Академический Документы
Профессиональный Документы
Культура Документы
The 13th of May, 1861 was historical day when the first railway line
was opened for public traffic between Karachi City and Kotri, a
distance of 169 Kms. By 1897 the line from Keamari to Kotri was
converted to double track.
1
In 1885, the Sindh, Punjab and Delhi Railways were purchased by
the Secretary of State for India. On 1st January, 1886 this line and
other State Railways (the Indus Valley, the Punjab Northern,
inclusive of Sindh Sagar Eastern section, and the Kandahar or
Sindh-Pishin Southern section) were integrated and North
Western State Railway was formed; which was later on renamed as
North Western Railways
2
Organization:
Pakistan Railways is a Federal Government Department under
Ministry of Railways. The Secretary for Ministry of Railways is the
ex-officio Chairman of the Railway Board.
5
CHAPTER-I
Operating Unit
A. Infrastructure:
The unit is headed by the Additional General Manager Infrastructure.
who is assisted by the following head of Departments.
2. Chief Engineer Open Line.
3. Chief Engineer Survey and Construction.
4. Chief Engineer Design.
5. Chief Engineer Signal.
6. Chief Engineer Telecommunication.
7. Director Property and Land.
6
* Total track length = 11778 Kms
* Bridges = 13841 Nos.
* Level Crossings = 3949 Nos.
* Unmanned = 2540 Nos.
* Manned = 1409 Nos.
b) Buildings
Pakistan Railways has vast infrastructure comprising service
and residential buildings scattered all over the country. There
are 70100 residential buildings which include 67939 staff
quarters, 1809 houses for senior scale officials and 423
officer’s residences. Service buildings which include Stations,
Schools, Hospitals, Offices, Stores/Sheds, Workshops, Rest
Houses and Running Rooms etc., occupy an area of 25.807
million Sft.
7
c) Bridges
There are 13841 bridges including 532 major and 13309 minor
over the system. Most of the bridges were constructed when
Railway system was introduced in the subcontinent in 1870.
Due to dedicated inspection and regular maintenance, bridges
are generally in satisfactory condition for safe train operation.
Bridges which require major repair or rehabilitation are being
attended through different projects. Rehabilitation of
17-bridges has been included in Track Rehabilitation Project
of Khanpur-Lodhran section at cost of Rs. 309.975 Million.
13-bridges are being rehabilitated in the Project of 87-KM on
Lodhran-Sahiwal section at cost of Rs.44.71 Million.
Similarly, 96 bridges are being repaired/rehabilitated
including protection works through Project of Rehabilitation
of Flood Damages at the anticipated cost of Rs. 1432 Million.
Bridge Rehabilitation Project of 159 bridges at an anticipated
cost of Rs. 412.00 Million is in progress, out of which 60-
bridges have been completed so far.
8
2. Doubling of Track from Khanewal to Raiwind (246 Kms)
PC-I amounting to Rs.5.497 Billion was approved by the ECNEC,
for doubling of track from Khanewal to Raiwind (246 KMs) on
04-08-2005.The same was subsequently revised to Rs.8.326
Billion on 12-11-2007 and then to Rs. 12.617 Billion on
26-5-2011. The work on this project was commenced during
the financial year 2005-06. The section from Khanewal to
Sahiwal (119 KM) was completed and opened for traffic on 17-
09-2011, which was further extended for 28 KM. Upto Okara
and opened for train on 30-12-2013. Another section from
Raiwind to Bhoe Asal (22 Km) was also completed and the
same was opened for traffic on 12-09-2012. The work on
remaining section is expected to be completed by 31-12-2014.
Benefits:
On completion of this project, Karachi to Lahore will be
connected through double track. Sectional capacity will
increas from 18 to 34 trains per day. The journey time from
Lahore to Karachi will be reduced by one hour for
mail/express trains and seven hours for freight trains.
B) Future Projects:
1. Doubling of Track from Lalamusa to Chaklala (including
Realignment of Track from Kalowal to Pindora)
* Total Length 152 Km.
* Cost of the Project Rs. 39111 Million
* Completion period 03 years
* PC-I PC-I submitted to Planning
Commission by Ministry of
Railway.
10
2. Feasibility study for construction of new rail link from
Islamabad to Muzaffarabad via Murree. This study has been
taken in hand on the directives of Prime Minister of Pakistan.
Design Department:
Pakistan Railway Design Office was established in the year 2002,
with the objective of redefining old design codes to facilitate the
effective and efficient integration of newly acquired Technologies
into the existing codes, design & rules and to design new bridges.
The Design Office has provided all the necessary skill and
knowhow for implementation of new development projects, besides
providing support services to the field staff, for the rehabilitation and
up-gradation of the existing infrastructure. The tasks which design
office is performing are as under:-
11
(iv) Development of standards of design for different type of
structures like R.C. Box Culverts, R.C. Slabs Retaining Walls
so as to provide a quick design for its construction/execution
in the field especially in projects like Doubling of Track, Road
over Bridge Project Karachi, Bridge Rehabilitation, Track
Rehabilitation etc.
12
There are 123 stations equipped with non-interlocked mechanical
signaling, 185 stations with Standard-I, 20 stations with Standard-II
217stations with Standard-III Mechanical Signaling, whereas 40
stations are equipped with All Relay Interlocking. Auto block
signaling is provided on 160 Kms double line section between
Landhi and Hyderabad and Centralized Traffic Control on 24 Kms
section between Karachi Cantt and Landhi.
13
stop automatically, in case, the Driver does not apply brake while
approaching red signal. Most of the civil works, cable works and
provision of electric connections have been completed and ready
for handing over to the Consortium. After completion of the project,
the line capacity, efficiency, safety and punctuality of train shall be
enhanced manifold. The project is expected to be completed by
31-03-2016.
(B) Organization
Project Director/Signal Rehabilitation is co-ordinator of the
following units:
1. CME / Locomotive
2. CME / C&W
3. CEN / Open Line (Civil Works)
4. Dy: CEN / Track
5. PD / Signal Rehabilitation
6. CEN / Telecom
1. 65 station buildings
2. 35 Nos. Locomotives
3. 39 Nos. Coaches
4. 02 Nos. Track Machines
5. 55 No. Stations Damaged of Signaling system
6. 55 Nos. Stations damaged of Telecommunication system.
14
(C) Executive Agency: Approved by
Date of Date of
Approval Completion
Pakistan Railways ECNEC 24-03-2010 31-03-2015
Note:- Provision of LC of SEK 410.227(M) = PKR (M) 4890 (M) included in the
total cost of Project Rs. 7855.953 (M).
Cumulative Expenditure:
Cumulative Expenditure upto June, 2014 = 7258.220 (M)
(E) Achievements:
Percentage end
Targets Achievements Remarks
of June, 2014
15
Sukkur & Karachi Division (Signalling Rehabilitation Project)
Percentage up
Targets Achievements Remarks
till April, 2014
Part-1 1. All work have been restored/ 1. 100% Completed
Karachi Division completed.
M/s. Siemen's (Restorations
auto block between BDNL-
HDR section with four
stations GDR, DBJ, JHP &
JGS).
Part-2
Sukkur Division i.. Construction ()Equipment, Battery 1. 100% i.Completed
Provision of Computer Based & Generator) room work 22 stations
Interlocking at 22 stations at have been completed.
Sukkur & One station (BQM)
in Karachi Division. ii. Equipments Consignments. 2. 94% ii.Work will be completed in
end of Dec, 2014.
iii. Bucheri & NWS Stations work has 3. 100% iii. Work has been Completed
been completed and will be opened soon
iv. Sarhari to Shahdadpur section. Work 4. 70% iv. Work will be completed
is under progress. end of Sep,2014
v. Jalal Mari to Padidan section (on nine 5. 100% v.Work will be completed end
block section). 113 Km Fiber Optic of Dec,2014
cable have been laid.
vi. Six stations (Jalal Mari- Dour) Indoor/ 6. 70% All remaining stations work
Outdoor Equipments have been will be Completed up to
installed. & outdoor work 60% Dec,2014.
completed.
