Вы находитесь на странице: 1из 6

Geotechnics Fundamentals and Applications in Construction – Mangushev et al.

(Eds)
© 2019 Taylor & Francis Group, London, ISBN 978-0-367-17983-0

Surcharge preloading as a method for engineering reservoir


foundations in silty soils

A.A. Ananyev
Saint-Petersburg State University of Architecture and Civil Engineering, Saint-Petersburg, Russia

ABSTRACT: When a construction site is, geologically, composed of thick layers of soft, water-satu-
rated, clayey soil, piled foundations are economically unviable and surcharge preloading is used as soil
consolidation method. With general intention to introduce surcharge preloading into the practice of con-
struction engineering, in this study the author aims to determine the dimensions of the surcharge fill;
and the time needed for the silty soils that comprise the foundation of the reservoir to be consolidated, to
reach the required degree of consolidation. The results of the geological engineering survey are presented
in the article. Description is given of the water reservoir design. Rationale is provided of the foundation
deformation design diagram. The fill settlement monitoring results are presented, as well as calculation of
the silt consolidation coefficient. Calculations were carried out of strength, deformation, and consolida-
tion of the foundation, based on soil engineering theories and building regulations. It was found expedient
in the soil conditions under analysis to apply the surcharge load to the foundation for it to yield to the
maximum allowed level. The dimensions of the surcharge fill were calculated, as well as the time needed
for the settlement to reach the target level. This article is recommended for use by design engineers as ref-
erence materials for foundation calculation or road bed design, as well as by students as a study aid.

1 INTRODUCTION parameters of fill and reservoir foundation; and


surcharge fill design development.
The mechanical and physical properties of silts
include high porosity and water saturation, low
strength, high plasticity, low permeability, lengthy 2 GEOTECHNICAL SURVEY RESULTS
consolidation, and thixotropy (Neizvestnov et  al.
2004). In general practice, the foundations com- Geologically, the site for the projected water sup-
posed of or including silts may not be used as ply line is represented, within the drilling depth of
natural foundations of buildings or structures, as 19–20  m, by superimposed layers of quaternary
their estimated deformation appears to be higher deposits. A total of three engineering geological
than the ultimate one or their bearing capacity is elements (EGE) have been identified. The surface
too low. Where silty soils are thick, the use of piled
foundations for structures that convey only minor
downward forces into foundations – low-rise build-
ings, airfield or road paving, etc. – appears techni-
cally and economically unviable. In this case, more
expedient is fill surcharge preloading (Ilyichev
et al. 2016, Stroganov 1985).
In this regard, the author aims to provide a
rationale for the use of surcharge preloading as
a method of preconstruction consolidation of
a water reservoir foundation. The analysis aims
to determine the height and dimensions of the
surcharge fill, and the time needed for the silty
foundation to consolidate and reach the required
settlement. The methods of the analysis included Figure 1. Lithological column and reservoir foundation
surveying of building regulations and reference design diagram: 1 − water-saturated, medium-density
literature; geotechnical survey; monitoring of sandy silt (EGE 1); 2 − mineral loamy silt (EGE 2); 3 −
the foundation settlement; calculations of the fine, water-saturated, medium-density sands (EGE 3).

