Вы находитесь на странице: 1из 18

Province:Farah

Distric: Purchaman
Willge: warg
CDC/CCDC ID # : 21-2104-M0033-1-A
1. Design of Total Water Demand (TWD) Calculation
General Information Quantity Unit
Spring discharge 0.4 lit/sec
Present Population(Po) 67 family
Num of Family 6 person
Design Period (N) 10 Year
Growth Rate (GR) 2 %
Peak Factor (PF) 1.2 constant
Wastage - Leakagae (WL) 1.2 constant
Water Demand (WD) 25 lit/capital.day
Population in N year (PN)= Po
PN =67*6 (1+ 2/100)10 490 Person
N
(1+ GR/100)
Total Water Demand (TWD) =
lit/day-
TWD = 490* 25 * 1.2 * 1.2 17641 18
PN * WD * PF * WL night

2. Water Reservoir Capacity Calculation Based on villager Consumption TIME PATTRON

Yield of source 0.4 Lit/sec


Timep period Source Supply (liter) Village demand(lit)

06:00 Am - 09:00 AM- 3 hour 4320 4410 25% total demand


09:00 Am-05:00 PM- 8 hour 11520 8821 50% total demand
05:00 Pm-10:00 PM- 5 hour 7200 4410 25% total demand
10:00 Pm - 06:00 Am-8hour 11520 Negligible Total
Total
2nd alternative of WR Capacity as per
st
1 alternative of WR Capacity as per source source
liter

We can assume total water reservoir capacity 10% additional factor for its good
capacity=>11520+11520*10/100=12672m 3

Village population =67 families


Expected Population growth in 10 years at a 2% (growth rate. Number of family calculated 6 persons
Water demand calculated 25 lit/cap. day
Peak demand factor considered 1.2
Leakage and wastage factor considered 20% (1.2) for the system Pipe line extend with PE pipes

stand tap and line discharge calculation


A.stand taps and water demand calculation table

total
present water
stand taps families families water demand deman
d
STP1 17 6 102 124 4352
STP2 17 6 102 124 4352
STP3 16 6 96 117 4096
STP4 17 6 102 124 25 1.4 4352
STP5 0 6 0 0 0
STP6 0 6 0 0 0
STP7 0 6 0 0 0
67 402 17151
Line discharge calculation as per network path

B-Line discharge calculation

Discharge
Line Mark Calculation Remarks
L/sec
Stp7-Stp 6 Q1 0.0590 As per Stand tap table calculation
Stp6-Stp 5 Q2 Q1+Q2=0.059+0.059=0.118 lit/sec
Stp4-Sp3 Q3 0.0500 As per Stand tap table calculation
Stp 3-Sp1 Q4 0.0970 Q3+Q4=0.047+0.05=0.097 lit/sec
Stp1-Stp2 Q5 0.1000 Q1+Q2=0.05+0.05=0.1 lit/sec
Stp2-Sp1 Q6 0.0500 Q1+Q2=0.05+0.05=0.1 lit/sec
Stp1-WR Q7 Q6+Q7=0.352+0.059=0.42 lit/sec
490

1.218

m3/day

Diffence

-90
2699
2790
11520 10%
16919
WR Capacity as per
urce 1152 12672
liter

s
86400 1.21

discharg
e/sec
Demand
/86400

0.050 1.219
0.050
0.047
0.050
0.000
0.000
0.000
0.199

Remarks
#VALUE!
Distribution Lines Hydraulics Calculation in total length 0f ( 2386.65
Line head loss calculation length elevation(m)
5% t
ofotal dischrge
length(m) fitting
lengte total lit/sec
from to equivelant Upper lower Diffrence
duebto length(m)
length (m)
pipe
indirect
Spring WR 5000 250.00 5250.00 250.00 224.000 26.00 0.4
WR A 460 23.00 483.00 224.00 212.000 12.00 0.05
A B 920 46.00 966.00 212.00 200.000 12.00 0.1
B C 250 12.50 262.50 200.00 190.000 10.00 0.097
B D 300 15.00 315.00 190.00 180.000 10.00 0.05
B E 0 0.00 0.00 0.00 0.00 0
E F 0 0.00 0.00 0.00 0.00 0
F G 0 0.00 0.00 0.00 0.00 0
6930 346.50 7276.50
n total length 0f ( 2386.65m )

pipe
pipe market
velocity fraction Remaining
inside T.HL(m) available remarks
(m/sec) factor(mm) pressure(m)
Dia(mm) outside
dia (mm)

38 0.5 0.1 525 -499.00 38 1.5 inch 25.4


13 0.5 0.1 48.3 -36.3 13 0.50 25.4 2 elbow and valve
25 0.5 0.09 86.94 -74.9 25 1.00 tee 2inch/2inch
25 0.5 0.35 91.875 -81.9 25 1.00
13 0.5 0.1 31.5 -21.5 13 0.50
0 0 0 0 0.0 0 0.00
0 0 0 0 0.0 0 0.00
0 0 0 0 0.0 0 0.00
2 elbow and valve
2inch/2inch
CCNPP

Bill Of Quantity (BoQ) Water Reservoir 14 M3


ID-number CDC/CCDC ID # 2: 1-2104-M0075-1-A
Province: Farah
District: Purchaman
Village: shin jimin
Project purpose: Water reservoir V = 14.0 m3 Estimated total project cost = Afs
Date: 2020 / 02 /20
Bold items to be filled by in Tenderer (A1,A2,A3…..An). light items for cost estimation
No. Contribution
unit
Nor
m/

