Вы находитесь на странице: 1из 1

GAS DEVELOPMENT PROJECT FOR THE UNITIZATION OF

THE JAMBARAN – TIUNG BIRU FIELD


(GAS PROCESSING FACILITIES)
Activity Name At Start Finish August September October November December January February March April May June July August September October November December January February March April May June July
Completion 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Duration 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
11-Jun-21, 323 - SAU
323 - SAU 842 28-Dec-18 A 11-Jun-21
15-Apr-20, Engineering
Engineering 406 12-Feb-19 A 15-Apr-20
IFC Piling DWG for Equipment Area 323 (Approval by Company) 290 12-Feb-19 A 15-Apr-20 IFC Piling DWG for Equipment Are a 3 23 (Approval by Company)
IFC Piling DWG for EQP (J140) (Approval by Company) 0 15-Apr-20 IFC Piling DWG for EQP (J140) (Approval by Company),
Procurement 738 28-Dec-18 A 15-Feb-21 15-Feb-21, Procurement

Acid Tower Area 420 30-Nov-19 15-Feb-21 15-Feb-21, Acid Tower Area
Manufacturing for Acid Towers 258 30-Nov-19 16-Oct-20 Manufacturing for Acid Towers
Manufacturing for Acid Pumps 173 26-Dec-19 30-Jul-20 Manufacturing for Acid Pumps
Manufacturing for Acid Coolers 221 31-Dec-19 02-Oct-20 Manufacturing for Acid Coolers
Manufacturing for Saramet Piping 151 08-Jun-20 04-Dec-20 Manufacturing for Saramet Piping
Shipping for Acid Pumps 70 01-Aug-20 11-Oct-20 Shipping for Acid Pump s
Shipping for Acid Coolers 70 03-Oct-20 12-Dec-20 Shipping for Acid Coolers
Shipping for Acid Towers 70 17-Oct-20 27-Dec-20 Shipping for Acid Towers
Shipping for Saramet Piping - 1st Lot 70 23-Oct-20 04-Jan-21 Shipping for Saramet Piping - 1st Lot
Shipping for Saramet Piping - 2nd Lot 70 05-Dec-20 15-Feb-21 Shipping for Saramet Piping - 2nd Lot
Converter Area 680 28-Dec-18 A 16-Dec-20 16-Dec-20, Converter Area
Manufacturing for Converter 518 28-Dec-18 A 02-Oct-20 Manufacturing for Converter
Manufacturing for SAU Converter Air Cooler 278 23-Oct-19 A 02-Oct-20 Manufacturing for SAU Converter Air Cooler
Manufacturing for Preheater 138 26-Dec-19 19-Jun-20 Manufacturing for Preheater
Shipping for Preheater 70 20-Jun-20 31-Aug-20 Shipping for Preheater
Shipping for Fans 70 22-Aug-20* 31-Oct-20 Shipping for Fans
Shipping for Converter 70 03-Oct-20 12-Dec-20 Shipping for Converter
Shipping for SAU Converter Air Cooler 74 03-Oct-20 16-Dec-20 Shipping for SAU Converter Air Co oler
Heat Exchanger Area 372 30-Nov-19 27-Dec-20 27-Dec-20, Heat Exchanger Area
Manufacturing for Gas Heat Exchanger 237 30-Nov-19 22-Sep-20 Manufacturing for Gas Heat Exchanger
Manufacturing for Blowers 258 30-Nov-19 16-Oct-20 Manufacturing for Blowers
Shipping Gas Heat Exchanger 70 23-Sep-20 02-Dec-20 Shipping Gas Heat Exchanger
Shipping for Blowers 70 17-Oct-20 27-Dec-20 Shipping for Blowers
Cooling Water Area 376 15-Apr-19 A 17-May-20 17-May-20, Cooling Wat er Area
Manufacturing for ACHE Package-3 311 15-Apr-19 A 02-May-20 Manufacturing for ACHE Packa ge-3
Manufacturing for Drum 276 16-May-19 A 20-Apr-20 Manufacturing for Drum
Manufacturing for General Service (ANSI) Pump 214 28-May-19 A 15-Feb-20 Manufacturing for General Service (ANSI) Pump
