Вы находитесь на странице: 1из 4

Analysis No.

X
: Analysis of rate for Overhead Gantry Sign Board

Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflected with high
intensity retro-reflective sheeting with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as
per clause 802.7 over a designed support system of galvanized steel trusses of section and type to be mounted by
bolts and nuts over RCC structure as per drawing

(A) 300 mm
outside dia MS
1 pipe

(i) Vertical post


2x 6.00 .= 12.00 Rm
@ 49.5 Kg/m Total= .= 12.00 Rm 594.00 Kg

(ii) Horizontal
MS square tube
(60mmx60mm) 4x 12.60 .= 50.40 Rm
15 x 2x 0.90 .= 27.00 Rm
15 x 2x 0.60 .= 18.00 Rm

Stiffener
(60mmx60mm) 2x 2.5 .= 5.00 Rm
@ 6.71 Kg/m Total= .= 100.40 Rm 673.684 Kg

(B) Cross
member
-38mmx38mm
size 2x 14 x 1.30 .= 36.40 Rm
2x 14 x 1.10 .= 30.80 Rm
@ 3.95 Kg/m Total= .= 67.20 Rm 265.44 Kg

( C ) Base
plate 25mm
thickness 2x 0.80 x 0.80 .= 1.28 Sqm
@ 196.25 Kg/sqm Total= 251.2 Kg

Stiffener -10mm
thickness 2x 4x 0.30 x 0.3 .= 0.72 Sqm
@ 78.5 Kg/sqm Total= 56.52 Kg

Plate-10mm
thickness 2x 2x 0.20 x 0.6 .= 0.48 Sqm
@ 78.5 Kg/sqm Total= 37.68 Kg

Top Plate 12mm


thickness- 2x 2x 0.90 x 0.9 .= 3.24 Sqm
@ 94.2 Kg/sqm Total= 305.208 Kg

Stiffener at top ,
10mm thickness 2x 4x 0.30 x 0.4 .= 0.96 Sqm
@ 78.5 Kg/sqm Total= 75.36 Kg
Rib-10mm
thickness 2x 2x 0.10 x 0.2 .= 0.08 Sqm
@ 78.5 Kg/sqm Total= 6.28 Kg
10mm thickness
plate - 2x 2x 0.20 x 0.2 .= 0.16 Sqm
2x 1x 0.10 x 0.1 .= 0.02 Sqm
Total= 0.18 Sqm
@ 78.5 Kg/sqm Total= 14.13 Kg

Pedestal-10mm
thickness- 2x 2x 0.80 x 0.8 .= 2.56 Sqm
@ 78.5 Kg/sqm Total= 200.96 Kg

Anchor bolts
-20mm dia.
x750mm long 2x 12.00 .= 24.00 Nos
.= 18.00 Rm
@ 2.47 Kg/M Total= 59.28 Kg
Total= 2539.74 Kg
15% for cutting,welding and wastage etc. 380.9613 Kg
Total= 2920.70 Kg
.= 2.92 Tonne

Rate per Sqm (as


per SOR 2013-14) @ 98500.00 per tonne Rs. 287689.275

Retro--
2 reflective sheet
Area = 2x 12.00 x 1.2 .= 28.8 Sqm

Rate per Sqm (as


per SOR 2013-14)

Cost of Retro-
reflecting Sheet @ 11000.00 Rs. 316800.00

E/W in
3 excavation

Quantity= 2x 1.50 x 1.50 x 1.65 .= 7.425 Cum

Rate per Cum (as


per SOR 2013-14) @ 108.00 per Cum Rs. 801.90

Cost of
Excavation

P.C.C work (M-


4 15) 2x 1.50 x 1.50 x 0.15 .= 0.675 Cum

Quantity = @ 5605.00 per Cum Rs. 3783.38

Rate per Cum (as


per SOR 2013-14)
Cost of PCC M-15
5 12mm Jali 2x 2x 11 x 1.15 .= 50.6 Rm
@ 0.89 kg per .= 45.034 Kg
16 mm dia. TMT
@150 mm c/c 2x 24 x 2.75 .= 132.00 Rm
@ 1.60 kg per .= 211.2 Kg
Stirrups -8mm
dia. 2 x 14 x 4.25 .= 119.00 Rm
@ 0.39 kg per .= 46.41 Kg
Total= .= 302.644 Kg
Total= .= 0.302644 MT

Cost of
Reinforcement,R
ates per MT (as
per SOR 2013-14) @ 73343.00 per Cum Rs. 22196.82

M 20 grade of
6 RCC work

Quantity= 2x 1.00 x 1.00 x 2.5 .= 5.00 Cum

Rate per Cum (as


per SOR 2013-14) @ 8761.00 per Cum Rs. 43805.00

Cost of RCC M-20

Total= Rs. 675076.00

Executive Engineer,PWD,
Nagaon NH Division,Nagaon.