Survey & Design Workshop

For Ukraine GU Project

2015-9-30
Zhang Hualong
Contents

1 TSSR output Procedure

2 ZTE Equipment Description

3 Engineering scenarios

4 Output Documents
Internal use only▲

Engineering Scope

ZTE MTS

• BBU+RRU • Equipment room or Outdoor cabinet


• All cables for BBU&RRU(Power and space
grounding cables, transmission • Grounding Bar(Indoor and outdoor)
cables, Fibers, jumpers, Aisg ready
cables(3G only), etc.) • Transmission equipment and port
• BBU and RRU installation kit(Gantry ready
included) • Power ready(Include enough power
capacity and proper breaker for
DCPDs)
• RF Antenna and antenna installed
ready
• RRU support structure(Exclude RRU
gantry)
• Main feeders if needed

© ZTE All rights reserved


3
Internal use only▲

TSSR output procedure

TSSR
MTS Cell Data certificate
and sign
Cell Data
confirmed
Information
Cell data TSSR and collection
ZTE Check and
Connection
drawing check
evaluate and approve
Diagram End
BOM output

TSSR and
Subcon drawing
output

Site information
Cell data
TSSR and Form
Output Doc. drawing
Connection BOM
Diagram

© ZTE All rights reserved


4
Contents

1 TSSR output Procedure

2 ZTE Equipment Description

3 Engineering scenarios

4 Output Documents
Internal use only▲

Product Description – BBU B8200

FS Baseband Processing Board


PM
FAM

SA

CC

Board Description
CC Control and Clock Module
FS Fabric Switch Module
PM Power Module
SA Site Alarm Module
FAN Fan Module
UPBG Universal Baseband Processing for GSM
BPK Baseband Processing Board Type K

Specifications of B8200
Dimension 88.4mm(H) x 482.6mm(W) x 197(D)
Weight 8.75kg
Typical Power
240W
consumption
DC Requirement 10A

© ZTE All rights reserved


6
Internal use only▲

DCPD6

DCPD6

1,DC input interface Dimensions: 43.6 (h) x 482.6 (w) x 228 (d)
2,Switch for DC output for 9 paths(20A*9 paths) (That means 1U space standard)
3,Connector for DC output 9 paths Weight: 5.0kg
4,LP_ALM provides lighting protection alarm(Dry contact output)

Maximum (6 RRUs)+(1 BBU) to be connected to a single DCPD6.


Notes:
1,The 6 RRUs mentioned not include R8863, R8863 should not be connected to DCPD6 because of single
R8863 got big power consumption.
2, 63A or 80A breaker in DC power system for DCPD6 will be provided by MTS.

We can find site wise DCPD configuration in ZTE input data.

© ZTE All rights reserved


7
Internal use only▲

DCPD7

DCPD7
1,DC input interface Dimensions: 43.6 (h) x 482.6 (w) x 228 (d)
2,Switch for DC output for 10 paths(25A*10 paths) (That means 1U space standard)
3,Connector for DC output 10 paths Weight: 5.0kg
4,LP_ALM provides lighting protection alarm(Dry contact output)

Maximum (4 R8863)+(1 BBU) to be connected to a single DCPD7


Notes:
1, The R8863 only can be connected to DCPD7, not DCPD6.
2, Other RRUs also can be connected to DCPD7, as a sample, (3 R8863)+(2 other RRUs)+(1 BBU) or (2
R8863)+(3 other RRUs)+(1 BBU) . (The mentioned “other RRUs” include all types RRU except R8863.
3, 80A breaker in DC power system for DCPD7 will be provided by MTS.

We can find site wise DCPD configuration in ZTE input data.


