Вы находитесь на странице: 1из 5

PROJECT:

King Abdullah Financial District (KAFD) Cluster J1

Document Title:

ITP for Injection Work of Basement Walls

Document Number: Issue Date:

ITP - CIV - 001 3/21/2019

REVISION HISTORY
REV PREPARED CHECKED APPROVED
DESCRIPTIONS/REASON FOR ISSUE DATE
NO. BY BY BY

MAA MAA PJM


0 Issue for Approval 23/03/2019

5
ITP No. H HOLD

King Abdullah Financial District (KAFD) Cluster J1 I INSPECTION


ITP - CIV - 002
R REVIEW

Name: PJM S SURVEILLANCE

ITP for Fire Stopping to Parcels 4.05, 5.06, 5.03, 5.04 and 5.05 A APPROVAL
discipline Architectural Finishes
W WITNESS

Persons Responsible for Checking


Activity Frequency of
INSPECTION ACTIVITY REF SPECS / PROCEDURE ACCEPTANCE CRITERIA and Approval of VERIFICATION DOCUMENTS
No. Inspection Consultant
Workmanship/Submittals SUB-CON SAUDICO
(DAR/JLL)

1.0 PRE-Work / SUBMITTALS (i) All Material Submittals to be reviewed in accordance with SAUDICO-SOP-GEN-MANAGEMENT REVIEW PROCEDURE -003-VER 00-20180226. (ii) Reference Method Statement/Risk Assesment Submittals.

(a) Maintain barrier and structural floor fire resistance ratings (see vol I section 3.0 for
(a) Vol. 2 Specification Section 07270 including cl 1.05 specific fire rating requirements) including resistance to cold smoke at all construction
(performance requirements), cl. 2.02(materials) and gaps/penetrations including connections with other surfaces or types of construction,
cl.1.06 (submittals) (b) Vol 1 Specification Section separations required to permit building movement and for sound or vibration absorption- (a) Technical Manager. (b) Procurement Each Material and
1.1a Material Submittal -1 X H H/R Material Approval Request (MAR)
3.0 : Fire Resistance Considerations (c) SAUDICO note latex or acrylic based sealants are not acceptable and only urethanes or slicone base Manager © Quality Director) Fire Stop System
SOP PROC Material Proceurement Procedure- materials to be used. (b) Fire stopping materials to comply with ASTM E119, ASTM E814,
003ver.01.20180611 UL 263, UL 1479 to achieve a fire rating as noted on drawings and required by codes and
standards.

(a) Vol. 2 Specification Section 07270 including cl 1.05 (c) Surface burning: conforming to ASTM E84 products to have a zero smoke and
interruptions to fire related assemblies materials and components.(d) Smoke barrier
(performance requirements), cl. 2.02(materials) and
construction design requirements to ensure barrier and structural floor fire resistance
cl.1.06 (submittals) (b) Vol 1 Specification Section (a) Technical Manager. (b) Procurement Each Material and
1.1b Material Submittal -2 ratings are maintained including resistance to cold smoke at all penetrations, connections X H H/R Material Approval Request (MAR)
3.0 : Fire Resistance Considerations (c) SAUDICO Manager © Quality Director) Fire Stop System
with other surfaces or types of construction, at separations required to permit building
SOP PROC Material Proceurement Procedure-
movement and sound or vibration absorption, and at other construction gaps.(e) Reference
003ver.01.20180611 correct UL systems designations are correct as specified under Section 07170 cl 1.05E

(a) Vol. 2 Specification Section 07270 including cl 1.05 located at either concrete, gysum and wood substrate openings and dependent upon type
of penetrating item including (i) plastic pipe, (ii) metal pipe,(iii) insulated metal pipe,(iv)
(performance requirements), cl. 2.02(materials) and
insulated cable, (v) cable tray, (vi) busway, (vii) glass pipe blank, (viii) construction gap, (ix)
cl.1.06 (submittals) (b) Vol 1 Specification Section (a) Technical Manager. (b) Procurement Each Material and
1.1c Material Submittal -3 mixed penetrating items and (x) miscellaneoues mecahnical vent ducts . (f) Submit data on X H H/R Material Approval Request (MAR)
3.0 : Fire Resistance Considerations (c) SAUDICO Manager © Quality Director) Fire Stop System
product characteristics, performance and limittaion criteria. (g) Issue manufacturer
SOP PROC Material Proceurement Procedure- installtion instructions. (h) Issue manufacturers certificate certifying that products meet or
003ver.01.20180611 exceed specification requirements.