Telecommunication Department:
Mission Statement:
To provide reliable, secure and independent telecom facilities for
efficient and safe train operation.
Telecommunication System:
i) Pakistan Railways Telecommunication System comprises of
Microwave, UHF & VHF Radios, Telephone Exchanges Network,
Train Control System, overhead and underground cable.
16
iii) Microwave Radio System having 960 channels capacity is
working at 38 sites as backbone. UHF Radio System
having 36 channels capacity is working at 230 locations for
station to station communication. VHF Radio System
having 576 base stations & equipped on 460 locomotives
provides communication between Station Masters and
Train Drivers. HF Radio uses single channel for long
distance and also for coded messages.
17
Achievements During 2013-2014:
In some divisions solar panels have been introduced to cater the
electricity demands.
Future Plan:
1. PC-I for replacement of EPABX with VOIP Gateway at
Lahore, Multan and Sukkur is under process.
18
the commercial exploitation of more than 04 Kanals are processed
and dealt by REDAMCO. The Divisions earning from short term
leases for the last 04 years remains Rs. 2107.57 million.
3. Removal of Encroachment:
An anti-encroachment campaign was initiated on the orders of
Honourable supreme court of Pakistan w.e.f. 01-02-2012 and an
area of 3047.884 acres of Pakistan Railway land having assessed
value of approximately Rs. 8749.82 million got vacated from
encroachers on the entire system. during 2013-14.
19
5. Dispute regarding Title of Land.
The issue of the title of land and sharing of proceed of Railway land
in the Provinces has been taken up vigorously with Chief Minister
Punjab & Khyber Pakhtunkhwa (KPK) who have issued directives
to Chief Secretaries to resolve the issue in consultation with
Member Board of Revenue.
1 2 3 4 5 6
20
Target Earning Against Revenue Targets For 2013-14 (Directorate
of Property & Land) For the Period 01-07-2013 to 30-06-2014.
Target Recovery (Rs. In Million).
Divisions for July August September October November December January February March April May June Total
year 2013 2013 2013 2013 2013 2013 2014 2014 2014 2014 2014 2014 from
2013-14 1-7-2013-
2014.
Peshawar 180.00 4.229 1.931 4.985 11.458 4.428 28.085 8.381 11.137 11.864 23.680 16.412 19.103 145.693
Rawalpindi 90.00 1.881 48.401 9.122 1.372 1.325 16.709 14.530 19.962 2.579 1.496 1.725 34.049 153.151
Lahore 420.00 9.358 3.853 14.422 8.825 10.387 598.55 5.901 9.365 6.747 1.885 21.707 21.866 712.866
Moghalpura 60.00 6.636 4.593 4.991 1.990 2.012 1.919 2.104 1.884 5.222 26.764 2.306 1.334 61.755
Multan 300.00 9.688 3.647 6.444 8.277 10.817 196.645 12.531 9.188 6.819 8.950 14.471 12.216 299.693
Sukkur 120.00 4.318 3.684 5.444 28.937 1.083 1.936 7.916 1.836 4.433 4.328 0.778 4.836 69.529
Karachi 240.00 3.983 3.749 3.012 4.648 1.178 8.765 4.892 1.057 0.225 1.629 0.035 1.006 34.179
Quetta 90.00 1.529 1.087 1.975 2.069 1.74 1.288 1.459 1.252 1.914 3.497 1.940 2.483 22.233
Total 1500.00 41.622 70.945 50.395 67.576 32.97 853.897 57.714 55.681 39.803 72.229 59.374 96.893 1499.099
(An amount of Rs. 787.711 million was received from Food Department, Punjab and accordingly
shown as recovery in Peshawar, Rawalpindi, Lahore & Multan in December 2013).
B. Mechanical Department:
The Unit is headed by the Additional General Manager Mechanical
who is assisted by the following Head of Departments:-
Mechanical Engineering:
Functions and Duties:
Mechanical department is responsible for maintenance of rolling
stock including passenger coaches, freight wagons, diesel and
electric locomotives, cranes. It also maintains large number of
machinery and plants in workshops, sheds and other work center.
Mechanical department ensure safety and reliability of stock in train
21
operations. Main area of responsibility of Mechanical department are:
Achievements:
89 coaches have been inducted in system from the project of 202
new designs China Coaches in year 2013-2014.
Carriages:
S. No. Description B.G. NG MG. Total.
1. Passenger Coaches. 1434 -- -- 1434
2. Other Vehicles. 262 -- -- 262
3. Brake Vans. 282 -- -- 282
4. Trailers. 01 -- -- 01
Wagons:
S. No. Description B.G. M.G. Total.
1. Covered wagons. 4531 .. 4531
2. Open wagons. 4549 .. 4549
3. For Container. 1741 .. 1741
4. Tank Wagons 3810 .. 3810
5. Special Type Wagons. 524 .. 524
6. Departmental wagons 625 .. 625
7. Brake Vans. 399 .. 399
8. Four wheeled wagons. 10887 .. 10887
9. Eight wheeled wagons. 5292 .. 5292
10. Freight wagons in numbers. 16179 .. 16179
11. Goods wagons in terms of 4 wheeled. 21471 .. 21471
12. Carrying capacity of freight wagons in tones. 476656.2 .. 476656.2
*Meter Gauge and Narrow Gauge Goods Stock is no more available on P.R.
System. Average ineffective of Goods Stock during the year 2013-2014 = 25.9%.
22
Future Plan:
1. The project of 500 High Capacity Wagons is in pipeline.
Locomotives:
S.
No. Description Quantity Remarks
an average Daily 210 Nos. locomotives
1 DE Locos 409 Nos. remained available for various services.
The remaining locomotives are stabled
for want of imported spares.
2 Steam Locos ( 5 BG + 7 MG Steam safari Operates as per demand of
M/s PRACS.
= 12 Nos.)
Material Management:
A. Purchase Department:
Supply system is the life line of any organization. The objective of
purchase department is to provide maintenance Stores & Spares
for efficient and safe running of Rolling Stock, such as Diesel
Electric Locomotives, Passenger Coaches and Freight Wagons.
The system also cater for the maintenance requirement of material
for Track, Signaling System, Bridges etc. The material required for
the Railway Workshops and Sheds is also either purchased or
manufactured in Workshops. There are about 18651 shop made,
regular buy-out stock and emergency stock items, which are
purchased every year besides,a good number of non-stock items.
23
Broad analysis of Purchases made during the year 2013-2014 is
given below :-
(Rupees in Millions)
1. Imports 28.508
2. Customs Duty & Sales Tax etc. 83.682
3. Indigenous purchases: ..
i. Chief Controller of Purchase/TSO 1290.821
ii. Steel Shop/Moghalpura 11.269
iii. Divisional Superintendents 4.139
iv. Other than Chief Controller of Purchase ..
v. Sea Freight (Internal) 5.927
vi. Fuel other than operation purpose ..
vii. Value added in Workshops 232.173
viii. Value added in Steel Shop 314.377
TOTAL : 1932.550
Mode of Procurement:
The Purchase Branch of Pakistan Railways was created in 1961,
when Railway had dis-linked from the Directorate of General,
Supplies & Development, Ministry of Industries, Government of
Pakistan. All the purchases are made through Tender System
according to modern principles of Supply Management.
Shipping:
All the material purchased by the Pakistan Railway from abroad is
cleared by its own clearing agent i.e., District Controller of Stores
24
(Shipping), Pakistan Railways, Karachi Cantt. He also acts as
clearing agent of the other Government Departments as and when
ordered to get their consignments cleared.
