Concrete Volume Total Concrete Material Quantity (per Single Unit) Material Quantity (Total)

Location QTY UNIT Strength (Mpa)


(m^3) Volume (m^3) Cement (bags) Cement (bags) Cement (bags) Cement (bags) Sand (cu.m) Gravel (cu.m) Cement (bags) Sand (cu.m) Gravel (cu.m)
1. Abutment 2 set/s 60.36 120.72 724.32 60.36 724.32 60.36 30.18 60.36 1448.64 60.36 120.72 28
2. Approach Slab 2 set/s 10.95 21.9 131.4 10.95 131.4 10.95 5.48 10.95 262.8 10.95 21.9 28
3. Bored Pile 36 set/s 152.05 5473.8 1824.6 2736.9 1824.6 2736.9 76.03 152.05 65685.6 2736.9 5473.8 28
4. Pier 1,2,3,5,6,8,9 7 set/s 53.73 376.11 644.76 188.06 644.76 188.06 26.87 53.73 4513.32 188.06 376.11 28
5. Pier 4 & 7 2 set/s 56.76 113.52 681.12 56.76 681.12 56.76 28.38 56.76 1362.24 56.76 113.52 28
6. Pier 10 & 13 2 set/s 68.82 137.64 825.84 68.82 825.84 68.82 34.41 68.82 1651.68 68.82 137.64 28
7. Pier 11,12,14,15,16 5 set/s 65.79 328.95 789.48 164.48 789.48 164.48 32.9 65.79 3947.4 164.48 328.95 28
8. Prestressed Girder 68 set/s 19.61 1333.48 274.54 666.74 274.54 666.74 9.81 19.61 18668.72 666.74 1333.48 37.7
9. Superstructure (3-span) 3 set/s 228.74 686.22 2744.88 343.11 2744.88 343.11 114.37 228.74 8234.64 343.11 686.22 28
10. Superstructure (4-span) 2 set/s 311.79 623.58 3741.48 311.79 3741.48 311.79 155.9 311.79 7482.96 311.79 623.58 28
10% CEMENT 30% 30% 3/4" TOTAL TOTAL 3/4"
SAND GRAVEL cement SAND GRAVEL
144.864 18.108 36.216 1593.504 78.468 156.936
26.28 3.285 6.57 289.08 14.235 28.47
6568.56 821.07 1642.14 72254.16 3557.97 7115.94
451.332 56.418 112.833 4964.652 244.478 488.943
136.224 17.028 34.056 1498.464 73.788 147.576
165.168 20.646 41.292 1816.848 89.466 178.932
394.74 49.344 98.685 4342.14 213.824 427.635
1866.872 200.022 400.044 20535.59 866.762 1733.524
823.464 102.933 205.866 9058.104 446.043 892.086
748.296 93.537 187.074 8231.256 405.327 810.654
124583.8 5990.361 11980.696
CONCRETE MATERIAL RE
TOTAL
CONCRETE
Item Description Unit
VOLUME for Cement Unit S1-Sand Unit
BRIDGE ONLY

1. Abutment 120.72 cu.m 1,593.50 bag 78.47 cu.m


2. Approach Slab 21.90 cu.m 289.08 bag 14.24 cu.m
3. Bored Pile 5,473.80 cu.m 72,254.16 bag 3,557.97 cu.m
4. Pier 1,2,3,5,6,8,9 376.11 cu.m 4,964.65 bag 244.48 cu.m
5. Pier 4 & 7 113.52 cu.m 1,498.46 bag 73.79 cu.m
6. Pier 10 & 13 137.64 cu.m 1,816.85 bag 89.47 cu.m
7. Pier 11,12,14,15,16 328.95 cu.m 4,342.14 bag 213.82 cu.m
8. Prestressed Girder 1,333.48 cu.m 20,535.59 bag 866.76 cu.m
9. Superstructure (3-span) 686.22 cu.m 9,058.10 bag 446.04 cu.m
10. Superstructure (4-span) 623.58 cu.m 8,231.26 bag 405.33 cu.m
TOTAL 9,215.92 cu.m 124,583.80 bag 5,990.36 cu.m
Note: Total Qty are still under final review and evaluation as per approved plans (Concrete requirements for Bridge only)
CONCRETE MATERIAL REQUIREMENTS
G1
1/2" 3/8"
3/4" Crushed Unit crushed Unit crushed Unit Crushed/r Unit
Gravel ounded
Gravel Gravel
Gravel
156.94 cu.m - cu.m - cu.m cu.m
28.47 cu.m - cu.m - cu.m cu.m
7,115.94 cu.m - cu.m - cu.m cu.m
488.94 cu.m - cu.m - cu.m cu.m
147.58 cu.m - cu.m - cu.m cu.m
178.93 cu.m - cu.m - cu.m cu.m
427.64 cu.m - cu.m - cu.m cu.m
1,733.52 cu.m - cu.m - cu.m cu.m
892.09 cu.m - cu.m - cu.m cu.m
810.65 cu.m - cu.m - cu.m cu.m
11,980.70 cu.m - cu.m - cu.m - cu.m
e requirements for Bridge only)
Remarks

Priority, w/ PR#135341, No PO yet

waiting for final decision for the changes