Академический Документы
Профессиональный Документы
Культура Документы
Keywords: Social Cost Benefit Analysis-UNIDO Approach, Coal Plant, Hydro Plant, Power
Project
Abstract:
Capital is the limited resource in a developing economy like India and must be invested with
utmost care. While a private individual investor is not expected to be an altruistic seeker of
only national interest, he must be motivated by commercial return on his investment. It is also
true that development financial institutions of country must examine social cost benefit
implication of their investment decisions. Social cost benefit analysis is an appraisal tool to
evaluate a project from the view point of the society as a whole. It refers to the analysis of the
costs and/or the benefits that a society may have to bear and/or get from the proposed project.
It is a study of feasibility of a project in terms of its total economic cost and total economic
benefits. The paper analyses the application of Social Cost Benefit Analysis using UNIDO
approach on thermal coal based power plant and a hydro power plant and tries to highlight
the social costs and benefits associated with each project. It also focuses on the comparative
analysis of the coal and hydro projects. The paper suggests the key steps that can be taken to
make the projects more lucrative.
1. Introduction
Social Cost Benefit Analysis (SCBA) is also referred as Economic Analysis (EA). SCBA or
EA is a feasibility study of a project from the viewpoint of a society to evaluate whether a
proposed project will add benefit or cost to the society. That is, it is an approach that is
concerned to judge the economic and social viability of a project especially public
expenditure project or donor-led programs.
SCBA model is based on the theory of welfare economics, according to which the welfare of
a society depends on the aggregate individual utility levels of all members of that society.
SCBA had, at first, used for evaluating public investments in the decade of 1960s and 1970s.
In those decades, this model had got a good emphasis; because public investments in many
countries, especially in developing countries, were immensely increased. Nowadays, SCBA
is also becoming important for private project or investment as more often there is a
possibility for this kind of projects to bring adverse impact to the society.
In the context of planned economies, SCBA aids in evaluating individual projects within the
planning framework which spells out national economic objectives and broad allocation of
resources to various sectors. In other words, SCBA is concerned with tactical decision
making within the framework of broad strategic choices defined by planning at the macro
level. The perspectives and parameters provided by the macro level plans serve as the basis of
SCBA which is a tool for analyzing and appraising individual projects.
As an aid to planning, decision-making, evaluation and control, the social cost benefit
analysis provides a scientific and quantitative base for the appraisal of projects with a view to
determine whether the total social benefits of a project justify the total social costs.
The need for a scientific social cost benefit analysis arises because of the fact that the criteria
used for measuring commercial or trading profitability that normally guide capital budgeting
in the private sector investing projects may not be appropriate for public or social (macro)
projects investment decisions. Private investors are most interested in minimizing private
costs and hence they take into consideration only those elements or costs which directly
affect their private earnings i.e. the private expenses and private benefits. Both private
earnings and private costs are valued at the prevailing market prices for al accounting
purpose. But the existence of externalities i.e. the social costs and social benefits introduces
bias in the market price based investment decisions.
To make a scientific and systematic social cost benefit analysis of projects, it is necessary to
weigh each project’s advantages (benefits) and disadvantages (costs) to the society or nation
as a whole. Thereafter, various projects under consideration are ranked on the basis of social
cost benefit ratio and the final decision about the selection of a project is taken based on the
score in ranking. In other words, a social costs benefit analysis is a vital tool for comparing
economic alternatives.
In general, any project appraisal must distinguish between three components: Financial,
Economic, and Social Appraisal.
a. Financial Appraisal examines the financial flows generated by the project itself,
and the direct costs of the project measured at market prices.
b. Economic Appraisal adjusts costs and benefits to take account of costs and
benefits to the economy at large, including the indirect effects of the project that are
not captured by the price mechanism.
Cost Benefit Analysis can only perform the financial appraisal wholly for evaluating a
project. In some instances, it can adjust costs and benefits to the economy except
environmental externalities. But in case of social appraisal, it is fully incapable to do so. On
the other hand, SCBA is able to perform all of these three appraisals to judge a project.
CBA determines all costs and benefits of a project in terms of market price. But in imperfect
market, market price can not reflect social value. That’s why; SCBA quantifies all social cost
and benefits of a project at shadow price instead of market price. In addition, typically CBA
uses consumer surplus to compute benefits and costs. But SCBA determine those in terms of
either consumption or uncommitted social income. In fine, it can be said that CBA often
produces inferior results in terms of both environmental protection and overall social welfare
in comparison to SCBA.
