Вы находитесь на странице: 1из 15

Coronavirus (COVID-19)

Client guidance note | March 2020


Contents
01 | Introduction
02 | Key impact areas
04 | NEC contracts
07 | JCT contracts
10 | FIDIC contracts
Coronavirus (COVID-19) | Client guidance note

Introduction
This paper outlines some key impact areas for you to consider in connection to:

Contracts

Supply chain

Operations

It provides some guidance for dealing with COVID-19 under NEC, JCT and FIDIC contracts.

On the 11th March 2020, the World Health Organisation already in delay for other reasons, COVID-19 may not
(WHO) declared the COVID-19 outbreak to be a to lead to compensation.
pandemic. The UK government has since stepped up its
The content of this document does not purport to
response to COVID-19.
constitute legal advice and you must not rely on it as
The virus is having a serious effect on the global such. Where you require legal advice it should be from
economy with global supply chains affected. Current a recognised legal firm. We shall not be liable for any
factory shut downs in China and Italy will lead to losses or damages whatsoever, whether in contract, tort
delays, shortages and likely higher prices. (including negligence) or otherwise arising from reliance
on information contained in this document.
It is our opinion that COVID-19 is likely to cause serious
disruption and even suspension of works to projects due Our helpdesk is available to support you with any
to labour and material shortages. contract related queries you may have at this time
or anticipate in the future. We can help in particular
As a client we are recommending that you are proactive
with issues relating to contract risks and effective
in managing your projects, especially in the following
management, detailed assessments, commercial
key impact areas:
impacts and guidance on potential delivery delay
◼ Contracts through to comprehensive supply chain audits. We
◼ Supply chain can also assist in protecting your commercial interests
◼ Operations should your project shut down or you require detailed
protocols to be implemented if a site or project team’s
Practical ways of dealing with COVID-19 under NEC,
office needs to close, helping you to maintain a focus on
JCT and FIDIC contracts have been identified within this
safety, speed and site security.
document. We recommend that you seek professional
advice on the best solution for your project as each Our Contract Services Helpdesk is operated by a
situation is unique. team of highly experienced contract and procurement
specialists. They will guide you through your options
COVID-19 is a significant event and is likely to be
and support you to navigate through COVID-19 and its
classed as an event/change under the contract. This
short, medium and long term impacts. We’re offering
does not mean that the Contractor is automatically
our clients one hour of free advice on any contractual
entitled to full or partial compensation. The event will
problem.
still need to be assessed and its impact understood
against the progress of the works. If the project is Contact us on: cshelpdesk@turntown.com

Page | 1
Coronavirus (COVID-19) | Client guidance note

Key impact areas

Page | 2
Coronavirus (COVID-19) | Client guidance note

Key impact areas


COVID-19 will have a significant impact on many projects currently being undertaken. We have identified
three key impact areas which require serious consideration in order to manage the risks from COVID-19.
Being proactive and carrying out detailed reviews of projects and identifying strategies to manage these risks will
help to reduce the impact on projects. Below we have produced a short (non-exhaustive) summary of issues that
you should be considering.

Contracts Supply chain


A full and detailed understanding of the conditions In order to be able to manage and deal with risks
of each specific contract, where risk lies and how to within your supply chain, you need to understand
manage these risks. the issues they are encountering in order to assess
the impact on your project.
Review contract
What does your contract say about: Audit supply chain
◼ Force majeure, epidemics or pandemics Conduct end-to-end supply chain audits to identify
possible delivery delays, shortages and higher
◼ Suspension provisions
costs.
◼ Termination provisions
◼ Extension of Time provisions and entitlement Monitor supply chain
to time and money Monitor supply chains for early warning signs of
distress, such as requests to change payment
Insurance terms; deliveries not in accordance with the
Check whether your insurances cover any of programme; a lack of communication, or
your losses. Seek specialist advice with regard to suppliers not delivering in accordance with agreed
existing insurance provisions. schedules or contract terms.