Title Norm Item Quantity Unit Unit cost Total cost


CDC, Afs CCAP, Afs
A1 1.00 Site preparation 19.0 md 14 266 266 -
1.01 0.04 Site preparation, clearing site ect. 0.8 md 350 266 266 -
Preparation of site for the project, preparation of hand tools etc
A2 2.00 Foundation excavation 40.0 m3 280 11,200 11,200 -
2.01 0.8 Unskilled labour 32.0 md 350 11,200 11,200 -
The excavation of foundation in grad 3 land
A3 3.00 Stone masonry with 35% mortar ( M:250,1:5) 38.0 m3 4,397 167,086 - 167,086
3.01 1.1 Stone including transportation 41.8 m3 1,100 45,980 45,980
3.02 0.394 Sand 15.0 m3 1,000 14,972 14,972
3.03 95 Cement (M: 250, 1:5) 3610.0 kg 21 75,810 75,810
3.04 48 Water 1824.0 liter 1 1,824 1,824
3.05 0.50 Skilled labour on site 19.0 md 800 15,200 15,200
3.06 1.0 Unskilled labour on site 38.0 md 350 13,300 13,300
Stone will be crushed stone, cement will be fresh, inside the reservoir will be insulated,
A4 4.00 RCC ( M:250,1:1:2) 5.3 m3 11,434 60,029 - 60,029
4.01 0.338 Sand 1.8 m3 1,000 1,775 1,775
4.02 0.676 Gravel 3.5 m3 1,000 3,549 3,549
4.03 400 Cement 2100.0 kg 21 44,100 44,100
4.04 200 water 1050.0 liter 1 1,050 1,050
4.05 0.7 Skilled labour on site 3.7 md 800 2,940 2,940
4.06 3.6 Unskilled labour on site 18.9 md 350 6,615 6,615
The cement is fresh, the sand and water is clean, mixer and vibrator should be used for mixing and placing concrete
A5 5.00 Reinforcement 490.0 kg 67 32,905 - 32,905
5.01 Steel bar 6 mm 70.0 kg 90 6,300 6,300
5.02 Steel bar 12 mm 230.0 Kg 90 20,700 20,700
5.03 0.012 Skilled labour on site 5.9 md 800 4,704 4,704
5.04 0.007 Unskilled labour on site 3.4 md 350 1,201 1,201
Steel should be without rust and clean, the tensile stress of the steel will not be less than 2400 kg/cm2
A6 6.00 Shuttering 22.9 m2 300 6,876 - 6,876
Before placing concrete the shuttering should be checked that it is well tied and no spacing between two adjacent plank
A7 7.00 PCC (floor,uner stone)M:150,1:2:4 3.5 m3 7,760 27,158 - 27,158
7.01 0.386 Sand 1.4 m3 1,000 1,351 1,351
7.02 0.771 Gravel 2.7 m3 1,000 2,699 2,699
7.03 230 Cement 805.0 kg 21 16,905 16,905
7.04 115 water 402.5 liter 1 403 403
7.05 0.65 Skilled labour on site 2.3 md 800 1,820 1,820
7.06 3.25 Unskilled labour on site 11.4 md 350 3,981 3,981
The cement is fresh not older than 3 months, the sand and water is clean, the cement proportion is considered
A8 8.00 Plastering inside reservoir wall (M:300,1:4) 62.0 m2 253 15,667 - 15,667
8.01 0.017 Sand 1.0 m3 1,000 1,035 1,035
8.02 4 Cement 248.0 kg 21 5,208 5,208
8.03 2 water 124.0 liter 1 124 124
8.04 0.1 Skilled labour on site 6.2 md 800 4,960 4,960
8.05 0.2 Unskilled labour on site 12.4 md 350 4,340 4,340
The cement is fresh, the sand and water is clean, at least 1.5 cm thickness will be plastering,3 layers
A9 9.00 Pointing (M:400,1:3) 36.0 m2 221 7,938 - 7,938
9.01 0.024 Sand 0.9 m3 1,000 864 864
9.02 2 Cement 72.0 kg 21 1,512 1,512
9.03 1 water 36.0 liter 1 36 36
9.04 0.17 Skilled labour on site 6.1 md 800 4,896 4,896
9.05 0.05 Unskilled labour on site 1.8 md 350 630 630
A10 10.00 Filling with soil and compaction,25cm 21.0 m3 116 2,426 - 2,426
10.01 1 Soil 21.0 m3 - - -
10.02 0.33 Unskilled labour on site 6.9 md 350 2,426 2,426
Filling soil will be well compacted -
A11 11.00 Filling with stone 15 cm of floor 1.2 m3 1,216 1,422 - 1,422
11.01 1 Stone 1.2 m3 1,100 1,287 1,287
11.02 0.33 Unskilled labour on site 0.4 md 350 135 135
Stone or gravel will be used for this filling
A12 12.00 Floor and wall insulation (bitumen) 20.0 m2 560 11,200 - 11,200
12.01 1 bitumen 20.0 m2 400 8,000 8,000
12.02 0.2 Skilled labour on site 4.0 md 800 3,200 3,200
The reservoir should be well insulated by bitumen -
A13 13.00 Site clearance 115.0 m2 7 805 805 -
13.10 0.02 Unskilled labour on site 2.3 md 350 805 805 -
Inside and out side the reservoir will be well cleaned at the end
A14 14.00 GI.Pipes and fittings 18.0 m 2845.0 51210.0 - 51,210
14.01 Pipe dia 4 inch 12.0 m 2,000 24,000 24,000
14.02 Pipe dia 3 inch 6.0 m 1,600 9,600 9,600
14.03 Gate valve dia 3 inch 1.0 Nos 1,200 1,200 1,200

Prepared by NOORULLAH EHSAS 06/08/2020 Page 10


CCNPP

No. Contribution

unit
Nor
m/
Title Norm Item Quantity Unit Unit cost Total cost
CDC, Afs CCAP, Afs
14.04 Elbow, dia 3 inch 3.0 Nos 1,500 4,500 4,500
14.05 Elbow, dia 3 inch 3.0 Nos 1,400 4,200 4,200
14.06 Tee dia 3 inch 1.0 Nos 1,500 1,500 1,500
14.07 Valve dia 3 inch 1.0 Nos 1,400 1,400 1,400
14.08 Joint dia 3 inch 1.0 Nos 1,300 1,300 1,300
14.09 End cup(0.75 in) ‫یتیلین‬K‫ولیا‬KKK‫وع پ‬KK‫لقن‬KKK‫ف‬ 6.0 Nos 90 540 540
14.10 coupler(2"*2")‫ولیایتیلین‬KKK‫وع پ‬KK‫ ن‬K‫ مستقیم‬K‫ننده‬KKK‫وصلک‬ 3.0 Nos 250 750
14.11 coupler(0.75"*0.75")‫یتلین‬K‫ولیا‬KKK‫وع پ‬KK‫ ن‬K‫ مستقیم‬K‫ننده‬KKK‫وصلک‬ 2.0 Nos 85 170
14.12 Union dia 3 inch 1.0 Nos 1,700 1,700 1,700
14.13 Unskilled labour on site 1.0 md 350 350 350
Well galvanized pipe and fitting should be used
Lining
15.00 Excavation of Pipe lines+ Excavation of Pipe line from
spring to WR 681.30 m3 175.00 119,228 119,228 -
A15
15.01 0.5 Unskilled labor 340.65 md 350.00 119,227.50 119,227.50 -