(i) At duct damper penetrations ensure annular space is filled with mineral wool safing and
(a) Vol. 2 Specification Section 07270 including cl 1.05 sealedwith flexible fire stop sealant (j) Systems or devices listed in the UL directory under
(performance requirements), cl. 2.02(materials) and categories XHCR and XHEZ can be optionally provided so long at they conform to the
cl.1.06 (submittals) (b) Vol 1 Specification Section construction type, penetrant type, annular spacing requirements and fire rating required in (a) Technical Manager. (b) Procurement Each Material and
1.1d Material Submittal -4 X H H/R Material Approval Request (MAR)
3.0 : Fire Resistance Considerations (c) SAUDICO each separate instance, and the system is suitable for wall applications . Systems to be Manager © Quality Director) Fire Stop System
SOP PROC Material Proceurement Procedure- verified these can withstand the passage of cold smoke either as an inherent property of
003ver.01.20180611 the poduct , or by use of a separate product included as a part of the UL or device, and
designed to perform this function. (j) Attach all fire test reports

(a) Vol. 2 Specification Section 07270 including cl 1.05


(k) Through penetration smoke stopping; Verify any system complying with requirements
(performance requirements), cl. 2.02(materials) and
for through penetration fire stopping in fire rated construction as specified under section
cl.1.06 (submittals) (b) Vol 1 Specification Section (a) Technical Manager. (b) Procurement Each Material and
1.1e Material Submittal -5 07270 is acceptable and system provides a smoke seal taking into conideration latex and X H H/R Material Approval Request (MAR)
3.0 : Fire Resistance Considerations (c) SAUDICO Manager © Quality Director) Fire Stop System
acrylic based sealants are not acceptable and only urethanes or silicone base materials are
SOP PROC Material Proceurement Procedure-
to be used.
003ver.01.20180611

(a) Vol. 2 Specification Section 07270 cl 1.06 B (b)


Provide layouts and necessary detailed drawings showing the location and type of fire (a) Technical Manager. (b) Procurement Each Material and
1.2 Shop Drawings SAUDICO SOP GEN Engineering Plan 017 X H H/R Shop drawing Submittal
stopping to be used. Manager © Quality Director) Fire Stop System
ver.00020180226

(a) Manufacturering company specializing in manufacturing the products under section


07270 of the specification requires minimum 5 years documented experience. (b)
Applicator specializing in performing the work under Section 07270 of the Specification (a) Technical Manager. (b) Procurement Each Material and
1.3 Qualifications Vol. 2 Specification Section 07270 cl 1.07 and 1.06 X H H/R Supplier Approval Submittal.
requires minimum 5 years documented experience.(c) Compliance to be demonstrated Manager © Quality Director) Fire Stop System
with applicable code for fire resistance and surface burning characteristics. (d) Provide
certificate of compliance from the authority having jurisdiction to approve the materials.

INSPECTION SEQUENCE: (1) Complete Mock up inspection under ITP item no. 2.2. (2) Hold Point under MIR is required for item 2.1. (3) Hold point under single WIR for each Location is required Prior to Commencement under ITP item nos. 2.3 . (4) Surveillance Inspections on a Daily Basis to be
2.0
carried out to record compliance under ITP item no's 2.4 a-c inclusive before final WIR hold point inspection is completed on Completion of Works under ITP item no. 2.5. (5) Surveillance is required for item 2.5 Protection Requirements

(a) Approval required on Material Inspection Requests-see


item 1.1 above with MAR and delivery note copy attachments.
SAUDICO SOP PROC Material Proceurement
2.1 Material Delivery and Storage Inspection Check materials are stored in accordance with the manufacturer instructions. QAQC Engineer and Site Engineer Each Delivery x H H (b) Material Log updated by the Storeman and reference MIR
Procedure-003ver.01.20180611
document number.. © Materials to be signed out and recorded
by the Storeman .

