Abstract of Cost
Name of Project: Gachhiya Lochani Gharamani Seshnarayan Divydham koyalpur sadak Morang.
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
2.6
Providing , Preparing and Installing form work
including necessary supports and removing after m2 84.00 1032.66 86743.44
completion for walls all complete as per specification.
(1804,1805)
2.7 Providing and laying reinforcement including cutting,
bending, binding, fixing in position etc. all complete as MT. 0.12 123321.98 14798.64
per specification and drawing.(Spec.2000)
2.8
Providing and placing machine mixed cement concrete
for the foundation and footing etc. including
compaction, curing, testing and lead 30m. etc. all m3 8.25 12212.79 100755.52
complete as per specification and drawing.(M20/20)
( Spec. 2000)
2.9
Providing suitable material and Back filling behind
abutment, wing wall and return wall complete as per
Drawing and Technical Specifications.( Locally m3 33.60 562.07 18885.55
available material) (Without watering& Compction by
Tamping rod)ss/sp(908)
Abstract of Cost
Name of Project: Gachhiya Lochani Gharamani Seshnarayan Divydham koyalpur sadak Morang.
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities
Name of Project: Gachhiya Lochani Gharamani Seshnarayan Divydham koyalpur sadak Morang.
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
1 General Works
1.1 Insurance for the loss or damage to works, materials and
contractor's equipments including personal injury or 1.00 1.00 LS
death as per Contract Data all Complete.
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities
Name of Project: Gachhiya Lochani Gharamani Seshnarayan Divydham koyalpur sadak Morang.
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
3.0 Pavement Construction Works
3.1
Formation of embankment including compaction in
layers not exceeding 150 mm compacted depth,
watering , rolling and transporting etc. all complete as
per specification [SS/SP- 907 ] 2 203 1.5 0.65 395.9 m3
3.2
Subgrade preparation / Regrading of gravel surface by
scarifying with grader machine including watering,
levelling , formation of camber and compaction all
complete for sub grade preparation work all complete as
per Specification. [SS/SP- 1003]
3.5
Providing and spraying bituminious prime coat
including cleaning the road surface using wire, brushes, 1.00 255.00 5.50 1402.50 m2
broom etc. before applying prime coat all complete as
per Specification. [SS/SP-1301, 1302]
Total Spray rate 1lit/m2 1402.50 Lit
3.6
Providing and spraying bituminious tack coat including
cleaning the road surface using wire, brushes, broom
etc. before applying tack coat all Complete as per 1 255.00 5.50 2926.00 m2
Specification. [SS/SP-1301, 1302]
General Works
NA PS 1
Insurance for the loss or damage to works,
materials and contractor's equipments
including personal injury or death as per
Contract Data all Complete. LS 1.00 30000.00