Sl. NO. CUSTOMER CUSTOMER PO NO. CUSTOMER PO DATE U2 SALE ORDER NO.

. CUSTOMER PO DATE U2 SALE ORDER NO. & DATE WEB ERP ORDER NO. & DATE Work  order No. & date

1 JINDAL STEEL & POWER LIMITED, UNIT II 4514005111 24/04/2015 S1100003 5/5/2015 GI6912 dated 30/05/2015 000009 dated 04/06/2015
2 DIGI DRIVES PVT LTD MAY-M-1 0-2015-2016 5/5/2015 S1100004 8/5/2015 GI6279 dated 29/05/2015 000010 dated 04/06/2015
3 JINDAL STEEL & POWER LIMITED 4571012942 14/05/2015 S1100005 14/05/2015 GI6914 dated 30/05/2015 000011 dated 04/06/2015
4 JINDAL STEEL & POWER LIMITED, UNIT II 4514005186 21/05/2015 S1100006 28/05/2015 GI6913 dated 30/05/2015 000012 dated 04/06/2015
5 JINDAL STEEL & POWER LIMITED, UNIT II 4514005165 15/05/2015 S1100007 28/05/2015 GI6251 dated 29/05/2015 000013 dated 04/06/2015
6 STEEL AUTHORITY OF INDIA LTD (SALEM) PU-L66 1003/01 30/05/2015 S1100008 30/05/2015 GI6915 dated 29/05/2015 000014 dated 04/06/2015
SSIPL - DESIGN DEPT. INDUSTRIAL PRODUCTS
October 2015
T 1
F 2 Gandhi Jayanthi
S 3
S 4 (working on account of bharath bhand- sept 2nd 2015)

M 5
T 6
W 7
T 8
F 9
S 10 Second Saturday
S 11 Sunday
M 12

T 13
W 14

T 15
F 16
S 17 Manual upgradation (Digidrive-II)
S 18 Sunday
M 19 Manual (Digidrive-II) fine tuning, 1+3 sets arranged & given for printing, packing list initiated

T 20 Work track sheet- preparation, Packing list format prepared for Digi Drive-II and sent to Satish
Involved in inspection of DN28 turbulance cooling pipe with Mr.Manjunath. Updating & writing the drawings for
W 21 CD (RSP HSM)

T 22 Initiated manual Digidrive-I manual, half day holiday


F 23 Vijaya Dashami
S 24 Fourth Saturday
S 25 Sunday
M 26 manual Digidrive-I BOM upgradation in manual

T 27 manual Digidrive-I manual in progress, (DN28 inspection- dispatch)


W 28 Manual preparation , O&M browsing

T 29 Completed the manual till date , drawings left out for filing
F 30 oil coating drawing updated wit coupling details. Initiated vault activity (splitting up the drawing)
S 31 vault activity continued…

SSIPL - DESIGN DEPT. INDUSTRIAL PRODUCTS


November 2015
S 1 Sunday
M 2 vault activity continued…
T 3 vault activity continued…
W 4 vault activity continued…
T 5 vault activity continued…
F 6 vault activity continued…
S 7 vault activity continued…
S 8 Sunday
M 9 vault activity continued…
T 10 Narak chaturdashi
W 11 1/4 day leave , vault activity continued…
T 12 Deepavali
F 13 vault activity continued…
S 14 Saturday
S 15 Sunday
M 16 vault activity continued…
T 17 vault activity continued… (digidrive - discussion, for temperature switch & SV interlocking)
W 18 vault activity continued…
T 19 excel formulation / documentation
F 20 excel formulation / documentation
S 21 Training program
S 22 Sunday
M 23 excel formulation / documentation
T 24 excel formulation / documentation - final freezed, team meeting .
W 25 drafting of checklist
T 26 drafting of checklist…..
F 27 Rework of oil coating system(DD-1),new PHE proposal reviews
S 28 Saturday
S 29 Sunday
M 30 Assembly of DD-I,working on amended PO for DD-II

SSIPL - DESIGN DEPT. INDUSTRIAL PRODUCTS


December 2015
T 1 testing of oil coating system
W 2 testing of oil coating system
T 3 testing of oil coating system
F 4 testing of oil coating system
S 5 testing of oil coating system
S 6
M 7 testing of oil coating system
T 8 testing of oil coating system
W 9 pump found wrong, replacement, new corrections made
T 10 updating the drawing as per new modifications/instructions
F 11 modification of drawing continued
S 12
S 13
M 14 drawing continued
T 15 bom generation & release
W 16 testing of rectifying pump
T 17 testing of rectifying pump , BOM follow up
F 18 process chart preparation
S 19 process chart preparation
S 20
M 21 assembly of DD-I
T 22 assembly of DD-I
W 23 assembly of DD-I
T 24 assembly of DD-I
F 25
S 26
S 27
M 28 testing of DD-I
T 29 testing of DD-I
W 30 testing of DD-I
T 31 testing of DD-I

SSIPL - DESIGN DEPT. INDUSTRIAL PRODUCTS


January 2016
F 1 testing of DD-I
S 2
S 3
M 4 testing of DD-I
T 5 testing of DD-I, RESULT FOUND SATISFACTORY FOR 730077 NOZZLE, 730039 WAS NOT OK
W 6 INDIVIDUAL NOZZLE TESTING CARIED OUT, HELD ISM AFTERNOON
T 7 INDIVIDUAL NOZZLE TESTING CARIED OUT
F 8 Manual correction for DD-I
S 9 Manual correction for DD-I
S 10
M 11 MPD send off
T 12 Manual correction for DD-I
W 13 nozzles were planned to import from USA
T 14 Base frame drawing & BOM
F 15
S 16
S 17
M 18 base frame drawing updation and released to production
T 19 Manual updation
W 20 Manual updation
T 21 tank rework monitorring
F 22 tank rework monitorring
S 23 drawing correction for manual , NEW PUMP RECEIVED
S 24
M 25 drawing correction for manual - digi drive dispatched
T 26
W 27 Manual page set up
T 28 FULL LIFT RELIEF VALVE ARP 250 - 95478 initiated
F 29 manual completed, made 4 sets n was given for spiral binding
S 30 Manual completed - DD-I
S 31

SSIPL - DESIGN DEPT. INDUSTRIAL PRODUCTS


Feb 2016
M 1 95478 ……, MANUAL HANDED OVER TO M/s. VITTAL
95478 …., meeting reg extra work ( sample arrangement, steel business dwg list out & remove from vault,
T 2 catalogue arrangement, vault activity status,..)
W 3 CATALOGUE SEGREGATION, EXCEL SHEET PREPRATION
T 4 CATALOGUE SEGREGATION, EXCEL SHEET PREPRATION
F 5 old catalogue files were traced & listed out
S 6
S 7
M 8
T 9
W 10 arranged the catalogues
T 11 RSP laminar cooling -95802 spare order initiated, spray performance chart preparation
F 12 meeting regarding visit of bob adam. RSP laminar cooling -95802 continuation
S 13 RSP laminar cooling -95802 continuation
S 14
M 15 SPX coding initiation
T 16 SPX coding ….
W 17 SPX coding ….
T 18 spx released
F 19 PPT preparation
S 20
S 21
M 22 Personal discussion with Bob adam , PHE received
PPT with Bob adam & Lee regarding our dept . & product management, nozzle training . Modification dawing
T 23 issued to prodn -Digidrive-II, part dwgs in auocad format (ROT Laminar) given to Hemgiri
W 24 digidrive-II manual & drawing updation
T 25
F 26
S 27
S 28