The land is ordinary soil


A16 16.00 Filling with soil and compaction 681.30 m3 70.00 47,691 47,691 -
16.01 1 Soil - m3 - - -
16.02 0.2 0.2 Unskilled labor on site 136.26 md 350.00 47,691 47,691.00 -
Filling soil will be the excavated soil
A17 17.00 Filling with fine sand 119.18 m3 1,070.00 127,517 3,591 123,926
17.01 1 fine sand 119.18 m3 1,000.00 119,175 - 119,175
17.02 0.33 0.2 Unskilled labor on site 23.84 md 350.00 8,342 3,591.00 8,342

Pipe Polyetline 1" with 10 ATM presure And PE 80 including


A18
18.00
transportation ansd extension 1,228.50 ML 50.00 61,425 61,425
All pipe must be PE 80 with 10 ATM presure and standard thickness
19.00
A19 Pipe Polyetline 1.5" with 10 ATM presure And PE 80 5,250.00 ML 100.00 525,000 525,000
All pipe must be PE 80 with 10 ATM presure and standard thickness
A20 20.00 Pipe Polyetline 0.75 with 10 ATM presure And PE 80 798 ML 45.00 35,910 35,910.0

Transport of all pipe 1 Ls 80,000.0 80,000 80,000.0


All pipe must be PE 80 with 10 ATM presure and standard thickness

BoQ of Stone Masonary Gate Valve Box (water supply network component)
A21 21.00 Site preparation 8.0 m2 14.0 112.0 0.0 112.0
21.01 0.04 Site preparation, clearing site ect. 0.3 md 350.0 112.0 0.0 112.00
Preparation of site for the project, preparation of hand tools and equipment
A22 22.00 Foundation excavation 8.0 m3 280.0 2240.0 0.0 2240.0
22.01 0.80 Unskilled labour 6.4 md 350.0 2240.0 0.0 2,240.00
Excavation of foundation in grad 3 land
A23 23.00 Stone work Mortor with 35% mortar (M:300,1:4) 28.0 m 3
4789 134092 0.0 134092.0
23.01 1.1 Stone including transportation 30.8 m3 1,100.0 33880.0 0.0 33,880.00
23.02 0.378 Sand 10.6 m3 1,000.0 10584.0 0.0 10,584.00
23.03 114 Cement 3192.0 kg 21.0 67032.0 0.0 67,032.00
23.04 57 water 1596.0 liter 1.0 1596.0 0.0 1,596.00
23.05 0.5 Skilled labour on site 14.0 md 800.0 11200.0 0.0 11,200.00
23.06 1.0 Unskilled labour on site 28.0 md 350.0 9800.0 0.0 9,800.00
Stone should be crushed mountain stone, sand and water is clean, cement should not be more than 3 months old, the cement - sand proportion will be considered
A24 24.00 RCC (M250, 1:1:2) 0.08 m3 11434 914.7 0.0 914.7
24.01 0.338 Sand 0.03 m3 1,000.0 27.0 0.0 27.04
24.02 0.676 Gravel 0.05 m3 1,000.0 54.1 0.0 54.08
24.03 400 Cement (M:250) 32.00 kg 21.0 672.0 0.0 672.00
24.04 200 water 16.00 liter 1.0 16.0 0.0 16.00
24.05 0.70 Skilled labour on site 0.06 md 800.0 44.8 0.0 44.80
24.06 3.60 Unskilled labour on site 0.29 md 350.0 100.8 0.0 100.80
Mixer and vibrator should be used for concrete placing, possibly washed crushed aggregate is used, water is drinkable water, fresh Portland or Charat cement is used, at least 15 days curing
A25 25.00 Reinforcement 24.0 kg 102.1 2449.2 0.0 2449.2
25.01 Steel bar 6 mm 4.0 kg 90.0 360.0 0.0 360.00
25.02 Steel bar 12 mm 20.0 Kg 90.0 1800.0 0.0 1,800.00
25.03 0.012 Skilled labour on site 0.3 md 800.0 230.4 0.0 230.40
25.04 0.007 Unskilled labour on site 0.2 md 350.0 58.8 0.0 58.80
A26 26.00 Shuttering (footing, column, beam, slab) 4.0 m2 300.0 1200.0 0.0 1200.0
Before placing concrete shuttering is checked that it is well tied and no gap between two planks
A27 27.00 PCC (M:150, 1:2:4) 0.6 m3 7759.5 4655.7 0.0 4655.7
0.386
27.01 Sand 0.2 m3 1,000.0 231.6 0.0 231.60
27.02 0.771 Gravel 0.5 m3 1,000.0 462.6 0.0 462.60
27.03 230 Cement 138.0 kg 21.0 2898.0 0.0 2,898.00
27.04 115 water 69.0 liter 1.0 69.0 0.0 69.00
27.05 0.65 Skilled labour on site 0.4 md 800.0 312.0 0.0 312.00
27.06 3.25 Unskilled labour on site 2.0 md 350.0 682.5 0.0 682.50
Under PCC there will be a layer of sand, the cement is fresh, the sand is washed, the water is clean, the proportion of cement-sand is considered, at least 10 days curing
A28 28.00 Back Filling 2.0 m 3
1,387.50 2775.0 2,775.00
28.01 1 soil 2.0 m3 300.00 600.0 600.00
28.02 1 Gravel 2.0 m3 1,000.00 2000.0 2,000.00
28.03 0.2 Unskilled labour on site 0.5 md 350.00 175.0 175.00

Prepared by NOORULLAH EHSAS 06/08/2020 Page 11


CCNPP

No. Contribution

unit
Nor
m/
Title Norm Item Quantity Unit Unit cost Total cost
CDC, Afs CCAP, Afs
A29 29.00 Pipe/Fittings GI (Galvanized Iron) 64.0 m 260.00 16640.0 16,640.00
29.01 2 in Dia 12.0 m 300.00 3600.0 3,600.00
29.02 2 in Dia 4.0 m 300.00 1200.0 1,200.00
29.03 2" dia Brass Gate Valve ‫ی‬( ‫رنج‬KKK‫)ب‬ 4.0 nos 1,000.00 4000.0 4,000.00
29.04 2 in Dia Union 4.0 nos 200.00 800.0 800.00
29.05 2 in dia Nipple 4.0 nos 160.00 640.0 640.00
29.06 Plumper 8.0 md 800.00 6400.0 6,400.00