10

GFAC219_Book 1.indb 10 4/8/2019 10:53:01 AM


Table 1. Mechanical and physical properties of soil. water filtration, rely on the theory of filtration
consolidation, first proposed by K. Terzaghi in
Soil parameter Sand Silt 1924 and improved by Russian scientists N.M.
Gersevanov and V.A. Florin, among others. In its
γ − specific weight, kN/m3 16.4 14.1
simplest version, the theory describes deformation
e − porosity factor, unit fraction 0.76 2.5
of a completely water-saturated soil, i.e. soil mass.
ϕ − internal friction angle, degree 22 6
In many cases, variation of stressed-deformed
c − specific cohesion, kPa 2 11
state in time can be analyzed within the framework
E − modulus of deformation, MPa 10 0.6
of one-dimensional problem of filtration consoli-
ν − Poisson’s ratio, unit fraction 0.23 0.4
dation in soil layer.
k − filtration coefficient, m/day 3.5 0.01 The compressible strata of the foundation of
the reservoir comprises two engineering-geological
elements. The bearing layer is water-saturated,
layer is water-saturated, medium-density sandy silt medium-density sandy silt (EGE 1). Under the cen-
(EGE 1). This layer has a thickness of 7 ÷ 8.5 m. tral part of the footing of the reservoir, its layer has
The sandy silt is underlain by 7.5 ÷ 9.5  m thick height h1 = 6.3 m. EGE 1 is underlain by silt with
layer of mineral loamy silt (EGE 2), which, in turn, layer height h2 = 8.5 m (EGE 2). Let us not take into
is underlain by fine, water-saturated, medium-den- account the compressibility of sand (EGE 3) with
sity sands (EGE 3). Their penetrated thickness is layer height h3 = 3 m, because the sand has a modu-
3 m. Groundwater occurs in the sandy silt (EGE 1) lus of deformation which is 10 times higher than
at the depth of 0.4 ÷ 1.5 m from the surface of the that of silt. The lower boundary of the compressible
natural terrain (Fig. 1). strata of the foundation is set at Hc = 14.8 m (Fig. 1).
The mechanical and physical properties of the Since the footing of the reservoir has breadth
soil under analysis (EGE 1, EGE 2) are shown in b = 36 > 10 m and the ratio Hc/b = 14,8/36 = 0,41 < 1,
Table 1 (Ivanov et al. 2015). the variation of stressed-deformed state of soil dur-
ing filtration consolidation can be analyzed within
the framework of one-dimensional problem.
3 RESERVOIR DESIGN Let us determine other mechanical and physical
properties of the soil required for further calcula-
The 10.000 m3 water storage reservoir is designed tions. In the compressible strata, all pores are filled
to form part of a potable water supply system. It is with water. The specific weight of sand γ1sb and silt
a rectangular, composite, ferro-concrete tank with γsb2 is calculated with account of the suspension
dimensions l × b × h = 60 × 36 × 4.8 m to be embed- action of water as follows:
ded in soil to depth d = 1.7 m (Fig. 1) and designed
for a 2 m groundwater dam. γ s γ w 26 − 10
γ sb1 = = = 9,1 kN / m 3 (1)
1+ e1 1+ 0, 76
4 RATIONALE FOR THE FOUNDATION γ s γ w 24 − 10
SOIL SETTLEMENT CALCULATION γ sb 2 = = = 4, kN / m 3 (2)
1+ e2 1+ 2, 5
The building codes for large-scale construction
where γs1 = 26  kN/m3 is specific weight of sandy
projects prescribe that the settlement of founda-
soil particles p.2.180 (Sorochan et  al. 1986); γs2 =
tions be calculated with the use of linearly elastic
24 kN/m3 is specific weight of loamy silt particles
half-space design model with conventional height of
(Ananyev et  al. 2014); γw = 10  kN/m3 is specific
compressible strata Hc (Code 22.13330.2016 “Con-
weight of water. Coefficients β1 and β2 which takes
struction Norms and Regulations 2.02.01–83* Foun-
into account the absence of transverse extension
dations of Buildings and Structures”). This model
under compression, will be calculated as follows:
is commonly used in engineering practice as it is
simple, allows the use of mathematical tools of elas-
2ν12 2 0, 232
ticity theory, is standardized and therefore requires β1 = 1 − = 1− = 0, 863 ; (3)
no additional verification. The validity limit of this 1 − ν1 1 0, 23
model is defined as the limitation of superload,
2ν 2 2 2 0, 4 2
within the compressible strata, by estimated soil β2 = 1 − = 1− = 0, 467, (4)
resistance R. With regard to estimating settlements 1 − ν2 1 0, 4
of road embankments, the pressure must not exceed
safe load psec (Kazarnovsky et al. 2004). where ν1 = 0.23 and ν2 = 0.4 are transverse defor-
The current methods for predicting consolida- mation coefficients of sand and silt, respectively,
tion of clayey soils in conditions of very slow-rate found based on the survey data.