Future contracts
Instruct lawyers to include express infection Operations
disease/epidemic provisions in new contracts and,
where possible, amend existing contracts. You Without a ‘Plan B’ operational issues will cause
should consider who will hold this risk and how problems on projects as project teams will have
best it can be managed and by whom. disparate methods of dealing with issues, such as
when and how to shut sites down.
Other agreements
Site shutdowns
Are there any other agreements, such as
development agreements or agreements for Produce protocols to be implemented if a site or
lease, which need to be notified of delays and/or project team’s office needs to close. Consider
increased costs? how this can be done safely and quickly, whilst
maintaining the security of the site. Take note of
Records any insurance requirements.
Request/mandate that main contractors collate Health and safety
detailed records of resources and additional costs
Understand your health and safety obligations
incurred as a pre-requisite to claims for additional
to your employees, but also those of the
time and/or money on projects.
Contractors. What facilities do you need to
provide to minimize the risks (i.e. increased
washing facilities).

Page | 3
Coronavirus (COVID-19) | Client guidance note

NEC contracts

Page | 4
Coronavirus (COVID-19) | Client guidance note

NEC contracts
The NEC is a family of contracts used by our Project Managers on NEC3 projects should ensure
clients for procuring a diverse range of works, they give proper consideration to the recent COVID-19
services and supply, spanning major framework legislation.
projects through to minor works and purchasing
of supplies and goods. It is used and promoted by Clause 19: Prevention
the UK Government on a range of projects. The The un-amended version of both the NEC3 and NEC4
choice of NEC contract will depend on the project ECC contracts include Clause 19 Prevention and its
complexity and level of risk the client wishes to associated compensation event 60.1(19). In effect
pass on. these clauses provide that if an event occurs which
The NEC contracts do not specifically identify epidemics prevents the Contractor from completing the whole
under the contract clauses, therefore consideration of of the works by the date for planned Completion, and
the various contractual mechanism is required and the which neither party could prevent, and which had
one which should be used will be heavily dependent on such a small chance of occurring it would have been
the specifics of the project. unreasonable to have expected the Contractor to allow
for it.
Four possible ways of dealing with COVID-19 under
NEC: The wording of the clauses is slightly different between
NEC3 and NEC4 but clause 19 in NEC4 states:
1. Option X2 Changes in the Law
“If an event occurs which
2. Clause 19 Prevention and the associated
compensation events ◼ stops the Contractor completing the
whole of the works or
3. Compensation events 60.1(2) and (4)
◼ stops the Contractor completing the
4. Termination whole of the works by the date for
Option x2: changes in the law planned Completion shown on the
Accepted Programme,
If the Secondary Option clause X2 Changes in the Law
has been included as an option in a contract, which and which
often is the case, then new legislation such as ‘The ◼ neither Party could prevent,
Health Protection (Coronavirus) Regulations 2020’ ◼ an experienced contractor would
recently brought in by the Government, which affects have judged at the Contract Date
the works, would be a compensation event. to have such a small chance of
The wording under NEC3 and NEC4 is different and occurring that it would have been
parties should check the exact wording in order unreasonable to have allowed for it
to comply with the contractual requirements for the Project Manager gives an instruction to the
notification of the event. Under NEC3 a change in the Contractor stating how he is to deal with the
law after the Contract Date allocates the risk to the event”
employer. The second sentence of the clause contains
the wording “The Project Manager may notify the This clause sets out a number of criteria which need
Contractor of a compensation event…”. As this clause to be overcome, however we believe it is likely
uses the word “may” in relation to notification it could that COVID-19 would be an event caught by these
be reasonably concluded that if the Project Manager provisions as it will impact the carrying out of the
fails to notify, the Contractor will not be time barred Works. The wording ‘completing the whole of the
under Clause 61.3. works’ used in NEC4 could be interpreted as only being

Page | 5
Coronavirus (COVID-19) | Client guidance note

applicable in circumstances when there is no realistic What can an Employer/Client do?


way that completion of the works can be achieved on
Contractors under the NEC contract, (particularly
time or at all. If such an event does occur, it is for the
cost based options C D E and F), should already
Project Manager to issue instructions to the Contractor
be keeping comprehensive records of Defined
on how the event is to be dealt with. This would be
Cost as required by the contract, together with
a compensation event in accordance with clause
additional records as required by the Scope/Works
60.1(19) and therefore at the Employer’s (or Client’s)
Information. It would be prudent for Clients/
liability. Depending on the severity of the impact on
Employers to ensure that the following are carried
a construction site, the compensation event could be
out:
challenging to assess in terms of both cost and time.