B. Stores Department:
Stocking Depots:
In order to ensure un-interrupted supply of material to the end
users, Pakistan Railway has set up 17 Stocking Depots located at
Moghalpura Lahore, Karachi, Hyderabad, Sukkur, Quetta, Jehlum
and Rawalpindi and 16524 regular stock items are stocked in the
above said store depots.
Distribution of Material:
Central Transportation Section is responsible for distributing
Imprest/Non-imprest Stores at the door steps of Consumers all over
Pakistan Railway and also collects the Stores returned from all the
Indent offices (I/OS). In case of emergency, material is distributed
to Indenters through Special Escort except flammable materials.
25
Scrap, Surplus and obsolete Material:
An important activity of Stores department is the disposal of scrap,
surplus and obsolete material, which is generated during normal
course of operation of Railway System. After inspection by a
Survey Committee to assess the possibilities of utilization in the
system, material declared scrap is sold out through open Tenders.
On implementation of New Scrap Policy, duly approved by Ministry
of Railways, Islamabad, in the year 2013-14, the Railway
Divisions as well as Locomotive Factory, Risalpur, Carriage
Factory, Islamabad and Concrete Sleeper Factories have also been
allowed to dispose off their scrap for speedy generation of revenue
for Railways. During the year 2013-14 total value of sold out scrap
by the department was about Rs. One Billion which is highest ever
in history of Pakistan Railways.
Computerization:
All the depots provide Material Source Documents to I.T. Directorate
Pakistan Railway, where necessary data is fed for processing and
monthly reports for each depot, covering total transactions, are
generated. Various other reports including buyout and shop made items,
detail of surplus stocks and over stocks are also produced regularly.
Printing Press:
Pakistan Railway has its own Printing Press at General Stores,
Moghalpura Lahore which caters for all the requirements of printing
of forms, and different stationery items. The Printing Press has
been equipped with offset Printing Machines & Word Processors.
Pakistan Railway Year Book and Annual Audit Reports are also the
product of this press.
Clothing Factory:
It stitches uniforms and different clothing items for Railway staff of
different departments, according to their requirements.
26
Electrical Engineering Department:
The main responsibility of Electrical Department is to provide and
ensuring proper working of air conditioning in the coaching stock
alongwith lights, fans and electrical gadgets of train kitchenet. Fuel
dispensing units have been installed for accountal of fuel used in
power vans and train lighting vans.
27
6. Against the project of Procurement of 40 Power vans will arrive
as CBU and 18 Power vans will expected to be received as
CKD in next financial year and Pakistan Railway will restore
its suspended Air-conditioned services in various trains.
Railways Electrification:
The electric traction system between Lahore to Khanewal was
installed on single line in 1969 with a fleet of 29 Electric Locomotives.
It remained in operation upto October, 2009. On launching of Doubling
of Track Project from Khanewal to Raiwind the operation of train with
ET Locomotives was suspended. After completion of Doubling of
Track Project between Khanewal-Sahiwal the ET operation on single
line was not possible, hence it was completely closed in November,
2009. Now the electrification of main line (ML-1) from Lahore to
Karachi (1260km) is included under China-Pak Economic Corridor
(CPEC), which is a priority project of Government of Pakistan.
Feasibility Study for the project is under way, which would decide
technical & financial viability of the project, followed by its detailed
designs and implementation.
C. Traffic Department:
The Unit is headed by the Additional General Manager Traffic, who
is assisted by the following Head of Departments:-
1. Chief Commercial Manager.
2. Chief Marketing Manager.
3. Chief Traffic Manager.
4. Chief Operating Superintendent.
28
Passenger Department:
The passenger wing of commercial department of Pakistan
Railway's headed by Chief Commercial Manager is responsible for
the creation, maintenance and delivery of passenger services and
all related amenities to the traveling public, including the
transportation of parcel traffic.
29
Statement of Ticketless Checking From July 2013 to June 2014
S. No. Month Cases Fare Penalty Total
30
st th
Running of Special Trains form 1 July, 2013 to 30
June, 2014 (Up & Down).
S. No. Month Special Train Total
1. July-2013 Nil Nil
2. Aug-2013 Eid-ul-Fitter Special =3 3
3. Sep-2013 Nil Nil
4. Oct-2013 Eid-ul-Azha Special = 3 3
5. Nov-2013 Raiwind Special Phase-I & II= 3+3 6
6. Dec-2013 Larkana Special = 1 1
7. Jan-2014 Nil Nil
8. Feb-2014 Nil Nil
9. Mar-2014 Raiwind QTA Special = 1 1
10. April-2014 Indian Sikh = 3 3
Pakistani Sikh = 3 3
11. May-2014 Raiwind QTA Special=1 1
12. June-2014 Indian Sikh = 2 2
Sehwan Special = 2 2
Total Special 25
st th
Running of Extra Coaches from 1 July, 2013 to 30 June, 2014 (Up & Dn)
1. July-2013 73 73 146
2. Aug-2013 19 21 40
3. Sep-2013 26 23 49
4. Oct-2013 29 28 57
5. Nov-2013 44 44 88
6. Dec-2013 44 49 93
7. Jan-2014 44 45 89
8. Feb-2014 26 28 54
9. Mar-2014 46 49 95
10. April-2014 38 32 70
11. May-2014 33 35 68
12. June-2014 56 47 103
31
Marketing Department:
Organization setup:
The Marketing Department is managed by the Chief Marketing
Manager assisted by the Deputy Chief Marketing Manager, Senior
Rates Officer and Assistant Commercial Managers.
Scope of Work:
Preparation of budget, monitoring of earnings and analyzing shortfall, its
causes and recommending remedies.
Modification and Periodic review of Rate structures to attract both
Passenger & Freight traffic.
Exploring new avenues to market services offered by Pakistan
Railways.
Competitive analysis of logistic & transportation industry and redefining
role of Pakistan Railways.
Suggesting policy guideline to develop methodology for maximum
utilization o assets.
Executing agreements.
32
Important Goals:
1. To increase interaction with Customers and the Business
Community.
33
Agreement is in progress with NLC to use their ten locomotives in
progress.
No of oil carrying trains for Lal Pir and Muzaffargarh increased
substantially.
Efforts are underway to restart ECO train via ML-3.
Efforts started to reintroduced Cargo express 501 up/502 down between
Karachi Bander/Lahore/Badami Bagh and vice versa.
Pricing Policy:
Pakistan Railways move cargo on rails at a lesser fuel cost as
compared to moving the same by road. The organization by
reasons of this advantage is able to formulate its pricing policy to
the maximum advantage allowable to the customers and the
organization. Promotional reduced rates are quoted to provide
incentive to move the commodities by rails instead of road.
34
Passenger sector Marketing.
Pakistan Railways has a dedicated pool of long-lead & branch-line
passenger coaches. Due to cheap & comfortable service, our
customers are loyal to our service. However, the ever present threat
from the road runners remain looming in the background. In order to
effectively deal with these threats, the Marketing department pursues
an aggressive policy in pricing & provision of service.
