Abstract:Completion of a construction within planned budget is one of the main criteria of project success.
However, budget overrun has become a recurring phenomenon in construction industry, which can result in
multiple negative effects such as loss of economy, disputes among construction stakeholders, project abandonment,
and drop in construction activities. This study aims to identify factors causing budget overrun in Malaysian
Building projects and then to establish mitigation measures for the identified significant causative factors.
Literature review, questionnaire survey and interviews were used in this study. Detailed literature review results in
identification of 28 causative factors of budget overrun. The significant causative factors of budget overrun in
building projects in Malaysia were investigated through a questionnaire survey of 83 contractors, 57 clients and 40
owners. The feedback of questionnaire survey was analyzed statistically. It was revealed that the significant
causative factors of budget overrun include improper planning, variation in materials price, poor site management,
lack of communication between parties, frequent design changes, incompetent contractors, mistakes during
construction, shortage of site workers, delay in material procurement, and low speed of decisions making. After
questionnaire survey, interviews with 16 construction experts were carried out in order to develop mitigation
measures for the top ten significant causative factors. Based on semi-structured interviews, a list of mitigation
measures for each of the top ten significant causative factors were derived. The findings of this study can be useful
for construction practitioners in controlling budget overrun and to achieve project success.
Keywords: Budget overrun, Causative factors, Mitigation measures, Building projects, Project success.
2
U.Kaleem et al., Int. J. Of Integrated Engineering Vol. 10 No. 9 (2018) p. 66-71
Causes of budget Overrun RII Rank ii)All parties should understand their task.
Improper planning 0.91 1 ii)Consider true constraints of market and
Variation in materials price 0.90 2 logistics during planning.
Poor site management 0.88 3
Lack of communication between parties 0.86 4 i) Acquiring Bulk of Materials.
Variation in
materials
communication.
Low productivity of labour 0.67 17 ii)Arrange workshops to spell out partner
Lack of
stage.
changes
design
3
U.Kaleem et al., Int. J. Of Integrated Engineering Vol. 10 No. 9 (2018) p. 66-71
Incompetent i) Select contractors having history for incompetent contractors which is ranked as the sixth
contractors ofquality workmanship. factor, its mitigation measures consist of selecting
ii)Regular communications between contractors having history ofquality workmanship,
contractor and client. regular communications between contractor and client,
iii) Define contractor’s scope of work clear and define contractor’s scope of work clear and in
and in details. details.Measures for the seventh factor namely mistake
during construction comprise assigning experienced
i) Assign experienced workers to repetitive
Mistakes During
management for materials delivery. its mitigation measures consist of avoiding centralization
Delay in
Material
ii) Ensure sufficient quantity of materials of decisions, ensuring quick approval, and effective flow
on construction site. of information among construction stakeholders.
5. Conclusion
i) Avoid centralization of decisions. Budget overrun is one of the major problems in
of Decision
Low Speed
4
U.Kaleem et al., Int. J. Of Integrated Engineering Vol. 10 No. 9 (2018) p. 66-71
causes of construction time and cost overruns. International Journal of Project Management, 30(2),
IOP Conference Series: Materials Science and 188–198.
Engineering, 271(1), 012032. [16] Meeampol, S., &Ogunlan, S. O. (2006). Factors
[3] Sohu, S., Abdullah, A. H.,Nagapan, S.,Buriro, A. affecting cost and time performance on highway
A.,&Ullah, K. (2018). Stakeholders’ Perception on construction projects: Evidence from Thailand.
Critical Cost Variation Factors in Malaysian Journal of Financial Management of Property and
Building Projects. Civil Engineering Journal, 4(9), Construction, 11(1), 3–20.
2075–2081. [17] Sohu, S., Abdullah, A. H, Nagapan, S., Chandio, A.
[4] Sohu, S., Abdullah, A. H.,Nagapan, S.,Jathial,A. F., Latif, I., &Ullah, K. (2017). Causative factors of
A.,& Tahir,M. (2018). Contributing Cost Variation cost overrun in highway projects of Sindh province
Factors in Highway Projects. Civil Engineering of Pakistan. IOP Conference Series: Materials
Journal, 4(8), 1793–1798. Science and Engineering, 271(1), 012036.
[5] Kim, S., Tuan, K. N., Lee, J. Do, Pham, H., &Luu, [18] Sohu, S., Abdullah, A.H., Nagapan, S., Chandio, A.
V. T. (2017). Cost Overrun Factor Analysis for F., Ullah, K., &Kumar, K. (2017).Contractors
Hospital Projects in Vietnam. KSCE Journal of Civil perspective for critical factors of cost overrun in
Engineering, 20(2), 519–529. highway projects of Sindh, Pakistan.
http://doi.org/10.1007/s12205-017-0947-5 AIP Conference Proceedings, 1892, 080002.
[6] Koushki, P. A., Al Rashid, K., &Kartam, N. (2005). [19] Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D.
