Академический Документы
Профессиональный Документы
Культура Документы
M. Jiménez
Technical Committee on Underground Works, Costa Rica.
Geomekca Consultores Geomecánicos de Centro América S.A., San José, Costa Rica.
LANDSLIDE
PENSTOCK
FAULT
Penstock
Lagoon
River
Landslide
Fault zone
(normal)
A transversal geological profile of the ground that underground water was one of the main
around the pipeline can be observed in Figure 1. destabilizing agents of the ground.
The profile is parallel to the landslide
displacement vector; thus, it affects the pipeline 3. GROUND STABILITY DIAGNOSIS
in its perpendicular direction. This profile,
considered together with geophysical The pseudostatic stability analysis, using even a
interpretation and the geomechanical very low horizontal pseudostatic coefficient
characterization of materials, was the basic (0.05), produced safety factors under 1.0;
input for the geotechnical model used to analyze correspondingly, the probability of failure is
the stability of the ground and penstock. practically of 100% in all cases.
Figure 1 show how the pipeline is located Subsequently, by means of a sensitivity
over the instable ground mass, that overlaps analysis, modifying the cohesion and the
with the Upper sequence (described before) and friction angle of the altered lahar, the minimum
the altered breccia. Likewise, it is affected and values for both parameters that produce
delimitated by the oblique form of the instability were obtained.
geological faults, contributing to create a Thus, the slope requires a minimum cohesion
geologically adverse zone. of 10 kPa and a friction angle of 16°,
The underground water also behaves in a approximately, to be stable.
complex manner; generally, the soil present in The cohesion values and friction angles,
the zone shows low permeability, and water defined as more representative for the altered
flows through existing preferential paths in the lahar correspond to 10 kPa and 15°,
soil mass (fissures, voids). However, the respectively.
material saturation remains high, and affects the All results confirmed the unstable actual
geo-materials shear strength. It was recognized condition of the landslide.
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Table 1 shows all the geotechnical Due to the low safety factors and high
parameters used in the analysis, and Figure 2 probabilities of failure, it was necessary to
show the geotechnical model used for suggest alternatives in order to reduce the
calculations. pipeline operation level of risk before against
the landslide. Therefore, two options were
Table 1. Geomechanical properties of geomaterials studied. These are presented in the following
section.
GU-1 GU-2 GU-3
Altered Altered Fresh 4. OPTIONS FOR SECURING THE
Lahar breccia breccia PENSTOCK
t (kN/m3) 17 – 18 19 – 20 21 – 22
c (MPa) - 1,0 – 2,5 2,5 – 7,5
Erm (MPa) 5 – 10 500 – 800 1500–3000
Stabilization solutions using retaining walls,
0,30 – 0,35 0,25 – 0,30 0,25 – 0,30 anchorages, micropiles, piles, piers or
mi - 17 – 19 19 – 21 modifications to topography by earth moving
GSI - 30 – 40 50 – 60 represent all very expensive and ineffective
RMR - 30 – 40 50 – 60 solutions for the magnitude and depth of the
Q - 0,1 – 0,4 0,4 – 1,0 landslide. Therefore, two alternatives were
c (kPa) 0 – 20 90 – 100 150 – 200 proposed to solve the stability problems of the
(°) 10 – 20 30 – 33 35 – 39 pipeline zone.
k (cm/s) 1 to 5x10-6 - -
Penstock
Elevation (m.a.s.l)
Altered lahar
Altered breccia
Fresh breccia
Distance (x)
The first option consisted in creating a deep prefabricated permeable concrete tubes, which
drainage using microtunneling construction will serve as draining elements once they are
technique (pipe jacking), and the second installed in the ground.
solution was to excavate a tunnel in the stable The usage of the pipe jacking technique
ground under the landslide zone. A scheme for requires the construction of vertical shafts that
both solutions is shown in Figure 3. are used to start the excavation of micro tunnels,
but also as drainage shafts. These shafts were
4.1 Option 1: slope stabilization by drainage proposed with a circular section of 4,5 m
diameter (excavation section of 15,9 m2) and a
The location of the drainage screen is shown in distance of 12 m between them.
Figure 3 (NE of the penstock), and the main The starting shaft for microtunnelling will be
characteristics of the screen are: constituted by reinforced shotcrete and steel
The screen will be built with the pipe jacking arches. Shaft walls will be lined with shotcrete,
technique. This technique consists in excavating reinforced with steel fiber or synthetic fiber.
tunnels of small diameter (600 mm), using
3
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Powerhouse
Tunnel
Tunnel (OP-2)
Tunnel exit portal (OP-2)
Reservoir
Landslide
Intake shaft
(OP-2)
Figure 3. Options for ensuring the penstock: surficial (OP-1) or underground (OP-2)
The stability analysis of the landslide taking enough into the Basal sequence, considered
into account the influence of the draining stable. The basic premise is based on the
screen, showed safety factors in the range of stability analysis and geological mapping, since
1,14 to 1,21 (static condition) and from 0,53 to the geotechnical units GU-3 and GU-4 do not
0,92 (seismic condition). These values have the influence of the landslide at the depth
correspond to probability of failure between of the tunnel excavation.
