  LARSEN & TOUBRO LIMITED - ECC DIVISION

    Name of Project Samakhiali Gandhidham Road Project

    Job Procedure for Methodology For Tree Cutting

    Job Procedure No Sl. No. – 004

CONTENTS

S. No. PAGE NO.

1 Scope

2 Reference

3 Method

4 Tolerance

5 Documentation

(5a) Inspection & Test Plan (ITP)

(5b) Formats

              
00 01/03/2011

Rev Date Prepared By Reviewed By Approved by

Page 1 of 3
LARSEN & TOUBRO LIMITED
ENGINEERING, CONSTRUCTION AND CONTRACTS
PROJECT QUALITY PLAN
SITE: SAMAKHIALI GANDHIDHAM ROAD PROJET
FROM 306.800 TO 362.420
QUALITY MANAGEMENT

METHODOLOGY FOR TREE CUTTING WORKS

MANPOWER REQUIRED:

1. Supervisor
2. Helpers
3. Labours

EQUIPMENT/ MACHINERY REQUIRED:

1. Excavator / JCB
2. Dumpers / Tractors
3. Axe
4. Saw

WORK PROCEDURE:

1. The trees shall be numbered jointly with SGTPL and shall be marked on the stem.

2. The girth of the tree shall be measured 1m above the ground level.

3. After due tree cutting permission from the forest officials which is to be obtained
by SGTPL the equipment shall enter the right of way.

4. Prior approval shall be taken from the Engineer for number of trees to be cut, size
of the girth and disposal/stacking them with in row and the methodology
suggested by the forest officials shall be implemented.

5. Road side trees, shrubs monuments, buildings, pipelines, sewers and all highway
facilities with and adjacent to the highway which are not to be disturbed shall be
protected from injury or damage, and shall be intimated to the Engineer.

6. Dozers, excavators and dumpers shall be used for clearance purpose, all trees
stumps, etc. Falling with in excavation and fill lines shall be cut to such depth
below ground.

Page 2 of 3
Safety Measures:

1. All safety precautionary measures shall be taken as stated below: -

2. Signboards shall be placed along the right hand side on increasing chainage
at every 500 meters i.e. “KEEP RIGHT WORK IN PROGRESS”, GO SLOW
WORK IN PROGRESS”.

3. Moveable signboards shall be place at area where heavy machineries and


survey works being carried out. The movement of machines and lorries at
these areas shall be controlled by flagman’s Signboards such as “CAUTION
MAN AT WORK GO SLOW”, “CAUTION GO SLOW WORK IN
PROGRESS”.

4. Safety as per IRC-SP-55-2001 may be taken up in location warranting need.

Page 3 of 3