In SCBA the focus is on the social costs and benefits of the project. These often tend to differ
from the monetary costs and benefits of the project. The principal sources of discrepancy are:
• Market Imperfection
• Taxes and Subsidies
• Concern for Savings
• Concern for redistribution
• Merit Wants
Market Imperfections
Market prices, which form the basis for computing the monetary costs and benefits
from the point of view of the project sponsor reflect social values only countries.
When imperfections exist, market prices do not reflect social values.
Rationing of a commodity means control over its price and distribution. The price
paid to labor is usually more than what the wages would be in a competitive labor
market free from such wage legislations. The official rate of foreign exchange in
developing countries, which exercise close regulation over foreign exchange, is
typically less than the rate that would prevail in the absence of exchange regulations.
Taxes Subsidies
From the private point of view, taxes are definite monetary costs and subsidies are
definite monetary gains. From the social point of view, however, taxes and subsidies
are generally regarded as transfer payments and hence considered irrevalant.
Unconcerned about how its benefits are divided between consumption and savings, a
private firm does not put differential valuation on savings and consumption and
savings (which leads to investment) is relevant, particularly in the capital-scarce
developing countries. A Rs of benefits saved is deemed more valuable than a Rs of
benefits consumed. The concern of the society for savings and investment is duly
reflected in SCBA where in a higher valuation is placed on savings and a lower
valuation is put on consumption.
A private firm does not bother how its benefits are distributed across various groups
in the society. The society, however, is concerned about the distribution of benefits
across different groups. A Rs of benefit going to an economically poor section is
considered more valuable than a Rs of benefit going to an affluent section.
Merit Wants
Goals and preferences not expressed in the market place, but believed by policy
makers to be in the larger interest, may be referred to as merit wants. For example, the
government may prefer to promote an adult education programme or a balanced
nutrition programme for school-going children even though these are not sought by
consumers in the market place. While merit wants are not relevant from the private
point of view, they are important from the social point of view.
The objective of social cost-benefit analysis is, in its widest sense, to secure and achieve the
value of money in economic life by simply evaluating the costs and benefits of alternative
economic choices and selecting an alternative which offers the largest net benefit. Therefore,
it can be said that the main focus of Social Cost Benefit Analysis i to determine:
1. Economic benefits of the project in terms of a price (shadow price) that reflect
social value;
2. The impact of the project on the level of savings and investments in the society;
3. The impact of the project on the distribution of income in the society;
4. The contribution of the project towards the fulfilment of certain merit wants (self-
sufficiency, employment etc).
2. Methodology
The UNIDO Approach for Social Cost Benefit Analysis as prescribed by United Nation
Industrial Development Organization (UNIDO) was applied to a thermal coal based power
plant and a hydro plant.
The United Nation Industrial Development Organization (UNIDO) and the Centre for
Organization of Economic Co-operation and Development (COECD) have come with useful
publications dealing with the problem of measuring social costs and social benefits. It may be
noted, in this context, that the actual cost or revenues from the goods and/or services to the
organization do not necessarily reflect the monetary measurement of the cost ant or benefit to
the society. This is because these figures are grossly distorted on account of restriction and
controls imposed by the government. Hence a different yardstick has to be used for
evaluating a particular in terms of cost and sacrifice on the part of the society. Such payments
are easily valued at opportunity cost or shadow prices to judge their real impact in terms of
cost to society for the purpose of social cost benefit evaluation.
A good technical and financial analysis must be done before a meaningful economic
evaluation can be made. For this reason, financial profitability is a prerequisite in all cases.
Financial profitability produces an estimate of the project’s financial profit or the net present
value of the project when all inputs and outputs are measured at market prices. The first step
in stage one is to complete standard tables of income statement, balance-sheet and cash-flow.
The financial income statement is the central table in this analysis as it is used to record the
inputs and outputs of the project. Cash flow statement is also important here as the financial
income statement only shows the annual profit and disguise investment. The net cash flow is
derived from the financial income statement by standard accounting procedures and is equal
to the gross cash flow (operating profit before interest and taxes plus allowances for
depreciation) minus capital investments.
2.1.2 Obtaining the Net Benefit of the Project Measured in Terms of Economic Prices
Stage two of the UNIDO approach is concerned with the determination of the net benefit of
the project in terms of economic prices, also referred to as shadow prices.
