Вы находитесь на странице: 1из 15

REVISED QUANTITY CALCULATION

PROPOSED DETOUR ROAD INTERSECT WITH EXISTING BRIDGE (STA. 0+000.00 TO STA. 0+678.99)
Department of Public Works and Highways
Client
Regional Office - II

OO 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD


SYSTEM BRIDGE - REPLACEMENT OF PERMANENT :
Project & Location
WEAK BRIDGES ABUSAG BRIDGE (B04258LZ) AND Contractor
: APPROACHES Along Baybayog - Baggao - Dalin -Sta. FREY-FILCORPORATION
Margarita Road, Baggao. Cagayan

Pay Item No :104(2)a

Description Embankment - from Borrow (Selected common) Required Qty 6,796.88 cu.m.

Unit cu.m.

Item 104(2)a : Embankment from Borrow,Selected Common


Embankment from borrow 7027.66 cu.m
Embankment from Roadway
excavation(qty x 0.80)= 230.78 cu.m
Vol. required(A-B)= 6,796.88 cu.m

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
AS-STAKED QUANTITY
AS-STAKED QUANTITY CALCULATION
PROPOSED DETOUR ROAD INTERSECT WITH EXISTING BRIDGE (STA. 0+000.00 TO STA. 0+678.99)

Pay Item No : 104(2)d Embankment from Borrow - Selected Common ###


BACKFILL
STATION LENGTH (m)
AREA (m²) - FILL) VOLUME (m³) - CUT
ALIGNMENT A
0 + 000.00 0.000 ###
0 + 020.00 20.00 0.653 6.530
0 + 040.00 20.00 3.707 43.600
0 + 060.00 20.00 4.071 77.780
0 + 080.00 20.00 5.746 98.170
0 + 100.00 20.00 8.725 144.710
0 + 120.00 20.00 14.069 227.940
0 + 140.00 20.00 17.037 311.060
0 + 160.00 20.00 15.598 326.350
0 + 180.00 20.00 12.724 283.220
0 + 200.00 20.00 12.214 249.380
0 + 220.00 20.00 12.630 248.440
0 + 240.00 20.00 12.439 250.690
0 + 260.00 20.00 13.433 258.720
0 + 280.00 20.00 14.639 280.720
0 + 300.00 20.00 14.177 288.160
0 + 320.00 20.00 10.112 242.890
0 + 340.00 20.00 0.090 102.020
0 + 360.00 20.00 0.000 0.900
0 + 380.00 20.00 1.316 13.160
0 + 400.00 20.00 1.330 26.460
0 + 420.00 20.00 2.712 40.420
0 + 440.00 20.00 4.881 75.930
0 + 460.00 20.00 7.831 127.120
0 + 480.00 20.00 10.800 186.310
0 + 500.00 20.00 12.300 231.000
0 + 520.00 20.00 15.258 275.580
0 + 540.00 20.00 17.813 330.710
0 + 560.00 20.00 22.625 404.380
0 + 580.00 20.00 23.876 465.010
0 + 600.00 20.00 26.706 505.820
0 + 620.00 20.00 17.748 444.540
0 + 640.00 20.00 9.652 274.000
0 + 660.00 20.00 4.587 142.390
0 + 678.99 18.99 0.000 43.554
SUB-TOTAL 7,027.664
Prepared and Submitted by: Checked and Reviewed by: fill
cut(80%)
###
TEODORICO A. GUICO ERNESTO R. ANGOLUAN
Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
PROPOSED DETOUR ROAD INTERSECT WITH EXISTING BRIDGE (STA. 0+000.00 TO STA. 0+678.99)
Department of Public Works and Highways
Client
Regional Office - II

OO 1 - ENSURE SAFE AND RELIABLE NATIONAL


ROAD SYSTEM BRIDGE - REPLACEMENT OF
Project & Location PERMANENT WEAK BRIDGES ABUSAG BRIDGE :
Contractor
: (B04258LZ) AND APPROACHES Along Baybayog - FREY-FILCORPORATION
Baggao - Dalin -Sta. Margarita Road, Baggao.
Cagayan

Pay Item No 104(1)a

Embankment - from Roadway Excavation


Description As-Staked Quantity 230.78 cu.m.
(Common Soil)
Unit cu.m.

Item 104(1)a : Embankment from Roadway Road Excavation, Common Materials


Vol. actual x 80% = 230.78 cu.m
230.78 cu.m

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
PROPOSED DETOUR ROAD INTERSECT WITH EXISTING BRIDGE (STA. 0+000.00 TO STA. 0+678.99)

Pay Item No : 104(1)a - Embankment - from Roadway Excavation (Common Soil)


ROADWAY EXCAVATION
STATION LENGTH (m)
AREA (m²) - CUT) VOLUME (m³) - CUT
ALIGNMENT A
0 + 000.00 6.223
0 + 020.00 20.00 0.176 63.990
0 + 040.00 20.00 - 1.760
0 + 060.00 20.00 - 0.000
0 + 080.00 20.00 - 0.000
0 + 100.00 20.00 - 0.000
0 + 120.00 20.00 - 0.000
0 + 140.00 20.00 - 0.000
0 + 160.00 20.00 - 0.000
0 + 180.00 20.00 - 0.000
0 + 200.00 20.00 - 0.000
0 + 220.00 20.00 - 0.000
0 + 240.00 20.00 - 0.000
0 + 260.00 20.00 - 0.000
0 + 280.00 20.00 - 0.000
0 + 300.00 20.00 - 0.000
0 + 320.00 20.00 - 0.000
0 + 340.00 20.00 1.516 15.160
0 + 360.00 20.00 1.644 31.600
0 + 380.00 20.00 0.857 25.010
0 + 400.00 20.00 - 8.570
0 + 420.00 20.00 - 0.000
0 + 440.00 20.00 - 0.000
0 + 460.00 20.00 - 0.000
0 + 480.00 20.00 - 0.000
0 + 500.00 20.00 - 0.000
0 + 520.00 20.00 - 0.000
0 + 540.00 20.00 - 0.000
0 + 560.00 20.00 - 0.000
0 + 580.00 20.00 - 0.000
0 + 600.00 20.00 - 0.000
0 + 620.00 20.00 - 0.000
0 + 640.00 20.00 0.800 8.000
0 + 660.00 20.00 2.830 36.300
0 + 678.99 18.99 7.500 98.083
SUB-TOTAL 288.473
Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
DETOUR ROAD GOING TO (LEFT) TALLANG AREA (STA. 0+000 TO STA. 0+300.83)
Department of Public Works and Highways
Client:
Regional Office - II