A30 30.00 Site clearance 8.0 m2 7.0 56.0 0.0 56.0


30.01 0.02 Unskilled labour on site 0.2 md 350.0 56.0 0.0 56.00
Inside and around the block will be cleaned
It includes hand tools like shovel pick axe etc, stationary for CDC use and transportation cost for CDC travel to the market or bank.
BoQ of Stone Masonary Spring Protection Structure (Component of WSN)
A31 31.00 Site preparation 15.0 m2 14.0 210.0 0.0 210.0
31.01 0.040 Site preparation, clearing site ect. 0.6 md 350 210 0.0 210
A32 32.00 Foundation excavation 12.0 m3 280.0 3360.0 2429.0 931.0
32.01 0.80 Unskilled labour 9.6 md 350 3,360 2429.0 931
Excavation of foundation in grad 3 land
A33 33.00 Stone masonry with 35% mortar( M:300,1 :4 ) 6.0 m3 4789.0 28734.0 0.0 28734.0
33.011.100 Stone including transportation 6.6 m3 1,100 7,260 0.0 7,260
33.020.378 Sand 2.3 m3 1,000 2,268 0.0 2,268
33.03 114 Cement 684.0 kg 21 14,364 0.0 14,364
33.04 57.0 water 342.0 liter 1 342 0.0 342
33.05 0.50 Skilled labour on site 3.0 md 800 2,400 0.0 2,400
33.06 1.00 Unskilled labour on site 6.0 md 350 2,100 0.0 2,100
Stone should be crushed mountain stone, sand and water is clean, cement should not be more than 3 months old, the cement - sand proportion will be considered -
A34 34.00 RCC ( M:250, 1:1:2 ) 1.0 m3 11434.0 11434.0 0.0 11434.0
34.01 0.338 Sand 0.3 m3 1,000 338 0.0 338
34.02 0.676 Gravel 0.7 m3 1,000 676 0.0 676
34.03 400 Cement 400.0 kg 21 8,400 0.0 8,400
34.04 200 Water 200.0 liter 1 200 0.0 200
34.05 0.70 Skilled labour on site 0.7 md 800 560 0.0 560
34.06 3.60 Unskilled labour on site 3.6 md 350 1,260 0.0 1,260
A35 35.00 Reinforecement 190.0 kg 103.1 19584.7 0.0 19584.7
35.01 Steel bar 10mm 50.0 kg 90 4,500 0.0 4,500
35.02 Steel bar 12mm 140.0 Kg 90 12,600 0.0 12,600
35.03 Steel bar 6 mm 1.3 Kg 90 120 0.0 120
35.04 Wire 1 mm 2.0 Kg 90 180 0.0 180
35.05 0.010 Skilled labour on site 1.9 md 800 1,520 0.0 1,520
35.06 0.010 Unskilled labour on site 1.9 md 350 665 0.0 665
A36 6.00 Shuttering (footing, column, beam, slab) 8.0 m2 300.0 2400.0 0.0 2400.0
Before placing concrete shuttering is checked that it is well tied and no space between two planks
A37 37.00 PCC (M:150, 1:2:4) 1.0 m3 7759.5 7759.5 0.0 7759.5
37.01 0.386 Sand 0.4 m3 1,000 386 0.0 386
37.02 0.771 Gravel 0.8 m3 1,000 771 0.0 771
37.03 230 Cement 230.0 kg 21 4,830 0.0 4,830
37.04 115 water 115.0 liter 1 115 0.0 115
37.05 0.65 Skilled labour on site 0.7 md 800 520 0.0 520
37.06 Unskilled labour on site 3.3 md 350 1,138 0.0 1,138
3.25
37.07 water for curing
Under PCC there will be a layer of sand, the cement is fresh, the sand is washed, the water is clean, the proportion of cement-sand is considered, at least 10 days curing
A38 38.00 Pointing with mortar (M:400,1:3) 12.0 m2 220.5 2646.0 0.0 2646.0
38.01 0.024 Sand 0.3 m3 1,000 288 0.0 288
38.02 2.0 Cement 24.0 kg 21 504 0.0 504
38.03 1.0 water 12.0 liter 1 12 0.0 12
38.04 0.17 Skilled labour on site 2.0 md 800 1,632 0.0 1,632
38.05 0.05 Unskilled labour on site 0.6 md 350 210 0.0 210
the proportion of cement - sand is a must, cement is not older than 3 months, sand and water is clean
A39 39.00 Filling of Bolder stone in spring catchment 1.0 m3 1115.5 1115.5 0.0 1115.5
39.01 1.00 Gravel 1.0 m3 1,000 1,000 0.0 1,000
39.02 0.33 Unskilled labour on site 0.3 md 350 116 0.0 116
Stone or gravel can be used for filling
A40 40.00 Site clearance 15.0 m2 7.0 105.0 0.0 105.0
40.01 0.020 Unskilled labour on site 0.3 md 350 105 0.0 105
Inside and around the block will be cleaned
Bill of Quantity (BoQ) of Public Stand Tap (component of WSN)
A41 41.00 Site preparation 80.0 m2 35.0 2800.0 0.0 2800.0
41.01 0.10 Site preparation, clearing site ect. 8.0 md 350.0 2800.0 0.0 2800.0
Preparation of site for the project, preparation of hand tools and equipment
A42 42.00 Foundation excavation 1.6 m3 315.0 504.0 0.0 504.0
42.01 0.9 Unskilled labour 1.4 md 350.0 504.0 0.0 504.0
The land is ordinary soil
A43 43.00 RCC (M:250, 1:1:2) 1.2 m3 11424.7 13709.6 0.0 13709.6
43.01 0.338 Sand 0.4 m3 1000.0 405.6 0.0 405.6
43.02 0.676 Gravel 0.80 m3 1000.0 800.0 0.0 800.0
43.03 400 Cement ( M:250) 480.0 kg 21.0 10080.0 0.0 10080.0