Market prices represent shadow prices only under conditions of perfect markets which are
almost invariably not fulfilled in developing countries. Hence, there is a need for developing
shadow prices and measuring net economic benefit in terms of these prices.
2.1.3 Adjustment for the Impact of the Project on Savings and Investment
Most of the developing countries face scarcity of capital. Hence, the governments of these
countries are concerned about the impact of a project on savings and its value thereof. Stage
three of the UNIDO method, concerned with this, seeks to answer the following question:
• Given the income distribution impact of the project what would be its effects on
savings?
• What is the value of such savings to the society?
Impact on Savings
∑ Δ Yi MPSi
Where Δ Yi is the change in income of group i as a result of the project, and MPSi is
the marginal propensity to save of group i.
Determination of Weights:
If there are only two groups in a society, poor and rich, the determination of weight is
just an iterative process between the analysts (at the bottom) and the planners (at the
top). This is called “bottom-up” approach. When more than two groups are involved,
weights are calculated by the elasticity of marginal utility of income. The marginal
utility of income is the weight attached to an income is
Wi = (b/ci)n
2.1.5 Adjustment for the Impact of the Project on Merit Goods and Demerit Goods
3. Application
The UNIDO Approach was applied to a thermal coal based power plant and a hydro plant.
Table 3.1.1 presents the estimates of revenue collected by the project during its lifetime.
3.1.2 Obtaining the Net Benefit of the Project Measured in Terms of Economic Prices
Social Benefits:
The major benefit of setting up this Thermal Power Plant would be the
establishment of fly ash bricks manufacturing that will lead to creation of
employment opportunities for unskilled and skilled workers. Also, after the ban on
manufacturing of Red Bricks as per the mandate of Hon’ble Supreme Court, fly
ash bricks will be used for construction purpose going forward.
The use of fly ash in manufacturing of fly ash bricks would lead to reduction in
waste disposal costs and environmental costs as plant residue can be reused.
The total project workforce is estimated to peak at 1,700 during the 5-year
construction period and additional employment of about 100 workers per fly ash
manufacturing plant will be generated. This labor will be otherwise unemployed
or under employed in the Indian economy.
The project provides employment benefits to the skilled labor during its
operational period.
By indulging in coal washing process, the ash content in Indian coal can be
reduced significantly, which will lead to reduction in residue/ash produced in a
plant. Thus, the cost of electricity would increase marginally but there will be
huge environmental benefits. Also, currently only 4% of coal in India is washed
by Coal India.
Social Costs:
Coal sludge, also known as slurry, is the liquid coal waste generated by washing
coal. It is typically disposed of at impoundments located near coal mines, but in
some cases it is directly injected into abandoned underground mines. Since coal
sludge contains toxins, leaks or spills can endanger underground and surface
waters.
Increased costs of power to end consumers due to rising fuel and coal costs.
Table 3.1.2 shows the Operation and Maintenance (O&M) cost of the project in terms of
shadow (economic) prices.
Table 3.1.3 presents the estimates of revenue collected by the project during its lifetime after
taking into account net social benefits and costs.
The NPV calculation was done after doing below mentioned adjustments for social costs and
social benefits:
The health costs of workers amounting to Rs. 8 crores will be incurred during the
construction phase of the project.
The O&M cost components i.e. spares, salaries and other expenses were multiplied by
factor of 1.1, 0.8 and 1 to convert into corresponding components in shadow prices.
The water availability costs were also taken into account.
The Carbon, SO2, NO2 emissions of the plant are well below the global baseline
emission standards for a thermal plant, thus, the emission reduction savings have been
added as revenues.
Another important new revenue source for NTPC will be the revenue from selling fly
ash to brick manufacturers as after the ban on red bricks for construction purposes, fly
ash bricks will be used for construction and NTPC will earn revenue of about Rs. 500
per tonne of fly ash.
NPV of the project after Stage 2 turns out to be Rs. 120.51 crores. This shows that after taking
into account the net social benefits and costs, it is worthwhile to take up the project as NPV is
positive.
3.1.3 Adjustment for the Impact of the Project on Savings and Investment
Government
NTPC
Labor
Table 3.1.4 gives the calculation of saving impact on the above mentioned stake holders
I = r(1-a)/(k-ar)
Where,
The value of I used in this study is 1.55, which is taken from the study done by Murty (1980)
in which he has explored the problems related to the evaluation of income distributional
effects of public investment projects.
