Академический Документы
Профессиональный Документы
Культура Документы
Y. K. CHOW,G. P. KARUNARATNE,
K. Y. WONG, AND S. L. LEE
Department of Civil Engineering, National University of Singapore, 10 Kent Ridge Crescent, Singapore 0511
Received February 16, 1987
Accepted September 1 1, 1987
Two methods are presented to estimate the load-carrying capacity of driven piles. These methods use a new wave equation
model that incorporates the loss of energy to the soil mass through radiation damping of the soil. Conventional soil parameters
are used in this new model. Both methods use the load-test result of a test pile to estimate the soil parameters at the site by set
matching. These soil parameters are then used to predict the load-carrying capacity of similar piles at the site in subsequent
analyses from set measurements. The two methods are demonstrated by the prediction of the load-carrying capacity of 21 piles
at four sites.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
Key words: load-carrying capacity, pile foundations, pile driving, soil setup, wave equation model.
L'on prisente deux mCthodes pour tvaluer la capacitt portante des pieux forks; elles font appel B un nouveau modble qui
utilise 1'Cquation de transmission des ondes et qui incorpore la perte d'knergie dans la masse de sol par amortissement radiant
du sol. Ce modble fait appel aux parambtres conventionnels de sol. Les deux mtthodes utilisent les rksultats de l'essai de
chargement du pieu d'essai pour kaluer par appariement les parambtres du site qui servent alors pour prtdire la capacitC
portante de pieux similaires sur le site dans des analyses subskquentes B partir des mesures. Les deux mtthodes sont
dCmontrtes au moyen de la prtdiction de la capacitC portante de 21 pieux sur quatre sites.
Mots clks : capacitt portante, fondations sur pieux, fonqage de pieux, modble d'Cquation de transmission des ondes.
[Traduit par la revue]
Introduction that the soil resistances at the end of driving and at the time of
Undoubtedly, the most reliable method to determine the load testing are the same. Although this assumption may be
"true" load-carrying capacity of a pile is by a load test. For applicable for cohesionless soils, cohesive soils generally
economic reasons, only a prespecified number of piles per site exhibit a regain in strength or soil setup after the end of driv-
are load tested. A common alternative to predict the load- ing. Seed and Reese (1957), among others, showed that con-
canying capacity of the driven piles is by the use of "pile driv- siderable soil setup with time can occur for driven piles in
ing foknulae." These formulae assume rigid-body mechanics. cohesive soils. This regain in soil strength with time is gener-
The parameters used in these formulae are based on experience ally attributed to the restructuring of the cohesive soil particles
for a particular soil type, pile type, or driven depth. Extrapola- and the dissipation of the excess pore-water pressure generated
tion of these parameters for use in other soil or pile types during driving. The increase in excess pore-water pressure in
can be unreliable. In addition, the assumption of rigid-body the immediate vicinity of the piles as a result of driving in
mechanics does not represent the physical phenomenon of cohesive soils has been reported by a number of investigators
stress wave propagation in the pile during driving. It is, there- (for example, Lo and Stermac 1965; Rigden et al. 1979). In
fore, not surprising that the accuracy of these formulae varies practice, a considerable time may have elapsed prior to the
considerably. load testing of the pile, resulting in substantial soil setup.
Smith (1960) presented a one-dimensional wave equation Hence, by assuming no soil setup, the method of load-carrying-
model using a finite difference scheme for pile driving analy- capacity prediction of piles using the Smith (1960) model does
sis. The soil resistance to driving is represented by a series of not reflect the physical behaviour of driven piles in cohesive
springs and dashpots. The total resistance to driving consists of soils. Although this method is not strictly rational, it does
two components: a static soil resistance component and a appear to give practical solutions (for example, Forehand and
dynamic component to represent the damping of the soil. Reese 1964; Radhakrishnan et al. 1980). This is because,
Smith (1960) mentioned the possibility of predicting the load- in the correlation with the test pile, the influence of soil setup
carrying capacity of a pile from the pile set using the wave has been implicitly accounted for in the "soil" parameters
equation. The load-carrying capacity of the pile is given by the determined.