11

GFAC219_Book 1.indb 11 4/8/2019 10:53:01 AM


5 CALCULATION OF FINAL where γc1 = γc2 = 1 are operating conditions coef-
SETTLEMENT OF RESERVOIR ficients from Table 5.4 for liquidity index IL > 0.5
FOUNDATION and flexible structure design; k = 1 is coefficient
used because the strength characteristics of soil are
5.1 Monitoring of foundation footing dimensions survey-based; kz = z0/b + 0.2 = 8/36.5+ 0.2 = 0.42 is
The calculation orients to the underlaying layer of coefficient used because b > 10 m; γ2sb = 4 kN/m3 is
silt, as the bearing layer of sand has higher strength. specific weight of silt with account of suspension
The formula and coefficients used in the calcula- action of water; γ ′ = (γ1⋅0.5 + γ1sb⋅7.5)/dz = (16.4⋅0.5 +
tion are from Building Code 22.13330.2016. 9.1⋅7.5)/8 = 9.6  kN/m3 is mean specific weight of
The mean pressure across the footing of the res- the sand above the footing of the conventional
ervoir of breadth b = 36  m during the operating reservoir; Mγ = 0.1; Mq = 1.39; Mc = 3.71 are the
period is p = σzp0 = 69  kPa (Fig. 1). The vertical coefficients from Table 5.5 depending on internal
intensity σzp1 in soil at depth z1 = 6.3  m from the friction angle of silt ϕ2 = 6°; c2 = 11 kPa is specific
footing of the reservoir, which presses on the sur- cohesion of silt (Table 1).
face of the silt layer, equals: Let us compare the actual load σz on the surface
layer of silt with Rz
σ zp1 α 1 p = 0, 9775 ⋅ 69 = 67 kPa (5)
( )
σ z σ zp1 − σ zγ 1 + σ zg1 = ( − ) + 76 = (10)
where α1 = 0,9775 is coefficient from Table  5.8 125 < 154 kPa
dependent on relative depth ζ = 2z1/b = 2⋅6,3/36 =
0.35 and height-to-width ratio η = l/b = 60/36 = which means that the condition is satisfied and
1.67. Vertical dead stresses of soil σzg0 and σzg1 that the footing of the foundation slab has suf-
equal: at foundation footing d = 1.7 m ficient dimensions. The linearly elastic half-space
design model is suitable for calculating the settle-
σ zg 0 γ ′ d = 11, 3⋅ 1, 7 = 19 kPa (6) ment of the foundation of the reservoir.

at depth z1 = 6.3 m from the footing of the reservoir


5.2 Calculation of final settlement of foundation

σ zg1 = σ zgg 0 + γ 1sb h1 = 19 + 9,1⋅ 6, 3 = 76 kPa (7) Let us calculate the settlement using the layerwise
summation method. Height h1 = 6.3  m and h2 =
8.5  m of the estimated soil layers that comprise
where γ ′ = (γ1 ⋅ 0.5 + γ1sb ⋅ 1.2)/d = (16.4 ⋅ 0.5 + 9.1 the compressible strata. do not exceed 0.4b =
⋅ 1.2)/1.7 = 11.3 kN/m3 is mean specific weight of 0.4⋅36 = 14.4  m. Loads σzp2 = 59  kPa. σzg2 =
the sand (dry and water-saturated) above the foot- 110 kPa and σzγ2 = 16 kPa at z2 = 14.8 m at com-
ing of the reservoir; and γ1sb = 9.1 kN/m3 is specific pressible strata height Hc (Fig. 1) are calculated
weight of sand calculated with account of suspen- on analogy with 5.1.
sion action of water. The design dimensions of the Let us calculate the average stabilized settlement
reservoir are lk × bk = 62 × 38 m. Let us calculate the under the center of the reservoir according to for-
dead stress of the soil excavated from the reservoir mula (5.16).
at z1 = 6.3 m using the formula:

σ zγ ασ γ0 = 0, 9783⋅ 19 = 18 kPa (8)