Therefore,
Net saving impact in terms of shadow prices is:
= Total savings × I
= 1241.05 × 1.55
= Rs. 1923.62 crores
Thus, the NPV after taking into account the savings impact turns out to be Rs. 2044.14
crores.
Now, distributing the difference in income over the life of the plant i.e. 25 years, we get
present value of income to be adjusted which turns out to be Rs. 259.33 crores.
Table 3.1.7 gives the Calculation of NPV after Income Distribution Impact
Adjusted NPV
NPV from Stage 3 Rs. cr 2044.14
Income distribution Impact Rs. cr -259.33
New NPV of the project Rs. cr 1784.81
Thus, the NPV after Income Distribution Impact turns out to be Rs 1784.81 crores.
3.1.5 Adjustment for the Impact of the Project on Merit Goods and Demerit Goods
The adjustment factor turns out to be 0.39. This shows that social value of the project exceeds
its economic value by 39%.
Thus, the final NPV of the project after application of Social Cost Benefit Analysis turns out
to be Rs. 2480.68 crores. Hence, the project should be undertaken as it has multiple social
benefits which are reflected in the final positive NPV of the project.
3.2 Application of UNIDO Approach on Hydro Plant
Table 3.2.1 presents the estimates of revenue collected by the project during its lifetime.
Year Revenue Year Revenue Year Revenue Year Revenue (Rs. Cr)
The calculation of NPV at market prices for the Thermal based Coal Power Plant turned out
to be Rs. -594.23 crores, therefore as per financial evaluation of the project since NPV is
negative, project should not be undertaken.
3.2.2 Obtaining the Net Benefit of the Project Measured in Terms of Economic Prices
Social Benefits:
The major benefit of setting up this Hydro Power Plant would be the creation of
employment opportunities for unskilled and skilled workers.
The total project workforce is estimated to peak at 2,600 during the 7-year
construction period and about 8,200 additional people (project workforce, service
people, and families) will be residing in the valley during construction. This labor
will be otherwise unemployed or under employed in the Indian economy.
The project provides employment benefits to the skilled labor during its
operational period.
The 2,353 GWh of electricity to be generated each year by the Project will offset
the electricity now generated from other sources.
According to the CERC’s database on CO2 emissions in the Indian power sector,
the combined margin for the Northern grid is 0.75 ton of CO2 emissions per MWh
(based on a 75:25 mix of thermal power to hydropower generation). The CO2
emission reduction from the above Project is estimated to be 1.756 million MT per
year. In addition, the Project is expected to offset the emission of 73.87 MT/day of
SO2 and 37.47 MT/day of NOx, given the emissions from an equivalent amount
of electricity generated from the NTPC Sipat Thermal Power Plant, a modern
coal-fired plant.
Social Costs:
Rehabilitation costs.
Table 3.2.2 shows the Operation and Maintenance (O&M) cost of the project in terms of
shadow (economic) prices.
Year Cost Year Cost Year Cost Year Cost (Rs. Cr)
Table 3.2.3 presents the estimates of revenue collected by the project during its lifetime after
taking into account net social benefits and costs.
Year Revenue Year Revenue Year Revenue Year Revenue (Rs. Cr)
3.2.3 Adjustment for the Impact of the Project on Savings and Investment
Government
NTPC
Labor
Table 3.2.4 gives the calculation of saving impact on the above mentioned stake holders
I = r(1-a)/(k-ar)
Where,
The value of I used in this study is 1.55, which is taken from the study done by Murty (1980)
in which he has explored the problems related to the evaluation of income distributional
effects of public investment projects.
Therefore,
Net saving impact in terms of shadow prices is:
= Total savings × I
= 1241.05 × 1.55
= Rs. 1923.62 crores
Table 3.2.5 gives the calculation of NPV at Stage 3
Thus, the NPV after taking into account the savings impact turns out to be Rs. 5432.86
crores.
Net Impact
Stakeholder Income (Rs. cr) Weight (Rs. cr)
Workers (Unskilled) 10.33 1.00 10.33
Government 4469.39 0.000203755 0.91
Project 1033.27 0.001583264 1.64
Total Net Income Impact Rs. cr 12.87
The average annual income turns out to be Rs. 35.07 crores from the cash flows obtained in
Stage 2. The total net income impact is Rs. 12.87 crores. So, the difference in income turns
out to be Rs. 22.20 crores.
Now, distributing the difference in income over the life of the plant i.e. 35 years, we get
present value of income to be adjusted which turns out to be Rs. 147.93 crores.
