Multipurpose Disaster Shelter Project

Work Plan Report of feni,Sonagazi (NW-1)


12 November 2018 to 31 December 2018
ShelteShelter/GPS Project Summary Duration Start Date Finish Date
2nd/Roof Slab Rebar binding wor 12 days 12/11/2018 24/11/2018
FEP Palgiri Ibne Ali
2nd/Roof Slab casting work 01 days 25/11/2018 25/11/2018
335 Akbar Gps
Brick wall & Plastering work 35 days 26/11/2018 31/12/2018
2nd/Roof Slab (1st lift) column 02 days 12/11/2018 13/11/2018
casting work
2nd/Roof Slab (2st lift) column 6 days 14/11/2018 20/11/2018
casting work
FEP
339 Swarajpur Gps 2nd/Roof Slab Shuttering work 10 days 21/11/2018 30/11/2018
2nd/Roof Slab Rebar binding 10 days 1/12/2018 10/12/2018
work
2nd/Roof Slab casting work 1 days 11/12/2018 11/12/2018
Brick wall & Plaster 35 days 12/12/2018
11 nos Base Casting 1 days 12/11/2018 12/11/2018
22 nos Bases Shuttering + Casting 10 days 13/11/2018 23/11/2018
Sand filling work 10 days 24/11/2018 4/12/2018
G.B shuttering Work 10 days 4/12/2018 14/12/2018
G.B Re bar binding Work 6 days 5/12/2018 21/12/2018
G.B Casting Work 1 days 23/12/2018 23/12/2018
Ramp Shuttering Work 5 days 24/12/2018 28/12/2018
FEP Moddom
Ramp Re bar binding Work 3 days 29/12/2018 31/12/2018
293 Sultanpur
Ramp Casting Work 1 days
Tubewall boring Work 13 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
Sand filling work 7 days 12/11/2018 19/11/2018
G.F Slan Shuttering Works 10 days 20/11/2018 30/11/2018
G.F Re bar binding Works 7 days 1/12/2018 7/12/2018
G.F Re casting Works 1 days 8/12/2018 8/12/2018
1st floor column re bar binding 2 days 9/12/2018 10/12/2018
1st floor column Shuttering work 3 days 11/12/2018 13/12/2018
FEP Shulakhali Khaza
341 Ahmed 1st floor column Casting Work 1 days 14/12/2018 14/12/2018
1st floor column re bar binding 2 days 15/12/2018 16/12/2018
1st floor column Shuttering work 3 days 17/12/2018 20/12/2018
1st floor column Casting Work 1 days 21/12/2018 21/12/2018
1st floor Slab Shuttering work 10 days 22/12/2018
1st floor Slan re bar binding 10 days
1st floor Slab Casting Works 1 days
Tubewall boring Work 16 days 12/11/2018 27/11/2018
G.F Slan Shuttering Works 10 days 28/11/2018 7/12/2018
G.F Re bar binding Works 10 days 8/12/2018 17/12/2018
G.F Slab Casting Works 1 days 18/12/2018 18/12/2018

FEP Ragunathpur
292 KaisarRaihan
1st floor column re bar binding 2 days 19/12/2018 20/12/2018
1st floor column Shuttering work 3 days 21/12/2018 23/12/2018
FEP Ragunathpur
292 KaisarRaihan 1st floor column Casting Work 1 days 24/12/2018 24/12/2018
1st floor column re bar binding 2 days 25/12/2018 26/12/2018
1st floor column Shuttering work 3 days 27/12/2018 29/12/2018
1st floor column Casting Work 1 days 30/12/2018 30/12/2018
1st floor Slab Shuttering work 10 days 31/12/2018
1st floor Slan re bar binding 10 days
1st floor Slab Casting Works 1 days
Road construction work on goi 10 days 12/11/2018 22/11/2018
Piling Works 39 days 23/11/2018 31/12/2018
33 nos Base Rod+ Shuttering + Ca 20 days
Sand filling work 3 days
G.B shuttering Work 5 days
G.B Re bar binding Work 6 days
G.B Casting Work 1 days
Ramp Shuttering Work 5 days
Ramp Re bar binding Work 3 days
FEP Daskhin Purbo Ramp Casting Work 1 days
309 Char Chandia Tubewall boring Work 16 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days
G.F Slan Shuttering Works 10 days
G.F Re bar binding Works 10 days
G.F Casting Works 1 days
33 nos Base Rod+ Shuttering + Ca 20 days 12/11/2018 2/12/2018
Sand filling work 10 days 3/12/2018 13/12/2018
G.B shuttering Work 10 days 14/12/2018 24/12/2018
G.B Re bar binding Work 6 days 24/12/2018 30/12/2018
G.B Casting Work 1 days 31/12/2018 31/12/2018
FEP Uttar Paschim Ramp Shuttering Work 5 days
324 Char Darbesh Ramp Re bar binding Work 3 days
Ramp Casting Work 1 days
Tubewall boring Work 16 days
G.F column re bar binding 2 days
G.F Column Shuttering Works 3 days
G.F Column Casting Works 1 days