Dry Port:
The containerization of cargo and the establishment of Dry Ports were
steps that further facilitated multimodal movement of goods. Pakistan
Railways foresee that the cargo transportation in future is going to rely
heavily on container traffic hence Dry Ports were established as under:-
35
been inducted to further facilitate Container Traffic. The earnings
and Tonnage of Import & Export traffic handled during the year
2013-2014 pertaining to different Dry ports are given below:-
IMPORT EXPORT
Name of Dry Ports Earning No. of Earning No. of
(Million) Tonnage Containers (Million) Tonnage Containers
Karachi Dry Port 61.75 29660 1023 Nil 2714 242
________________________________________________________________________________
Lahore Dry Port 73.58 135536 8471 1.27 2192 137
_______________________________________________________________________________
Prem Nagar Dry Port 17.20 107543 13267 R/Trip 26896 2295
________________________________________________________________________________
Faisalabad Dry Port 18.764 2933 336 Nil Nil Nil
________________________________________________________________________________
KRK Container Nil Nil Nil Nil Nil Nil
Terminal ________________________________________________________________________________
Chi Cho ki Milian Nil Nil Nil Nil Nil Nil
________________________________________________________________________________
Rawalpindi Dry Port 114.32 109280 4959 0.108 184 22
________________________________________________________________________________
Peshawar Dry Port 103.486 174752 15399 0.711 1225 84
________________________________________________________________________________
Quetta Dry Port Nil Nil Nil Nil Nil Nil
________________________________________________________________________________
Operating Department:
Freight Loading:
During the year 2013-14, 76307 wagons were loaded on the entire
systems against 46617 wagons during the corresponding period
registering increase of 29690 wagons (+64%). Comparative loading
of all divisions remained as under:-
36
Punctuality:
The punctuality position of Mail/Express and Intercity trains during
2013-2014 as compared to the corresponding period is as under:-
Period
Trains Variation
2013-2014 2012-2013
Mail Express 27% 11% 16 %
Intercity 62% 59% 3%
16% increase in the punctuality of Mail/Express trains is due to
concerted efforts of all concerned branches by optimal useage of
the available resources.
Safety of Trains:
The comparative figures of the accidents with description for the
calendar year 2012 and 2013 is given blow:-
Number of accidents
Description of Accidents Variation
2012 2013
Collision of Passenger Train -- 1 +1
Derailments of Passenger Trains. 9 13 +4
Derailments of Goods Trains. 4 9 +5
Collisions at Manned level Crossings 9 14 +5
Collision at Un-Manned level Crossings 64 71 +7
Fire in Trains 3 4 +1
Others 7 5 -2
Total 96 117 21
In the wake of recent law & order in the country, the following steps
have been taken to safeguard the Railway system/property and
precious lives of the travelling public:-
37
All entry/exit point are manned and the passengers and their
luggage are detected with Metal & Explosive Detectors by
Bomb Disposal/Police Staff. The Unauthorized entrance of
important stations have been closed.
Unclaimed/suspicious articles like bags, tins, bottles, crates,
gunny bags parcels or any unattended luggage etc. found in
the Railway premises or in the train are immediately
reported to the Police/Civil Defense Authorities.
All rakes of the trains at terminal stations are locked and
escorted upto Washing Lines and form Washing Lines to the
Platforms.
Station Managers/Station Superintendents and Station
Masters of the important stations ensure regular
announcement on public address system for their appraisal
regarding subversive activities.
Lighting arrangements has been beefed up at Railway
Stations/Station Yards/Installations as well as in the trains
and proper security provided in the yards.
Joint patrolling of P-Way and Police officials over key
identified areas is being ensured.
The Patrollers intimate the nearest station about any mob on
the track through quickest possible means of
communication.
The availability of Fire Fighting Appliances are being
ensured at Railway stations.
38
D. Personnel Department :
The formation of the Personnel Branch was the natural and
necessary corollary of the introduction of the Divisional System on
Pakistan Railway. The existence of Personnel Branch aims at an
efficient co-ordination of all sorts of matters dealing with the human
resource of the Pakistan Railway, maintenance of uniform policy as
a whole in regard to recruitment, training, conditions of service,
leave rules, retirement & post retirement etc.
39
arranged by this office out of contribution of the officers holding
posts BS-17 & above.
40
Monthly contribution towards Benevolent Fund recovered from the
salary bills of regular employees is as under:-
During the year 2013-2014 a sum of Rs. 268.745 million was paid
to the beneficiaries towards monthly grants out of Benevolent Fund.
These grants are met with from the monthly contribution by the
Railway Servants as well as profit on investments.
41
G. Police Department:
Pakistan Railways Police is functioning under the administrative
control of General Manager/Operations. The area of jurisdiction of
Pakistan Railways Police is further divided into the following Eight
Divisions:-
S. No. Name of Division
1. Peshawar Division.
2. Rawalpindi Division.
3. Lahore Division.
4. Multan Division.
5. Sukkur Division.
6. Karachi Division.
7. Quetta Division.
8. Workshop Division Mughalpura.
Each Division is headed by one Superintendent of Police but due to
light work, only one Deputy Superintendent has been provided at
Quetta and Peshawar Divisions. One Prosecuting Inspector is also
provided at least to each Division. There exists one Police Training
school at Walton Lahore under the supervision of one DSRP with
direct command of DIG. Organization.
42
Recovery of Stolen Railway Material During the Period from
01-07-2013 to 30-06-2014.
11 4 2 60 1 28 1 1463
43
Help Extended to the Passengers/General Public during the
Period from 01-07-2013 to 30-06-2014.
No. of Lost Children No. of Ran Away Any
Handed over to (Girls/Boys & Women) Retrieval of Lost
Other
Parents/Legal Heirs Handed over to their Luggage/Valuable
Help
Legal Heirs.
44
F. Directorate Of Public Relations:
Background:
The Directorate of Public Relations of Pakistan Railways is
responsible for publicity, promotion of Railway Products/services
and interaction with the print and electronic media. The incumbent
Minister took keen interest in revamping this Directorate up to the
need of modern media relations and brought the so far scattered
Directorate under one roof for ensuring better media monitoring
system. To meet the modern media challenges and to have an
effective Liaison with the print and electronic media, a new post of
Director General Public Relations (DGRP: MP-III scale) was created.
The Directorate of Public Relations is equipped with LEDs/LCDs for
keeping up with current developments being aired from different
Electronic Media Channels. The matters relating to print media are
also being dealt more effectively under the supervision of Director
General, who is a senior journalist having a wide experience of
more than 30 years in the realms of print and electronic media.
1. Advertisements:
For promotion of different rail services and products this office
manages to publish the required advertisements in print media and
at times get them aired through electronic media as well. Tenders
are also got published through this office.
45
b This office also arranges for publicity/promotion campaigns of
remarkable developments, such as introduction/restoration of
trains including campaigns of Special trains at the eve of Eids,
Tableghi Ijtemas, National events, Azadi Train etc.
3. Electronic Media:
TV News Channels are watched to keep up with broadcasted
developments regarding Railways and responded to accordingly
through modern electronic techniques.
4. Print Media:
News of any important event is prepared and released to Media
Offices through email and fax formats. Information with the media
offices, is also shared telephonically for clarification of the news to
be released. In this connection, Media Houses are also visited by
staff of this office as and when required. As per nature of the
expanded assignments, this office works till late hours in two shifts.
46
6. Videography in railway Premises:
This Directorate facilitates and grants permission of shooting of
scenes/events in Railway premises, as desired by interested
parties for official, commercial or charity purposes. This office
grants cost-free shooting permission to educational institutions,
charity organizations and Government Media Houses, while
shooting is charged on commercial basis, depending upon nature
of the videography. In this vein, this office has earned Rs. 0.415
million during June-2013 to November-2014.
47
PSDP Budget Order
S.
No. Name of the Project
D
N
P
S
P
S
o
.
.
1 2 3
1 890 Doubling of track Khanewal to Raiwind Section(Revised).
___________________________________________________________________________________________________________________________________________
2 891 Doubling of Track from Shahdara to Faisalabad.
___________________________________________________________________________________________________________________________________________
3 892 Doubling of Track from Shahdara to Lalamusa.
___________________________________________________________________________________________________________________________________________
4 893 Doubling of Track on Lodharan to Khanewal Section via Multan Cantt. (Revised) (OPEC).
___________________________________________________________________________________________________________________________________________
5 894 Feasibilities Studies (Lumpsum) (Revised).
___________________________________________________________________________________________________________________________________________
6 895 Mechanization of Track Maintenance (Pilot Project).
___________________________________________________________________________________________________________________________________________
7 896 Pilot Project for Manufacture of 5 (3000 HP) Locos.
___________________________________________________________________________________________________________________________________________
8 897 Procurement/Manufacture of 530 High Capacity Wagons (Revised).