Prepared by NOORULLAH EHSAS 06/08/2020 Page 12


CCNPP

No. Contribution

unit
Nor
m/
Title Norm Item Quantity Unit Unit cost Total cost
CDC, Afs CCAP, Afs
43.04 200 Water 240.0 liter 1.0 240.0 0.0 240.0
43.05 0.7 Skilled labour on site 0.8 md 800.0 672.0 0.0 672.0
43.06 3.6 Unskilled labour on site 4.3 md 350.0 1512.0 0.0 1512.0
Mixer and vibrator should be used for concrete placing, possibly washed crushed aggregate is used, water is drinkable water, fresh Portland or Charat cement is used, at least 15 days curing
A44 44.00 Steel Working( footing) 100.0 kg 101.5 10150.0 0.0 10150.0
44.01 Steel bar 6 mm 84.0 kg 90.0 7560.0 0.0 7560.0
44.02 Steel bar10 mm 16.0 Kg 90.0 1440.0 0.0 1440.0
44.03 0.01 Skilled labour on site 1.0 md 800.0 800.0 0.0 800.0
44.04 0.01 Unskilled labour on site 1.0 md 350.0 350.0 0.0 350.0
A45 45.00 Shuttering (footing, column, beam, slab) 7.5 m2 300.0 2250.0 2250.0
Before placing concrete shuttering is checked that it is well tied and no space between two planks
A46 46.00 PCC ( floor, Pavement) M:150, 1:2:4 1.5 m3 7759.5 11639.3 0.0 11639.3
0.386
46.01 Sandy 0.6 m3 1000.0 579.0 0.0 579.0
0.771
46.02 Gravel 1.2 m3 1000.0 1156.5 0.0 1156.5
46.03 230 Cement 345.0 kg 21.0 7245.0 0.0 7245.0
46.04 115 water 172.5 liter 1.0 172.5 0.0 172.5
46.05 0.65 Skilled labour on site 1.0 md 800.0 780.0 0.0 780.0
46.06 3.25 Unskilled labour on site 4.9 md 350.0 1706.3 0.0 1706.3
Under PCC there will be a layer of sand, the cement is fresh, the sand is washed, the water is clean, the proportion of cement-sand is considered, at least 10 days curing
47.00 Plastering in side and out side with cement mortar
A47 (1:4)
6.0 m2 252.7 1516.2 0.0 1516.2
47.01 0.017 Sand 0.10 m3 1000.0 100.2 0.0 100.2
47.02 4.0 Cement 24.0 kg 21.0 504.0 0.0 504.0
47.03 2 water 12.0 liter 1.0 12.0 0.0 12.0
47.04 0.10 Skilled labour on site 0.6 md 800.0 480.0 0.0 480.0
47.05 0.20 Unskilled labour on site 1.2 md 350.0 420.0 0.0 420.0
A48 48.00 Earth Work (Filling with gravel) 2.0 m3 1125.5 2251.0 0.0 2251.0
48.01 1.00 Gravel 2.0 m3 1000.0 2000.0 0.0 2000.0
48.02 1.00 Sand 0.0 m3 1000.0 20.0 0.0 20.0
48.03 0.33 Unskilled labour on site 0.7 m3 350.0 231.0 0.0 231.0
Soil filling should be well compacted
A49 49.00 GI and PE Pipe and Fitting 12.0 m 2340.0 28080.0 0.0 28080.0
49.01 tap 4.0 pcs 500.0 2000.0 2000.0
49.02 RCC pipe 20 cm L= 1 m 4.0 pcs 1200.0 4800.0 0.0 4800.0
49.03 Pipe 0.5' 12.0 m 600.0 7200.0 0.0 7200.0
49.04 Brass Bib cock 3/4' 4.0 pcs 1800.0 7200.0 0.0 7200.0
49.05 Reducer 0.5 x3/4' 4.0 pcs 200.0 800.0 0.0 800.0
49.06 Nipple 0.5' 4.0 pcs 100.0 400.0 0.0 400.0
49.07 Elbow 0.5' 8.0 pcs 100.0 800.0 0.0 800.0
49.08 PE female adapter 20 x0.5' 4.0 pcs 80.0 320.0 0.0 320.0
49.09 Glass wool thick 2cmm w=10 cm L= 2m 12.0 m2 300.0 3600.0 0.0 3600.0
49.10 0.1 Plumber 1.2 md 800.0 960.0 0.0 960.0
A50 50.00 Site clearance 8.0 m2 7.0 56.0 0.0 56.0
50.01 0.020 Unskilled labour on site 0.2 md 350.0 56.0 0.0 56.0
Inside and around the block will be cleaned
A51 51.00 Personal 30.0 md 3,450 103,500 - 103,500
51.01 1 Foreman 90.0 md 800 72,000 72,000
51.02 1 Storekeeper 90.0 md 350 31,500 31,500
51.03 1 Guard 0.0 md - - -
It includes foreman (engineer), store keeper and guard assigned by community and paid by NSP.
A52 52.00 Health education 1.0 lumpsum 5,000 5,000 - 5,000
It includes a couple man and woman for disseminating health massages, Sanitary and health kit (soap, pictured template regarding health and sanitation) and a car for transport
A53 53.00 Hand tools, stationary and transportation 1.0 Lump sum 35,200 35,200 - 35,200
53.01 Transportation 3.0 lumpsum 2,000 6,000 6,000
53.02 Pickax (‫لند‬KKK‫)ک‬ 10.0 Nos 300 3,000 3,000
53.03 Shovel (‫یل‬KKK‫) ب‬ 10.0 Nos 300 3,000 3,000
53.04 Wheel barrow (‫چی‬K‫را‬KK‫)ک‬ 4.0 Nos 4,000 16,000 16,000
53.05 Marter basin ( ‫لح‬KK‫شتمصا‬KKK‫)ت‬ 2.0 Nos 300 600 600
53.06 Trowel ( K‫نه‬KKK‫)دستپ‬ 4.0 Nos 250 1,000 1,000
53.07 Crowbar (‫)مارتول‬ 1.0 Nos 400 400 400
53.08 Stationary ( K‫رطاسیه‬KK‫) ق‬ 1.0 lumpsum 1,150 1,150 1,150
53.09 bank opening 1.0 lumpsum 350 350 350
53.10 CDC sing board (‫ورا‬KK‫ ش‬K‫وحه‬KK‫)ل‬ 1.0 Nos 700 700 700
53.11 Project sing board (K‫روژه‬KKK‫ پ‬K‫وحه‬KK‫)ل‬ 1.0 Nos 3,000 3,000 3,000
Total cost of Procured items, services and goods (A15+A16+A17) 1,852,097 185,210 1,666,888
Total cost of (A1&A17) 185,210 1,666,888
* A is amendment norm (if the existing norm does not fit to the site condition please ignore it and write
the actual norm to this column and follow the procedure)
Note: Any other needed activities which is not included here can be added