18,9% and 21,9% for static condition and up to Figure 4 shows the layout plan of the tunnel,
67,9% until 100% in pseudostatic condition. which begins with a vertical shaft within the
Thus, even with improved safety factors in current reservoir area, so its construction
static condition, these were considered still process, is closely related to the reservoir.
relatively low (less than 1,21) and the odds of Tunnel length would be approximately 580 m
failure were high (generally greater than 12% in till connecting again with the current penstock,
the case the altered lahar had a thickness of 26 as shown in Figure 4. Tunnel diameter is 3,5 m,
m or so). In the case of the pseudostatic with a horseshoe cross-section, and a base width
analysis, safety factor values were unacceptable of 2,56 m.
(less than 1,0 with corresponding extremely The geotechnical model along the line of
high probability of failure, above 68%), tunnel is shown in Figure 5.
indicating that during an earthquake the The following summarizes the main
deformations may become high despite the characteristics of the underground work,
presence of the drainage screen. proposed as an alternative to surface
According to these results, this option alone conduction:
does not guarantee the stability of the ground The tunnel will serve only to place the
and the operational continuity of the Plant. penstock inside, so it is not a pressure tunnel. It
must be constructed using the conventional
4.2 Option 2: Underpass with tunnel method of drilling and blasting, in complete
section. The excavation shape is curved in order
The second alternative for the passage of the to generate a stable section and a geometry
pipeline involves the relocation of the current which contributes to reducing the need for
path in the surface to an excavated tunnel, deep support.
4
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Penstock
Tunnel exit
portal
Existing reservoir
Tunnel
Exit portal
Powerhouse
Tunnel
Fresh breccia
The primary support of the excavation shall in the area where the pipeline is located and
consist of reinforced shotcrete and/or steel then connects to it, going to the powerhouse.
arches. This support will be part of the final The maximum slope of the excavation is 2%
tunnel lining that shall consist of reinforced (compatible with the use of machinery
shotcrete. mobilization on wheels). The maximum
A 15 cm thick concrete floor slab must be coverage is around 55 m.
build, and it should be completed during the The proposed shaft is approximately 50 m
progress of the excavation. deep. It is proposed with a circular geometry
The tunnel would begin in a shaft from inside with a diameter of 5,0 m (19,6 m2 excavation
the reservoir and it would ends at an exit portal section). The shaft lining consist of reinforced
shotcrete and steel arches.
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
5. GEOTECHNICAL DESIGN
Table 2. Estimated support using Q system
The assessment of the excavation behavior Shotcrete Bolts
using geomechanics classification systems thickness
showed the need to use at least 2 different types (cm)
of support. Based on the Q system (Figure 6) of GU- 3 5 spot
Fresh breccia
Barton (2002), a support consisting of at least 5 GU-4 9 – 12 1,3m x 1,3m
cm of fiber reinforced shotcrete (FRS) must be Fault zones
necessary for the GU-3 (fresh breccia) while at
least 10 cm of FRS must be used for the
geotechnical unit GU-4 (fault zones). Table 3. Estimated support using RMR system
In Figure 7, the support estimation from Shotcrete Bolts Arches Stand-
RMR system of Bieniawski (1989) is shown. thickness up time
For the GU-3 shows good stand-up time (days (cm)
to weeks), so the use of shotcrete as support is GU- 3 5 – 10 1,5m x No Weeks
completely valid in this GU. Meanwhile, stand- Fresh 1,5m for 6 m
up time for fault zones is very low (in the order breccia
of hours), making it necessary the use of steel GU-4 8 – 15 1,0m x W6x20 Hours
Fault 1,0m @1,5m for 2 m
arches.
zones
Unsupported 5 520
maximum
convergence (mm) (0,2%) (14,9%)
Table 5. Properties and safety factors of the support breccia is located at a depth of about 33 m from
and final lining the natural ground level.
GU-3 GU-4 The thickness of the altered lahar varies
RFS (cm) 5 7,5 between 17 m and 26 m, while the thickness of
Temporary W6x20 @ the altered breccia varies between 8 m and 17
Arches NA
support 1,5 m m. The water table surface was observed in
SF 1,5 1,1 boreholes, so it was considered that its location
varies from surface to 16 m depth, with
RFS (cm) 5 10
Final lining reference to the natural ground level.