static component of the soil resistance. Subsequently, Fore- Although the Smith (1960) model represents the first
hand and Reese (1964) illustrated the load-carrying-capacity approach to simulate the propagation of stress waves in a pile
prediction potential of the wave equation using the Smith driving analysis, the oversimplification of the complex prob-
(1960) model. lem of dynamic pile-soil interaction resulted in the use of
The common procedure using the Smith (1960) model is to empirical parameters. These parameters are generally deter-
determine the "soil" parameters applicable to the site by mined from a back analyses of pile driving records and pile
matching the predicted set with the field set of a test pile. The load tests. A large number of combinations of the quake, Q,
"failure load" determined from a ~ i l loade test is used as the and damping constants, J, and J p , can, theoretically, match the
static soil resistance during driving. The load-carrying capacity field-observed set using the load-test value as the static soil
of other piles in the same site may then be estimated by set resistance during driving. This results in an experience-
matching using the determined "soil7' parameters from the dependent situation when selecting the "correct" values for
analysis of the test pile. This method of prediction assumes these parameters. Furthermore, the manner of defining set in
Printed in Canada 1 imprim6 au Canada
14 CAN. GEOTECH. 3 . VOL. 25, 1988
impact load comprises mainly high-frequency components, G,/c, ratio of 150 for cohesive soils and a G,/a{ ratio of 200
these frequency-dependent coefficients may be replaced by for cohesionless soils where cu is the undrained shear strength
frequency-independent ones. The frequency-independent stiff- and a{ the effective vertical stress. The Poisson's ratio, v,,
ness (k,) and radiation damping (c,) coefficients per unit length may be assumed to be 0.5 for saturated cohesive soils and 0.35
of the pile prior to soil failure are for cohesionless soils. The G,/c, ratio of 150 is commonly
assumed in the analysis of axially loaded piles in cohesive soils
while the G/a{ ratio of 200 for cohesionless soils was deter-
mined by the authors from back analysis of driving and load-
test data.
where G, is the soil shear modulus, ro the pile radius, and p, The authors have presented correlations of the rate effect
the soil density.
coefficients for the soil at pile shaft and tip, J: and J,* respec-
For the tip soil behaviour, the response is assumed to be tively, with the undrained shear strength, c,, for cohesive soils
similar to that of a rigid disc on the surface of an elastic half-
and Jp" with the angle of internal friction, 6 , for cohesionless
space (Lysmer and Richart 1966). The frequency-independent
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
METHOD 1
soil type
v
A
Deterrr~ine
Gs Cu
+
I
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
Predict set
Predict set -
using wave eq. Reestimate
Use 6, Gs Iq'
ratio, K, and Nq
for subsequent
Use a, Gs /C, predictions
ratio for
subsequent
predict ions
\I
I T
( END )
FIG. 2. Flow chart for method 1.
Focht 1972). Instead of determining the value of a, the value the pile-soil friction angle, a{ is the vertical effective stress
of p or X is determined for the ,t?method and X method respec- given by the product of the submerged unit weight, y',and the
tively. For cohesionless soils, the unit skin friction is assumed depth, and Nqis an empirical factor for the base resistance. The
to be K,a{ tan 6 and the unit base resistance is assumed to be values of c, and y' may be estimated from soil investigation.
Nqa{where K, is the coefficient of lateral earth pressure, 6 is The pile-soil friction angle, 6, may be estimated from the
ET AL.
ml
be observed in determining the shaft resistance (Vesic 1967).
The base resistance may now be determined by subtracting the
shaft resistance from the "failure load" estimated from the
load test. The unit base resistance determined is compared with Define a=-
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
for capblock
Cushion stiffness (kN1m)
Coefficient of restitution
for cushion
Mass of pile cap (t)
Hammer drop (m)
Set (mmlblow)
Load test (kN)
Predicted capacity,
method 1 (kN)
For personal use only.
Predicted capacity,
method 2 (kN)
Predicted capacity,
Smith (1960)
method (kN)
- -
NOTES:
(1) Figures within ( ) denote percentage error in predicted capacity. (2) Figures within < > denote elapsed time prior to
*Reference test pile.
the cohesive layers with the soil setup factor determined from [12] may be less than that determined by using the same effi-
the reference test pile. Thus, this soil setup factor corrects ciency multiplied by the rated or maximum energy indicated
for the soil regain in strength with time up to the period of the by the hammer manufacturer. This is because the rated energy
load test. corresponds to the maximum stroke possible for the hammer.