Mock up to be completed over 1/3 liner meter to a representative substrate surface for Prior to
(a) Vol. 2 Specification: Section 07270 cl 1.09.(b) each type of opening applied on masonry, concrete, stud wall and substrate surfaces to Commencement of Approval required on WIR with attached checklist ref.no.
2.2 Field Mock Up Panels and Benchmarks QAQC Engineer and Site Engineer x H H
Approved shop drawings demonstrate minimum standard for the work. The mock up as specified may not remain Permanent Plaster OC/CIV-004/01,
as part of the work unless alternative requirements are accepted by the Engineer. Works
ITP No. H HOLD

King Abdullah Financial District (KAFD) Cluster J1 I INSPECTION


ITP - CIV - 002
R REVIEW

Name: PJM S SURVEILLANCE

ITP for Fire Stopping to Parcels 4.05, 5.06, 5.03, 5.04 and 5.05 A APPROVAL
discipline Architectural Finishes
W WITNESS

Persons Responsible for Checking


Activity Frequency of
INSPECTION ACTIVITY REF SPECS / PROCEDURE ACCEPTANCE CRITERIA and Approval of VERIFICATION DOCUMENTS
No. Inspection Consultant
Workmanship/Submittals SUB-CON SAUDICO
(DAR/JLL)

(a) Cleaning of the substrate is required to remove dirt, dust, graese, oil, loose material
or any other matter that may affect bond of the firestopping material. (b) Check previous
Preparation of Surfaces prior to (a) Vol. 2 Specification: Section 07270 cl 3.02.(b) material applications and remove incompatible materials that will affect the bond.(c) Approval required on WIR with attached checklist ref.no.
2.3 QAQC Engineer and Site Engineer Each Location x H H
Commencement Approved shop drawings Protect adjacent surfaces from damage during material installation. (d) Check OC/CIV-004/01 and snagging list.
size/locations of all openings. (e) Site Engineer to coordinate inspections ahead of
ceiling closures.
ITP No. H HOLD

King Abdullah Financial District (KAFD) Cluster J1 I INSPECTION


ITP - CIV - 002
R REVIEW

Name: PJM S SURVEILLANCE

ITP for Fire Stopping to Parcels 4.05, 5.06, 5.03, 5.04 and 5.05 A APPROVAL
discipline Architectural Finishes
W WITNESS

Persons Responsible for Checking


Activity Frequency of
INSPECTION ACTIVITY REF SPECS / PROCEDURE ACCEPTANCE CRITERIA and Approval of VERIFICATION DOCUMENTS
No. Inspection Consultant
Workmanship/Submittals SUB-CON SAUDICO
(DAR/JLL)

(a) Reference correct UL systems located at either concrete, gysum and wood substrate
(a) Daily surveillance by QAQC Engineer reporting referenced
openings designations are correct as specified under Section 07270 cl 1.05E .depending
compliance criteria on KAFD-CL1-SCL-DAR-SUB-00301
upon type of penetrating item including (i) plastic pipe, (ii) metal pipe,(iii) insulated metal
(a) Volume 2: Specification: Section 07270 cl 2.02. (b) rev.0. (b) Attach referenced specification and demonstrate
pipe,(iv) insulated cable, (v) cable tray, (vi) busway, (vii) glass pipe blank, (viii) Daily during
2.4a Application of Firestopping-1 Shop drawings and/or Material Approval Request UL QAQC Engineer and Site Engineer x S S compliance with approved details at all locations.(c) Atttach all
construction gap, (ix) mixed penetrating items and (x) miscellaneoues mechanical vent. Application
Details. product manufacturer instructions/compliance criteria or
Ducts (b) Check compliance for the following approved products with required MIR in
reference on updated checklist and demonstrate compliance
accordance with the manufacturer instructions: (i) Fire rated silicone sealant required
based on recorded site inspection.
with extension and compression properties of plus/minus 40 percent of the original gap.

