Summary
1.2 Prerequisite.............................................................................................................................. 3
1.3 Glossary................................................................................................................................... 3
1.5 Modification........................................................................................................................... 11
1.6 Display.................................................................................................................................... 11
2. Business recommendations.................................................................................12
Page 2 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Maintenance notifications put in process have to lead to the creation of a work order so that the work
can be executed.
Work orders can be raised directly through "In process" notifications list.
A work order must always be created from a notification. During order creation, it automatically
retrieves the data from notification. Once the work is completed, activity feedback has to be done in
the notification.
The work order breaks down into several operations which can be independently closed.
Several notifications can be integrated in one work order, several trades may be involved in one work
order.
No maintenance activity should start without an approved work order. Urgent maintenance work will
have to be documented in SAP after executing the work.
1.2 Prerequisite
The released notifications exist in the corresponding plant.
1.3 Glossary
Work order : A work order is a technical document which gathers together the tasks and resources
required to carry out the operations. It is also a financial document capturing all corresponding costs
(activity allocation, external services, procurement, purchasing) from operations.
Page 3 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
1.4.1 Transaction
Path :
Page 4 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Page 5 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Page 6 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Use the scroll bar to go to the « main work center » field (in the « General data/administrative
data » area).
Plant for work center Plant to which the work center in charge belongs
to display the list of PM notifications according to the required criteria from selection variants.
Page 7 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Select a PM notification.
to close the « object information » window. This provides some technical information from
the PM notification.
Page 8 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
Page 9 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
The system proposes basic start date. Basic end date is from
aggregation of all operations.
Page 10 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
1.5 Modification
The PM order can be changed individually using transaction IW32 and collectively using transaction
IW38.
1.6 Display
The PM order can be displayed individually using the transaction IW33 and collectively using
transaction IW39.
Page 11 of 12
Date : 15/06/20
Work Instruction
Doc : 480171007.doc
2. Business recommendations
Always note your work order number in case you have to come back to it for any reason. This will