© ZTE All rights reserved
8
Internal use only▲

BBU and DCPD installation

1, To install on 2, To install in simplified wall 3, To install in existing


new 19’ rack mounting rack outdoor cabinet
© ZTE All rights reserved
9
Internal use only▲

Product Description – RRU (RRU types)

System GSM900M DCS1800M UMTS2100M

R8881,G(120
RRU type R8861, G R8863 G R8862, D R8882,D R8863,D R8861, U R8863 U
W)

RRU Qty. 227 386 78 678 538 307 603 136

Remark No Need Aisg No Need Aisg Need Aisg

We can find site wise RRU configuration in ZTE input data.

© ZTE All rights reserved


10
Internal use only▲

Product Description – RRU (R888X)

Dimensions
Type Weight
(H*W*D)mm
R8882 23Kg 480x320x150

R8881 R8882

Dimensions
Type Weight
(H*W*D)mm
R8881 18Kg 370x320x170

© ZTE All rights reserved


11
Internal use only▲

Product Description – RRU (R886X)

Type Weight Dimensions (H*W*D)mm


R8862 14Kg 422x218x133
R8862

R8861

Type Weight Dimensions (H*W*D)mm


R8861 18Kg 370x320x170

© ZTE All rights reserved


12
Internal use only▲

Product Description – RRU (R886X)

R8863

Type Weight Dimensions (H*W*D)mm


R8863 25Kg 440x360x133

© ZTE All rights reserved


13
Internal use only▲

DC Power Cable Size of RRU

Two core DC power cable with shield layer will be used for connection
between DCPD6 and RRU. Size of power cable as choosed below:

Power Max. cable run Max. cable run Max. cable run Max. cable run Max. cable run
Cable for for for for for
Size R8881 R8882 R8861 R8862 R8863
4mm2 >0m =<80m >0m =<55m >0m =<80m >0m =<55m >0m =<30m
6mm2 >80m =<120m >55m =<80m >80m =<120m >55m =<80m >30m =<45m
10mm2 >120m =<205m >80m =<145m >120m =<205m >80m =<145m >45m =<80m

ODCPD1 needed
for R886X if
2*10mm DC
cables used.

© ZTE All rights reserved


14
Internal use only▲

Different types of Fiber for different RRU


The type of BBU-RRU fiber for R888X and R886X is different.

Fiber for R888X: Fiber for R886X:


There is a protection sleeve for There is no protection sleeve
fiber at the RRU side for fiber at the RRU side

© ZTE All rights reserved


15
Internal use only▲

RRU installation components-RRU gantry installation

RRU installed on the Indoor RRU


Indoor RRU gantry
gantry

© ZTE All rights reserved


16
Internal use only▲

RRU installation components-Wall mount

Wall mount fixing bracket kit---One RRU need 1 set bracket

© ZTE All rights reserved


17
Internal use only▲

RRU installation components-”1-on-1 pole”

1 RRU fixing on pole kit-1 RRU need 1 set bracket

© ZTE All rights reserved


18
Internal use only▲

RRU installation components-”2-on-1 pole”

2 RRU combined fixing on 1 pole kit - 2 RRU need 1 set bracket

© ZTE All rights reserved


19
Internal use only▲

RRU installation components-”3-on-1 pole”

2 RRU combined fixing on 1 pole kit - 3 RRU need 1 set bracket


© ZTE All rights reserved
20
Internal use only▲

RRU installation components-”4-on-1 pole”

2 RRU combined fixing on 1 pole kit - 4 RRU need 1 set bracket


© ZTE All rights reserved
21
Internal use only▲

AISG-U2100 R8861-R8861 installed close to Antenna

Cell 3 Ant
Cell 1 Ant

Cell 2 Ant
AISG Only
for UMTS

R R R
E E E
T T T

AISG
AISG

AISG

AISG AISG AISG TX/RX RX


TX/RX RX TX/RX RX

R8861 R8861 R8861

R8861 installed close to Antenna-AISG cable maximum 20m long


© ZTE All rights reserved
22
Internal use only▲

AISG-U2100 R8861-R8861 installed not close to Antenna

Cell 1 Ant

Cell 2 Ant

Cell 3 Ant
R R R
E E E
T T T
AISG

AISG

AISG
ASBT ASBT ASBT

NSBT NSBT NSBT


AISG

AISG

AISG
AISG TX/RX RX AISG TX/RX RX AISG TX/RX RX

R8861 R8861 R8861

R8861 installed not close to Antenna-More than 20m © ZTE All rights reserved
23
Internal use only▲