Prepared by NOORULLAH EHSAS 06/08/2020 Page 13


‫‪CCNPP‬‬

‫‪Work Plan (WP) Water Supply Reservoir 14 M3‬‬


‫‪ID-number:‬‬ ‫‪21-2104-M0075-1-A‬‬

‫‪Province:‬‬ ‫‪Farah‬‬

‫‪District:‬‬ ‫‪Purchaman‬‬

‫‪Village:‬‬ ‫‪shin jimin‬‬

‫‪Project Type:‬‬

‫‪Date:2020/02 /08‬‬

‫هقته ها‬
‫شماره‬

‫تشريحات‬
‫‪1‬‬ ‫‪2‬‬ ‫‪3‬‬ ‫‪4‬‬ ‫‪5‬‬ ‫‪6‬‬ ‫‪7‬‬ ‫‪8‬‬ ‫‪9‬‬ ‫‪10‬‬ ‫‪11‬‬ ‫‪12‬‬ ‫‪13‬‬ ‫‪14‬‬ ‫‪15‬‬ ‫‪16‬‬

‫کندن کاری محل پایپ ها و ذخیره‬


‫‪1‬‬ ‫‪.‬‬

‫اعمار ذخیره سنگی با سلب کانکریتی‬


‫‪2‬‬

‫اعمار ساختمان گیت والف ها‬


‫‪3‬‬

‫تمدید شبکه با پرکاری‬


‫‪4‬‬

‫لوحه‬
‫‪5‬‬

‫پرسونل‬
‫‪6‬‬

‫ابزار کار ‪ ،‬قرطاسيه و ترانسپورتیشن شورا‬


‫‪7‬‬

‫‪Apil 2013‬‬ ‫‪Page 14‬‬


‫بخش ج‪ :‬بل های قیمت دار‪ /‬گستره فعالیت ها‪( :‬به اساس رهنمود تخنیکی تا جایکه قابل تطبیق باشد)‬

‫قیمت محاسبه شده‬ ‫قیمت فی واحد‬ ‫اجناس ‪ /‬کارها‪ /‬غیر خدمات‬


‫مقدار‬ ‫واحد‬ ‫‪#‬‬
‫مجموعی‬ ‫محاسبه شده‬ ‫مشوره ای‬
‫‪35224‬‬ ‫‪1,000.00‬‬ ‫‪35.22‬‬ ‫متر مکعب‬ ‫ریگ همراه با انتقال‬ ‫‪1‬‬
‫‪15168‬‬ ‫‪1,000.00‬‬ ‫‪15.17‬‬ ‫متر مکعب‬ ‫جغل همراه با انتقال‬ ‫‪2‬‬
‫‪119175‬‬ ‫‪1,000.00‬‬ ‫‪119.18‬‬ ‫متر مکعب‬ ‫ریگ برای پر کاری جر‬ ‫‪3‬‬
‫‪88407‬‬ ‫‪1,100.00‬‬ ‫‪80.37‬‬ ‫متر مکعب‬ ‫سنگ شکسته کوهی‬ ‫‪4‬‬
‫‪260064‬‬ ‫‪21.00‬‬ ‫‪12,384.00‬‬ ‫کیلو گرام‬ ‫سمنت با کیفیت اعلی‬ ‫‪5‬‬
‫‪6211‬‬ ‫‪1.00‬‬ ‫‪6,211.00‬‬ ‫لیتر‬ ‫آب‬ ‫‪7‬‬
‫‪12726‬‬ ‫‪300‬‬ ‫‪42.42‬‬ ‫متر مربع‬ ‫قالب بندی‬ ‫‪8‬‬
‫‪14340‬‬ ‫‪90.00‬‬ ‫‪159.33‬‬ ‫کیلو گرام‬ ‫سیخ گول ‪ 6‬ملی متر‬ ‫‪9‬‬
‫‪5940‬‬ ‫‪90.00‬‬ ‫‪66.00‬‬ ‫کیلو گرام‬ ‫سیخ گول ‪ 10‬ملی متر‬ ‫‪10‬‬
‫‪35100‬‬ ‫‪90.00‬‬ ‫‪390.00‬‬ ‫کیلو گرام‬ ‫سیخ گول ‪ 12‬ملی متر‬ ‫‪11‬‬
‫‪180‬‬ ‫‪90.00‬‬ ‫‪2.00‬‬ ‫کیلو گرام‬ ‫سیم یک ملی متر‬ ‫‪12‬‬
‫‪ Polyetline‬های‬
‫‪Pipe‬‬ ‫ایزوگام کف و دیوار‬
‫‪1" with‬‬
‫‪8000‬‬ ‫‪400.00‬‬ ‫‪20.00‬‬ ‫مترمربع‬ ‫‪16‬‬
‫ذخیره‪10 ATM‬‬‫‪presure And‬‬
‫‪61425‬‬ ‫‪50.00‬‬ ‫‪1,228.50‬‬ ‫متر‬ ‫‪PE 80 including‬‬ ‫‪19‬‬
‫‪transportation‬‬
‫‪Pipe‬‬ ‫‪Polyetlineansd‬‬ ‫"‪1.5‬‬
‫‪525000‬‬ ‫‪100.00‬‬ ‫‪5,250.00‬‬ ‫‪with 10‬‬‫‪extension‬‬
‫‪ATM presure‬‬ ‫‪20‬‬
‫متر‬
‫‪And‬‬
‫های پولی‬ ‫انتقال‪PE‬‬
‫پایپ‬ ‫کرایه ‪80‬‬
‫‪80000‬‬ ‫‪80,000.00‬‬ ‫‪1.00‬‬
‫شورا‬
‫الی‪Pipe‬‬ ‫ایتلین از شرکت‬
‫‪Polyetline‬‬ ‫‪0.75‬‬
‫‪35910‬‬ ‫‪45.00‬‬ ‫‪798.00‬‬ ‫متر‬ ‫‪with 10 ATM presure‬‬ ‫‪21‬‬
‫‪And PE 80‬‬
‫خاک برای پر کاری اطراف‬
‫‪600‬‬ ‫‪300.00‬‬ ‫‪2.00‬‬ ‫متر مکعب‬ ‫‪22‬‬
‫ذخیره سنگی با تپک کاری‬
‫‪All GI and PE Pipe and‬‬
‫‪88220‬‬ ‫‪88,220.00‬‬ ‫‪1.00‬‬ ‫مجموعه‬ ‫‪Fitting for WR and‬‬ ‫‪23‬‬
‫‪stand tap‬‬
‫‪7150‬‬ ‫‪7,150.00‬‬ ‫‪1.00‬‬ ‫بسته‬ ‫مصارف اداری‬ ‫‪24‬‬
‫وسایل و افزار کار و لوحه‬
‫‪27700‬‬ ‫‪27,700.00‬‬ ‫‪1.00‬‬ ‫سیت‬ ‫‪25‬‬
‫شورا‬
‫‪350‬‬ ‫‪350.00‬‬ ‫‪1.00‬‬ ‫بسته‬ ‫باز نمودن حساب بانکی‬ ‫‪26‬‬
‫‪5000‬‬ ‫‪5,000.00‬‬ ‫‪1.00‬‬ ‫بسته‬ ‫تعلیمات صحی‬ ‫‪27‬‬
‫‪281975‬‬ ‫‪350.00‬‬ ‫‪805.65‬‬ ‫روزی کاری‬ ‫کارگر غیر فنی‬ ‫‪28‬‬
‫کارگر فنی ( مشخصا" گلکار ‪,‬‬
‫‪138232‬‬ ‫‪800.00‬‬ ‫‪172.79‬‬ ‫روزی کاری‬ ‫‪29‬‬
‫نجار‪ ,‬برقی ‪ ,‬نلدوان وغیره)‬
‫مجموع قیمت اجناس ‪/‬‬
‫‪1,418,540‬‬
‫=مواد‬
‫‪420,207‬‬ ‫=مجموع قیمت کارگر‬
‫‪7,500‬‬ ‫=مجموع مصارف اداری‬
‫‪1,846,247‬‬ ‫مجموع قیمت عمومی‪ :‬محاسبه شده‪( :‬افغانی)‬

