Вы находитесь на странице: 1из 3

PROJECT: Provision of road maintenance Services

CLIENT: MAZARINE ENERGY TUNISIA BV


CONTRACTOR: ESTS (SAHRAOUI COMPANY)

COMPANY: MAZARINE ENEGY BV TUNISIA CONTRACTOR: ESTS


STATUS DATE: 26/02/2020 REPORT DATE: 26/02/2020

CONTRACT No: MTU-PRJ-CON-004-2019 PREPARED BY: SADDEM HADFI

Site Supervisor Ali Ben Mosbah LOCATION: M AZARINE S I T E CAT- 1

WEATHER: Good WEATHER TEMPERATURE: 25°C

HSSE:

HSSE KPI To Date Month to date Project start to date

Total Number of employees 8 8 8

Working hours 12 12 12

Total Safe Work hours 96 96 96

Lost Work Days 0 0 0

Restricted Work Case 0 0 0

Restricted Work Days 0 0 0

Medical Treatment Case 0 0 0

First Aid Case 0 0 0


Incident 0 0 0

Near Miss 0 0 0

Hazards/Finding 0 0 0

Total of HSSE Training 0 0 0


Hours

Total driven distance (in Km) 40 40 40

WORK DESCRIPTION& PROGRESS of the Day (machinery related to each task)


Limitation of work area

Scraping of the area (area inside EPF)

P AGE1 OF3
PROJECT: Provision of road maintenance Services
CLIENT: MAZARINE ENERGY TUNISIA BV
CONTRACTOR: ESTS (SAHRAOUI COMPANY)

MANPOWER

S/ Company Trade/Qualification Discipline No Working hours


N
1 ESTS HSSE Engineer HSSE Management 1 12

2 ESTS Construction Manager Construction Management 1 12

3 ESTS Project Director Construction Management 0 0

5 ESTS Truck Driver Transport 0 0

6 ESTS Wheel-Loader driver Construction 1 12

7 ESTS Backhoe-driver Construction 0 0

8 ESTS Compactor driver Construction 0 0

9 ESTS Grader driver Construction 1 12

10 ESTS crawler excavator driver Construction 0 0


ESTS Ordinary Labour Construction 3 36
11
ESTS Watering truck driver Construction 0 0
12
13 ESTS Crew Transport Transport 1 12

TOTAL 8 96
MAJOR EQUIPMENT
Worki Working
S/ Type No ng S/ Type N
N hours N o hours
1 Truck 8/4 1 0 6 crawler excavator 1 0
2 Grader 1 12 Backhoe CASE 1 0
7
3 Compactor 1 0 8 Backhoe SEREX 1 0

Wheel-loader 1 12 dump truck 7 T 1 0


4 9
Watering truck 1 0 Forklift 1 0
5

Вам также может понравиться