A flow chart showing schematically the procedures for The use of an efficiency multiplied by the rated energy may not
method 2 is shown in Fig. 3. be reasonable for a diesel hammer, since the energy delivered
by a diesel hammer depends on the magnitude of the soil resist-
Additional remarks about the prediction methods ance encountered. In the analyses for piles driven with a diesel
The set of a pile is dependent on the amount of energy trans- hammer, the diesel hammer is treated as an equivalent drop
mitted to the pile from the impact of the hammer. In most wave hammer with the energy determined from the observed stroke.
equation analyses, this energy is estimated from the impact For a steam or drop hammer, the stroke can be controlled by
velocity with allowance made for the efficiency, [, of the presetting. For a diesel hammer, the stroke is determined from
hammer. This impact velocity, uo, is determined by multiply- the O-ring levels, since control of the stroke of the ram by reg-
ing the observed ram stroke, h , by this efficiency, such that ulating the fuel intake is generally difficult. The sensitivity of
the load-carrying-capacity prediction to the input hammer
energy, was discussed by Tavenas and Audibert (1977). There-
where g in the acceleration due to gravity. Equation [12] is a fore, the methods of load-carrying-capacity prediction by set
measure of the ram energy. The energy transmitted to the pile matching require that this energy be reasonably estimated. The
top may be less than the ram energy because of energy losses effect of input hammer energy on the load-carrying capacity
as a result of hysteresis due to restitution of the capblock, prediction is demonstrated by one of the case studies presented
cushion, and (or) cap and the interaction of the stress waves herein.
due to the impedance differences of the capblock, cushion, pile It may be noted that the analysis in method 2 requires the
cap, and pile. These energy losses are implicitly determined in rate coefficients, J,*and Jp*, for pile shaft and tip respectively
the wave equation analysis from the specified material and and the exponent N. These parameters are not required in
geometric properties of the capblock, cushion, cap, and pile. method 1.
It is of interest to note that the ram's energy determined from It is of interest to note the similarity between method 1 and
and wave equation results
the Smith (1960) method. In method 1, the soil setup effects maintained load-test method or the constant rate of penetration
for piles driven in cohesive soils are implicitly accounted for in method (Whitaker 1976). For site D, the "failure load" was
the value of a determined from the wave equation analysis. In determined, from the load-settlement curve of a maintained
the method using the Smith (1960) model, these soil setup load test, as the load corresponding to a pile settlement of 10%
effects are implicitly accounted for in either the Q or J values of the pile diameter. For the piles in site C, Blendy (1979)
determined by the wave equation analysis. Thus, both methods defined the allowable load as half of that determined by the
attempt to correlate the event at the time of driving to that Davisson method (1973) from the load-settlement curve
during load test by the adjustment of these parameters to determined from a maintained load test. Since the method of
include possible thixotropic effects. set matching requires the use of the "failure load" of a
reference pile, the load-carrying capacity predicted for other
Case studies piles in the same site should be compared only with those
determined by the method used for the reference pile.
Twenty-one driven piles at four sites were examined by the
proposed methods to predict the load-carrying capacity of Site conditions
these piles. Three of the sites consist of predominantly cohe- Site A-This site is situated on the East Lagoon in the
sive sbils. The fourth site consists of cohesionless soils and, Republic of Singapore. The soil profile consists of a top layer
for the reason mentioned earlier, is only studied using method of soft marine clay underlain by stiff to very stiff clay. The soil
1. All the 21 piles were load tested to "failure." It is worth profile is shown in Fig. 4. Prestressed concrete piles were
noting that, very few piles have a load-settlement driven to depths of between 30 and 35 m using British Steel
curve that has a well-defined plunging failure and defining the Piling (BSP) 8.13 and 12.19 t steam hammers, for a container-
"failure load" of a pile depends on the methods employed (for terminal project managed by the Port of Singapore Authority.
example, Davisson's method (1973) or Chin's method (1970)). Five pile load-test results were available for this site.