OO 1 - ENSURE SAFE AND RELIABLE NATIONAL


ROAD SYSTEM BRIDGE - REPLACEMENT OF
PERMANENT WEAK BRIDGES ABUSAG BRIDGE
Project & Location: (B04258LZ) AND APPROACHES Along Baybayog - Contractor :
FREY-FILCORPORATION
Baggao - Dalin -Sta. Margarita Road, Baggao.
Cagayan

Pay Item No: 104(2)a

Description: Embankment - from Borrow (selected common) Required Qty: 2,214.50 cu.m.

Unit: cu.m.

Item 104(2)a : Embankment from Borrow, Selected common


A. Detour Road going to Left (0+000.00 to 0+300.83): 2375.4254
B. Roadway Excavation (going Left) x 0.80 160.93
(Embankment from borrow - Excavation (0.80) =
TOTAL= 2,214.50 cu.m

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
DETOUR ROAD GOING LEFT TO TALLANG AREA (STA. 0+000 TO STA. 0+300.83)
Pay Item No : 104(2)d Embankment from Borrow - Selected Common

Backfilling
STATION LENGTH (m)
AREA (m²) VOLUME (m³)-fill
ALIGNMENT A
0 + 000.00 0.000
0 + 020.00 20.00 0.000 0.000
0 + 040.00 20.00 1.370 13.700
0 + 060.00 20.00 5.616 69.860
0 + 080.00 20.00 9.587 152.030
0 + 100.00 20.00 9.076 186.630
0 + 120.00 20.00 8.693 177.690
0 + 140.00 20.00 7.606 162.990
0 + 160.00 20.00 6.299 139.050
0 + 180.00 20.00 4.389 106.880
0 + 200.00 20.00 6.498 108.870
0 + 220.00 20.00 9.934 164.320
0 + 240.00 20.00 13.486 234.200
0 + 260.00 20.00 19.053 325.390
0 + 280.00 20.00 16.116 351.690
0 + 300.00 20.00 1.951 180.670
0 + 300.83 0.83 1.556 1.455
SUB-TOTAL 2,375.425

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
DETOUR ROAD GOING LEFT TO ANNAYATAN AREA (STA. 0+000 TO STA. 0+300.83)
Department of Public Works and Highways
Client:
Regional Office - II

OO 1 - ENSURE SAFE AND RELIABLE NATIONAL


ROAD SYSTEM BRIDGE - REPLACEMENT OF
PERMANENT WEAK BRIDGES ABUSAG BRIDGE
Project & Location: Contractor:
(B04258LZ) AND APPROACHES Along Baybayog - FREY-FILCORPORATION
Baggao - Dalin -Sta. Margarita Road, Baggao.
Cagayan

Pay Item No: 104(1)a

Embankment - from Roadway Excavation


Description: As-Staked Quantity: 160.93 cu.m.
(Common Soil)
Unit: cu.m.

Item 104(1)a : Embankment from Roadway Road Excavation, Common Materials


Road going to Left (0+000.00 to 0+300.83)(Qty. x 0.80) 160.93 cu.m.
TOTAL= 160.93 cu.m.

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED QUANTITY CALCULATION
DETOUR ROAD GOING TO (LEFT) TALLANG AREA (STA. 0+000 TO STA. 0+300.83)
Pay Item No : 104(1)a - Embankment - from Roadway Excavation (Common Soil)

ROADWAY EXCAVATION
STATION LENGTH (m)
AREA (m²) - CUT) VOLUME (m³) - CUT
0 + 000.00 5.381
0 + 020.00 20.00 4.373 97.540
0 + 040.00 20.00 0.425 47.980
0 + 060.00 20.00 4.250
0 + 080.00 20.00 0.000
0 + 100.00 20.00 0.000
0 + 120.00 20.00 0.000
0 + 140.00 20.00 0.000
0 + 160.00 20.00 0.000
0 + 180.00 20.00 0.659 6.590
0 + 200.00 20.00 6.590
0 + 220.00 20.00 0.000
0 + 240.00 20.00 0.000
0 + 260.00 20.00 0.000
0 + 280.00 20.00 0.000
0 + 300.00 20.00 3.534 35.340
0 + 300.83 0.83 3.386 2.872
SUB-TOTAL 201.162

Prepared and Submitted by: Checked and Reviewed by:

TEODORICO A. GUICO ERNESTO R. ANGOLUAN


Project Manager Project Engineer
(Contractor) DPWH
REVISED
QUANTITY CACULATION
FOR

DETOUR ROAD A
104(2)a - Embankment - from Borrow (Selected common)
104(1)a - Embankment - from Roadway Excavation (Common Soil)

DETOUR ROAD B GOING LEFT


104(2)a - Embankment - from Borrow (Selected common)
104(1)a - Embankment - from Roadway Excavation (Common Soil)
backfill 9011.38085 A+B
cut 391.70812 A+B