WORK PROCEDURE THAI KANDENKO CO.,LTD.

DATE 4-Mar-20
SUBJECT LOCKOUT CIRCUIT BREAKER (Turn Off)
SHEETS WP-E-011-0

WORK DESCRIPTION Miniature Circuit Lockout

1. Engineer prepare breaker locking devices that will shut down the electrical supply to the equipment.

& Lock Out Tag Out

2. Engineer check the equipment before confirm the Turn-off for power electric to equipment.
3. Engineer install a [Lock Out & Tag Out] at inside of the Breaker in panel, and then fill in In-charge name and date of working.

Lock Out
Miniature Circuit Install Tag Out
Breaker

WORK DESCRIPTION Locked out check

1. Engineer or Supervisor prepare Voltage Detector and Measurement Voltage meter

Voltage Detector Measurement Voltage meter

2. Engineer or Supervisor check Lock Out Breaker and check confirm the power OFF.
By Voltage Detector and Measurement Voltage meter.

Voltage Detector Check Measurement Voltage meter Check

3. Engineer or Supervisor After check sure finish confirm no power supply to equipment for worker start install & connection cable work.

WORK DESCRIPTION Lock Out Miniature Breaker for Inspection

1. Engineer check the [Lock Out and Tag Out Breaker] whether all item is filled in or not.

2. Engineer make [Lock Out and Tag Out Breaker] and fill in all item.

WORK DESCRIPTION Approval

1. Project Engineer or Project Manager check the [Tag Out] whether all item are passed or not.

2. Project Engineer or Project Manager sign on [Tag Out check list]

REMARK
1.Engineer, Project Engineer or Project manager must be not same person.