However, the pile-top settlement may be the limiting criterion Site B-This site is also located in the Republic of Singapore
and for the piles in sites A, B, and D, this criterion was at Pasir Panjang. The soil profiles at this site vary quite consid-
adopted. The "failure loads" for piles at sites A and B were erably in the thickness of the various strata. In general, the soil
determined as the load corresponding to a pile-top displace- consists of soft to stiff marine clay interbedded with thin sand
ment of 20 mm using the load-settlement curve of either the seams. A typical soil profile is also shown in Fig. 4. Pre-
CAN. GEOTECH. J . VOL. 25, 1988
Description Description
L'
Very s o f t t o s o f t
0 - -- - -
- - --
marine c l a y - -- - -- Water
C, = 5 - 15 W a
C, = 30 - 50 kPa
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
S t i f f t o very s t i f f
clay Shale I
-- C, = 60 - 120 kPa
end o f b o r e h o l e
Description Description
Soft clay
C, = 10 - 25 kPa
S t i f f clay
C, = 80 - 160 kPa
-. -
,
%
,, , Medium d e n s e sand
.' . ... ..
' .. -
SPT 40 - 55
. . I
i
- ..
- end of b o r e h o l e -- -
- .-.>:.- - -
'
S t i f f clay
C, =
SPT 80 - 95
50 - 110kPa
Very d e n s e s a n d
Very d e n s e sand
SPT 4 9 - 116
end of b o r e h o l e
stressed concrete piles were driven to depths of between 25 and layer of dense sand. The soil profile as described by Blendy
30 m below seabed using Kobe K42 and K45 diesel hammers, (1979) is also shown in Fig. 4. Precast concrete piles were
for a wharf project. This project was also managed by the Port driven to depths of 9-25 m using Vulcan VUL 80C diesel
of Singapore Authority. Four pile load test results were avail- hammers. Six pile load-test results were available for these
able for this site. piles.
Site C-This site is located in Missouri. The site consists of Site D-This site is located in Bangkok, Thailand. The soil
an upper layer of sand fill underlain by a layer of silt and a profile at this site consists of alternating layers of clay and
CHOW ET AL
Site A-East Lagoon Site B-Pasir Panjang Site C-Missouri Site D-Bangkok
Method 1 Method 2 Method 1 Method 2 Method 1 Method 1 Method 2
a! (average) 1.0 0.5 0.7 0.333 - 0.54 0.29
Ks - - - 1.5" 1.OOi 1.Ot
Ng
- - - - 30 50t 50:
Soil setup - 1.87 - 2.07 - - 2.0
*Unit skin friction in cohesionless soil limited to 120 Wa.
+Unit skin friction in cohesionless soil limited to 100 Wa.
'Unit base resistance limit of 10 000 kPa reached for all piles.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
sand, and is also shown in Fig. 4. Steel pipe piles were driven This is primarily due to the small tip resistance of piles in cohe-
to depths of between 55 and 60 m with Kobe K45 diesel ham- sive soils, resulting in only small shaft residual forces at the
mers, and founded on a very dense and sand layer for a hotel end of the hammer blow.
project (Lee et al. 1984). In anticipation of ground subsidence The piles at sites A and B were driven in cohesive soils and
as a result of water withdrawal from the sand substrata, the thus were studied using single-blow analysis. However, the
piles were coated with bitumen at certain sections to reduce the piles in sites C and D were driven into cohesionless and lay-
negative skin friction. For the purpose of pile driving analysis, ered soils respectively. Therefore, the piles at sites C and D
the effect of the bitumen was neglected. This assumption is were analysed by multiple-blow analysis. Five hammer blows
justified, since at the velocities experienced during driving the were applied consecutively when the hammer energy due to
shear strength of the bitumen-pile surface is very much higher the previous blow vanishes. In general, the residual forces
than the skin friction between the soil -bitumen interface. The "stabilized" after about three blows and the sets of subsequent
piles were initially jacked through the soft upper layers and blows after the third are similar. It is interesting to note that
augered prior to driving. Six piles were load tested. even for a hammer blow rate of 60 blows/min, the duration
For personal use only.