___________________________________________________________________________________________________________________________________________
9 898 Procurement/Manufacture of 75 Nos. New D.E. Locos Risalpur (China).
___________________________________________________________________________________________________________________________________________
10 899 Procurement of 150 D.E.Locos.
___________________________________________________________________________________________________________________________________________
11 900 Procurement of 500 High Capacity Bogie Wagons & 40 Power Vans.
___________________________________________________________________________________________________________________________________________
12 901 Procurement of Plant & MAchinery for C&W Shop Mughalpura.
___________________________________________________________________________________________________________________________________________
13 902 Procureen/Manufacture of 50 Nos. D.E.Locomotives.
___________________________________________________________________________________________________________________________________________
14 903 Procureen/Manufacture of 202 New Design Passenger Carriages (Revised) (China)
___________________________________________________________________________________________________________________________________________
15 904 Project Management Unit (PMU) in Ministry of Railways (Revised).
___________________________________________________________________________________________________________________________________________
16 905 Reconstruction of assets Damaged during 2010 Floods.
___________________________________________________________________________________________________________________________________________
17 906 Rehabilitation and Improvement of Track (Revised)
___________________________________________________________________________________________________________________________________________
18 907 Rehabilitation of 27 number (HGMU-30) Diesel Elecric Locomotives(Revised PC-1).
___________________________________________________________________________________________________________________________________________
19 908 Rehabilitation of Railway Assets Damaged during riols of 27th 28th December, 2007.
___________________________________________________________________________________________________________________________________________
20 909 Rehabilitation of Rolling Stock and Track.
___________________________________________________________________________________________________________________________________________
21 910 Rehabilitation, Up gradation & Conversion of 400 Coaches.
___________________________________________________________________________________________________________________________________________
22 911 Replacement of three brake down/rescue cranes and procurement of 5 sets relief train equipment.
___________________________________________________________________________________________________________________________________________
23 912 Replacement of Metal Sleepers and track renewal on Lodhran Shahdara Section.
___________________________________________________________________________________________________________________________________________
24 913 Replacement of old and obsolete signal gear from Lodhran Khanewal Shahdara Bagh Mainline
Section of P.R (IBD).
___________________________________________________________________________________________________________________________________________
25 914 Revival of Karachi Circular Railways as modern commuter system (JICA).
___________________________________________________________________________________________________________________________________________
26 915 Special Repair of 150 Nos. D.E. Locomotives.
___________________________________________________________________________________________________________________________________________
27 916 Strengthening/Rehabilitation of 159 weak Bridges.
___________________________________________________________________________________________________________________________________________
28 917 Strengthening of Planning Directorate, Ministrate of Railways, Islamabad.
___________________________________________________________________________________________________________________________________________
29 918 Track Rehabilitation Khanpur-Lodhran Section.
___________________________________________________________________________________________________________________________________________
30 919 Construction of an underpass bridge at K.M 1116/6-9 near class-II level crossing No. 148 between
Renala Khurd-Habibabad Station on Lahore-Sahiwal Section (Akhtarabad) Improvement/renovation of Hassan Abdal Railway
Station.
___________________________________________________________________________________________________________________________________________
31 920 Improvement/renovation of Hasan Abdal Railway Station.
___________________________________________________________________________________________________________________________________________
32 921 Improvement/renovation of Narowal Raillway Station.
___________________________________________________________________________________________________________________________________________
33 922 Up-gradation/improvement of Nankana Sahib & Kamalia Railway Station.
___________________________________________________________________________________________________________________________________________
Total
48
for the year 2013-2014.
Estimated Cost Expenditure Allocation 2013-14
upto
June
Total Foreign 2013. CFE CD/ST & Ports Cash & Foreign Total
Aid Shipping Store Loan
Charges
4 5 6 7 8 9 10 11
12,617.400 .. 10,672.190 200.000 424.463 1,340.840 .. 1,965.303
___________________________________________________________________________________________________________________________________________
10,281.000 .. 32.109 .. .. 15.000 .. 15.000
___________________________________________________________________________________________________________________________________________
13,593.000 .. 29.455 .. .. 15.000 .. 15.000
___________________________________________________________________________________________________________________________________________
3,678.500 804.500 3,146.325 .. .. 50.000 .. 50.000
___________________________________________________________________________________________________________________________________________
150.000 .. 24.875 .. .. 10.000 .. 10.000
___________________________________________________________________________________________________________________________________________
4,850.000 .. 53.912 250.000 80.000 170.000 .. 500.000
___________________________________________________________________________________________________________________________________________
955.000 .. 31.174 .. .. 10.000 .. 10.000
___________________________________________________________________________________________________________________________________________
4,134.732 2,418.700 3,823.143 .. .. 10.000 .. 10.000
___________________________________________________________________________________________________________________________________________
12,700.000 8,400.451 2,622.286 .. .. 750.000 .. 750.000
___________________________________________________________________________________________________________________________________________
55,488.000 .. 3.500 .. .. 400.000 .. 400.000
___________________________________________________________________________________________________________________________________________
11,998.000 .. 1,165,522 915.000 295.000 20.000 .. 1,230.000
___________________________________________________________________________________________________________________________________________
199.940 .. 181.475 .. .. 2.000 .. 2.000
___________________________________________________________________________________________________________________________________________
19,406.610 .. 1,506.715 8,100.000 2,595.000 5.000 .. 10,700.000
___________________________________________________________________________________________________________________________________________
15,889.900 11,085.548 17,813.355 .. .. 460.000 .. 460.000
___________________________________________________________________________________________________________________________________________
720.773 493.540 84.929 .. .. 25.000 .. 25.000
___________________________________________________________________________________________________________________________________________
6,365.239 .. 45.198 .. .. 150.000 .. 150.000
___________________________________________________________________________________________________________________________________________
9,405.000 .. 8,541.738 .. .. 331.077 .. 331.000
___________________________________________________________________________________________________________________________________________
5,108.000 .. 716.407 2,100.000 672.000 328.000 .. 3,100.000
___________________________________________________________________________________________________________________________________________
7,855.953 .. 5,665.345 390.000 77.000 233.000 .. 700.000
___________________________________________________________________________________________________________________________________________
4,000.000 .. 755.518 300.000 96.000 504.000 .. 900.000
___________________________________________________________________________________________________________________________________________
3,434.000 .. 3,336.732 .. .. 289.644 .. 289.000
___________________________________________________________________________________________________________________________________________
1,638.000 .. 6.200 1,500.000 363.000 4.500 .. 1,867.000
___________________________________________________________________________________________________________________________________________
2,216.000 .. 1,156.928 70.374 144.000 585.226 .. 800.000
___________________________________________________________________________________________________________________________________________
10,720.382 7,988.969 7,575.453 .. 440.000 260.000 3,264.000 3,964.000
___________________________________________________________________________________________________________________________________________
9,616.944 .. 252.178 .. .. 1,000.000 .. 1,000.000
___________________________________________________________________________________________________________________________________________
5,005.031 .. 662.555 960.000 310.000 30.000 .. 1,300.000
___________________________________________________________________________________________________________________________________________
412.000 .. 209.126 .. .. 150.000 .. 150.000
___________________________________________________________________________________________________________________________________________
58.000 .. 1.400 .. .. 15.000 .. 15.000
___________________________________________________________________________________________________________________________________________
8,978.000 .. 30.000 20.000 7.000 123.000 .. 150.000
___________________________________________________________________________________________________________________________________________
139.000 .. .. .. .. 40.000 .. 40.000
___________________________________________________________________________________________________________________________________________
59.000 .. .. .. .. 25.000 .. 25.000
___________________________________________________________________________________________________________________________________________
59.000 .. .. .. .. 25.000 .. 25.000
___________________________________________________________________________________________________________________________________________
15.370 .. .. .. .. 15.370 .. 15.370
___________________________________________________________________________________________________________________________________________
49
Progress Report of on Going P.S.D.P. Projects of
S. Estimated Expenditure Budget Budget Expenditure Commulative
No. Name of Project Cost of the upto the Release Allotment during the Expenditure
Project end of upto for year 2013-14 upto May,
June, March, 2013-14. upto May, 2014
2013. 2014. 2014. (Column No.