‫کارگر (زن)‬ ‫کارگر (مرد)‬ ‫روزهای کاری‬ ‫کارگر‬


‫‪0‬‬ ‫‪806‬‬ ‫‪806‬‬ ‫کارگرغیره فنی‬
‫‪0‬‬ ‫‪173‬‬ ‫‪173‬‬ ‫کارگرفنی (گلکار‪،‬نجار‪،‬برقی و غیره)‬
‫‪0‬‬ ‫‪978‬‬ ‫‪978‬‬ ‫مجموع‬

‫‪:‬بخش د‪ :‬قیمت محاسبه شده مصارف اداری شامل ذیل است‬


‫قیمت محاسبه شده‬ ‫قیمت فی واحد‬
‫مقدار‬ ‫واحد‬ ‫اقالم‬ ‫‪#‬‬
‫مجموعی‬ ‫محاسبه شده‬
‫‪6,000‬‬ ‫‪2,000‬‬ ‫‪3‬‬ ‫‪ls‬‬ ‫سفر‬ ‫‪1‬‬
‫‪-‬‬ ‫‪0‬‬ ‫‪0‬‬ ‫غذا‬ ‫‪2‬‬
‫‪-‬‬ ‫‪0‬‬ ‫‪0‬‬ ‫محل بودوباش‬ ‫‪3‬‬
‫‪350‬‬ ‫‪350‬‬ ‫‪1‬‬ ‫‪ls‬‬ ‫حق الزحمه بانک‬ ‫‪4‬‬
‫‪1,150‬‬ ‫‪1,150‬‬ ‫‪1‬‬ ‫‪ls‬‬ ‫قرطاسیه‬ ‫‪5‬‬
‫قیمت مجموعی محاسبه‬
‫‪7,500‬‬
‫شده‪ :‬افغانی‬
‫‪:‬بخش هـ‪:‬چک لست های مربوطه حفاظت محیط زیستی و اجتماعی‬
‫در صورت نخیر واضح سازید‬ ‫اسناد موجود است (بلی‪/‬نخیر)‬ ‫اسناد مورد نیاز‬ ‫‪#‬‬
‫چک لست ارزیابی‬
‫بلی‬ ‫‪1‬‬
‫ساحه‬ ‫انتخاب‬
‫ارزیابی‬ ‫ومعیارلست‬
‫چک‬
‫بلی‬ ‫‪2‬‬
‫محیطی‬
‫ارزیابی‬ ‫لست‬‫تاثیرات‬
‫چک‬
‫بلی‬ ‫‪3‬‬
‫اجتماعی‬
‫محیطی و‬ ‫تاثیرات‬
‫تنظیم‬ ‫پالن‬
‫بلی‬ ‫‪4‬‬
‫اجتماعی‬
‫بلی‬ ‫فورمه ماین‬ ‫‪5‬‬
‫بلی‬ ‫سند زمین‬ ‫‪6‬‬
‫‪:‬بخش و‪ :‬پالن سهم گیری شورا‬
‫ق‹‹یمتمجموعیمحاسبه‹ ش‹‹ده‹ پ‹‹‹روژه‹)ح‹ا‹‹لتحقیقی‪ %‬ق‹‹ابلت‹‹‹طبیقمربوط ب‹‹‹ه‹ موقعیت روستا‪ /‬ش ‹ه‹ر ب‹‹‹را‹یش‹‹ورا‹یا‹نکشافی‪/‬گ‹‹‹ذر میباشد( ‪%‬‬
‫ف‹‹‹رعیا‹فغ‹انی‬
‫قیمت محاسبه شده‬ ‫قیمت فی واحد‬
‫مقدار‬ ‫واحد‬ ‫اقالم‬ ‫‪#‬‬
‫مجموعی‬ ‫محاسبه شده‬
‫‪0‬‬ ‫‪0‬‬ ‫‪0‬‬ ‫پول نقد‬ ‫‪1‬‬
‫‪0‬‬ ‫‪0‬‬ ‫‪0‬‬ ‫متر مکعب‬ ‫مواد‪/‬تجهیزات‬ ‫‪2‬‬
‫‪0‬‬ ‫مجموع شماره =‪1‬‬
‫‪185,210‬‬ ‫‪350‬‬ ‫‪529‬‬ ‫روز کاری‬ ‫کارگر غیرفنی‬ ‫‪3.1‬‬
‫‪0‬‬ ‫‪800‬‬ ‫‪-‬‬ ‫روز کاری‬ ‫کارگرفنی‬ ‫‪3.2‬‬
‫‪185,210‬‬ ‫مجموع شماره =‪2‬‬
‫‪185,210‬‬
‫‪:‬بخش ز‪ :‬زمان‪ -‬تعین پالن کار‬
‫شروع تخمینی پروژه فرعی ‪)05/03/2020 ( :‬‬
‫ختم تخمینی ختم کار فرعی ‪)05/07/2020( :‬‬
‫فیصدی‬
‫فیصدی پیشرفت پیشرفت مالی‪:‬‬
‫تعداد هفته ها از شروع پروژه فرعی‬ ‫عطف ها(مراحل) که میباید تکمیل گردد‬
‫مصرف وجه‬ ‫فزیکی‬
‫مالی‬
‫هفته‹ ‪4‬‬ ‫‪25%‬‬ ‫‪25%‬‬ ‫کندن کاری محل پایپ ها و ذخیره‬
‫هفته‹ ‪4‬‬ ‫‪50%‬‬ ‫‪50%‬‬ ‫اعمار ذخیره سنگی با سلب کانکریتی‬
‫هفته‹ ‪4‬‬ ‫‪75%‬‬ ‫‪75%‬‬ ‫اعمار ساختمان گیت والف ها‬
‫هفته‹ ‪4‬‬ ‫‪100%‬‬ ‫‪100%‬‬ ‫تمدید شبکه با پرکاری‬
‫‪:‬بخش ح‪ :‬پالن حفظ و مراقبت‬
‫بلی‬ ‫کمیته فرعی حفظ و مراقبت در قریه تاسیس گردید است‪( :‬بلی ‪/‬نخیر)‬
‫‪:‬در صورت بلی ‪ ،‬اعضای ان عبارتند از‬
‫امضآ ‪ /‬شصت‬ ‫نمبر تیلفون‬ ‫ولد‬ ‫اسم مکمل‬ ‫‪#‬‬
‫‪1‬‬
‫‪2‬‬
‫‪3‬‬
‫‪4‬‬
‫نخیر‬ ‫کمیته فرعی حفظ و مراقبت توسط انجنیر ولسوالی‪/‬موسسۀ همکار آموزش دیده اند‪( :‬بلی ‪ /‬نخیر)‬
‫آیا جمع اوری پول ضروری همیشگی (شامل مصارف روغنیات‪ ،‬برق و مزد میخانیک) پروژه فرعی پیشنهاد گردیده است؟ (بلی ‪ /‬نخیر)بلی‬
‫‪ .‬در صورت بلی‪ ،‬مقدار پول پیشنهاد شده که بایدماهوار که از هر خانوار جمع آوری میگردد چند خواهد بود (الف)‪ 15‬افغانی و یا (ب) به اساسس سیستم میتری هر مترمکعب افغانی‬
‫مبلغ که غرض مصرف حفظ و مراقبت ترمیم ‪ ،‬استهالک و غیره پروژه فرعی مربوطه (خارج از مصارف فعالیت های پروژه فرعی) از هر خانوار در ماه جمع اوری و ذخیره میگردد ‪ ،‬چه مبلغی است؟‬

