vertical
93 4,04 ≤10 Vertical 235 5,05 ≤10 Vertical
94 4,04 ≤10 Vertical 236 5,05 ≤10 Vertical
95 4,04 ≤10 Vertical 237 5,05 ≤10 Vertical
96 4,04 ≤10 Vertical 238 5,05 ≤10 Vertical
97 5,05 ≤10 Vertical 239 5,05 ≤10 Vertical
98 5,05 ≤10 Vertical 240 5,05 ≤10 Vertical
99 5,05 ≤10 Vertical 241 5,05 ≤10 Vertical
100 5,05 ≤10 Vertical 242 5,05 ≤10 Vertical
101 5,05 ≤10 Vertical 243 5,05 ≤10 Vertical
102 5,05 ≤10 Vertical 244 5,05 ≤10 Vertical
103 5,05 ≤10 Vertical 245 5,05 ≤10 Vertical
104 5,05 ≤10 Vertical 246 5,05 ≤10 Vertical
105 5,05 ≤10 Vertical 247 5,05 ≤10 Vertical
106 5,05 ≤10 Vertical 248 5,05 ≤10 Vertical
107 5,05 ≤10 Vertical 249 5,05 ≤10 Vertical
108 5,05 ≤10 Vertical 250 5,05 ≤10 Vertical
109 5,05 ≤10 Vertical 251 5,05 ≤10 Vertical
5,05 ≤10 Vertical 5,05 ≤10 Vertical
110 252
5,05 ≤10 Vertical 5,05 ≤10 Vertical
111 253
5,05 ≤10 Vertical 5,05 ≤10 Vertical
112 254
5,05 ≤10 Vertical 5,05 ≤10 Vertical
113 255
5,05 ≤10 Vertical 5,05 ≤10 Vertical
114 256
5,05 ≤10 Vertical 5,05 ≤10 Vertical
115 257
5,05 ≤10 Vertical 5,05 ≤10 Vertical
116 258
5,05 ≤10 Vertical 5,05 ≤10 Vertical
117 259
Earth
Earth system
Tower Rc, Ωm Rate Tower Rc, Ωm Rate system
type
type
118 5,05 ≤10 Vertical 260 5,05 ≤10 Vertical

119 5,05 ≤10 Vertical Gantry Maritsa East switchyard


120 5,05 ≤10 Vertical
121 5,05 ≤10 Vertical
122 5,05 ≤10 Vertical
123 5,05 ≤10 Vertical
124 5,05 ≤10 Vertical
125 5,05 ≤10 Vertical
126 5,05 ≤10 Vertical
127 5,05 ≤10 Vertical
128 5,05 ≤10 Vertical
129 5,05 ≤10 Vertical
130 5,05 ≤10 Vertical
131 5,05 ≤10 Vertical
132 5,05 ≤10 Vertical
Section 2: LIST OF DRAWINGS

TABLE OF CONTENTS

1. LINE ROUTE PLAN


2. LONGITUDINAL ROUTE LINE PROFILES
3. PLAN OF THE LINE BAY AT SUBSTATIONS
4. OUTLINE DRAWINGS OF TOWERS
5. FITTINGS FOR CONDUCTORS
6. FITTINGS FOR EARTHWIRES
7. EARTHING
8. MISCELLANEOUS

1. LINE ROUTE PLAN


• 400 kV OHTL Plovdiv s/s – Maritsa Iztok s/s
 D104-01C1-01-0A - Topo map-1920-297 # 1
 D104-01C1-01-0A - Topo map-1920-297 #2
• 110 kV OHTL for Katunitsa
 D104-03C1-01-0A - Topo map of OHTL 110 kV Katunitsa_ part for reconstruc...

2. LONGITUDINAL ROUTE LINE PROFILES


• 110 kV OHTL for Katunitsa
 D104-03C2-01-0A - Profile of OHTL 110 kV Katunitsa

3. PLAN OF THE LINE BAY AT SUBSTATIONS


• Plovdiv s/s
 D104-01C1-02-0A - situation PL_1-A3
• Maritsa Iztok s/s
 D104-01C1-03-0A - Situation_MI-Layout1-A3
 D104-01C1-05-0A - Situation MI OPUG-A3

4. OUTLINE DRAWINGS OF TOWERS


• 400 kV OHTL Plovdiv s/s – Maritsa Iztok s/s
 D104-01C4-02-0A - СЕН1 and СЕН2 towers-1
 D104-01C4-04-0A - N3 towers-1
 D104-01F1-01-0A - Schemes of СНД-01 towers
 D104-01F2-01-0A - Schemes of СНД 02 towers -A1
 D104-01F3-01-0A - 20.NN towers -A1
 D104-01F4-01-0A 60.NN tower-A1
 D104-01F5-01-0A - СЕН 1(2) +12+20 towers - A1

5. FITTINGS FOR CONDUCTORS


 D104-01C3-01-0A - Tension string 1х3х3хАСО-400 for 400kV, single, double-A2 EO new
 D104-01C3-02-0A - Tension string 1х3х3хАСО-400 for 400kV, treeple-A2 TO new
 D104-01C3-03-0A - V suspension string 1х3х3хАСО-400 for 400kV-A2 left, middle and right
NEW
 D104-01C3-04-0A - Single suspension string 1х3х3хАСО-400 for 400kV-A2 ЕО NEW
 D104-03C3-02-0A - Tension string on tower No 22 and 23-A3

6. FITTINGS FOR EARTHWIRES
• For OPGW
 D104-01C3-05-0A - OPGW on NN tower-ACS 68-5.5
 D104-01C3-06-0A - OPGW on СНД tower-A3 ACS 68-5.5
 D104-01C3-09-0A - OPGW on MI and Pl portals-A3
• For C-70
 D104-01C3-07-0A - C-70 on NN tower-C-70
 D104-01C3-08-0A - С-70 on СНД tower-A3
 D104-03C3-05-0A - Tension set ground ware -1-2
7. EARTHING
 D104-01C3-13-0A - Earthing installation - type 1-A3
 D104-01C3-13-0A - Earthing installation - type 2-A3
 D104-03C3-06-0A - Grounding systems of new tower -A3

8. MISCELLANEOUS
 D104-01C3-12-0A - Phase sequence-A3
 D104-03C3-01-0A - Phase sequence - A3
 D104-03C3-08-0A - Bird protective rod-A3
 D104-01F6-02-0A - Strengthening of foundations on tower No 445A OHTL Vezhen
Supplementary Information

Completed Schedule of Supplementary Information.


Schedule of Supplementary Information shall accompany the Tender but does
not form part of the Tender and is required to be submitted in sufficient detail
to demonstrate the Tenderer’s capability to perform the Contract.

Schedule of Supplementary Information shall comprise:

a) Attachment 1 - Preliminary Programme

• Site organisation and Method statement (including Personnel and


Equipment which the Tenderer proposes to adopt for the execution of
the Works);
• Mobilisation and Construction Schedules;
• Declaration that the tenderer is familiar with conditions of the Site
(route of the Power Line);
• List of Proposed Subcontractors;
• Manufacturer’s Authorisation in accordance with ITT 16.2;

c) Attachment 2 - Other Information


• Details of Proposed Insurer (s); and
• Details of Proposed Bank Issuing Performance and Advance Payment
Securities.