Results and discussions between blows is more than sufficient for the dissipation of the
Table 1 summarizes the hammer and pile parameters used in hammer energy from the previous blow. For example, for a
the study. The measured load-carrying capacity of the 21 piles, 30 m long concrete pile, 1 s duration represents about 105~lc,,
the predicted capacity using both methods, and the predicted where L is the length of the pile. In general, stress wave mea-
capacity using the Smith (1960) model for sites A, B, and C surements indicated that the energy would have been dissi-
are also included in Table 1. The predicted load-carrying pated long before 105Llcw. here fore, the assumption in the
capacity using the Smith (1960) model for sites A and B were wave equation analysis of applying the subsequent blow when
presented by Quek et al. (1979) and those for site C were pre- the hammer energy due to the previous blow has dissipated is
sented by Blendy (1979). The elapsed times after installation reasonable.
prior to load testing of the piles in site D are also indicated in The results obtained using the two methods described in this
Table 1. Table 2 shows the a , K,,and N, values and soil setup paper showed favourable predictions of the load-cawing
factors determined using the reference test piles for the four capacity of the piles. The results also showed that the load-
sites. The efficiencies, l, of the steam hammers and diesel carrying capacity predicted appears to be insensitive to either
hammers used to determine the impact velocity were assumed method, since the order of accuracy is about the same. The
to be 65 and 85 % respectively. It should be reiterated here that predicted capacities of both methods are plotted against the
these efficiencies are used with the observed stroke of the load-tested capacities in Fig. 5. The load-carrying capacities of
hammer and not the maximum stroke. the piles predicted by both methods were all within 85% of the
It was shown in Wong et al. (1987) that the set determined load-tested capacities with the exception of four.
from a single-blow analysis for piles with large shaft and (or) In general, the accuracy of the predicted capacity by the new
tip resistances may not be representative of subsequent sets model using either method is a marginal improvement over the
determined by multiple-blow analysis where residual forces predicted capacity by the Smith (1960) model for cohesive
due to the preceding blows are taken into account. The set soil. However, this improvement in accuracy is quite signifi-
determined by a single blow may overestimate the sets of sub- cant for the case of the piles driven in sand at site C.
sequent blows for piles driven in soils where large residual Pile 5 at site D showed a load-carrying-capacity underpre-
forces can build up along the pile shaft and at the tip. This diction of about 30% by both methods. This underprediction is
situation is common, for example, for piles driven in sand. In in part attributed to the larger soil setup due to the longer
the first hammer blow (single blow) the pile and soil are elapsed time (36 days) prior to load testing for pile 5 compared
assumed to be stress free. The pile tip will be prevented from with the elapsed time of the reference test pile, pile 1 (11
rebounding to the full elastic limit or "quake" owing to the days). Therefore, the use of the soil setup factor determined by
residual forces along the shaft that have built up at the end of the reference test pile in method 2 may result in the underpre-
the blow. The subsequent hammer blow has to reverse the diction of the load-carrying capacity of other piles with elapsed
direction of these residual forces along the shaft prior to soil times that are significantly larger than that of the reference test
plasticity in the downward direction. Wong et al. (1987) pile. Note that the other four piles at site D had better predicted
showed that for piles driven in cohesionless soils, the differ- load-carrying capacities owing to the much smaller deviations
ence in sets for the first and subsequent blows can be signifi- in elapsed time from the elapsed time of the reference test pile
cant. However, for cohesive soils this effect is generally small. (Table 1).
22 CAN. GEOTECH. J . VOL. 2 5 , 1988
2oooj " 0
L&
Ram
Ram
energy : 11.7 l . m
energy : 9.915 1.m
+ Ram energy = 7.6 I - m
Ram energy = 5.85 1.m
Biows Irn
FIG.7. Load-carrying capacity versus blow counts for various input
LOAD - TEST CAPACITY [ kN) ram energies for test piles in site D.
FIG. 5. Comparisons of predicted and measured load-canying
capacities. using static design methods. This comparison allows an inde-
pendent check on the long-term capacity of the pile determined
by static design methods. By this comparison, it may be pos-
A sible to check the validity of the assumed parameters (a and c,)
in the static design methods and allow adjustments of these
X
parameters for the design of other piles in the same or similar
soils. This method of long-term capacity prediction is not pos-
sible with either the method using the Smith (1960) model or
method 1.
For personal use only.
-
I
I tration of 55 m. For this site. the maximum deviation between
I
o I the predicted and measured load-carrying capacities for the six
o 10 20 30 36 LO piles is about 35% for a doubling of the input energy from
ELAPSED TIME (DAY)
5.85-11.7 t.m.
FIG. 6. Variation of soil setup of cohesive layers with time for
site D.