(Engr. Mahamudul Hasan)


Project Engineer.
SS-AE JV
Remarks

Slab Casting

1st Lift

2nd Lift

Slab Casting

Slab Casting

1st Lift

2nd Lift

4 nos

Slab Casting
1st Lift

2nd Lift
Multipurpose Disaster Shelter Project
Work Plan Report of feni,Chagalnaiya,Parshuram,Daganbhuiyan (NW-2)
12 November 2018 to 31 December 2018
SheltShelter/GP Project Summary Duratio Start Date Finish Date Remarks
1st floor shuttering Work 8 days 12/11/2018 20/11/2018
1st floor Re bar binding 10 days 21/11/2018 30/11/2018
1st floor Casting Work 1 days 1/12/2018 1/12/2018 Slab Casting
2nd floor column re bar bi 2 days 2/12/2018 4/12/2018
2ndColumn Shuttering W 3 days 5/12/2018 7/12/2018 1st Lift
2nd Column Casting Work 1 days 8/12/2018 8/12/2018
FEP Purbo
Pathannogor 2nd floor column re bar bi 2 days 9/12/2018 10/12/2018
014 Gps 3 days 11/12/2018 13/12/2018 2nd Lift
2nd Column Shuttering W
2nd Column Casting Work 1 days 14/12/2018 14/12/2018
2nd floor Slan Shuttering 10 days 15/12/2018 25/12/2018
2nd floor Re bar binding 10 days 26/12/2018
2nd floor Casting Works 1 days

G.F shuttering Work 10days 12/11/2018 24/11/2018


G.F Re bar binding Work 10 days 25/11/2018 4/12/2018
G.Fslab Casting Work 1 days 5/12/2018 5/12/2018 Slab Casting
1st floor column re bar bi 2 days 6/12/2018 8/12/2018

3 days 9/12/2018 11/12/2018 1st Lift


1st Column Shuttering W
FEP 1 days 10/12/2018 10/12/2018
Bathania Gps 1st Column Casting Works
015 1st floor column re bar bi 2 days 11/12/2018 13/12/2018
1st Column Shuttering Wo 3 days 14/12/2018 16/12/2018 2nd Lift
1st Column Casting Works 1 days 17/12/2018 17/12/2018
1st floor Slan Shuttering 10 days 18/12/2018 28/12/2018
GF 10 days 29/12/2018
1st floor Casting Works 1 days
FEP 2nd/Roof Slab Rebar bind 10days 12/11/2018 24/11/2018
020 Uttat Jashpur 01 days 25/11/2018 25/11/2018
Gps 2nd/Roof Slab casting wor Slab Casting
Brick wall & plastering Wo 35 days 26/11/2019 31/12/2018
Sand filling work 8 days 12/11/2018 20/11/2018
G.B Shuttering Works 10 days 21/11/2018 30/11/2018
G.B Re bar binding Works 5 days 1/12/2018 5/12/2018
G.B casting Works 1 days 6/12/2018 6/12/2018
GF floor column re bar bin 2 days 7/12/2018 8/12/2018
FEP Protappur Gps GF Column Shuttering Wo 3 days 9/12/2018 11/12/2018 1st Lift
077
GF Column Casting Works 1 days 12/12/2018 12/12/2018
GF floor column re bar bin 2 days 13/12/2018 14/12/2018
GF Column Shuttering Wo 2days 15/12/2018 16/12/2018 2nd Lift
Protappur Gps
077

2nd Lift
GF Column Casting Works 1 days 17/12/2018 17/12/2018
GF floor Slan Shuttering 10 days 22/12/2018
2nd/Roof Slab Rebar bind 10days 12/11/2018 24/11/2018
FEP21 Malipathar 01 days 25/11/2018 25/11/2018
7 Gps 2nd/Roof Slab casting wor Slab Casting
Brick wall & plastering Wo 35 days 26/11/2019 31/12/2018
2nd Column Casting Work 1 days 15/11/2018 15/11/2018 1st Lift
2nd floor column re bar bi 2 days 16/11/2018 18/11/2018
2nd Column Shuttering W 3 days 19/11/2018 21/11/2018 2nd Lift
FEP33 Char luxmiganj 2nd Column Casting Work 1 days 22/11/2018 22/11/2018
3 Gps 2nd floor Slan Shuttering 10 days 23/11/2018 3/12/2018
2nd floor Re bar binding 10 days 4/12/2018 14/12/2018
2nd floor Casting Works 1 days 15/12/2018 15/12/2018 Slab Casting
Brick wall & plastering Wo 35 days 16/12/2018
(Engr.Mahamudul Hasan)
Project Engineer.
SS-AE JV
DHAKA CITY NEIGHBORHOOD UPGRADING PROJEC
Contract Package No. DCNUP/W-07/LAL
Safety Equipment for Covid-19
ITEMS Quantity

(Engr.Amlan Saha Antu)


Project Manager.
SSECL-AB JV
IGHBORHOOD UPGRADING PROJECT (DCNUP)
Contract Package No. DCNUP/W-07/LAL
Safety Equipment for Covid-19