AISG-U2100 R8863-R8863 installed close to Antenna

Cell 3 Ant
Cell 1 Ant

Cell 2 Ant
R R R
E E E
T T T
AISG cascading AISG cascading
AISG

AISG TX/RX RX TX/RX RX TX/RX RX

R8863

R8863 installed close to Antenna-AISG cable maximum 20m long


© ZTE All rights reserved
24
Internal use only▲

AISG-U2100 R8863-R8863 installed not close to Antenna

Cell 1 Ant

Cell 2 Ant

Cell 3 Ant
R R R
E E E
T T T
AISG cascading AISG cascading
AISG

ASBT

NSBT
AISG

AISG TX/RX RX TX/RX RX TX/RX RX

R8863 R8863 installed not close to


Antenna-More than 20m

© ZTE All rights reserved


25
Contents

1 TSSR output Procedure

2 ZTE Equipment Description

3 Engineering scenarios

4 Output Documents
Internal use only▲

Site configure types

N Site Site 3<RRU< 6<RRU< 9<RRU< 12<RRU 15<=RR


RRU<=3
o. type Qty =6 =9 =12 <=15 U
1 D 55 21 31 2 1

2 DG 18 1 8 5 3 1
3 DGU 125 13 69 17 15 11
4 DU 184 12 130 26 14 2
5 G 58 31 27
6 GU 5 1 3 1
7 U 19 19
Total 464 85 212 103 35 18 11

MTS input data

© ZTE All rights reserved


27
Internal use only▲

Site connection diagram


Connection Diagram shows detailed connection for RRUs and Antennas.

PO1_Mukachevo PO1_Uzhorod PO2_Lviv_80 PO3_Lviv&Rovn PO3_Khmelnytsk


o iy&Vinnytsa

Connection diagram
sample

© ZTE All rights reserved


28
Internal use only▲

Swap solution and scenarios

We can check Swap solution and scenarios in attached file.

Swap procedure

© ZTE All rights reserved


29
Internal use only▲

Sample of Swap solution and scenarios

Typical Swap Process _ Scenario 1 _G900/1800


Feeder/Jumper cable G 900/1800
Power cable
Transmission
ANT
Fiber optic
MW
Power
Power
After onoff
ZTE BSand
BBU disconnect
,download
works existing
the
normally, versionGand
connect 900/1800
dry by BS.
the file USB,
Disconnect
Install
connectBBU(with
contact the feeder
IP and
cable from
DCPD7/6)
transmission, antenna
to to
existing
let the
test dry alarm SIEMENS
19’ BTS.
BTS communicate
status,dismantle Power on
900/1800RRU
ZTE
rack
with orRRU
BSC
existing BSand
andconnect
Gantry, install to antenna
clean RRUs
site to tower.with
Lay jumper and feeder if
needed,
jumpers, Set Gcables
power 900/1800 on air fibers
and optical

BBU
DCPD7/6

Existing 19’’ rack Power Rack G 900/1800

© ZTE All rights reserved


30
Internal use only▲

Sample of Swap solution and scenarios

Scenario 1 - On-site Activity and Timetable

© ZTE All rights reserved


31
Internal use only▲

Antenna and RRU support Scenarios-Summary

Scenario
Scenario Description Scenario Ratio
No.
1 Shelter + Monopole 34%

2 Shelter + GF Guyed Master 8%


3 Shelter or Outdoor cabinet + RT Guyed Master 17%
4 Shelter or Outdoor cabinet + RT Pole 13%
5 Shelter + Brick chimney structure 7.5%
6 Shelter + Steel chimney structure 15%
7 Shelter + Self support tower 5.5%