Conclusions
Two methods have been presented to predict the load-
Using the "failure loads" determined from the load tests of carrying capacity of piles using a rational new wave equation
the six piles and the static soil resistance immediately after model (Lee et al. 1988) that uses conventional soil mechanics
driving, R,, determined using method 2, an estimate of the parameters. These two methods, methods 1 and 2, use a load-
average soil setup variation with time for the cohesive layers at test result to estimate the soil parameters at the site by set
site D is shown in Fig. 6. The points in this figure were matching. These estimated soil parameters are then used in
obtained by plotting the ratios of the soil resistance due to the subsequent analyses to predict the load-carrying capacity of
cohesive layers (from "failure load") to the soil resistance of similar piles at the same site. Twenty-one piles were examined
the same layers immediately after driving (from wave equation and the predicted load-carrying capacities of these piles by
analyses) for the six piles against the respective elapsed times. both methods compare favourably with the load-tested capac-
The resistance of the cohesive layers (from "failure load") ities. Method 2 is able to account for the phenomenon of soil
was determined by subtracting, from the "failure load," the setup generally observed in cohesive soil. This method repre-
shaft and base resistances of the cohesionless layers deter- sents a rational approach to estimating the load-carrying capac-
mined from wave equation analysis. ity of driven piles in cohesive soils. The time dependency of
From the line of best fit (Fig. 6), the setup factor for pile 5 at the load-carrying capacity of driven piles in cohesive soils is
36 days after driving was 3.8 (compared with 2.0 determined demonstrated by six piles using method 2. The ultimate soil
from the reference test pile). The ultimate soil setup factor, setup factor for the site can then be determined and the long-
from the asymptotic value of the line of best fit in Fig. 6, for term capacity of piles estimated. This long-term-capacity pre-
the piles in site D, was approximately 4.0. Hence, 36 days diction for driven piles in cohesive soil is not possible with
after driving, the cohesive layers have regained about 95 % of method 1 or the method using the Smith (1960) model.
their long-term shaft capacity.
Using the ultimate setup factor and the resistance immedi-
ately after driving, R,, of the cohesive layers from the wave Acknowledgement
equation analysis, the long-term shaft capacity of any pile in The authors are grateful to Mr. R. Radhakrishnan of the Port
the site may be estimated. The long-term capacity determined of Singapore Authority for permission to use and publish the
can then be compared with the long-term capacity calculated soil data for sites A and B.
ET AL. 23
BLENDY,M. M. 1979. Rational approach to piled foundations. wave equation analysis to friction piles in sand. Canadian Geotech-
American Society of Civil Engineers National Convention, Atlanta, nical Journal, 14: 34-5 1.
GA, pp. 38-47. TOMLINSON, M. J. 1970. Foundation design and construction.
BURLAND, J. 1973. Shaft friction of piles in clay; a simple fundamen- Pitman, London, United Kingdom.
tal approach. Ground Engineering, 6(3): 30-42. TOOLAN, F. E., and Fox, D. A. 1977. Geotechnical planning of piled
DAVISSON, M. T. 1973. Higher capacity piles. Proceedings of Lec- foundations for offshore platforms. Proceedings-the Institution of
ture Series, Innovations in Founndation Construction, ASCE, Civil Engineers, Part 1, 69: 221 -244.
Illinois Section, Chicago, pp. 81 - 112. VESIC,A. S. 1967. A study of bearing capacity of deep foundation.
CHIN,F. K. 1970. Estimation of the ultimate load of piles not canied Final report, project B- 181, Georgia Institute of Technology,
to failure. Proceedings, 2nd Southeast Asia Conference on Soil Atlanta, GA.
Engineering, Singapore, pp. 81 -90. VIJAYVERGIYA, V. N., and FOCHT,J. A., JR. 1972. A new way to
EGOROV,K. E. 1965. Calculation of bed for foundation with ring predict the capacity of piles in clay. 4th Annual Offshore Technol-
footing. Proceedings, 6th International Conference on Soil ogy Conference, Houston, TX, Vol. 2, OTC paper 1718.
Mechanics and Foundation Engineering, Canada, Vol. 2, pp. WHITAKER, T. 1976. The design of pile foundations. 2nd ed. Per-
41 -45. gamon Press, Oxford, United Kingdom.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by 68.148.154.147 on 06/27/20
FOREHAND, P. W., and REESE,J. L. 1964. Prediction of pile capacity WONG,K. Y., CHOW,Y. K., KARUNARATNE, G. P., and LEE,S. L.
by the wave equation. ASCE Journal of the Soil Mechanics and 1987. Effect of residual stress on the pile driveability and driving
Foundations Division, 90(SM2): 1-25. stresses. Department of Civil Engineering, National University of
GAZETAS, G., and DOBRY,R. 1984. Simple radiation damping model Singapore, internal report.
for piles and footings. ASCE Journal of Engineering Mechanics,
llO(EM6): 937-956.
