Performance Improvement

by Expert Consultancy
Presented By
R.Selvarethinam/
Sr.Manager/GEECO
GEECO DEPUTES ITS EXPERTS FOR
 Life assessment study of APH

 Trouble shooting

 Planned annual overhauls ,both minor and major

 During Installation of New APH.

 Breakdown Analysis

 Assessment study for the improvements.


GEECO DEPUTES ITS EXPERTS FOR
(CONT ….)
 Air Preheater Performance Testing as per the test code

ASME PTC 4.3.

 Conducting Training classes on APH

 GEECO is having engineering capability to work with

any make and any size of APH

 GEECO keeps the record of customers APH data's and

the performances
GEECO Expert consultancy for Different
Air Preheaters of Make
ALSTOM (CE -APCO), USA RUSSIAN
ALSTOM, GERMANY STEIN IND, FRANCE
ALSTOM, JAPAN GADELIUS KK , JAPAN
MHI, JAPAN BABCOCK & WILCOX
HOWDEN, U.K. PARSON, CANADA
HOWDEN, AUSTRALIA HARBIN, CHINA
ANSALDO, ITALY BHEL, INDIA
FRANCO TOSI, ITALY DONFONG,CHINA
RAFFACO,POLLAND
TYPES OF APH – SERVICES RENDERED
 Horizontal type.
 Vertical type.(Tri sector and Bisector)
 Routhmule type.
 From the smallest size 15HSX (Ø2600mm) to
the Biggest size 34VI (Ø16400mm)
From the 30 MW to 800 MW.
IN DETAIL ABOUT OUR SITE
ACTIVITIES
AT JANAMANJUNG
ABOUT JANAMANJUNG
Station : TNB Janamanjung Sdn. Bhd.,
Manjung Power Plant, Malaysia
Capacity : 3 x 700 MW – Coal Fired
APH Size : 33.5 VIT 95
Supplied : ABB Air Preheater Inc., Wellsville,
by New York
Commissioned on : 2002
 December 2005 - First Assessment Study.

 February 2006 – Second Assessment Study.


Problems Identified at Site
 More Leakage up to 23.3% - (Worn Out Sector plates, More Run
out in Circumferential Sealing Surface, Axial seal plate – not
concentric to rotor)
 More Pressure Drop
(Chokage in the Heating elements at the bottom of the hot end
elements and top of the hot intermediate elements and corroded
cold end baskets)
 High Vibration in Main Drive Gear Box – (Pin space in the last
segment is around 5mm more. Hence pinion engagement not
smooth)
Problems Identified at Site
cont...

Cracks in the Diaphragm / Rotor critical Weld

 Guide Bearing area – Hot air leakage ( Old type Air seal

housing. Seal air connection not given to air seal housing.

Tracking rod area not covered for sealing)


First Assessment Report
Customer has ordered all parts as per our
recommendation and
subsequently under GEECO´s expert
Supervision installation completed at site.
A few photographs taken at site after installation
RESULTS ACHIEVED

All the reported problems were fully eliminated


Customer
Recognition
 TNB Janamanjung,
Malaysia (3x 700 MW)
 Make : Alstom, USA
 Tender for Service

Engage Supervisor from


any one of the Gas Air
Heater Manufacturer
namely Alstom Power,
GEECO India or
Howden Australia
KEV Malaysia –
__

Tender for
Service
Kapar Energy
Ventures Sdn Bhd, is
the largest Power
utility in Malaysia
with its 2420 MW
generating
capacity

……….Engage at least
(1) Qualified Engineer
from any one if the Gas
Air Heater
Manufacturers namely
James Howden
Australia, Alstom
Japan or GEECO India
…….
Before concluding we would like to convey about

YET ANOTHER RECOGNITION


FROM TATA POWER
 1st 150 MW in India was installed by TATA POWER.
 1st 500 MW in India was installed by TATA POWER.
 1st 800 MW in India was installed by TATA POWER
(Under Commissioning )

For all these power stations customer continuously avail


the services only from GEECO for site supervision from
the year of formation of GEECO (i.e. 1999).