Shipping for 323-P9022 A/B CW Supply Pump 3 16-Feb-20 18-Feb-20 Shipping for 323-P9022 A/B CW Supply Pump
Shipping for 323-D9023 SAU CW Expansion Drum 7 21-Apr-20 27-Apr-20 Shipping for 323-D9023 SAU CW Expansion Drum
Shipping for ACHE Package-3 14 03-May-20 17-May-20 Shipping for ACHE Package-3
21-May-21, Construction
Construction 443 01-Feb-20 21-May-21
Acid Area 332 05-Jun-20 21-May-21 21-May-21, Acid Area
Piling Work for Equipment Foundation at Sulphuric Acid Unit 50 05-Jun-20 25-Jul-20 Piling Work for Equipment Foundation at Sulphuric Acid Unit
Foundation Work for Equipment at Sulphuric Acid Unit 60 05-Jul-20 06-Sep-20 Foundation Work for Equipment at Sulphuric Acid Unit
Prefabricated Support for Acid Tower at Sulphuric Acid Unit 14 29-Jul-20 12-Aug-20 Prefabricated Support for Acid Tower at Sulphuric Acid Unit
Excavation & Installation of Precast Sump at Sulphuric Acid Unit 5 05-Aug-20 10-Aug-20 Excavation & Installation of Precast Sump at Sulphuric Acid Unit
Road & Paving Work at Sulphuric Acid Unit 42 06-Sep-20 18-Oct-20 Road & Paving Work at Sulphuric Acid Unit
SAU Absorber Cooler (323-E9014) Installation at Sulphuric Acid Unit 1 13-Dec-20 13-Dec-20 SAU Absorber Cooler (323-E9014) Installation at Sulphuric Acid Unit
SAU Dry Cooler (323-E9004) Installation at Sulphuric Acid Unit 1 14-Dec-20 14-Dec-20 SAU Dry Cooler (323-E9004) Installation at Sulphuric Acid Unit
SAU Product Cooler (323-E9017) Installation at Sulphuric Acid Unit 1 15-Dec-20 15-Dec-20 SAU Product Cooler (323-E9017) Installation at Sulphuric Acid Unit
Equipment Structure (Inc. Grating & Stairway up to 6.000) around Acid Tower at Suplhuric
14 16-Dec-20
Acid Unit 30-Dec-20 Equipment Structure (Inc. Grating & Stairway up to 6.000) around Acid Tower at Suplhuric Acid Unit
Support Installation for Acid Tower at Sulphuric Acid Unit 2 18-Dec-20 20-Dec-20 Support Installation for Acid Tower at Sulp huric Acid Unit
SAU Absorber Tower (323-T9011) Installation at Sulphuric Acid Unit 1 31-Dec-20 31-Dec-20 SAU Absorber Tower (323 -T9 011) Installation at Sulphuric Acid Unit
SAU Dry Tower (323-T9001) Installation at Sulphuric Acid Unit 1 02-Jan-21 02-Jan-21 SAU Dry Tower (323-T9001) Installation at Sulphuric Acid Unit
Equipment Structure (Inc. Grating up to top level) around Acid Tower at Suplhuric Acid
14 Unit
03-Jan-21 16-Jan-21 Equipment Structure (Inc. Grating up to top level) around Acid Tower at Suplhuric Acid Unit
SAU Product Stripper (323-T9015) Installation at Sulphuric Acid Unit 1 17-Jan-21 17-Jan-21 SAU Product Stripper (323-T9015) Installation at Sulphuric Acid Unit
Scaffolding Installation Absorber Tower at Suplhuric Acid Unit 2 17-Jan-21 18-Jan-21 Scaffolding Installation Absorber To wer at Sup lhuric Acid Unit
Cooling Water Pipe Work at Acid Tower Structure 30 17-Jan-21 16-Feb-21 Cooling Water Pipe Work at Acid Tower Structure
Electrical Cable Tray Installation at Acid Tower at Sulphuric Acid Unit 15 17-Jan-21 31-Jan-21 Electrical Cable Tray Installation at Acid Tower at Sulphuric Acid Unit
Instrument Cable Tray Installation at Acid Tower at Sulphuric Acid Unit 15 17-Jan-21 31-Jan-21 Instrument Cable Tray Installation at Acid Tower at Sulphuric Acid Unit