s = β⎢
( )
⎡ σ zp1 − σ zγ 1 h1
+
(σ zp
z )
− σ zγ 2 h2 ⎤
⎥ =
⎢⎣ E1 E2 ⎥⎦
where α1 = 0.9783 is the coefficient from Table 5.8 ⎡( − ) 6,3 + ( − ) 8,5 ⎤ (11)
depending on relative depth ζ = 2z1/bk = 2⋅6.3/38 = 0, 8 ⎢ ⎥ =
0.33 and height-to-width ratio η = lk/bk = 62/38 = ⎣ 1
10000 600 ⎦
1.63. 0,02 + 0,52 = 0,54 M,
The design strength Rz of silt will be calculated
for conventional foundation with breadth b =36 m where β = 0.8 is coefficient; σzp1 = 68 and σzp2 =
at depth dz = d + z1 = 1,7 + 6,3 = 8 m (Fig. 1) using 63  kPa; σzγ1 = 18.5 and σzγ2 = 17  kPa are average
formula (5.7) stresses in estimated layers of sand h1 = 6.3 m and
silt h2 = 8.5 m; E1 = 10,000 kPa and E2 = 600 kPa
γ c γ c2 are survey-based moduli of deformation of sand
Rz =
k
(M k b z z sb
Mqdz ′ M cc ) = 11⋅ 1 (EGE 1) and silt (EGE 2), respectively, (Table 1).
According to Table D.1 of Building Code
( 0,1⋅ 0, 42 ⋅ 36, 5 ⋅ 4 + 1, 39 8 9 6 3 71⋅ 11) = 154 kPa
22.13330.2016, the average ultimate settlement
(9) of buildings and structures prone to differential

12

GFAC219_Book 1.indb 12 4/8/2019 10:53:02 AM


settlement is limited to 10 cm. The calculated set- 64 kPa roughly equaled the operating load of the
tlement of the foundation of the reservoir exceeds reservoir. To monitor the process of compaction
the one prescribed by the Building Code more than of the foundation as it was being preloaded, set-
five times. It is therefore inexpedient to lay the res- tlement points were put on the central part and
ervoir foundation slab without prior improvement the sides of the surcharge fill. The settlement of
of silt layer. The soil is too soft to install a piled foundation was monitored during and after the
foundation in it. In the given soil conditions, it is erection of the fill. The maximum settlement st1
expedient to reduce the settlement of foundation = 25  cm was registered, according to the central
to the maximum allowed level of 10  cm by way point, after t1 = 175 days = 6 months (Fig. 2).
of consolidating the foundation using surcharge The obtained data was used for calculating the
preloading. consolidation coefficient based on the following
principle: the pressure for the final settlement of
the foundation of the fill is pe1 = 64 kPa.
5.3 Prediction of consolidation in silt layer
To predict the time needed for silt to consolidate, ⎛ β1h1 β 2 h2 ⎞
s 1 = pe1 + =
E2 ⎟⎠
one should calculate consolidation coefficient cv,
the core soil parameter. For silt, it will be calcu- ⎝ E1
lated according to formula (6.35) (Dalmatov et al. ⎛ 0, 863⋅ 8 0, 467 ⋅ 8, 5 ⎞
64 ⎜ + ⎟ = (14)
2006): ⎝ 10000 600 ⎠
0, 044 + 0, 422 = 0, 466M
466 = 47 4 cm,
k2 1 10−2
cv 2 = = = 1, 25 2
/ day, (12)
mv 2 ⋅ γ w 8 10 4 10 where h1 = 8 m, h2 = 8,5 m are thicknesses of sand
and silt, respectively; β1 and β2 are the same as in
where mv2 = β2/E2 = 0,467/600 = 8⋅10−4 kPa−1 is rela- (3) and (4); E1 and E2 − are the same as in (11).
tive soil compressibility coefficient; k2 = 0.01 m/day The degree of consolidation will be calculated
and E2 = 600 kPa are survey-based filtration coef- as follows:
ficient and modulus of deformation of silt, respec-
tively; β2 = 0/467 is coefficient of absence of lateral st1 25
U 0= = = 0, 532. (15)
expansion of soil, found in Section 4. s∞1 47
Assuming that water will be squeezed out from
silt upwards and downwards (double-sided filtra- Limiting the calculation to one term of the dif-
tion) into sand, the consolidation time is found ferential equation of one-dimensional problem of
using formula (6.36): soil consolidation

h22 N 8, 52 ⋅ 2, 8 θ0 1 8 π 2 ⋅e−N , (16)


t= = = 16, 4 days, (13)
π 2 ⋅ cv 2 3,14 2 ⋅ 1, 25
let us determine N parameter using formula:
where N = 2.8 is coefficient from Table  6.14 for
cases of single-axis consolidation by continuous
e−N =
( − U )π 2
=
( − ) 3,142 = 0, 577, (17)
load (case 0) at the degree of soil consolidation of 8 8
U0 = 0.95.
Practice shows that the silt occurring in reser- then N = 0.550.
voir foundations takes years to consolidate (Ave- Given that the boundary surfaces of the silt
lev 1983). For this reason, the decision was taken layer are draining, let us use the following formula:
to preload the foundation with surcharge and to
determine the consolidation coefficient by way of
monitoring the consolidation process in time.