4+7).
1 2 3 4 5 6 7 8
1 Doubling of track from Khanewal to Raiwind Section(Revised) 12617.400 10672.190 1384.300 1965.303 896.013 11568.203
(Khanewal-Lahore). inclusiveFEC
4864.800
2 Doubling of Track from Shahdra to Faisalabad (Lahore- 10281.000 5.573 2.500 15.000 2.301 7.874
Faisalabad). inclusive FEC
3193.200
3 Doubling of Track from Shahdra to Lalamusa (Lahore-Gujrat). 13592.505 2.785 55.500 15.000 55.185 57.970
inclusive FEC
3342.148
4 Doubling of Track on Lodhran to Khanewal section via Multan 3678.500 3066.129 46.000 50.000 10.768 3076.897
Cantt (Revised) (O.F.I.D) (Lahore-Khanewal-Multan). inclusive FEC
804.500
5 Feasibilities studies (Lumpsum) Revised. 150.000 24.875 0.600 10.000 0.600 25.475
6 Mechanization of Track Maintenance (Pilot projects Lahore). 4055.000 53.912 102.000 500.000 2.174 56.086
inclusive FEC
2695.000
7 Pilot Project for Manufacture of 5 (3000 HP) Locos (All Paki- 955.000 31.174 923.650 10.000 189.190 220.364
stan).
8 Procurement/Manufacture of 530 High Capacity Wagons (Re- 4134.732 4506.368 3.500 10.000 3.068 4509.436
vised( (I.D. Bank) (All Pakistan). inclusive FEC
2418.681
9 Procurement/Manufacture of 75 Nos. New D.E. Locos (Exim 12700.000 2614.877 191.223 750.000 1465.436 1149.441
Bank China) (All Pakistan). inclusive FEC
8400.451
10 Procurement of 150 D.E. Locomotives (All Pakistan). 55488.000 3.500 0.000 400.000 0.000 3.500
inclusive FEC
40362.878
11 Procurement of 500 High Capacity Bogie Wagons and 40 11998.000 5.325 684.300 1230.000 1170.419 1175.744
Power Vans (All Pakistan Pakistan). inclusive FEC
7644.800
12 Procurement of Plant and Machinery for C & W Shop Moghlpura. 199.940 173.080 10.000 2.000 7.765 180.845
13 Procurement/Manufacture of 50 Nos. Diesel Electric Loco- 19406.610 1506.715 4483.397 10700.000 3052.434 4559.149
motives (All Pakistan). inclusive FEC
13487.360
14 Procurement/Manufacture of 202 New Design Passenger 15889.900 18441.924 437.000 460.000 425.150 18867.074
Carriages (Exim Bank China) (All Pakistan). inclusive FEC
11084.130
50
Pakistan Railways 2013-14 up to May, 2014.
Physical Target for year Physical Progress achieved during the Commulative Physical
2013-14. financial year 2013-14 (upto May, 2014) Progress achieved so far
9 10 11
7% 3% 96%
.. .. 0.2%
2% .. 0.2%
i. Remodeling of LON and SSH yards. Remodeling of Lodhran and Shershah Overall 100% (Except the work indicated against column No.
ii. Procurement of Track Machinery. yards have been completed except the work 12).
interlinking with CBI system/signal.
NIL NIL 55%
Procurement of machine and establish- 1. L.C. for Procurement of 2 cranes has NIL
ment of office. been established.
2. Tenders for Procurement of 2 track
temping, lifting & leveling, machines ac-
cepted by Director Procurement LC for
procurement of 02 Nos of track meachines
will be opened shortly
3.Tender for procurement and ballast
clearing machines as been floated. 4.
Technical evaluation for ballast cleasing
machine and
i Preparation works. NIL NIL
ii Shipment of Material from China.
iii.Manufacuring works on 5 D.E. Locos at
PLF.
Completion report (PC-4) submited to 1. Audit by the external audit firm Manufacfuring work of 530 High Capacity Wagons inculding
minstry of railway in july 2013. nominated by donor agency Islamic 30 Bogie Brake Vans have been complete on 30-06-2011 and
Development Bank (IDE) completed wagons handed over to the Operating Division
during June, 2014.
i. Technical bid opened on 25-09-2007.
NIL NIL ii. Financial bid opend on 30-06-2008.
iii. Contract agreement signed on 31-12-2008 with M/s
Danfang Electric Corporation China.
iv. Rs. 1279.996 million paid as 15% advance to the firm in
Letter of intent has been issued on 12-10- Jume, 2009.
.. 2012. v. Rs. 907.107 million paid as Bank Management Fee. Up front
fee and seno sure charges to EXIM Bank. China during 2009-
20.
90 CKD Coaches Tentative). 84-Coaches have been turned out besides 175-Coaches.
30% to 90%. Fabrication work have been
completed on 04 Nos. Coaches in
Fabriction Shop, 20% to 30% work have
been completed on 10 Nos. coaches in
Furnishing Shop.
51
Progress Report of on Going P.S.D.P. Projects of
S. Estimated Expenditure Budget Budget Expenditure Commulative
No. Name of Project Cost of the upto the Release Allotment during the Expenditure
Project end of upto for year 2013-14 upto May,
June, March, 2013-14. up to May, 2014
2013. 2014. 2014. (Column No.
4+7).
1 2 3 4 5 6 7 8
15 Project Management Units (PMU) in Ministry of Railways. 720.773 84.929 9.300 25.000 7.913 92.842
(Revised) World Bank (Islamabad). inclusive FEC
609.990
16 Reconstruction of Assets damaged during the Floods 2010 6365.239 45.198 150.000 150.000 142.353 187.551
(All Pakistan). inclusive FEC
1785.261
17 Rehabilitation and improvement of Track (Revised) Karachi to 9405.000 8541.738 331.077 331.077 321.652 8863.390
Khanpur. inclusive FEC
3328.000
18 Rehabilitation of 27 Nos. (HGMU-30 Class Diesel Electric 5108.000 716.407 2961.652 3100.000 2636.955 3353.362
Locomotives (All Pakistan).
52
Pakistan Railways 2013-14 up to May, 2014.
Physical Target for year Physical Progress achieved during the Commulative Physical
2013-14. financial year 2013-14 (upto May, 2014) Progress achieved so far
9 10 11
The following three projects have been bundled 1. FIS &MIS Project is in progress and in *ADB financed project of PPP Policy for Pakistan Railways
and given priority on directives of world Bank the advance stages. 2. The following three has been completed.
&Secretary/ Chairman Railways projects have been bundled and given priority
i. Study to Rehabilitate/reconstruct Bridges on directives of world Bank &Secretary/ Chair- 1. FIS &MIS Project is in progress and in its advance stages.
and Plan for Emergency restoration of Traffic man Railways. A. Consolidated Request for
in case of Failure of a major Bridge. Proposal (RFP) has been prepared con- 2. The following three projects have been bundled and a. Consoli-
ii. Capacity Building and Productivity taining the TORs for the bundled projects dated Request for Proposal (RFP) has been prepared contain-
Enchancement of Human Resource. already approved by Pakistan Railways. ing the TORs for the bundled projects already approved by Pa-
iii. Optimization of Low Revenue Railway Line i. Study to Rehabilitate/reconstruct Bridges kistan Railways.
and Plan for Emergency restoration of Traffic
in case of Failure of a major Bridge. i. Study of Rehabilitate/reconstruct Bridges and Plan for Emer-
gency Restoration of Traffic in case of Failure of a major Bridge.
be finalized and sent to short listed Con- ii. Capacity Building and Productivity Enhance ii. Capacity Building and Productivity Enchancement of Human
sultants for the above mentioned projects of Human Resource. Resource.
is supposed to be completed in the current Optimization of Low Revenue Railway Line
financial year. Bundled RFP has been sent to NTCMU, iii. Optimization of Low Revenue Railway Line.
