Transportation Problem – Stepping Stone

1. The RSV Gravel Supply Company has received a contract to supply gravel to three new road projects
located in three different locations. Project A needs 174 truck loads, project B, 204 truckloads and
project C, 143. 521

(521) The company has three gravel warehouses located in three different places. Warehouse 1 has
158 truckloads available, warehouse 2 has 184 and warehouse 3 has 179. The cost of transportation
from the warehouse to the projects are: from warehouse 1 to project A,B,C; P4, P8 and P8 per truckload,
respectively. From ware house 2: P16, P24, P16 and from warehouse 3: P8, P16, and P24, respectively.
The objective is to design a plan of distribution that will minimize the cost of transportation.

A B C Supply
1 158(4) (8) (8) 158 1A=632
2 16(16) 168 (24) (16) 184 2A=256
2B=4032
3 (8) 36(16) 143(24) 179 3B=576
3C=3432
174 204 143 Demand Total=8928

2B = -4 (8-24+16-4) = *COST ANG GAGAMITIN* (MINUS UNANG OPERATION)*SAL ITAN* ( + - + - )


1C = -12 ( 8-24+16-24+16-4)
2C = -16 (16-24+16-24) (PAPALTAN SA SUSUNOD NA TABLE)
3A = 0 (8-16+24-16)

A B C
1 158(4) (8) (8) 158 1A=632
2 16(16) 25(24) 143(16) 184 1B=256
2B= 600
2C=2288
3 (8) 179(16) (24) 179 3B2864
174 204 143 6640

1B = -4

A B C
1 133 (4) 25(8) (8) 158 1A=532
1B=200
2 41 (16) (24) 143(16) 184 2A=656
2C=2288
3 (8) 179(16) (24) 179 3B=2864
174 204 143 6540

3A = -4 (8-16+8-4)
2B = 4 (24-8+4-16)
A B C
1 (4) 158(8) (8) 158 1B=1264
2 41 (16) (24) 143(16) 184 2A=656
2C=2288
3 133(8) 46(16) (24) 179 3A= 1064
3B=736
174 204 143 6008

1A = 4
1C = 8

Decision: Transport 158 truckload from warehouse 1 to project B, 41 truckloads


from warehouse 2 to project a, 143 truckloads from warehouse 2 to project c, 133
truckloads from warehouse 3 to project a and 46 truckloads from warehouse 3 to
project b to minimize cost at P6,008

2. Fill out the initial table below and use the Stepping Stone Method to find the entries of the
subsequent tables. Write the decision and the minimum cost.

A B
3 2
5
5
2 7
10

2 6
15

18 12

3. A concrete company transports concrete from three plants, 1, 2 and 3, to three construction sites, A,
B and C.

The plants are able to supply the following numbers of tons per week as well as the requirement in the
site per week

Plant Capacity Construction Site Requirement


1 300 A 200
2 200 B 200
3 300 C 300

Cost
To Site A Site B Site C
From
Plant 1 4 3 8
Plant 2 7 5 9
Plant 3 4 5 5

Determine the plan of distribution that will minimize the cost.