This specification has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.
Lead Engineer
Engineering Manager:
Client Approval:
Record of Revisions
Revision Date Description
No.
This specification is intended to supplement American Petroleum Institute (API) Standard 611, 5th Edition, March
2008; General-Purpose Steam Turbines for Petroleum, Chemical, and Gas Industry Services; which is part of this
specification. Numbering of the following sections and paragraphs corresponds to section and paragraph numbering
of API Standard 611.
Paragraphs shall be highlighted as shown below to indicate the type of change from the API Standard.
(Add) Supplemental requirements/clarifications to an existing paragraph.
(Decision) A decision has been made as required. If no decision has been made by this specification, refer to
the corresponding data sheet.
(Mod) Clarification or rewording has been made to the corresponding paragraph, but not a substitution
invalidating the paragraph.
Note: Requirements of API Standard 611, 5th Edition, that are not revised remain applicable.
TABLE OF CONTENTS
1 SCOPE......................................................................................................................................................................5
6 BASIC DESIGN.......................................................................................................................................................5
6.1 General .....................................................................................................................................................5
6.3 Pressure Casings......................................................................................................................................6
6.5 Casing Connections .................................................................................................................................7
6.7 Rotating Elements ...................................................................................................................................7
6.8 Seals ..........................................................................................................................................................7
6.9 Dynamics ..................................................................................................................................................7
6.10 Bearings and Housings..........................................................................................................................8
6.11 Lubrication ............................................................................................................................................8
6.12 Materials ................................................................................................................................................8
7 ACCESSORIES .......................................................................................................................................................9
7.1 Gear Units ................................................................................................................................................9
7.2 Couplings and Guards ............................................................................................................................9
7.3 Mounting Plates.......................................................................................................................................9
7.4 Controls and Instrumentation..............................................................................................................10
7.5 Piping and Appurtenances....................................................................................................................10
7.7 Insulation and Jacketing.......................................................................................................................10
8 INSPECTION, TESTING AND PREPARATION FOR SHIPMENT .............................................................10
8.1 General ...................................................................................................................................................10
8.2 Inspection ...............................................................................................................................................11
8.3 Testing ....................................................................................................................................................11
8.4 Preparation for Shipment.....................................................................................................................11
9 VENDOR’S DATA ................................................................................................................................................12
9.2 Proposals ................................................................................................................................................12
9.3 Contract Data ........................................................................................................................................13
10 (NEW) GUARANTEE AND WARRANTY ......................................................................................................14
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 5 of 15
Revision 1
1 SCOPE
1.1 (New) Purpose
1.1.1 This specification covers the minimum mandatory requirements for the materials selection,
design, fabrication, inspection, testing, and preparation for shipment of general purpose
mechanical-drive steam turbines and their accessories.
1.1.2 Deviations from this standard must be approved in writing by the Buyer prior to
implementation.
1.1.3 Details not included in the Buyer’s documents shall be the responsibility of the Supplier.
1.1.4 Compliance by the Supplier with the requirements of this specification does not relieve the
Supplier of his responsibility to supply equipment fully suitable for all specified conditions.
1.1.5 Supplier shall be responsible to insure that all technical and data requirements of this
specification are followed by all his subcontractors
1.2 (New) Conflicting Requirements
1.2.1 In case of conflict among documents covering this scope of work, the order of precedence of
documents to resolve conflicts shall be, in descending order:
1.2.1.1 Special instructions in the inquiry or purchase order
1.2.1.2 Requisitions and data sheets by the Buyer
1.2.1.3 This specification, MQ-SP-M-4024, “API 611 5th Ed., General Purpose Steam
Turbines”
1.2.1.4 Other Marafiq specifications listed in paragraph 2.1.
1.2.1.5 Other references listed in section 2.
1.2.2 In all cases of conflict, however, the Buyer shall be advised before proceeding with affected
scope of work.
1.2.3 Metric fasteners constitute alternative design features and shall be cited as exceptions to the
Supplier’s proposal. Metric flanges are not acceptable.
6 BASIC DESIGN
6.1 General
6.1.4.b (Add) Steam turbines shall be capable of developing 115% of rated power at
minimum steam conditions, minimum temperature and pressure, and maximum back
pressure at the turbine coupling. However, turbine efficiency shall be optimized for
delivering normal power with normal steam conditions. Seller shall advise if a hand
valve is required to meet this requirement.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 6 of 15
Revision 1
6.1.11 (Add) Turbine bearing shall be forced circulation water cooled. Cooling water systems shall
be designed for not less than a gage pressure of 691 kPa (6.91 bar) (100 psi) design pressure,
a gage pressure of 1037 kPa (10.4 bar) (150 psi) test pressure, 69 kPa (0.69 bar) (10 psi)
maximum pressure drop, a maximum water inlet temperature of 32°C (90°F), an 11°C (20°F)
temperature rise and 0.003 fouling factor on the water side. In addition, the Supplier shall be
responsible to design the cooling system so that it will perform satisfactorily under the actual
operating conditions specified on the applicable turbine data sheets included in the inquiry or
purchase order. Provisions shall be made for complete drainage. Valved drains are required at
low points in the cooling water system.
