Академический Документы
Профессиональный Документы
Культура Документы
FEP Ragunathpur
292 KaisarRaihan
1st floor column re bar binding 2 days 19/12/2018 20/12/2018
1st floor column Shuttering work 3 days 21/12/2018 23/12/2018
FEP Ragunathpur
292 KaisarRaihan 1st floor column Casting Work 1 days 24/12/2018 24/12/2018
1st floor column re bar binding 2 days 25/12/2018 26/12/2018
1st floor column Shuttering work 3 days 27/12/2018 29/12/2018
1st floor column Casting Work 1 days 30/12/2018 30/12/2018
1st floor Slab Shuttering work 10 days 31/12/2018
1st floor Slan re bar binding 10 days
1st floor Slab Casting Works 1 days
Road construction work on goi 10 days 12/11/2018 22/11/2018
Piling Works 39 days 23/11/2018 31/12/2018
33 nos Base Rod+ Shuttering + Ca 20 days
Sand filling work 3 days
G.B shuttering Work 5 days
G.B Re bar binding Work 6 days
G.B Casting Work 1 days
Ramp Shuttering Work 5 days
Ramp Re bar binding Work 3 days
FEP Daskhin Purbo Ramp Casting Work 1 days
309 Char Chandia Tubewall boring Work 16 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
G.F Slan Shuttering Works 10 days
G.F Re bar binding Works 10 days
G.F Casting Works 1 days
33 nos Base Rod+ Shuttering + Ca 20 days 12/11/2018 2/12/2018
Sand filling work 10 days 3/12/2018 13/12/2018
G.B shuttering Work 10 days 14/12/2018 24/12/2018
G.B Re bar binding Work 6 days 24/12/2018 30/12/2018
G.B Casting Work 1 days 31/12/2018 31/12/2018
FEP Uttar Paschim Ramp Shuttering Work 5 days
324 Char Darbesh Ramp Re bar binding Work 3 days
Ramp Casting Work 1 days
Tubewall boring Work 16 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
Slab Casting
1st Lift
2nd Lift
Slab Casting
Slab Casting
1st Lift
2nd Lift
4 nos
Slab Casting
1st Lift
2nd Lift
Multipurpose Disaster Shelter Project
Work Plan Report of feni,Chagalnaiya,Parshuram,Daganbhuiyan (NW-2)
12 November 2018 to 31 December 2018
SheltShelter/GP Project Summary Duratio Start Date Finish Date Remarks
1st floor shuttering Work 8 days 12/11/2018 20/11/2018
1st floor Re bar binding 10 days 21/11/2018 30/11/2018
1st floor Casting Work 1 days 1/12/2018 1/12/2018 Slab Casting
2nd floor column re bar bi 2 days 2/12/2018 4/12/2018
2ndColumn Shuttering W 3 days 5/12/2018 7/12/2018 1st Lift
2nd Column Casting Work 1 days 8/12/2018 8/12/2018
FEP Purbo
Pathannogor 2nd floor column re bar bi 2 days 9/12/2018 10/12/2018
014 Gps 3 days 11/12/2018 13/12/2018 2nd Lift
2nd Column Shuttering W
2nd Column Casting Work 1 days 14/12/2018 14/12/2018
2nd floor Slan Shuttering 10 days 15/12/2018 25/12/2018
2nd floor Re bar binding 10 days 26/12/2018
2nd floor Casting Works 1 days
2nd Lift
GF Column Casting Works 1 days 17/12/2018 17/12/2018
GF floor Slan Shuttering 10 days 22/12/2018
2nd/Roof Slab Rebar bind 10days 12/11/2018 24/11/2018
FEP21 Malipathar 01 days 25/11/2018 25/11/2018
7 Gps 2nd/Roof Slab casting wor Slab Casting
Brick wall & plastering Wo 35 days 26/11/2019 31/12/2018
2nd Column Casting Work 1 days 15/11/2018 15/11/2018 1st Lift
2nd floor column re bar bi 2 days 16/11/2018 18/11/2018
2nd Column Shuttering W 3 days 19/11/2018 21/11/2018 2nd Lift
FEP33 Char luxmiganj 2nd Column Casting Work 1 days 22/11/2018 22/11/2018
3 Gps 2nd floor Slan Shuttering 10 days 23/11/2018 3/12/2018
2nd floor Re bar binding 10 days 4/12/2018 14/12/2018
2nd floor Casting Works 1 days 15/12/2018 15/12/2018 Slab Casting
Brick wall & plastering Wo 35 days 16/12/2018
(Engr.Mahamudul Hasan)
Project Engineer.
SS-AE JV
DHAKA CITY NEIGHBORHOOD UPGRADING PROJEC
Contract Package No. DCNUP/W-07/LAL
Safety Equipment for Covid-19
ITEMS Quantity
u)