Вы находитесь на странице: 1из 4

PROPOSED FOUR-STOREY RESIDENTIAL BUILDING

 Project Pre-Set-Up
 Set Objectives / Scope
 Identify Team
 Assign Roles
 Feasibility Study
 Identify Project Requirements
 Analyze Legal Approvals
 Conduct Land Survey
 Identify Competitors
 Gather Community Opinion
 Investigate Environment Impact
 List All Development Risks
 Produce Feasibility Report
 Project Design
 Identify Two Options
 Choose the Best Solution
 Create 2D and 3D Building Plans
 Project Initiation
 Get Design Approval, Design Approval from Client
 Apply for Permits
 Prepare Project Specification for Contracting
 Appoint the Contractors
 Select the Most Suitable Contractor
 Project Implementation
 Site Preparation
 Measure and Set Boundaries of the Land
 Secure the Site
 Earthworks
 Excavation
 Water and Sewer
 Insert Utility Pipes
 Laying the Foundation
 Backfill
 Structure
 Ground Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Second Floor Slab)
 Stripping of Formworks
 Second Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Third Floor Slab)
 Stripping of Formworks
 Third Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Fourth Floor Slab)
 Stripping of Formworks
 Fourth Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Roof Deck Floor Slab)
 Stripping of Formworks
 Roof Deck
 Rebar Laying of Exterior and Interior Walls
 Exterior CHB Wall Installation
 Formworks Installation of Slabs
 Rebar Laying of Slabs
 Slab Concreting
 Stripping of Formworks
 Roofing
 Truss Installation
 Laying of Electrical Wirings
 Galvanized Iron Sheet Installation
 Gutter Installation
 Down Sprout Installation

 Utilities
 Waterproofing
 Electrical and Plumbing Utilities Installation
 Ceiling Installation
 Handrail Installation (Bolted)
 Finishing
 Fixtures Installation
 Plastering
 Doors and Windows Installation
 Tiles Installation
 Painting
 Project Turn-Over
 Assures the Completion of the Project
 Identify Any Unfinished Activities
 Inspect the Site for Final Review Before the Turning Over Day
 Prepare the Site for Turning Over to the Client
 Sign the Ending Contract with the Client

Вам также может понравиться