Ducting Installation on Absorber Tower (Incl. Welding & Insulation) at Sulphuric Acid 5Unit19-Jan-21 23-Jan-21 Ducting Installation on Absorber Tower (Incl. Welding & Insulation) at Sulphuric Acid Unit
Scaffolding Installation Dry Tower at Suplhuric Acid Unit 5 19-Jan-21 23-Jan-21 Scaffolding Installation Dry Tower at Suplhuric Acid Unit
Ducting Installation on Dry Tower (Incl. Welding & Insulation) at Sulphuric Acid Unit 8 24-Jan-21 31-Jan-21 Ducting Installation on Dry Tower (Incl. Welding & Insulation) at Sulphuric Acid Unit
Platform & ladder Installation Absorber Tower at Suplhuric Acid Unit 6 24-Jan-21 29-Jan-21 Platform & ladder Installation Absorber Tower at Suplhuric Acid Unit
Platform & ladder Installation Dry Tower at Suplhuric Acid Unit 6 01-Feb-21 06-Feb-21 Platform & ladder Installation Dry Tower at Suplhuric Acid Unit
Pulling Electrical Cable at Acid Tower at Sulphuric Acid Unit 15 01-Feb-21 16-Feb-21 Pulling Electrical Cable at Acid Towe r at Sulphuric Acid Unit
Dry Tower & Absorber Tower Internals Installation at Sulphuric Acid Unit 21 01-Feb-21 22-Feb-21 Dry Tower & Absorber Tower Internals Installation at Sulphuric Acid Unit
Stairway Structure around Acid Tower at Suplhuric Acid Unit 21 07-Feb-21 28-Feb-21 Stairway Structure around Acid Tower at Suplhuric Acid Unit
Pulling Instrument Cable at Acid Tower at Sulphuric Acid Unit 10 17-Feb-21 26-Feb-21 Pulling Instrument Cable at Acid Tower at Sulphuric Acid Unit
Hydrotest and Flushing Cooling Water Pipe at Acid Tower Structure 7 17-Feb-21 23-Feb-21 Hydrotest and Flushing Cooling Water Pipe at Acid Tower Structure
Electrical Termination (For Motor; Inc. Meger Test) at Acid Tower at Sulphuric Acid10
Unit17-Feb-21 26-Feb-21 Electrical Termination (For Motor; Inc. Meger Test) at Acid Tower at Sulphuric Acid Unit
Touch Up Painting Cooling Water Pipe at Acid Tower Structure 5 24-Feb-21 28-Feb-21 Touch Up Painting Cooling Wate r Pipe at Acid To wer Structure
SAU Dry Pump (323-P9003A/B) Installation at Sulphuric Acid Unit 2 01-Mar-21 02-Mar-21 SAU Dry Pump (323-P9003A/B) Installation at Sulphuric Acid Unit
SAU Absorber Pump (323-P9013A/B) Installation at Sulphuric Acid Unit 2 03-Mar-21 04-Mar-21 SAU Absorber Pump (323-P9013A/B) Installation at Sulphuric Acid Unit
Sulfuric Acid Transfer Pump (323-P9016A/B) Installation at Sulphuric Acid Unit 2 05-Mar-21 06-Mar-21 Sulfuric Acid Transfer Pump (323-P9016A/B) Installation at Sulphuric Acid Unit
Ceramic Tile & Sump Pit Work at Sulphuric Acid Unit 20 07-Mar-21 28-Mar-21 Ceramic Tile & Sump Pit Work a t Sulphuric Acid Unit
Saramet Piping Work at Acid Tower Structure 15 29-Mar-21 13-Apr-21 Saramet Piping Work at Acid Tower Structure
Sump Pump Roof Installation at Sulphuric Acid Unit 1 29-Mar-21 29-Mar-21 Sump Pump Roof Installation at Sulphuric Acid Unit
Strong Acid Sump Pump (323-P9021) Installation at Sulphuric Acid Unit 1 30-Mar-21 30-Mar-21 Strong Acid Sump Pump (323-P9021) Installation at Sulphuric Acid Unit
Field Instrument Installation on Saramet Piping at Acid Tower Structure 15 14-Apr-21 28-Apr-21 Field Instrument Installation on Saramet Piping at Acid Tower Structure
Lighting & Fitting Installation at Acid Tower Structure 15 14-Apr-21 28-Apr-21 Lighting & Fitting Installation at Acid Tower Structure