(ii) Fire rated intumescent caulk.to comprise single component based materials.(iii) Fire
(a) Daily surveillance by QAQC Engineer reporting referenced
barrier sheet comprising galvanised shet metal/intumescent fire barrier /wire mesh
compliance criteria on KAFD-CL1-SCL-DAR-SUB-00301
composite for filling large openings in fire rated construction.(iv) Steel sheet collars with
(a) Volume 2: Specification: Section 07270 cl 2.02. (b) rev.0. (b) Attach referenced specification and demonstrate
tabs for mounting to decking and slabs to retain integral preformed fires. (v) Intumescent Daily during
2.4b Application of Firestopping-2 Shop drawings and/or Material Approval Request UL QAQC Engineer and Site Engineer x S S compliance with approved details at all locations.(c) Atttach all
putty comprising one component mouldable compund and non shrinking.(vi) Firestop Application
Details. product manufacturer instructions/compliance criteria or
mortar to comprise Portland cement based, non asbestos through penetration firestop
reference on updated checklist and demonstrate compliance
mortar. (vii) Firestop pillows to comprise mineral fiber treated with intumescent coating
based on recorded site inspection.
enclosed in 4 mil polyethylene bag. (viii) Mineral wool safing: Fire safing

to conform to federal Specifications HH-I-521F,Typei, Class A and applied at UL


approved curtain wall applications.(ix) Intumescent collars to be provided wherever (a) Daily surveillance by QAQC Engineer reporting referenced
necessary to all pipe penetrations through fire rated structures steel intumescent pipe compliance criteria on KAFD-CL1-SCL-DAR-SUB-00301
(a) Volume 2: Specification: Section 07270 cl 2.02. (b) collars.(x) Mineral fibre backing material to be suitable for friction fit in voids and comply rev.0. (b) Attach referenced specification and demonstrate
Daily during
2.4c Application of Firestopping-3 Shop drawings and/or Material Approval Request UL with manufacturer instructions and UL design.(xi) Backing rods to comply with QAQC Engineer and Site Engineer x S S compliance with approved details at all locations.(c) Atttach all
Application
Details. manufacturer instructions and UL design.(xii) Ensure comressed fibre material achieves product manufacturer instructions/compliance criteria or
a density of 25 % of its uncompressed density . (xiii) Check firestop materIal thicknesses reference on updated checklist and demonstrate compliance
are sufficient to achieve the correct fire rating. . (d) Check sealant depths at recorded based on recorded site inspection.
locations

(a) Volume 2: Specification: Section 07270 cl 2.02. (b) On Completion to Approval required on WIR with attached checklist ref.no.
Complete final inspection, record scope of inspection and verify all locations comply with
2.5 Final Inspection Shop drawings and/or Material Approval Request UL QAQC Engineer and Site Engineer Each Area and/or x H H OC/CIV-004/01,survey report of sealant depths and snagging
approved details and compliance criteria referenced under 2.4 a-c above.
Details. Floor Level list to be closed prior to Consultant inspection.

Daily surveillance by QAQC Engineer reporting referenced


Volume 2: Specification: Sections 01550 and 07270 cl
2.6 Protection of Works Ensure installed materials cannot be damaged and suitable protection is provided. QAQC Engineer and Site Engineer On Completion x s s compliance criteria on KAFD-CL1-SCL-DAR-SUB-00301
3.05 (b
rev.0. (
PIPING INSTALLATION CHECK LIST

RFI No. : Form No. : SCE-100-023

Client : RFI No. :

Project : Date :

Consultant : ITP Ref. No.:

Contractor : Location :

Sub-Contractor :

Reference Documents (Specifications, Drawings, others…..):

Activity/Item: Y/N
1. Condition of Material Accepted

2. All Pipes cut accurately to measurement

3. Condition of Expansion Joint Accepted

4. Clean-out size and location Accepted

5. Trap Location and Quality Accepted

6. Pipe Hangers Installation Accepted

7. Pipe Sleeves Installation Accepted

8. Fixture and Equipment Support Accepted

9. Drains Installation Accepted

10. Unions Installation Accepted

11. Pressure Test Performed and Accepted

12. Leakage Test Performed and Accepted

13. Cleaning Condition Accepted

14. Painting and Protection condition Accepted

15. Color code for exposed pipes Accepted

Remarks:

Checked by: Civil Works

Name : Position : Signature : Date :

Checked by: MEP Works

Name : Position : Signature : Date :