Compensation events 60.1(2) and (4) A review of the contractual provisions


with the Project Manager/lawyers/
The other alternatives would be, where the Employer/ other advisors and understand
Client does not allow access to the site (Clause 60.1(2)) the benefits and risks of different
or the Project Manager gives an instruction to stop the provisions.
Works (Clause 60.1(4)), to use these compensation
events. These can be valued as normal compensation Make sure that there is an Accepted
events and are probably the easiest to manage Programme, the programme is up-
contractually and commercially. to-date and complete with method
Under Clause 60.1(2) the Contractor must show that statements and schedules of resources
the Employer or others have failed to do something by as required by the contract, as well as
the date shown on the Accepted Programme in order an understanding of the critical path
to preserve entitlement. It is in the interests of both and concurrent/parallel delays. This
the Contractor and the Project Manager to have current will make agreement of any change to
realistic and achievable Accepted Programmes. the Completion Date easier.

Termination A detailed understanding of the


Contractors cost records so that the
Clause 91.7 of NEC3 and NEC4 gives the Employer/
Defined Cost of the compensation
Client (not the Contractor) a right to terminate the
event can be readily and objectively
contract where an event occurs:
assessed. Only Defined Costs in
◼ which stops the Contractor completing the works, accordance with the relevant Schedule
◼ where completion of the whole of the works will be of Cost Components is claimable.
delayed by longer than 13 weeks, The theory behind NEC being that
◼ which neither party could prevent, and the contractor should be not better
◼ which an experienced contractor would have judged or worse off as a result of the
at the Contract Date to have such a small chance of compensation event.
occurring.
This is similar to the prevention clause 19 and is Employers/Clients should also consider the other
effectively a force majeure clause. It should be noted issues identified in the key impact areas section of
that it only gives the Employer/Client the opportunity this document.
to terminate for this reason and not the Contractor.
Termination should only be considered with the
appropriate legal advice.

Page | 6
Coronavirus (COVID-19) | Client guidance note

JCT contracts

Page | 7
Coronavirus (COVID-19) | Client guidance note

JCT contracts
JCT contracts have been the dominant contract in The four stage test for force majeure is:
the UK for most of the last 100 years and are used ◼ It should be beyond a Party’s control
on a wide range of projects. The main contracts ◼ It could not be reasonably avoided
used are the Standard Building Contract (SBC) ◼ It is not attributable to a Party
and Design and Build Contract (DB). ◼ It could not have been reasonably foreseen
The JCT contracts do not specifically identify epidemics This test could be used in relation to COVID-19 and is
under the contract clauses, but do include “force likely to pass the test and be a force majeure event.
majeure” clauses. Force majeure is not the only method
of dealing with issues caused by COVID-19 and clients The two main JCT contracts in use - the Standard
should consider all the contractual mechanisms open to Building Contract and Design and Build 2016 Contracts
them. - both include force majeure as a Relevant Event but
not as a Relevant Matter. In contractual terms this
Four possible ways of dealing with COVID-19 under JCT: would entitle the contractor to additional time which
1. Postponement of work would relieve it of Liquidated Damages but it would not
entitle it to any additional monies.
2. Force majeure
3. Statutory power Statutory power (time, but no money)
4. Termination The statutory power Relevant Event would appear to be
relevant to COVID-19:
Postponement of work (time and money)
“2.26.12 The exercise after the Base Date
If the Employer instructs (clause 3.10 JCT Design
by the United Kingdom Government or any
and Build 2016) the Contractor to close the site and
Local or Public Authority of any statutory
postpone the works this is a Relevant Event (Clause
power that is not occasioned by a default of
2.26.2.2). It is also a Relevant Matter under clause
the Contractor or any Contractor’s Person but
4.21.2.1. This gives the Contractor entitlement to both
which directly affects the execution of the
time and money. Employers should therefore exercise
Works;”
caution before issuing instruction to postpone the work.
If the UK Government exercises powers, such as closing
Force majeure (time, but no money) borders, causing delays to deliveries or quarantining
Epidemic or pandemic events are not specifically an area as has happened in Italy, this would more than
listed as Relevant Events, entitling a contractor to an likely be an ‘exercise’ which was envisaged under clause
extension of time. COVID-19 would therefore likely be 2.26.12, as this was not caused by the Contractor and
covered under the “force majeure” relevant event. has directly affected the works.