Piping Work at Sump Pump at Sulphuric Acid Unit 2 14-Apr-21 15-Apr-21 Piping Work at Sump Pump at Sulphuric Acid Unit
Epoxy Coating on Paved Area at Acid Tower Structure 10 29-Apr-21 09-May-21 Epoxy Coating on Paved Area at Acid Tower Structure
Touch Up Painting Acid Structure at Acid Tower Structure 10 29-Apr-21 09-May-21 Touch Up Painting Acid Structure at Acid Tower Structure
Instrument Termination at Acid Tower Sulphuric Acid Unit 15 29-Apr-21 21-May-21 Instrument Termination at Acid Tower Sulphuric Acid Unit
Electrical Termination (lighting) at Acid Tower Sulphuric Acid Unit 15 29-Apr-21 21-May-21 Electrical Termination (lighting) at Acid Tower Sulphuric Acid Unit
Converter Area 124 13-Dec-20 21-Apr-21 21-Apr-21, Converter Area
SAU Converter (323-R9005) Lowest Section on Foundation at Sulphuric Acid Unit 1 13-Dec-20 13-Dec-20 SAU Converter (323-R9005) Lowest Section on Foundation at Sulphuric Acid Unit
Scaffolding Installation Around Converter Lowest Section on Foundation at Sulphuric3 Acid
14-Dec-20
Unit 16-Dec-20 Scaffolding Installation Aro und Converte r Lowest Section on Foundation at Sulphuric Acid Unit
Fit Up & Allignment of Converter Middle Section at Sulphuric Acid Unit 2 17-Dec-20 18-Dec-20 Fit Up & All ignment of Converter Midd le Sectio n at Sulp huric Acid Unit
SAU Cooling Air Blower Package (323-V9300/9400) Installation at Sulphuric Acid 15
Unit19-Dec-20 04-Jan-21 SAU Cooling Air Blower Package (323-V9300/9400) Installation at Sulphuric Acid Unit
Welding Converter Middle Section to Lowest Section at Sulphuric Acid Unit 8 19-Dec-20 27-Dec-20 Welding Converter Middle Section to Lowest Section at Sulphuric Acid Unit
Extend Scaffolding up to Top Section at Sulphuric Acid Unit 3 28-Dec-20 30-Dec-20 Extend Scaffolding up to Top Section at Sulphuric Acid Unit
Fit Up & Allignment of Converter Top Section at Sulphuric Acid Unit 2 31-Dec-20 02-Jan-21 Fit Up & Allignment of Converter Top Section at Sulphuric Acid Unit
Welding Converter Top Section to Middle Section at Sulphuric Acid Unit 8 03-Jan-21 10-Jan-21 Welding Converter Top Section to Middle Section at Sulphuric Acid Unit
Remove Scaffolding at Sulphuric Acid Unit 1 11-Ja n-21 11-Jan-21 Remove Scaffolding at Sulphuric Acid Unit
Lower Half Manifold Structure Installation at Sulphuric Acid Unit 7 12-Jan-21 18-Jan-21 Lower Half Manifold Structure Installation at Sulphuric Acid Unit
Converter Bottom Manifold Installation at Sulphuric Acid Unit (Fit Up & Welding) 10 19-Jan-21 28-Jan-21 Converter Bottom Manifold Installation at Sulphuric Acid Unit (Fit Up & Weld ing)
Upper Half Manifold Structure Installation at Sulphuric Acid Unit 5 29-Jan-21 02-Feb-21 Upper Half Manifold Structure Installation at Sulphuric Acid Unit
Converter Top Manifold Installation at Sulphuric Acid Unit (Fit Up & Welding) 10 03-Feb-21 13-Feb-21 Converter Top Manifold Installation at Sulphuric Acid Unit (Fit Up & Welding)
Lower Half Structure Installation From Air Blower to Converter at Sulphuric Acid Unit
12 03-Feb-21 15-Feb-21 Lower Half Structure Installation From Air Blower to Converte r at Sulphuric Acid Unit