Planning Commission for vetting and con-
sideration before submitting to World Bundled RFP has been sent to NTCMU, Planning Commis-
Bank. Expression of Interest (EOI) has sion for vetting and consideration before submitting to World
been prepared for the above mentioned Bank. Expression of Interest (EOI) has been prepared for the
three sub-projects. above mentioned three sub-projects.
3. Pre-Feasibility study for Rail Link from PSC to Jalalabad.
Short listing of EOI’s done and sent to World Bank alongwith
RFP for its clearance.
1 Disassembling phase of 17 Locomotives i. Stripping/ cleaning work of 17 Locomo- i. 17 Nos Locomotives nominoted for Rehabilitation were reached
will be completed. tives has been completed. in Loco rehabilitation shops MGPR.
2. Components of 17 locomotives will be ii. Main frams/Car Bodies of 11 Locomo-
washed/ cleaned. tives have been Rehabilitation/ modified ii. Their Stripping/Cleaning work was partially made.
3. Under frames of 17 Locomotives will be as per instructions of engineerd of M/s
washed Electro-Motive Diesel Limited, UK iii. 6 Locomotives alongwith bogies were sand blasted.
4. Car body remanufacturing of 17 Loco- iii. 06 Engine blocks have been hydrauli-
motives will be completed. cally tested by engineer of M/s EMD Lim- iv. Three Engine Blocks were hydraulically tested/by the engi-
5. Bogies (02 units per Loco) of 17 Loco- ited, UK. neers of M/s. EMD UK. v. Seven sets of Dummy bogies were
motives will be rehabilitated. iv. Plant / Machinery and over head Cranes arranged for minor movement of Locomotives in shop, vi Ware-
6. 1 Wiring of 04 Locomotives will be com- are house/storage arrangments for imported material were made.
st
pleted. vii. 1 Consignment of imported material was reached in Re-
7. Finally 03 Locomotives will be rolled out habilitation Shop, MGPR.
for train service.
i. Stripping/cleaning work of 14 Locomotives is continued.
ii. Main frames/Car Bodies of 07 Locomotives are being Re-
habilitated/modified as per instructions of Engineers of M/s.
EMD, UK.
iii. 06 Engine blocks have been hydraulically tested by engineer
of M/s EMD, UK.
iv. Plant/Machinery and over head Cranes are being upgraded.
v. 2nd to 16th consignments have been reached in Loco Shops,
MGPR.
53
Progress Report of on Going P.S.D.P. Projects of
S. Estimated Expenditure Budget Budget Expenditure Commulative
No. Name of Project Cost of the upto the Release Allotment during the Expenditure
Project end of upto for year 2013-14 upto May,
June, March, 2013-14. up to May, 2014
2013. 2014. 2014. (Column No.
4+7).
1 2 3 4 5 6 7 8
19 Rehabilitation of Railway Assets Damaged during riots
of 27th-28th December, 2007 (Sukkur-Karachi).
271.000
21 Rehabilitation Upgradation & Conversion of 400 Passenger 3434.000 3336.732 383.281 289.644 257.350 3594.082
Coaches (All Pakistan).
22 Replacement of three Breakdown Cranes/Rescue Crane and Pro- 1638.000 2.303 1867.500 1867.500 2040.854 2043.157
curement of Five sets of Relief Train Equipment (All Pakistan)
23 Replacement of Metal Sleepers and Track Renewal on 2216.000 1151.386 435.000 800.000 189.899 1341.285
Lodhran-Shahdara section. inclusive FEC
1274.884
24 Replacement of Old and Obsolete Signal Gear from Lodhran- 10720.381 9479.915 699.102 3964.000 1370.237 10850.152
Khanewal-Shahdara Bagh Main Line Section of P.R.(I.D.B). inclusive FEC
7988.969
25 Revival of Karachi Circular Railway (KCR) as Modern Com- 247000.000 252.178 35.000 1000.000 22.438 274.616
muters System (Revised) (Karachi). inclusive FEC
70730.00
54
Pakistan Railways 2013-14 up to May, 2014.
Physical Target for year Physical Progress achieved during the Commulative Physical
2013-14. financial year 2013-14 (upto May, 2014) Progress achieved so far
9 10 11
80% 66 Coaches 16 Coaches have been completed and turn- 37 Coaches 56%
out and 30 shells also completed & await-
ing interior work. Progress 24%.
500 Coaches 414 Coaches has been completed. 416 Coaches has been completed.
1. CTR with UIC Rails=18.50 KM. 1. 67 KM through sleeper renewal carried out in the length of
2. TSR with ESC Sleepers=20.50 KM. PWI/GRW on Lahore Lalamusa section. 2. 3.06 KM Casual
Sleeper Renewal carried out in the length of PWI/GRW on
LHR-LLM section.
30-Coaches 23.-Coaches have been turned out (30% to 298-Coaches.
(Subject to the Revision of PC-1). 90% work has been completed on 12 Nos.
Coaches in Fabrication shop.10% to 80%
work has been completed on 40 Nos/
Coaches in furnishing Shops. The remaning
work is held up for want of DG Set & wheel,
Axle & spring etc.
To received 03 Break Down/Rescue 1. Contract agreement for procurement of Modification of match trucks for BD cranes has been cop
Cranes (Capacity 160 tonne) from Ger- 3BD crane has signed on 27-06-12. LC
many and put into commission. has been established on 28-08-12. Cranes
shipped from Germany have been received.
ii. The tender of 05 set of rerailing equip-
ment was filed by the competent authority
during 2012-13. The case has been initi-
ated for re-tendering.
(i)-23% System Engineering. 18% Material arrived. Civil work on 80% System Engineering completed.
(ii)-90% Construction of Buildings. Lodhran-Habibabad completed. Remain- 78% meterial arrived at port & cleared.
ing works is in progress. Work of 19 stations on Lodhran, Gilwala, Shujabad, Sher Shah,
Multan, Piran Ghaib, Riazabad, Khanewal, Rajput Nagar, Mian
Channu, Kassowal and Chichawatni, Sahiwal, Yousafwala, Okara,
Kissan, Renala Khurd and Habibabad completed. Cables & equip-
ments transporterd at site. The installation at Piran Ghaib &
Riazabad completed the work.
(i). Main activity to be carried out: i. The revised cost of the Project US $ i. Environmental impact Assessment (EIA) Study approved.
(ii) Appraisal of the Project by JICA Ap- 2609.4 Million approved by ECNEC meet- ii. Satelite imagery of Route alignment finalized by SUPARCO.
praisal Mission. ing on August 16,2012. iii. A MOU with KESC signed on October 6,2010 and catego-
(iii). Designing and approval of Resettle- ii. ECC approved the waiver of 8.2% re- rized KUTC as strategic Customer for uninterrupted power
ment site. lending charges. supply for KCR Project.
(iv). Land acqisition in connection with the iii. GST, Duties, Federal Levies exempted iv. KPT authority have confirmed (Feb,04,2011) to handover 0.85
project to be finalized after signing of loan for Project on March 05, 2013 by ECC. Acres of KPT Land to KUTC on commencement of work. v. Re-
agreement. However the notification from FBR is still settlement Action Plan Study of the Project Affecties approved by
(v). Preparation of KUTC card by NADRA awaited. donor Agency. vi. On JICA request, MOR issued “Letter of com-
for each project affected Household for iv. Demarcation work at Resettlement Site fort” to lease the required P.R Land to KUTC at annualized lease
compensation after appraisal of the project completed and demarcation drawings charges of Rs. 1/-per sq.yd.
and loan signing agreement. signed all concerned Departments. v. Gov- vii Demarcation work at Resettlement site has been completed
ernment of Sindh agreed to provide land and dr
for Electric installation. viii. Encroachments have been removed from Resettlement
Site.
ix. Tender for the provision of Boundary wall process and rec-
ommendation of Tender Committe furnished to MOR for Ap-
proval.