The term force majeure is not defined under the JCT Like force majeure, this Relevant Event is not covered
contracts and it may be a source of dispute as to by a corresponding Relevant Matter and would entitle
whether an infectious disease is captured by force the contractor to additional time but not to any
majeure which itself is a Roman Law concept not a additional monies.
Common Law concept.

Page | 8
Coronavirus (COVID-19) | Client guidance note

Termination What can an Employer/Client do?


In a worst case scenario, as an alternative to claiming Issues with regard to delay and the associated
for additional time, parties may wish to consider costs are dealt with retrospectively under JCT
termination. Force majeure can also give rise to a contracts. This can often lead to Contractors and
right for either party to terminate under clause 8.11 Employers becoming involved in disputes, as they
of JCT Design and Build 2016, should the whole or argue about entitlement and then the extent of
substantially the whole of the uncompleted works be delay and associated costs. It would be prudent for
suspended for longer than the period of time stated in Employers to ensure that the following are carried
the Contract Particulars, with the default period being out:
two months.
A review of the contractual provisions
Following suspension for the specified period, either
with the Employer’s Agent/Architect/
party may give notice to the other that, unless the
lawyer/ other advisors and understand
suspension ceases within seven days of receipt of the
the benefits and risks of different
notice, the Contractor’s employment may be terminated
provisions.
on the service of a second notice.
Parties should seek legal advice if they are considering Make sure that the programme is up-
termination because, amongst other things, if the event to-date and there is an understanding
is deemed not to be “force majeure”, the party seeking of the critical path and concurrent/
to rely on it could be open to a claim for repudiatory parallel delays. This will also make
breach of contract. agreement of any Extension of Time
easier.
The Contractors obligations
The assessment of any time for any Relevant Event Advise the Contractor that only direct
is subject to the further conditions, for instance JCT loss and/or expense (if applicable) will
Design and Build 2016 clause 2.25.6.1, states: be paid and that they should collate
“the Contractor shall constantly use his best detailed records of additional costs
endeavours to prevent delay in the progress incurred.
of the Works or any Section, howsoever
caused, and to prevent the completion of the Employers should also consider the other issues
Works or Section being delayed or further identified in the key impact areas section of this
delayed beyond the relevant Completion document.
Date”.

There is no specific legal definition under English law for


‘best endeavours’. It would though be likely to require
the Contractor to take all commercially reasonable
actions, incur reasonable expenses, re-programme and
divert reasonable resources in order to mitigate any
delays to completion. Whether a contractor has done
this could be the cause of considerable debate.