SF 1,5 1,5
The stability analysis performed gave factors
of safety below 1.0 for all cases considered,
Design recommendations from the USA
consistent with the observed movements of the
Corps of Engineering (1997) were also used as
ground. The probability of failure against the
an important reference for the design.
slide for the case of static analysis showed
values between 51% and 86%, while for the
6. CONCLUSIONS
pseudo-static case, the probabilities of failure
were higher than 97% with pseudostatic
A small hydroelectric project in Costa Rica was
horizontal coefficients as low as 0.05. The result
experiencing problems due to earthquake-
of the stability analysis reflects the current
triggered land instabilities.
condition of the site, which is likely to continue
By means of the geological mapping
in the near future.
conducted in the study area, it was determined
For the short term, it is expected a similar
that the penstock was located in an area of
extent and rate of movements, with peak
critical instability, affected by fault zones and
displacement likely to occur after extreme
fractures. Sliding displacement rates greater
precipitation events or earthquakes of moderate
than 0.1 m per month were registered,
to strong intensity.
corresponding with a Class 3 - Class 2 (slow to
In such conditions, options to reduce
very slow) type of slide, according the scale
vulnerability of the pressure penstock were
defined by Cruden and Varnes (1996). This
mandatory. Two options were proposed: 1) to
gave the time to make continuous adjustments
preserve the alignment of the pipe trying to
on the steel penstock alignment, which are
increase the safety factor of the slope by a
considered not sustainable in the short or
treatment consisting on deep drainage to
medium term. Thus, the operational safety of
intercept groundwater, and 2) change the
the plant is not guaranteed.
alignment of the pipe using a tunnel passing
Based on geological and geotechnical
below the unstable area.
surveys, four materials with different physical
The drainage screen used in the analysis was
and mechanical properties were determined.
proposed with a depth between 17 m and 26 m,
The geotechnical units identified in the study
depending on the thickness of the altered lahar.
area were:
The proposed construction technique of the
Geotechnical Unit 1 (GU-1): Altered lahar,
screen is microtunnelling (pipe jacking),
essentially consisting of igneous blocks
building intermediate attack shafts, and with
surrounded by a silt-clayey matrix.
horizontal boreholes drilled from inside the
Geotechnical Unit 2 (GU-2): Altered breccia,
shafts to drain the surrounding terrain. The
weathered rock mass corresponding to the
diameter of the attack shafts is 4.5 m. They are
shallowest part of the bedrock.
lined with shotcrete and/or steel arches. Thus,
Geotechnical Unit 3 (GU-3): Fresh breccia,
the screen constitutes a barrier to intercept the
medium soft rock mass quality corresponds to
groundwater flow. The logic of this solution is
the base of the sequence identified in the site.
to extract water from the ground, being this one
Geotechnical Unit 4 (GU-4) fault zones, poor
of the main destabilizing factors of the soil
to very poor rock mass.
mass.
The geotechnical model is constituted by the
Stability analysis including the drainage
four geotechnical units mentioned above. The
screen (Option 1) gave a safety factor in static
geological contact between altered and fresh
condition between 1,14 and 1,21, with
probability of failure from 12% to 22%. While,
7
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
for the pseudo-static case, safety factors fall Hoek, E. y Marinos, P. (2000). Predicting tunnel
below 1.0 in all cases, with probabilities of squeezing problems in weak heterogeneous rock
masses. Tunnels and Tunnelling International, 1-21.
failure above 67%. Therefore, according to the United States Army Corps of Engineers (1997). Tunnels
analysis, this alternative by itself does not and shafts in rock. Washington, DC: Department of
guarantee the operational continuity of the plant. the Army.
The second proposal was further analyzed
with corresponding relocation of the pipe, under
passing the unstable region in a tunnel. The
pipeline would be installed inside the tunnel,
which would facilitate maintenance. This option
involves the construction of a vertical shaft of
5,0 m diameter for connecting the reservoir with
the pipe in the tunnel. The shaft depth is 55 m.
The tunnel should be built using the
traditional system of drilling and blasting. The
proposed excavation diameter is 3,5 m. The
slope of the tunnel is 2 %.
Primary support is considered to contribute
in carrying loads together with final lining, in
order to minimize construction costs. Thus the
support/lining proposed consists of shotcrete
reinforced with fiber and/or steel arches.
The excavation floor should be covered with
a concrete slab 15 cm thick, built during the
advance of the excavation.
The final lining of the tunnel is completed
with a second layer of shotcrete 15 cm thick for
a total thickness of 25 cm shotcrete.
It was determined that the option that
provides the highest level of security for the
hydroelectric plant is the change in the
alignment of the pressure line using the tunnel
that underpasses the unstable region.
In this case, despite cost considerations, the
underground solution was the only way to
rehabilitate the plant while assuring the required
operational safety standards.
8. REFERENCES