GIBSON,G. C., and COYLE,H. M. 1968. Soil damping constants List of symbols
related to common soil properties in sands and clays. Report radiation damping coefficient
No-125- 1, Texas Transport Institute, Texas A & M University, remoulded shear strength of cohesive soils
College Station, TX. radiation damping coefficient for shaft and tip respec-
GOBLE,G. G., LIKINS,G. E., and RAUSCH, F. 1975. Bearing capac-
ity of piles from dynamic measurements. Final report, Department tively
of Civil Engineering, Case Western Reserve University, undrained shear strength of cohesive soils
Cleveland, OH. longitudinal wave speed in pile
LEE, S. L., KARUNARATNE, G. P., and SITICHAIKASEM, S. 1984. soil shear modulus
For personal use only.
Non-negative skin friction piles in layered soil. International Con- damping coefficient in TTI soil model
ference on Case Histories in Geotechnical Engineering, Missouri, tip damping coefficient in Smith (1960) model
Vol. 1, 285-288.
LEE,S. L., CHOW,Y. K., KARUNARATNE, G. P., and WONG,K. Y. rate effect coefficient for tip
1988. Rational wave equation model for pile driving analysis. shaft damping constant in Smith (1960) model
ASCE Journal of Geotechnical Engineering, 114(3), in press. rate effect coefficient for shaft
LITKOUHI, S., and POSKITT,T. J. 1980. Damping constants for pile soil stiffness coefficient
driveability calculations. GCotechnique, 30: 77 - 86. soil stiffness for shaft and tip respectively
Lo, K. Y., and STERMAC, A. G. 1965. Induced pore pressure during
coefficient of lateral earth pressure
pile driving operations. Proceedings 6th International Conference
on Soil Mechanics and Foundation Engineering, Canada, Vol. 2, exponent for rate effects
pp. 285-289. empirical factor for base resistance in cohesionless
LYSMER, J., and RICHART, F. E. 1966. Dynamic response of footing soils
to vertical loading. ASCE Journal of the Soil Mechanics and Foun- maximum elastic deformation of soil, quake
dations Division, 92(SM1): 65 -91. total soil resistance during driving
NOVAK,M., NOGAMI, T., and ABOUL-ELLA, F. 1978. Dynamic soil ultimate soil resistance t o failure
reactions for plane strain case. ASCE Journal of the Engineering soil spring force
Mechanics Division, 104(EM4): 953 -959. maximum static resistance of soil
QUEK,T. B., SEOW,K. L., and YEO, S. H. 1979. A study of piled inner and outer pile radius respectively
foundations. B.Eng. thesis, University of Singapore, Singapore.
pile velocity
RADHAKRISHNAN, R., SUBRAMANYAM, R. V., and ABDULKHADER,
M. H. 1980. Wave equation analysis for steel piles. Proceedings impact velocity
6th Southeast Asia Conference on Soil Engineering, Taiwan, pp. empirical factor for pile - soil adhesion
273-281. empirical constant in Burland's P method
RIGDEN,W. J., PETTIT,J. J., ST. JOHN,H. D., and POSKITT,T. J. friction angle at pile - soil interface
1979. Developments in piling for offshore structures. Proceedings empirical constant in X method
of the 2nd International Conference on the Behaviour of Offshore efficiency of the hammer
structures, London, Vol. 2, pp. 279-296. Poisson's ratio of soil
SEED,H. B., and REESE,L. C. 1957. The action of soft clay along density of soil
friction piles. Transactions of the American Society of Civil Engi- angle of internal friction
neers, 122: 731 -754. a factor that accounts for changes in soil stiffness due
SMITH,E. A. L. 1960. Pile driving analysis by the wave equation.
ASCE Journal of the Soil Mechanics and Foundations Division, to changes in annulus thickness
86(SM4): 35-61. submerged unit weight of soil
TAVENAS, F. A., and AUDIBERT, J. M. E. 1977. Application of the vertical effective stress