Page | 9
Coronavirus (COVID-19) | Client guidance note

FIDIC contracts

Page | 10
Coronavirus (COVID-19) | Client guidance note

FIDIC contracts
The “Fédération Internationale des Ingénieurs – Force majeure
Conseils” (International Federation of Consulting
Alternatively, parties could use the force majeure
Engineers - FIDIC) contracts are used widely
clauses. The 1999 edition FIDIC contracts, for instance
around the world and have also been around for
the Red Book under clause 19.1, defines force majeure
the last 100 years.
as an exceptional event or circumstance beyond a
The current FIDIC contracts provide specifically for Party’s control which:
epidemics under the contract clauses and therefore
◼ such Party could not reasonably have provided
should be easier for parties to agree time and money.
against before entering into Contract,
There are however other contractual mechanisms that
◼ having arisen, such Party could not reasonably
should be considered depending on the specifics of the
have avoided or overcome, and
project.
◼ is not substantially attributable to the other Party
Four possible ways of dealing with COVID-19 under
and it provides for:
FIDIC:
◼ time and payment of costs (clause 19.4),
1. Extension of Time
◼ suspension of work (clause 8.8), and
2. Force majeure ◼ termination (clause 19.6)
3. Suspension
Under the FIDIC 1999 Red Book provision 19.2, it is
4. Termination stated that if a party is aware that it is not going to
perform its obligations under the Contract caused by
Extension of Time
force majeure, a notice shall be issued within 14 days
FIDIC deals with this scenario much better than other after the affected party becomes aware or should have
contracts. Both the 1999 and 2017 FIDIC Red Books become aware of the event. The term force majeure
include for epidemics directly under the Extension of is not included in FIDIC 2017 editions however it does
Time (EOT) for completion provisions. For instance include the term “Exceptional Event” (under clause 18)
under 8.5(d) of the 2017 Red Book it states the with very similar implications to “force majeure”.
following as reason for entitlement to an EOT:
The circumstances relating to COVID-19, when tested
“Unforeseeable shortages in the availability against each of the above criteria in clause 19.1, give
of personnel or Goods (or Employer-supplied a strong argument that a force majeure event has
materials, if any) caused by epidemic or occurred.
governmental actions”
Suspension
With the World Health Organisation (WHO) declaring Under clause 8.8 of the 1999 Red Book or clause 8.9
the outbreak a “pandemic” on the 11 March 2020, this of the 2017 Red Book, the Engineer may at any time
clause may be the obvious clause to use. instruct the Contractor to suspend progress of part
The claiming Party is required to give notice of claim or all of the works stating the date and cause of the
within 28 days of becoming aware of the event or suspension. Where the Contractor suffers a delay and
circumstance and risks losing entitlement if they fail to incurs cost due to the suspension, when resuming work
do so. the Contractor is entitled to an Extension of Time and/
or payment of cost plus profit.

Page | 11
Coronavirus (COVID-19) | Client guidance note

The use of the suspension provisions should be What can an Employer/Client do?
a serious consideration for clients if practical
With the FIDIC contracts providing specifically
circumstances dictate that all works need to be
for epidemics there is likely to be less argument
stopped.
regarding entitlement. It would still be prudent for
Termination Employers to ensure that the following are carried
out:
Under clause 8.11 of the 1999 Red Book or clause
8.12 of the 2017 Red Book, if a Suspension of Work A review of the contractual provisions
continues for 84 days, the Contractor may give a Notice with the Engineer/lawyers/other
to the Engineer requesting permission to proceed. If the advisors and understand the benefits
Engineer then fails to give a Notice under clause 8.13 and risks of different provisions.
Resumption of Work within 28 days the Contractor can
either:
Make sure that the programme is up-
◼ agree to a further suspension to-date and there is an understanding
◼ after giving a second notice to the Engineer, treat of the critical path and concurrent/
the suspension as an omission of the affected part parallel delays. This will also make
of the Works agreement of any Extension of Time
◼ where suspension affects the whole works, the easier.
Contractor may give a Notice of termination under
clause 16.2 Termination by Contractor Advise the Contractor (where
applicable) that the procedures in
Clients should be aware of these clauses and discuss
Clause 20.2 Claims for Payment
termination with the Contractor, if it is applicable to
and/or EOT procedures should be
do so. Parties should seek legal advice if they are
followed, with ‘detailed supporting
considering termination.
particulars of the amount of
additional payment claimed’ will be
required.

Employers should also consider the other issues


identified in the key impact areas section of this
document.

Page | 12
Coronavirus (COVID-19) | Client guidance note

For more information:


e: cshelpdesk@turntown.com

Daniel Cheung
t: +852 9412 2480
e: daniel.cheung@turntown.com
Chrystele Kan
t: +852 5201 0081
e: chrystele.kan@turntown.com
John Boultwood
t: +44 (0) 7768 794 540
e: john.boultwood@turntown.com

www.turnerandtownsend.com

© Turner & Townsend Contract Services Limited. This content is for general information purposes only and does not
purport to constitute professional advice. We do not make any representation or give any warranty, express or implied,
and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this
document.
It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including
orally, to any other party without our express written permission and we accept no liability of whatsoever nature for any
use by any other party.

Page | 13

Вам также может понравиться