‫آیا قیمت مجموعی حفظ و مراقبت (شامل فعالیت های پروژه فرعیو قیمت ترمیم و استهالک) پروژه فرعی قابل قبول تمام اهالی شورا انکشافی میباشد؟ بلی‪ /‬نخیر‬
‫‪:‬نوت‬
‫شروع تخمینی کار پروژه فرعی (باید ‪ 2‬هفته الی یک ماه بعد از تاریخ تسلیمی پروپوزل به دفتر والیتی)‬
‫ختم تخمینی کار پروژه فرعی (باید تحقق پزیر‪ /‬عملی باشد و حالت های موسمی و فصلی درنظر گرفته شود‪ ،‬مگر نباید از ‪ 12‬ماه‬
‫بعد از تاریخ شروع کار پروژه تجاوز نماید‬
‫‪ :‬نتیجه‬
‫‪1,846,247‬‬ ‫‪:‬قیمت مجموعی پروژه فرعی قرار ذیل میباشد‬

‫از وجوه مالی‬


‫تقسیمات هزینه پروژه فرعی به اساس منابع‬ ‫کتگوری به اساس تقسیمات هزینه پروژه فرعی‬
‫=‬
‫‪90%‬‬ ‫از سهم شورا ‪1,661,622‬‬ ‫‪99.17%‬‬ ‫‪1,830,923‬‬ ‫هزینه پروژه فرعی‬
‫‪1455985‬افغان‬ ‫‪7,500‬‬
‫‪10%‬‬ ‫مجموعی ‪184,625‬‬‫‪161776‬‬ ‫=ی‬
‫هزینه‬ ‫‪0.72%‬‬ ‫هزینه مصارف اداری‬
‫‪100%‬‬ ‫‪1617761‬افغ ‪1,846,247‬‬ ‫=افغانی‬ ‫‪100%‬‬ ‫‪1,846,247‬‬ ‫هزینه مجموعی‬
‫انی‬
‫پروپوزل‬ ‫‪ :‬منظوری‬
‫به نمایندگی از شورای انکشافی قریه یا شهری‪/‬کلسترشورای انکشافی‪/‬شورای گذر‪:‬همه ‪ 4‬نفر هیات اداری‬
‫صدرالدین‬
‫بی بی گل‬
‫عیدماه‬
‫رازمحمد‬
‫تصدیق میگردد که پیشنهاد پروژه فرعی مطابق رهنمود عملیاتی تهیه گردیده و موارد فوق تایید گردید‪:‬از طرف ادارۀ مستقل ارگانهای محلی امضا های‬
‫انجنیر‪ ،‬مدیر ولسوالی و مدیر والیتی موسسۀ همکار و ازطرف وزارت احیا وانکشاف دهات امضاهای انجنیر ولسوالی و مدیر دفتر ولسوالی‪:‬‬

‫انجینیر ولسوالی‬ ‫وحیداحمد برهانی‬


‫امضآ‬ ‫انجینیر والیتی‬ ‫میرویس فاروقی‬
‫امضآ‬ ‫مدیر ولسوالی‬ ‫حاجی عمادالدین (شیوانی)‬
‫‪:‬تایید محاسب واحد اداری ولسوالی‬
‫‪20/2/2020‬‬ ‫تاریخ‬ ‫امضآ‬
‫منظوری فوق و تایید ثبت نام شورایانکشافی قریه یاشهری‪/‬کلسترشورای انکشافی‪/‬شورای گذرتوسط‪ :‬مدیر والیتی وزارت احیا وانکشاف دهات‪/‬ادارۀ مستقل‬
‫ارگانهای محلی‬
‫میرویس( فاروقی ) سرپرست دفتر والیتی میثاق شهروندی‬ ‫اسم مکمل موقف امضا‬
‫مهر واحد اداری والیتی برنامۀ ملی میثاق شهروندی‬
‫‪20 /‬‬ ‫‪02‬‬ ‫‪/‬‬ ‫‪2020‬‬ ‫تاریخ ارسال فورمه به واحد اداری والیتی(روز‪/‬ماه‪/‬سال)‪/ :‬‬
‫‪20 /‬‬ ‫‪02‬‬ ‫‪/‬‬ ‫‪2020‬‬ ‫تاریخ درج فورمه در دیتابیس دفتر ولسوالی‪ /‬واحداداريواليتي (روز‪/‬ماه‪/‬سال)‪/ :‬‬

Вам также может понравиться