Table 3.2.7 gives the Calculation of NPV after Income Distribution Impact
Adjusted NPV
NPV from Stage 3 Rs. cr 5432.86
Income distribution Impact Rs. cr -147.93
New NPV of the project Rs. cr 5284.93
Thus, the NPV after Income Distribution Impact turns out to be Rs 5284.93 crores.
3.2.5 Adjustment for the Impact of the Project on Merit Goods and Demerit Goods
The adjustment factor turns out to be 0.41. This shows that social value of the project exceeds
its economic value by 41%.
Thus, the final NPV of the project after application of Social Cost Benefit Analysis turns out
to be Rs. 7457.95 crores. Hence, the project should be undertaken as it has multiple social
benefits which are reflected in the final positive NPV of the project.
4 Comparative Analysis
10 Govt. Savings of
8 Unemployment
6 allowances
4
2
0
Coal Plant Hydro Plant
300
Coal Plant
Rs. Crores
200
Hydro
100 Plant
0
Carbon Emission SO2 Emission NO2 Emission
Reduction Reduction Reduction
It is clearly evident from above graph that emission reductions are more in case of hydro
plant as compared to coal based power plant. The above graph supports the obvious fact that
since Carbon, SO2, NO2 emissions are negligible for a hydro plant, thus, the reduction
savings are more pronounced in a hydro plant. It can also be seen that in case of coal plant the
emission reduction savings are positive and quite significant as the coal plant emissions are
well below the specified threshold emission levels given by international standards for a
thermal plant. Also, NTPC can make use of reduced emissions from above plants in the form
of emission reduction certificates that can be tradeoff with plants whose emissions are above
threshold level, thereby adhering to emission norms in totality.
Year
Fig. 6.9 Trends for Employment Generation for Workers
The above graph shows the trends of employment generation for hydro plant and coal
plant. It can be seen from the above graph that hydro plant generates employment only during
the construction phase of the project while coal plant will be able to generate employment
even after the construction of the plant by means of manufacturing of Fly Ash bricks thereby
reducing the unemployment in the society and the unemployment will further reduce as in our
case the employment generation calculation has been done for a single coal plant.
Impact on Savings:
Impact on Savings
3000.00
2500.00
Rs. Crores
The graph shows the impact on savings for Government and NTPC. It can be seen that
construction of Hydro project will lead to more income in the hands of the Govt. and
consequently more savings for Govt. as compared to coal plant which increases the savings
of the Govt. by a marginal amount only. On the other hand, coal plant adds more to the
savings of NTPC, so coal project is more desirable from NTPC’s point of view. Thus, impact
on savings yields net gains for both the stakeholders i.e. Government and NTPC for Hydro as
well as Coal project
20.00
Plant
15.00
9.32 Coal Plant
10.00
5.00
0.00
Workers
Hydro Plant
6.00
4.00 Coal Plant
2.00
0.00
Workers (Unskilled) Government NTPC
The graph shows the income distribution impact on key stakeholders. It can be seen from the
graph that there are net gains in income to all the stakeholders – Government, NTPC and
Workers from both the plants, but the income re-distribution is more pronounced for workers
in case of hydro project which is more desirable as income re-distribution concept aims at
maximizing the benefits to the weaker income group of the society. So, hydro project is more
desirable as it leads to more income re-distribution to workers.
Social Cost Benefit Analysis is an important tool for analyzing a project to reflect its positive
and negative impact on the society. Today, it has expanded to evaluation of private projects
as they are much more responsible for good and bad effects on the society. SCBA differs
from financial analysis in the sense that it avoids market price and adopts shadow price to
value the inputs and outputs of a project.
There are two good approaches, viz., UNIDO approach & L-M approach for Social Cost
Benefit Analysis of a project. Practically, these methods are not widely used by private
sectors. The logic behind the appraisal criterion is to select those projects for which the
country’s resources are more appropriate. Thus, the decisions regarding capital allocation
should be taken with regard to Rule Utilitarian approach i.e. maximizing benefits to people
(various stakeholders) at large as businesses cannot strive on profit motives for long term. It
is high time that businesses should align their strategies in line with the needs of the
community in order to foster long term sustainability of the business.
The stage wise application of UNIDO approach to coal plant and hydro plant showed that net
savings impact, net income re-distribution impact are positive for the key stakeholders i.e.
