GUARANTEED TECHNICAL PARTICULARS FOR

THREE PHASE THREE WIRE HT ELECTRONIC TRIVECTOR METERS


Sl. No. Item Requirement
1. Make -
2. Type -
3. Country of origin -
4. Application 3 phase 3 wire, CTPT Operated Meter
5. Rated Voltage 110 Volts
6. Rated Current 5 Amp. (Basic Current)
7. Frequency 50 Hz ± 5 %
8. Overload capacity 200% of Ib
9. Minimum starting current 0.1% of Ib
in % of base current
10. Loss in potential circuit Specify
11. Loss in current circuit Specify
12. Change in error due to :
a. Variation in frequency 50 Hz ± 5 %
b. Variation in As per IS 14697:1999
temperature
c. Variation in voltage As per IS 14697:1999
13. Accuracy Class 0.5 S
14. Total Weight of meter To be specified by the supplier
15. Details of case Totally insulated Bakelite /Engineering plastic cover
body or any other improved version of material. The
advantage for using it may be specified in tender.
Earthing provision in case of wholly or partial
metallic body.The meters should be
ultrasonically welded.
16. H.V. withstand As per As per CBIP Technical Report No-88 voltage
in KV (RMS) ( Mention the KV for conducting &
Insulating portions, separately)
17. Insulation Resistance As per IS 14697:1999
18. Type of Energy To be specified
Registration Mechanism.
20 Insulation Test As per IS 14697:1999
( Voltage 50Hz for 1Min)
21 Temperature co-efficient As per IS 14697:1999
from 10% of rated load to
100 % rated load ( 5°C to
45°C )
22 Working range
Voltage -30% to +20% of rated voltage
Current 0.1% to 120% of Ib.
23 Type of load (linear, non All type of load.
linear, balanced
/unbalanced at any P.F.)
24 Display details
i. Display Cycle ™ Display on meter- LED TEST
(descriptive In order of ™ REAL TIME
™ DATE
display) ™ ACTIVE ENERGY
™ REACTIVE ENERGY
™ APPARENT ENERGY
™ RISING DEMAND WITH ET(KVA)
™ MAX. DEMAND (KVA)
™ MD RESET COUNT
™ INST POWER FACTOR
™ INST FREQUENCY
™ INST VOLTAGE( R ,Y, B PHASE)
™ INST CURRENT ( R, B PHASE)
™ INST LOAD (KVA)
™ TOD MAX. DEMAND
™ CUMULATIVE MAX. DEMAND
™ TOD ENERGY
™ TOD MD OF PREVIOUS BILLING PERIOD
™ PRESENT STATUS OF TAMPER
™ LAST OCCURANCE OF TAMPER WITH DATE & TIME
™ LAST RESTORATION OF TAMPER WITH DATE & TIME
™ TOTAL NO OF ABONORMAL EVENTS
™ POWER ON-HOURS

ii. Process of display Both


(Automatic in cyclic
manner / through push
button.
iii. Digits Specify
iv. Segments for display of 7 (Seven)
one digit
v. Period of display of Should be sufficient to read & note ( around 10
each parameter sec.)
25 Memory Non volatile memory without battery back-up at
least 12 years.
26 Non volatile memory Should be sufficient to store data of consecutive 12
billing periods(Energy , Max. Demand) with
Abnormal event details & TOD Zones, load survey
and other information as detailed in technical
specification.
27 Meter can be powered up Yes/No
by external power source
in absence of Supply
voltage

28 Abnormal event data Should be able to store at least 250 ( occurrences


preservation capacity and restoration are separate events)
29 Multiplying factor (If meter Specify
is used for Different
voltage / current ratio)
30 Load Survey capability
a. Parameter Logged KW, KVA, KVAr, Average Voltage(Vr,Vb),Average
Current(Ir,Ib), Power Factor.
b. Logging interval 30 / 15 Minutes-Programmable. Presently logging
interval should be set at 15 Minutes.
c. No. of days of Load 40 days
Survey
31 Earthing Terminal As per CBIP Technical Report.No.-88
32 Time of the day Zone 4 time zones per day will be available for demand:
07:00 – 10:00
10:00 – 18:00
18:00 – 22:00
22:00 – 07:00
2 time zones per day will be available for all
energies:
06:00 – 22:00
22:00 – 06:00
33 Capability for fraud 1. Missing Potential and Potential imbalance,
Prevention & detection 2.Voltage- High/Low,
3. Current Imbalance,
4. CT Reversal,
5. CT short,
6. CT open,
7. Power On/Off,
8. Over load / low load hrs.
9. External Magnetic Influence.
34 Sealing and Locking Adequate sealing & Locking arrangements will be
Arrangement provided, to avoid tampering (Specify)
35 Type of communication
i) Local
ii) Remote Low power Local
Radio
36 Real Time Clock Time Drift and adjustment facility with MRI to be
specified.
37 Mandatory Spare parts Specify
a. Interfacing cords As per CBIP Technical Report –111,
Along with 10 nos. communication cords
b. CMRI (DCD Software) As per CBIP Technical Report –111,
Along with Base Computer System software and software to
be installed in MRIs (RADIX, ANALOGIC) such that all our
MRIs should be able to read from both L & T and SEMs
meters. The installation of S/w. in MRIs and BCS would be
under the scope of the supplier of meters.