6.1.12 (Add) Maximum sound pressure level for each piece of driven equipment and its drive train
shall comply with the requirements of Marafiq specification MQ-SP-M-4032, “Sound Control
of Mechanical Equipment.”
6.1.13 (Add) All electrical components and their installations shall be suitable for the installation
location and electrical area classification specified in the material requisition and shall comply
with NFPA No. 70 and shall be in compliance with Marafiq specification MQ-SP-E-6002,
“Electrical Requirements for Mechanical Equipment.”
6.1.14 (Add) Unless otherwise specified on the datasheet, turbines and their auxiliaries shall be
suitable for unprotected outdoor installation in the severe service such as salt laden, H2S and
other environmental conditions typical of refinery and chemical plants.
6.1.17 (New) Any power transmission components, including couplings, gears and shafts shall
have power ratings at least equal to the driver power rating at maximum steam conditions and
shall be capable of transmitting the maximum torque developed by the driver or that portion
of the maximum driver torque transmitted through it.
6.1.18 (New) Fabrication
6.1.18.1 Shop fabrication and assembly of the various components supplied by the
Supplier shall be maximized, consistent with available shipping, receiving and
handling facilities.
6.1.18.2 Buyer’s written approval shall be obtained before and part of the fabrication or
assembly is subcontracted by the Supplier.
6.1.18.3 No repair to cast steel casing shall be made without the Buyer’s prior
concurrence based on the mutually agreed procedures involved. Submittal of such
procedures shall be made within three months of the receipt of the purchase order.
All repairs shall be witnessed by the Buyer’s inspector. No plating is permitted in
critical areas such as seal bores, etc., where sharp edges could damage “O” rings.
Buyer shall be informed in writing whenever a proposed casting is to be the first one
cast from a new set of patterns.
6.3 Pressure Casings
6.3.10 (Add) On condensing turbines with top exhaust, connections and a drain system shall be
provided to drain condensate continuously from the exhaust casing to suit condenser
location.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 7 of 15
Revision 1
6.12.2 Castings
6.12.2.3.c (Add) Leaking chaplets in a gray cast iron water jacket wall exposed
to the atmosphere may be repaired by plugging in accordance with
paragraph 9.2 of ASTM A395, except that radiography of the
surrounding area is not required.
6.12.4 Welding
6.12.4.1 (Add) Weld procedures for all major repair welding on pressure containing parts
shall be submitted to the Buyer for approval prior to commencement of the
repair work.
6.12.4.8 (New) Welding fittings for pressure parts shall be of seamless construction.
6.12.4.9 (New) Welded or brazed repairs on iron casting is prohibited.
6.12.4.10 (New) Nozzle welds shall be full penetration and full fusion.
6.12.4.11 (New) Records of any heat treatment or radiographs or any type repair record
shall be submitted to the Buyer as part of the Supplier data.
7 ACCESSORIES
7.1 Gear Units
7.1.2 (Add) Where gear units are required, they shall be separate rather than integral unless
approval is obtained from the Buyer. Gears shall be of the double helical type.
7.1.5 (New) All gear bearings shall be of the same type as the driven equipment bearings.
7.2 Couplings and Guards
7.2.1 (Add) Flexible element couplings shall be provided. When coupling guards are furnished by
the turbine Supplier it shall be non-sparking and shall conform to all local, state, and federal
safety regulations.
7.3 Mounting Plates
7.3.2 Baseplates
7.3.2.3 (Add) Baseplate shall be provided with leveling pads or targets.
7.3.2.5 (Add) Baseplate grouting holes shall be accessible without removing the
machinery and shall permit filling of the entire cavity under the baseplate
without trapping air pockets. Subsoleplates shall be provided by the Supplier.
7.3.2.9 (Add) Horizontal and vertical jack-screws shall be supplied for all equipment feet.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 10 of 15
Revision 1
8.1.7 (Add) A witnessed test requires that the Supplier successfully operate the unit in accordance
with all mechanical test guidelines prior to request for the Buyer’s witness, except where the
Buyer specifically requires witnessing the initial run.
8.1.9 (Add) Quality control procedures shall be agreed upon between the Supplier and Buyer at a
pre-inspection meeting.
8.2 Inspection
8.2.1 General
8.2.1.1 (Add) The following data shall be given to the Buyer’s inspector if inspection is
specified or sent to the Buyer if the equipment is not inspected:
o Physical and chemical data for all pressure containing parts, preferably actual
test data taken from the melt or heat from which the part is made.
o Evidence, such as purchase specifications of bills of material, to establish that
other major parts are made of specified materials.
o Measured critical speeds of flexible shaft turbines.
