TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET ii OF iii
MATERIAL HANDLING SYSTEM EQUIPMENT
CONTENTS
1.0 SCOPE 1
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET iii OF iii
MATERIAL HANDLING SYSTEM EQUIPMENT
REVISION STATUS
R0 30.09.1993 --
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET 1 OF 5
MATERIAL HANDLING SYSTEM EQUIPMENT
1.0 SCOPE
a) Preparation of specification
b) Review of tenders
c) Tender analysis and purchase recommendation
d) Preparation of purchase order
2.5 General procurement guide for mechanical equipment, systems and site
works contracts – TCE.M12-ME-000-901.
3.1 The following sections which will form part of the specification shall be
prepared specific to the project and system/equipment:
3.1.3 Section C
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET 2 OF 5
MATERIAL HANDLING SYSTEM EQUIPMENT
3.3.1 Applicable documents which generally include client’s General Terms and
Conditions of Contract and bid purpose drawings.
3.3.2 Time of completion and work schedule indicating the completion period of
contract, submission of net work schedule, etc.,
3.3.9 Inspection
3.3.12 In the event of splitting up of contract for the system between two or three
Bidders, the vendors shall co-operate with each other and shall exchange
the information required for interface engineering. It shall be stated that no
extra cost will be paid in the event of changes required to meet the
design/layout requirements of another VENDOR though details may differ
from those assumed by one VENDOR at the bid stage/detail engineering
stage.
3.4.1 Section-C for systems such as coal handling and ash handling system shall
cover the following aspects:
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET 3 OF 5
MATERIAL HANDLING SYSTEM EQUIPMENT
3.4.5 Miscellaneous services for the Vendor such as shop inspection, start-up and
commissioning, start-up and essential spares and painting.
3.4.12 Safety and sequential interlocks and permissive conditions for starting and
stopping of equipment.
3.4.14 List of essential spares required for three years trouble free operation.
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET 4 OF 5
MATERIAL HANDLING SYSTEM EQUIPMENT
4.1 After receipt of the bids, the following items are to be checked while
analysing the Bids:
4.1.1 In case any Bidder offers alternative(s) which is/ are technically superior
and it is beneficial to the client, if that alternative(s) is/are adopted, client
should be advised to obtain price change for including such alternative(s)
by all the Bidders. For such an acceptable alternative, suitable amendment
shall be issued after obtaining concurrence from the client.
4.1.2 Check for the capacity (Rated and design) of the system and equipment.
4.1.3 Review deviations from the specification, if furnished in the schedule for
deviations and check for acceptability of these deviations. If the deviations
are not acceptable ask the Bidder to comply with the specification. Even if
the deviations are acceptable, ask the Bidder to indicate the price change, if
any, for compliance with the specification. This may be required for
comparison purposes.
ISSUE
R2
TCE.M12-ME-CL-670-085
GENERAL CHECKLIST FOR PROCUREMENT OF
SHEET 5 OF 5
MATERIAL HANDLING SYSTEM EQUIPMENT
6.1 List all reference documents such as NIT specification amendments, offers,
clarification letters to Bidder and replies, Minutes of meeting with the
Bidder (If any) and letter of intent.
6.7 Total contract price and break-up of prices under major headings like
design and engineering, supply (FOR site) of Electrical and Mechanical
Items, Civil and structural works, Erection, Testing and Commissioning
and Taxes and Duties.
6.8 It is preferable to append the following documents with the purchase order :
6.8.2 Copies of clarification letters sent to the successful Bidder and replies to the
clarification letters.
ISSUE
R2