© ZTE All rights reserved


32
Internal use only▲

Base station scenario 1

Scenario No. Scenario Description Scenario Ratio


1 Shelter + Monopole 34%

© ZTE All rights reserved


33
Internal use only▲

Base station scenario 2

Scenario No. Scenario Description Scenario Ratio


2 Shelter + GF Guyed Master 8%

© ZTE All rights reserved


34
Internal use only▲

Base station scenario 3

Scenario No. Scenario Description Scenario Ratio


Shelter or Outdoor cabinet
3 17%
+ RT Guyed Master

© ZTE All rights reserved


35
Internal use only▲

Base station scenario 4

Scenario No. Scenario Description Scenario Ratio


Shelter or Outdoor cabinet
4 13%
+ RT Pole

© ZTE All rights reserved


36
Internal use only▲

Base station scenario 5

Scenario No. Scenario Description Scenario Ratio


5 Shelter + Brick chimney structure 7.5%

© ZTE All rights reserved


37
Internal use only▲

Base station scenario 6


+34.000 Антени
Київстар
+32.000

+30.000
Антени МТС
DCS/UMTS

RRU DCS UMTS RRL

DCS 320 DCS


60 UMTS

UMTS

50
12

RRU DCS UMTS


DCS UMTS 240

Фідерний міст

Приміщення
котельні

Контейнер МТС

2300
2600

Scenario No. Scenario Description Scenario Ratio


6 Shelter + Steel chimney structure 15%

© ZTE All rights reserved


38
Internal use only▲

Base station scenario 7

Scenario No. Scenario Description Scenario Ratio


7 Shelter + Self support tower 5.3%

© ZTE All rights reserved


39
Contents

1 TSSR output Procedure

2 ZTE Equipment Description

3 Engineering scenarios

4 Output Documents
Internal use only▲

Documents output

MTS ZTE Subcon


DPR Softcopy Site photo

TSSR checklist Softcopy TSSR(.doc)


Cell Data
Connection Diagram Hardcopy TSSR with
signature + Scaned
Cell Data
BOM and site information Softcopy Drawing(.DWG
or other tools made)

Survey and Design documents folder sample(Electrical documents)

Survey Photos
Cell Data
TSSR(.Doc)
Drawing(.Dwg or .Vsd)
Scaned TSSR with MTS signature
© ZTE All rights reserved
41
Internal use only▲

Documents output

TSSR(.Doc) sample Scaned TSSR with MTS signature

LVI_SNB_MUK.p
LVI SNB df
MUK_ок.

Photos folder defination

Antenna mount structure Photos

Cell coverage with cell mark Photos

Shelter or outdoor cabinets Photos

Panoramic Photos(12 photos with azimuth


mark

Other Photos
© ZTE All rights reserved
42
Internal use only▲

Overview Status of region sites

Till 2015-10-4
Site Qty of TSSR&Drawing TSSR&Drawing
PO Batch Region Site Qty. of Region TSS Done BOM finished
PO Batch prepared Signed
Uzhorod 87 87 87 87 87
PO_1 133
Mukachevo 46 46 46 46 46
PO_2 80 Lviv 80 80 80 80 80
Lviv 62 62 61 61 62
PO_3 166 Rovno 58 58 57 57
Vinnytsa 46 46 46 46
Ternopil 53 53 53 53
PO_4 85
Khmelnytskiy 32 32 25 24
Total 464 - 464 464 455 454 275

BOM finished 59%

TSSR&Drawing Signed 98%

TSSR&Drawing prepared 98%

TSS Done 100%

0% 20% 40% 60% 80% 100% 120%

Completion Ratio
© ZTE All rights reserved
43
Internal use only▲

Documents needed for installation

Doc for Site Installation team


TSSR(Drawing
Cell Data
included)

Connection Board position


Diagram Diagram

© ZTE All rights reserved


44
Thank you