Delays and cost increases in the construction of (2014). Cost overrun in the Malaysian construction
private residential projects in Kuwait. Construction industry projects: A deeper insight. International
Management and Economics, 23(3), 285–294. Journal of Project Management, 32(8), 1471–1480.
[7] Aziz, R. F. (2013). Factors causing cost variation for [20] Ibrahim, A. R., Roy, M. H., Ahmed, Z., &Imtiaz, G.
constructing wastewater projects in Egypt. (2010). An investigation of the status of the
Alexandria Engineering Journal, 52(1), 51–66. Malaysian construction industry. Benchmarking: An
[8] Sohu, S., Abdullah,A. H.,Memon,B. A.,Nagapan,S. International Journal, 17(2), 294–308.
& Bhatti,N. K. (2018). Mitigation Measures for [21] Rahman, I. A., Memon, A. H., Nagapan, S., Latif, Q.
Significant Factors Instigating Cost Overrun in B. A. I., &Azis, A. A. A. (2012). Time and Cost
Highway Projects. Civil Engineering Journal, 4(10), Performance of Costruction Projects in Southern and
2338–2344. Cenrtal Regions of Penisular Malaysia. In IEEE
[9] Kaliba, C., Muya, M., & Mumba, K. (2009). Cost Colloquium on Humanities, Science & Engineering
escalation and schedule delays in road construction Research, Kota Kinabalu, Sabah (pp. 52–57).
projects in Zambia. International Journal of Project [22] Jatarona, N. A., Yusof, A., Ismail, S., & Saar, C. C.
Management, 27(5), 522–531. (2016). Public construction projects performance In
http://doi.org/10.1016/j.ijproman.2008.07.003 Malaysia. Journal of Southeast Asian Research,
[10] Lee, J.-K. (2008). Cost Overrun and Cause in Korean 20(16). http://doi.org/10.5171/2016.940838
Social Overhead Capital Projects: Roads, Rails, [23] Akram, M., Ali, T. hussain, Memon, N. A.,
Airports, and Ports. Journal of Urban Planning and &Khahro, S. H. (2017). CAUSAL ATTRIBUTES
Development, 134(2), 59–62. OF COST OVERRUN IN CONSTRUCTION
[11] Love, P. E. D., Sing, C., Carey, B., & Kim, J. T. PROJECTS OF PAKISTAN. International Journal of
(2014). Estimating Construction Contingency: Civil Engineering and Technology, 8(6), 477–483.
Accommodating the Potential for Cost Overruns in [24] Olawale, Y. A., & Sun, M. (2010). Cost and time
Road Construction Projects. Journal of Infrastructure control of construction projects: inhibiting factors
Systems, 21(2), 1–10. and mitigating measures in practice. Construction
[12] Kostka, G., &Anzinger, N. (2016). Large Management and Economics ISSN:, 28, 509–526.
Infrastructure Projects in Germany: A Cross-sectoral http://doi.org/10.1080/01446191003674519
Analysis. In Large Infrastructure Projects in [25] Durdyev, S., Ismail, S., & Bakar, N. A. (2012).
Germany: Between Ambition and Realities (pp. 15– Factors causing cost overruns in construction of
38). Berlin, Germany: Palgrave Macmillan residential projects; Case study of Turkey. Asian
Publishers Limited Journal of Management Research, 1(1), 3–12.
[13] Chen, Q., Jin, Z., Xia, B., Wu, P., &Skitmore, M. [26] Mohammad, S., Tabatabaei, M., Taabayan, P.,
(2016). Time and Cost Performance of Design Build Hashemi, A. M., & Willoughby, K. (2016). Studying
Projects. Journal of Construction Engineering and the Reasons for Delay and Cost Overrun in
Management, 142(2), 51–60. Construction Projects : The Case of Iran. Journal of
[14] Senouci, A., Ismail, A., &Eldin, N. (2016). Time Construction in Developing Countries, 21(1), 51–84.
Delay and Cost Overrun in Qatari Public http://doi.org/10.21315/jcdc2016.21.1.4
Construction Projects. Procedia Engineering, 164, [27] Alzebdeh, K., Bashirb, H. A., &Siyabic, S. K. Al.
368–375. (2015). Applying interpretive structural modeling to
[15] Meng, X. (2012). The effect of relationship cost overruns in construction projects in the sultanate
management on project performance in construction. of Oman. The Journal of Engineering Research,
12(1), 53–68.
5
U.Kaleem et al., Int. J. Of Integrated Engineering Vol. 10 No. 9 (2018) p. 66-71
[28] Alinaitwe, H., Apolot, R., &Tindiwensi, D. (2013). [29] Asiedu, R. O., &Alfen, H. W. (2014). Factors
Investigation into the Causes of Delays and Cost Engendering Cost Misrepresentation of Public Sector
Overruns in Uganda’s Public Sector Construction Projects in Ghana. International Journal of
Projects. Journal of Construction in Developing Sustainable Construction Engineering & Technology,
Countries, 18(2), 33–47. 5(2), 13–24.