Project Pre-Set-Up
Set Objectives / Scope
Identify Team
Assign Roles
Feasibility Study
Identify Project Requirements
Analyze Legal Approvals
Conduct Land Survey
Identify Competitors
Gather Community Opinion
Investigate Environment Impact
List All Development Risks
Produce Feasibility Report
Project Design
Identify Two Options
Choose the Best Solution
Create 2D and 3D Building Plans
Project Initiation
Get Design Approval, Design Approval from Client
Apply for Permits
Prepare Project Specification for Contracting
Appoint the Contractors
Select the Most Suitable Contractor
Project Implementation
Site Preparation
Measure and Set Boundaries of the Land
Secure the Site
Earthworks
Excavation
Water and Sewer
Insert Utility Pipes
Laying the Foundation
Backfill
Structure
Ground Floor
Rebar Laying of Columns
Rebar Laying of Beams
Rebar Laying of Exterior and Interior Walls
Laying of Electrical Wirings and Plumbing
Formworks Installation of Columns
Formworks Installation of Beams
Exterior and Interior CHB Walls Installation
Formworks Installation of Stairs
Rebar Laying of Slabs
Rebar Laying of Stairs
Column Concreting
Beam Concreting
Slab and Stairs Concreting (Simultaneous with Second Floor Slab)
Stripping of Formworks
Second Floor
Rebar Laying of Columns
Rebar Laying of Beams
Rebar Laying of Exterior and Interior Walls
Laying of Electrical Wirings and Plumbing
Formworks Installation of Columns
Formworks Installation of Beams
Exterior and Interior CHB Walls Installation
Formworks Installation of Slabs
Formworks Installation of Stairs
Rebar Laying of Slabs
Rebar Laying of Stairs
Column Concreting
Beam Concreting
Slab and Stairs Concreting (Simultaneous with Third Floor Slab)
Stripping of Formworks
Third Floor
Rebar Laying of Columns
Rebar Laying of Beams
Rebar Laying of Exterior and Interior Walls
Laying of Electrical Wirings and Plumbing
Formworks Installation of Columns
Formworks Installation of Beams
Exterior and Interior CHB Walls Installation
Formworks Installation of Slabs
Formworks Installation of Stairs
Rebar Laying of Slabs
Rebar Laying of Stairs
Column Concreting
Beam Concreting
Slab and Stairs Concreting (Simultaneous with Fourth Floor Slab)
Stripping of Formworks
Fourth Floor
Rebar Laying of Columns
Rebar Laying of Beams
Rebar Laying of Exterior and Interior Walls
Laying of Electrical Wirings and Plumbing
Formworks Installation of Columns
Formworks Installation of Beams
Exterior and Interior CHB Walls Installation
Formworks Installation of Slabs
Formworks Installation of Stairs
Rebar Laying of Slabs
Rebar Laying of Stairs
Column Concreting
Beam Concreting
Slab and Stairs Concreting (Simultaneous with Roof Deck Floor Slab)
Stripping of Formworks
Roof Deck
Rebar Laying of Exterior and Interior Walls
Exterior CHB Wall Installation
Formworks Installation of Slabs
Rebar Laying of Slabs
Slab Concreting
Stripping of Formworks
Roofing
Truss Installation
Laying of Electrical Wirings
Galvanized Iron Sheet Installation
Gutter Installation
Down Sprout Installation
Utilities
Waterproofing
Electrical and Plumbing Utilities Installation
Ceiling Installation
Handrail Installation (Bolted)
Finishing
Fixtures Installation
Plastering
Doors and Windows Installation
Tiles Installation
Painting
Project Turn-Over
Assures the Completion of the Project
Identify Any Unfinished Activities
Inspect the Site for Final Review Before the Turning Over Day
Prepare the Site for Turning Over to the Client
Sign the Ending Contract with the Client