6 DETERMINATION OF SILT
CONSOLIDATION COEFFICIENT

The surcharge fill of he1 = 4  m was being laid in


layers of local sand during two months until it
reached compaction coefficient kcom = 0.95. With Figure  2. Increase in the settlement of the preloaded
the specific weight of soil γe = 16 kN/m3, the pres- foundation with time: 1 – fill height he1 = 4 m (pe1 = 64 kPa;
sure under the footing of the fill pe1 = γehe1 = 16⋅4 = γe =16 kN/m3); 2 – fill height he2 = 6 m (pe2 = 94 kPa).

13

GFAC219_Book 1.indb 13 4/8/2019 10:53:04 AM


π 2cvt
N= , (18)
h22

to determine the consolidation coefficient:

h2 2 N 8, 52 ⋅ 0, 550
cv = = = 0, 023 2
/ day, (19)
π2⋅t 3,14 2 ⋅ 175

Comparing the consolidation coefficient calcu-


lated using formula (12) and (19), it is evident that
one exceeds the other by two orders of magnitude.

7 DETERMINATION OF SURCHARGE
FILL DIMENSIONS AND FOUNDATION
CONSOLIDATION TIME Figure 4. Calculation diagram: Final settlement of the
foundation of the 6 m high fill.
As a result of the benchmarking of the consolida-
tions achieved by foundations of 4 m, 5 m and 6 m Let us analyze the soft underlying layer for strength
high fills, the fill with he2 = 6 was selected as the using the formulas and coefficients given in (Kazar-
most optimal to ensure adequate surcharge. novsky et al. 2004).
In accordance with sec.17.2.2 (Building Code Safe load will be calculated as follows:
45.13330.2012 “Construction Norms and Regula-
tions 3.02.01–87 Earthwork Structures and Foun- ⎡( + ⋅ ⋅ )⎤ =
psec = ⎢ sb
b

dations”), the top width of the fill had to 2 m wider ⎣ β ⎦ min
than the dimensions of the reservoir le × be = 64 ×
⎡( + ⋅ ⋅ °)⎤
40 m; slope angle 1:2,5; steepness of slope a = 6⋅2,5 = ⎢ ⎥ = (20)
15 m. Then, the bottom dimensions of the fill are ⎣ 0,195 ⎦ min
let × bet = 94 × 70 m. A 0.5 m thick drainage layer ⎡( + ⋅ ⋅ ) ⎤ = 96 kPa
needs to be laid under the fill. ⎢ ⎥
⎣ 0,195 ⎦ min
Figure 3 shows the layout and longitudinal pro-
file of the surcharge fill. The design load on the
foundation is pe2 = γehe2 = 16⋅6 = 96  kPa (Fig. 4). where c2 = 11  kPa and ϕ2 = 6° are strength para-
termers of silt; γ1sb = 9.1 kN/m3 is specific weight
of silt with account of suspension action of water;
z1 = 8 m is the depth of the silt payer from the earth
surface; and β = 0.195 is safe load coefficient deter-
mined based on the graphs in Appendix 4, repre-
sented as a function of parameters β = ƒ(ϕ2 = 6°;
a/b = 15/40 = 0.375; 2z1/be = 2⋅8/70 = 0.23), using
linear interpolation method.
Let us calculate the stability coefficient of the
silt layer as follows:

psec 96
kst = = = 1, (21)
pe 2 96

which means that the condition of stability is


satisfied. It is clear from the comparison of Rz =
154 kPa and psec + γ1sb h1 = 96 + 9,1⋅8 = 169 kPa that
their values are close.
Let us calculate the final settlement of the foun-
dation at load pe2 = 96 kPa using formula (14). It
equals s2∞ = 70 cm.
The prediction of the compaction of the foun-
Figure 3. Surcharge fill dimensions diagram: a – fill lay- dation under the fill uses consolidation coeffi-
out; b – longitudinal profile. cient cv = 0.023 m2/day. Points of time ti and their

