SECTION 12
GROUP 2
This project is a construction for the Flamingo Hotel. The project was about the
proposed to build a 4-stories hotel located on Lot 27139, Jalan Persiaran S2/B2, Seremban 2,
Mukim Rasah, Daerah Seremban, Majlis Perbandaran Seremban, Negeri Sembilan Darul
Khusus. The hotel is designed with 44 rooms, one elevator, a linen/laundry room on each floor,
administration office, meeting room, lobby and cafeteria. The building are proposed to build
on 5401 square feet area in Seremban.
1.2 Introduction
BBK Structural Engineers was established in Selangor in 1990. BBK is a full service
project delivery consultancy company offering integrated planning, architecture, engineering
and project management services for buildings, transportation, institutional and manufacturing
infrastructure with over 300 professionals in three offices which is one main office and two
branch offices.
BBK’s wide range of resources and expertise offer comprehensive and single umbrella
solutions (incorporating building design, infrastructure engineering, mechanical, electrical and
HVAC services) to technically challenging projects and services from planning to construction,
for local and national governments, private sector owners, contractors and public sector
institutions.
BBK places outmost value on its clients and offers them error-free and lower cost
designs with tight turnaround times by leveraging the resource base, cost structure and its
operation.
1.3 Mission
1. To perform for our customer, the highest level of quality services at fair and market
competitive prices.
2. To maintain the highest levels of professionalism, integrity, honesty and fairness in our
relationships with our suppliers, subcontractors, professional associates and customers
3. To ensure the longevity of our company through repeat and referral business achieved by
customer satisfaction in all areas including timeliness, attention to detail and service-
minded attitudes.
1.4 Vision
Group Formation
Company’s Logo
Never Let Success Get to Your Head and Never Let Failure Get to
Company’s Motto
Your Heart
No. 27-2, Jalan Putra Mahkota 7/7B, Putra Heights 47650 Subang
Company’s Address
Jaya, Selangor, Malaysia.
PROJECT MANAGER
KIRUBASHNI
RAVENDRAN
ARCHITECT
FARAH ARISHA BINTI
SHAHROM
Income Statement
Fixed Assets
Plant and Equipment 1,312,000 1,505,000 1,750,000 1,862,000
Buildings & Leasehold 0 0 0 0
Improvements
Land 0 0 0 0
Accumulated Depreciation (698,000) (796,000) (956,000) (1,018,000)
Net Plant Equipment 614,000 709,000 794,000 844,000
Other Intangible Assets 3,024,000 3,913,000 4,773,000 6,621,000
TOTAL ASSESTS 10,565,000 10,979,000 13,812,000 14,750,000
Liabilities
Current Liabilities 2017 2018 2019 2020
Accounts Payable 2,223,000 1,494,000 1,665,000 1,515,000
Other Current Liabilities 2,650,000 2,830,000 3,070,000 3,045,000
Unearned Income/Deposits 0 0 0 0
Line of Credit 0 0 0 0
Other Short Term Loans 0 0 0 0
Current Portion of Long Term 0 0 0 0
Debt
Total Current Liabilities 4,873,000 4,324,000 4,735,000 4,560,000
STOCKHOLDER EQUITY
Common Stock 10,000 10,000 10,000 10,000
Preferred Stock 0 0 0 0
Additional Paid In Capital 0 0 0 0
Dividends 0 0 0 0
Retained Earnings 0 0 0 0
Treasury Stock 0 0 0 0
Net Income 0 0 0 0
Other Stockholder Equity 0 0 0 0
Total Stockholder Equity 10,000 10,000 10,000 10,000
Duration of this project to complete is depending on the nature of the land, there may
be soil testing, site-levelling and clearing undertaken prior to actual construction. It includes
measuring out the design on the site, pouring the footings, under slab drainage, moisture barrier
and special mesh for termite protection. This includes the installation of your internal and
external support structure, along with walls, conduit for electrical and plumbing, the roof frame
and sheeting, gutters and insulation. It’s also safe for plumbers, electricians, cabinet makers
and other tradesman to begin fitting out the property. This is basically where all painting,
installations and detailing have been completed and effectively ready to move in. It’s all take
almost one year to complete.
The cost estimated to build ‘budget’ 6 level Hotel on Lot 27139, Jalan Persiaran S2/B2,
Seremban 2, Mukim Rasah, Daerah Seremban, Majlis Perbandaran Seremban Negeri Sembilan
Darul Khusus is about nearly 20 million.
2.4 Location of Project
The location of this project is on Lot 27139, Jalan Persiaran S2/B2, Seremban 2, Mukim
Rasah, Daerah Seremban, Majlis Perbandaran Seremban Negeri Sembilan Darul Khusus.
RASAH, DAERAH
DARUL KHUSUS
KONTRAKTOR :
REMBAU, NEGERI SEMBILAN
4.0 Lists of Facilities On Site
4.1 Hoarding