Complete Steel Structure Cross Member at Sulphuric Acid Unit 2 14-Feb-21 15-Feb-21 Complete Steel Structure Cross Member at Sulphuric Acid Unit
Insulation for Converter and Manifold at Sulphuric Acid Unit 15 14-Feb-21 28-Feb-21 Insulation for Converter and Manifold at Sulphuric Acid Unit
SAU Converter Air Cooler (323-E9006) Installation at Sulphuric Acid Unit 1 16-Feb-21 16-Feb-21 SAU Converter Air Cooler (323-E9 006) Installation at Sulphuric Acid Unit
Lower Ducting Installation From & To Converter Air Cooler Installation at Sulphuric Acid
10 17-Feb-21
Unit 26-Feb-21 Lower Ducting Installation From & To Converter Air Cooler Installation at Sulphuric Acid Unit
Steam Pipe Installation at Sulphuric Acid Unit 30 17-Feb-21 20-Mar-21 Steam Pipe Installation at Sulphuric Acid Unit
Upper Half Structure Installation From Air Blower to Converter at Sulphuric Acid Unit
14 27-Feb-21 13-Mar-21 Upper Half Structure Installation From Air Blowe r to Converter at Sulphuric Acid Unit
SAU Preheater (323-E9008) Installation at Sulphuric Acid Unit 1 15-Mar-21 15-Mar-21 SAU Preheater (323-E9008) Installation at Sulphuric Acid Unit
Upper Ducting Installation From & To Converter Air Cooler Installation at Sulphuric Acid
14 16-Mar-21
Unit 29-Mar-21 Upper Ducting Installation From & To Converter Air Cooler Installatio n at Sulp huric Acid Unit
Complete Insulation for Ducting at Sulphuric Acid Unit 7 30-Mar-21 06-Apr-21 Complete Insulation for Ducting at Sulphuric Acid Unit
Complete Steel Structure Cross Member at Sulphuric Acid Unit 5 07-Apr-21 11-Apr-21 Complete Steel Structure Cross Member at Sulphuric Acid Unit
Insulation for Steam Pipe at Sulphuric Acid Unit 15 07-Apr-21 21-Apr-21 Insulation for Steam Pipe at Sulphuric Acid Unit
Exchanger Area 85 03-Dec-20 28-Feb-21 28-Feb-21, Exchanger Are a
Insulation for SAU Cold Exchanger (323-E9009) at Laydown Area 10 03-Dec-20 12-Dec-20 Insulation for SAU Cold Exchanger (323-E9009) at Laydown Area
SAU Cold Exchanger (323-E9009) Installation at Sulphuric Acid Unit 2 13-Dec-20 14-Dec-20 SAU Cold Exchanger (323-E9009) Installation at Sulphuric Acid Unit
SAU SO2 Blower Package (323-V9100/9200) Installation at Sulphuric Acid Unit 15 28-Dec-20 12-Jan-21 SAU SO2 Blower Package (323-V9100/9200) Installation at Sulphuric Acid Unit
Steel Structure Installation (Inc. Platform) at Blower Package at Sulphuric Acid Unit 7 03-Jan-21 09-Jan-21 Steel Structure Installation (Inc. Platform) at Blower Package at Sulphuric Acid Unit
Ducting Installation from suction & discharge Blower at Sulphuric Acid Unit 8 10-Jan-21 17-Jan-21 Ducting Installation from suction & discharge Blower at Sulphuric Acid Unit
Scaffolding Installation at SAU Cold Exchanger at Sulphuric Acid Unit 7 10-Jan-21 16-Jan-21 Scaffolding Installation at SAU Cold Exchanger at Sulphuric Acid Unit
Install Scaffolding for Ducting from Dry Tower to Blower at Sulphuric Acid Unit 7 17-Jan-21 23-Jan-21 Install Scaffolding for Ducting from Dry Tower to Blower at Sulphuric Acid Unit
Ducting Installation to and from Converter at Sulphuric Acid Unit 15 01-Feb-21 16-Feb-21 Ducting Installation to and from Converter at Sulphuric Acid Unit