14

GFAC219_Book 1.indb 14 4/8/2019 10:53:05 AM


correspondent settlements sti will be calculated as preloading. Our prediction of the compaction of
follows: the foundation in time relied on the theory of fil-
tration consolidation of soils. The consolidation
h22 Ni 8, 52 ⋅ Ni coefficient was determined for silt based on the
ti = = = 319 ⋅Ni . (22) field monitoring of the settlement of surcharge
π ⋅ cv 3,14 2 ⋅ 0, 023
2
fill. Based on the calculation results and the work
method, the dimensions of the surcharge fill
(Fig. 3) were determined, as well as the time needed
sti U 0 i s∞ 2 , (23)
for the foundation to reach the target settlement,
which totaled one year.
where Ni = 0,02; 0,08; 0,17; 0,31; 0,49; 0,71; 1,0;
1,4; 2,09; 2,8 are coefficients from Table  6.14
(Dalmatov et al. 2006) at soil consolidation degree REFERENCES
U0i = 0,1; 0,2; 0,3; 0,4; 0,5; 0,6; 0,7; 0,8; 0,9; 0,95,
respectively. Abelev, M.Y. 1983. Erecting Industrial and Civil Projects
In Figure  2, the results are shown in graphical on Loose, Water-Saturated Soils. M.: Stroyizdat.
form. Considering the estimated settlement s = Ananyev, V.A. et  al. 2014. Prediction of the Settlement
54 cm and the ultimate settlement su = 10  cm of of Subsea Production Unit in the Pacific Ocean. Pro-
the foundation, it is necessary that the surcharge ceedings of the International Geoengineering Confer-
preloading to be performed prior to the construc- ence “Current Geoengineering Technologies: R&D”.
tion of the reservoir, targets the settlement of Vol. 1. SPb:SPbGASU. pp. 527–536.
Dalmatov, B.I. et  al. 2006. Designing Foundations and
44 cm. As follows from Diagram 1, the settlement Underground Spaces. M: ACB.
achieved by the trial fill over a 6-months’ time was Ilyichev, V.A., Mangushev, R.A. et al. 2016. Guidebook
st1 = 25 cm. As can be seen from Diagram 2, for of Geoengineering. Foundations and Underground
the foundation to achieve the remaining 19 cm, it Spaces. M.: ACB.
needs to be preloaded with 6 m high fill and be left Ivanov, V.A. et  al. 2015. Engineering Survey of Zele-
to compact for another 6  months. The total con- nogorsk-Reshetnikovo Water Pipeline. Technical
solidation time will in this case will be 1 year. Once Report. SPb.: Contour Ltd.
completed, the filled-up ground could be used as a Kazarnovsky, V.D. et  al. 2004. Guidebook: Designing
material for site area planning. Road Beds on Loose Soils. M.: RosAvtodor.
Neizvestnov, Y.V. et al. 2004. The Engineering Geology
of Ore Mining Province Clarion-Clipperton in the
Pacific Ocean. In Proceedings of RAS and RF Minis-
8 CONCLUSION try of Natural Resources’ Research Institute of Ocea-
nology. Vol. SPb.: Nauka.
The geological structure of the foundation of the Sorochan, E.A. et al. 1986. Guidebook on Designing the
reservoir contains a layer of silt which accounts for Foundations of Buildings and Structures (to Code
more than a half of the compressible strata. The 2.02.01–83). N.M. Gersevanov Research and Design
calculated settlement of the reservoir foundation Institute. M.: Stroyizdat.
exceeds the allowed average ultimate settlement, Stroganov, A.S. et al. 1985. Recommendations on Pre-Con-
struction Preloading Reinforcement of Loose Water-
prescribed by the building codes, more than five Saturated Soils by Using Geodrains. N.M. Gersevanov
times. In the given soil conditions, it is expedient Research and Design Institute. M.: Stroyizdat.
to improve the layer of silt by way of fill surcharge

15

GFAC219_Book 1.indb 15 4/8/2019 10:53:06 AM

Вам также может понравиться