8.2.2 Material Inspection
8.2.2.1 General
8.2.2.1.1 (Add) For equipment requiring post weld heat treatment, radiographs,
magnetic particle or liquid penetrant examination of completed welds shall
be performed after the post weld heat treatment.
8.2.2.2 (Add) Radiography
All radiographs taken during fabrication shall be available for examination by the
Buyer’s authorized inspector. The Buyer reserves the option to approve final radiographs
prior to shipment.
8.3 Testing
8.3.1 General
8.3.1.1 (Add) All testing shall be performed in the Supplier’s shop.
8.3.1.4 (New) All test reports shall be complete and shall describe all events and details
of the test accurately. Mechanical and other test procedures shall be submitted for
Buyer approval at least six weeks prior to testing.
8.3.1.5 (New) If a shop tested piece of equipment is damaged during shipment, the
equipment shall be retested to at least the shop pressure after repairs, if the Buyer
judges that the nature of the repairs so warrant.
8.4 Preparation for Shipment
8.4.1 (Add) Preparation for shipment shall be in accordance with the Supplier’s standards, API
686, and as noted herein. The Supplier shall be solely responsible for the adequacy of the
preparation for shipment with respect to materials and application, and for providing
equipment at the destination in ex-works condition when handled by the commercial carrier.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 12 of 15
Revision 1
9 VENDOR’S DATA
9.2 Proposals
9.2.1 (Add) General
Supplier’s proposal will be assumed to be in full compliance with the Buyer’s inquiry unless
specific exceptions are taken by the Supplier. The Supplier shall advise what changes, if any, are
required from the Buyer’s inquiry to enable the Supplier to provide the specified performance and
mechanical guarantees.
9.2.3 (Add) Technical Data
The Supplier’s proposal shall include, for the equipment specified and any alternate offered, the
information listed in API 611 paragraphs 9.2.3.a through 9.2.3.n, any additional information
requested with the inquiry, and the following additional requirements, as a minimum:
o A completed noise data sheet MQ-DS-M-4022, Equipment Noise Datasheet
o A schedule for submission of the required documentation and proposed shipping
schedule
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 13 of 15
Revision 1
o A priced spare parts list including the following information covering sufficient spare
parts for start-up and two years of operation (the items marked with an “*” must be
available for the initial evaluation of bids, the remaining items shall be provided as part
of the priced spare parts list submitted as part of the Supplier data):
o * Equipment item number
o * Discount for ordering spares with initial order or within a given time period
o Name of the original equipment manufacturer
o * Complete part description
o OEM part number
o Item identification number
o Material code
o * Unit pricing
o * Unit of measure
o Routine delivery
o * Any duplicate parts if the order is for multiple pieces of similar equipment
o Any special conditions such as handling or storage requirements
9.3 Contract Data
9.3.1 General
9.3.1.2 (Add) All data supplied by the Supplier shall be identified as per API 611
paragraph 9.1.2 and the following information:
o Name and location of project
o Any other identification specified in the purchase order
9.3.1.5 (New) All documents forwarded to the Buyer shall have been checked for
completeness and accuracy by the Supplier prior to their submission.
9.3.1.6 (New) The Supplier shall submit general arrangement drawings, calculations, and
any other documents required to provide, as a minimum, the information listed
below to the Buyer for his review and approval:
o Overall dimensions and details for all systems and components supplied by the
Supplier, including auxiliary equipment. Refer to API 611 paragraph 9.3.2.1 for
drawings information requirements.
o Materials of construction and respective corrosion allowances.
o Baseplate details and grouting requirements.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification MQ-SP-M-4024
Guideline Specifications Development Date: 28 Feb 2011
Contract: A5MU Page 14 of 15
Revision 1
o Anchor bolt holes size and locations and required anchor bolt material, size and
projection beyond support level.
o Noise data sheets.
o Definition of non-destructive examinations and mechanical tests required.
o Surface preparation, painting or other surface finish requirements.
o Required erection sequence.
o Any other data required by the Buyer’s inquiry or purchase order documents.
After receipt of the Buyer’s comments, the Supplier shall revise his documents and
issue them again to the Buyer as “certified for design and construction.” The
approval by the Buyer of the Supplier’s documents shall in no way relieve the
Supplier of his responsibility to meet the requirements of the Buyer’s inquiry and
purchase order documents.
9.3.5 Installation, Operation, Maintenance, and Technical Data Manuals
9.3.5.4 (Add) Technical Data Manual
Within 10 days after the completion of the equipment, the Supplier shall furnish the
Buyer with an electronic copy of the technical data manual, containing all information
listed in API 611, Annex C, line item 33, and the following additional information:
o Mill test reports
o Any other reports or data which are required by the Buyer’s inquiry or purchase
order documents, including factory acceptance reports
o Any other data required by the Buyer’s inquiry or purchase order documents