Electrical Cable Tray Installation at Exchanger Area 10 01-Feb-21 10-Feb-21 Electrical Cable Tray Installation at Exchanger Area
Instrument Cable Tray Installation at Exchanger Area 10 01-Feb-21 10-Feb-21 Instrument Cable Tray Installation at Exchanger Area
Complete Ducting Installation to Acid Tower at Sulphuric Acid Unit 12 17-Feb-21 28-Feb-21 Complete Ducting Installation to Acid Tower a t Sulphuric Acid Unit
Cooling Water Area 249 01-Feb-20 24-Oct-20 24-Oct-20, Cooling Water Area
Piling Work for Equipment Foundation Cooling Water Area at Sulphuric Acid Unit 8 01-Feb-20* 08-Feb-20 Piling Work for Equipment Foundation Cooling Wa ter Area at Sulphuric Acid Unit
Foundation Work for Equipment Cooling Water Area at Sulphuric Acid Unit 30 09-Feb-20 10-Mar-20 Foundation Work for Equipment Cooling Wat er Area at Sulphuric Acid Unit
Steel Structure Installation for Cooling Water Area (Inc. Grating ) 20 27-Mar-20 16-Apr-20 Steel Structure Installation for Cooling Water Area (Inc. Grating )
Dress Up for Expansion Drum (Incl. Accesories) 12 28-Apr-20 11-May-20 Dress Up for Expansion Drum (Incl. Accesories)
CW Expansion Drum 323-D9023 Installation at Sulphuric Acid Unit 2 12-May-20 13-May-20 CW Expansion Drum 323-D9023 Installation at Sulphuric Acid Unit
CW Supply Pump 323-P9022 A/B Installation (50T Crane) 6 14-May-20 19-May-20 CW Supply Pump 323-P9022 A/B Installation (50T Crane)
SAU CW Cooler Installation 323-E9024 (6 pcs used 100 T Crane) 10 18-May-20 05-Jun-20 SAU CW Cooler Installation 323-E9024 (6 pcs used 100 T Crane)
Shutdown for Piling Work 51 05-Jun-20* 25-Jul-20 Shutdown for Piling Work
Manifold CW Piping Installation 28 26-Jul-20 25-Aug-20 Manifold CW Piping Installation
Fans and Accessories Installation for SAU CW Cooler 323-E9024 30 26-Jul-20 27-Aug-20 Fans and Accessories Installatio n for SAU CW Co oler 323-E9024
CW Pipe Installation from CW Supply Pump 323-P9022 A/B to CW Expansion Drum
30 323-D9023
26-Aug-20 (50T crane)
24-Sep-20 CW Pipe Installation from CW Supply Pump 323-P9022 A/B to CW Expansion Drum 323-D9023 (50T crane)
Install Electrical Cable Tray 20 28-Aug-20 16-Sep-20 Install Electrical Cable Tray
Install Instrument Cable Tray 20 28-Aug-20 16-Sep-20 Install Instrument Cable Tray
CW Pipe Hydrotest Test 7 25-Sep-20 01-Oct-20 CW Pipe Hydrotest Test
Lighting and Fittings Installation 15 25-Sep-20 09-Oct-20 Lighting and Fittings Installation
Field Instrument Installation 15 25-Sep-20 09-Oct-20 Field Instrument Installation
Touch Up Painting 15 10-Oct-20 24-Oct-20 Touch Up Painting
11-Jun-21, Precomm & Commissioning
Precomm & Commissioning 42 22-Apr-21 11-Jun-21

Precomm & Comm of SAU 42 22-Apr-21 11-Jun-21 Precomm & Comm of SAU

No 323 - Acceleration of SAU 1417 23-Oct-17 A 03-Dec-21

Budgeted Units
Actual Units
Remaining Early Units

Crane 50T Histogram

3 36

2 29

2 21

1 14

1 7

0
04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
August September October November December January February March April May June July August September October November December January February March April May June July

SummaryActivity Activity/ Work Critical Activity Milestone 323 - SAU


Actual Work Near Critical Activity Primary Baseline Baseline Milestone Page 1 of 1