Government, Workers and Project (NTPC) identified for the project. This shows that both the
projects result in net gains to all the stakeholders. Also, electricity is a merit good, so its
social value exceeds its economic value. During the project study it was found that social
value of coal plant exceeded its economic value by 39% and that in case of hydro plant was
about 40%. Hence, it is evident from these figures that these projects are socially viable and
net social benefits will be accrued to the stakeholders.
The study shows that both the plants are improving the demographic factors namely –
savings, income distribution, employment generation. It can be seen from above SCBA
calculations of the plants that both the plants will lead to significant employment generation
with coal plant leading to sustained employment generation even after the commissioning of
the plant. The study has also thrown light on certain factors that will lead to more efficiency
such as coal washing in case of thermal plants that will reduce the ash content in domestic
coal from 40% to 10%, which will lead to reduced coal consumption in thermal plants and
consequently lower tariffs for the end user.
After applying UNIDO approach on the coal and hydro plants respectively, it can be seen that
rejecting the project on the basis of its financial viability is not justified as it is evident from
above results that incorporation of social cost benefit analysis mechanism yields positive
results (NPV) for both the projects i.e. coal plant and hydro plant. Thus, taking into account
the social costs and social benefits associated with the project plays a key role in project
assessment as needs and wants of community at large can’t be ignored.
Table 7.1 below shows the comparative analysis on key demographic factors for both coal
and hydro plants.
Table 7.1: Comparative Analysis of Key Factors for Coal and Hydro Plant
Employment Generation Benefit Rs. 6.93 cr. Benefit Rs. 10.33 cr.
Income Distribution Impact Benefit Rs. 8.82 cr. Benefit Rs. 12.87 cr.
The Social Cost Benefit Analysis of coal and hydro projects has reveals that these projects
are socially viable and net social benefits will be accrued to the stakeholders.
Suggestions
Social Cost Benefit Analysis should be a part of project assessment for projects whose
merit needs are more i.e. whose social value exceeds the economic value for instance,
electricity.
By determining the social costs and benefits of above said socially viable projects,
companies can eventually land up with low interest rate finance for the project.
Coal Washing should be made mandatory for Coal India as currently only 4% of total
domestic coal is washed by Coal India. This will lead to reduced ash content thereby
leading to reduced coal consumption in thermal plants and reduced tariffs for end
consumers.
NTPC should go for manufacturing fly ash bricks at their thermal plant sites or could
sell the fly ash produced to the fly ash brick manufacturers thereby leading to efficient
utilization of ash and generation of employment.
NTPC should look out for efficient methods for reducing water consumption in
thermal plants. For instance, using dry or hybrid cooling technologies in place of
traditional wet cooling towers would reduce the water consumption by about 30% -
40%.
Wet ash handling through slurry should be shifted to dry ash handling by use of
‘hydro bins’ where water is separated from the ash slurry within the plant and the dry
lumps are conveyed to the ash dykes through conveyer belts. This would significantly
reduce the amount of water consumed in ash handling units.
Government and power generation companies like NTPC should make some attempts
towards enhancement of the hydro power projects as India has a hydro potential of
about 1,48,701 MW of which only 25% i.e. 36878 MW has been utilized so far.
Wastewater should be treated and recycled to achieve zero discharge and savings on
freshwater intake.
Shadow prices of the inputs and the outputs used in the projects should be
benchmarked so as to avoid flaws and biasness in the calculation of the economic
costs and benefits.
References
1. Chandra, Prasanna, (2006), Project: Planning, Analysis, Financing, Implementation,
and Review, 7/e, Tata McGraw-Hill Publishing Co. Limited, New Delhi, Chapter 14.
2. Tevfik F. Nas, (2001), Cost-Benefit Analysis: Theory and Application, 1/e, Sage
Publications, New Delhi, Chapter 4
5. R. B. Khanna, (2011), Project Management, PHI Learning PVT. Ltd., New Delhi
6. Environmental Assessment Report 2007 Prepared by NTPC Limited for the Asian
Development Bank (ADB).
7. Social Cost-Benefit Analysis—The Kansas City Light Rail Project by Sudhakar Raju,
Rockhurst University.
10. Social and Environmental Impacts of a Mini-hydro Project on the Ma Oya Basin in
Sri Lanka Bhadranie Thoradeniya, Malik Ranasinghe and N T S Wijesekera,
Department of Civil Engineering, University of Moratuwa, Moratuwa , Sri Lanka.
12. The Energy And Resources Institute (TERI) (2012), Enhancing Water-Use Efficiency
Of Thermal Power Plants In India: Need For Mandatory Water Audits