55
Progress Report of on Going P.S.D.P. Projects of
S. Estimated Expenditure Budget Budget Expenditure Commulative
No. Name of Project Cost of the upto the Release Allotment during the Expenditure
Project end of upto for year 2013-14 upto May,
June, March, 2013-14 . upto May, 2014
2013. 2014. 2014 (Column No.
4+7)
1 2 3 4 5 6 7 8
26 Special Repair of 150 D.E Locomotives to Improve avaiablity 5005.000 662.555 1300.000 1300.000 1215.793 1878.348
&Reliability (All Pakistan). inclusive FEC
3521.000
million
27 Strengthening / Rehabilitation of 159 Weak Bridges on P.R. 412.000 209.126 65.000 150.000 31.313 240.439
(All Pakistan).
28 Strengthening of Planning Directorate Ministry of Railways, 58.000 0.000 8.000 15.000 0.000 0.000
Islamabad.
29 Track Rehabilitation on Khanpur-Lodhran section(Khanpur- 8978.000 29.429 155.000 150.000 49.458 79.187
Lodhran).
30 Construction of an underpass bridge at K.M 1116-9 near Class- 0.000 0.000 0.000 40.000 0.000 0.000
II Level Crossing No. 148 between Renala Khurd-Habibabad
station on Lahore-Sahiwal Section (Akhtarabad).
31 Improvement/ Renovation of Hassan Abdal Railway Station. 59.000 0.000 2.600 25.000 2.531 2.531
32 Improvement/Renovation of Narowal Railway station. 15.370 0.000 0.000 25.000 0.000 0.000
33 Upgradation/Improvment of Nankana Sahib & Kamalia Rail- 0.000 0.000 2.600 15.370 0.000 0.000
way Sation.
56
Pakistan Railways 2013-14 up to May, 2014.
Physical Target for year Physical Progress achieved during the Commulative Physical
2013-14. financial year 2013-14 (upto May, 2014) Progress achieved so far
9 10 11
Procurement of spare parts for special 1. Tender for procurement of spare parts i. Purchase orders for procurement of spare parts for special
repairs of DE Locomotives. for special repair of 105 D.E. Loco being repairs D.E. Locos issued during 2012-13. and letter of credit
finalized. established =1069 million
2. Purchase orders issued and LC
established=Rs. 1725 million ii.Purchase orders for spare parts during 2013-14 and L.C
3. Purchase orders for procurement of established=Rs. 1725 million.
sapare parts issued and letter credits and
being establish Rs.=409 million. iii. Purchase orders for sapare parts issued and letter credits
4. Purchase orders issued and MOR has are being established Rs.=409 million. (iv.) Perchase orders
been requested for CFE on commitment for spare parts issued and MOR has been requested for CFE
basis to establish letter of credit=Rs. 183 on commitment basis is establish letter of credit=Rs. 183mil-
5. Total commitment of funds upto 30-04- lion
2014=Rs. 2317 million.
(v.) Commulative total commitment upto 30-04-2014=Rs. 3386
million.
(vi) Remanufactured Traction Motoras fitted and GMU-30 D.E.
Loco attended at Motors fitted on Fifteen(15) GMU-30 D.E.
Locomotives.
(vi) Remanufactured Traction Motoras fitted on Fifteen(15)
GMU-30 D.E. Locomotives.
vii. Purchase orders for procurement of spare parts issued=Rs.
117 million Total=31
1. Procurement of P-way material and small 1) Contract agreement signed by Dir/Proc i) Contract agreement signed by Dir/Proc on 4th Feb 2013 for
machine. 2. Completion of Toographic Sur- on 4th Feb 2013 for Hydraulic Teklescopic Hydraulic Teklescopic Boom crane (10.0 Ton Capacity) with
vey=150 Route kms. Boom crane (10.0 Ton Capacity) with DP=23+1 months wef operative LC.
3. Rehabilitation of 20 BKW’s DP=23+1 months wef operative LC. ii) Contract agreement signed by Dir/Proc on 5th March 2014
4. Rail Renewal=20Kms. ii) Contract agreement signed by Dir/Proc for Duomatic Track Machine with DP=14+1 Months wef op-
5. Design and plans approval of 7 RCC on 5th March 2014 for Duomatic Track erative LC.
Box-culverts and 7 Ballasted-deck Bridges. Machine with DP=14+1 Months wef op- iii) Physical work of Topographic survey completed, reports
erative LC. thereof awaited.
iii) Physical work of Topographic survey iv) Tenders for procurement of small Machines have been opened
completed, reports are received and are and technical evaluation under proces.
under scrutiny. v.) Supply of Hardwood Sleepers in progress.
iv) Tenders for procurement of small Ma- vi.) Rails UIC-54(25.0 metres) aprom 15 Kilometre have been
chines have been opened and technical unloaded.
evaluation under process.
v.) Supply of Hardwood Sleepers in
progress.
vi.) Rails UIC-54(25.0 metres) aprom 20
Kilometre h.
42% NIL
NIL
..
57
I. Directorate of Information Technology:
The function of this Directorate is to maintain the running applications
and to automate the core activities of the Pakistan Railways.
Computerization in Pakistan Railways traditionally covers customer
related applications, like Pakistan Railway Reservation & Ticketing
System, Payroll, Financial Management, Inventory etc. The software
application development standardization has been introduced with the
implementation of ORACLE software environment.
Achievements:
1.1. Networking Methodology:
Pakistan Railways has LAN/WAN connectivity for implementation of
MIS/IT developed applications at all important locations including
Divisional Headquarters. The connectivity is based mostly on UTP
cabling within the building. Forty locations of Pakistan Railways
have been interlinked through PTCL fiber optic cross connect DXX
circuits. The LAN of Reservation offices have been connected with
WAN cloud provided by PTCL, Internet facility has also been
provided by using DSL connection of 4 MBPS bandwidth. MBPS at
Pakistan Railways Headquarters Lahore.
58
Moreover, it has increased the revenue earning due to
introduction of advance facility of return reservation.
1.2.5 Website
Pakistan Railways Web Site (www.pakrail.com) is available
to public world wide. The main features of the site includes:-
General Information about Railways.
Seat availability
Time Table.
Plan your Journey.
Latest news.
Public Notice.
Job opportunities.
Tender advertisements.
1.2.6 Payroll
At present the automated payroll is being used for
employees of Pakistan Railways. Payroll System since its
development has been generating monthly pay slips in
Headquarters and Divisional Offices.
59
1.2.7 Statistical System
The Software developed by this Directorate has been
deployed in the Statistical Section, it compiles figures of
revenue/earnings transaction and producing reports as per
requirement of the management. It also compiles data/
information for printing of the Pakistan Railways Year Book
and also brings out Monthly Performance Review.
60
1.2.11 Inventory visibility System (Web Based)
The Software has been developed and deployed on
Pakistan Railway web site to provide an access to all over
the Railways network. This system facilitate the Railway
employees to view stock available at different stores and
petty stores. It has enhanced and improved the Railways
working over different projects and day to day maintenance
by rapid accessibility/ visibility of available stock.
Phase-I
The software at existing Computerized Reservation Sites will be
replaced with the newly developed software.
Phase-II
All the Reservation Sites including current booking at stations will
be automated division wise, later on. The scope of this system is to
develop ticketing system which will:-
61
Provide online facility to book the passengers and other
information regarding PR to improve Railway image to the public.
Implement of report center which prints daily, monthly summary
and other MIS reports which will help for decision making.
Leverage the power Information Technology to enhance
system delivery to the passengers.
62
CHAPTER-II
Manufacturing Unit.
The Manufacturing Unit is headed by the General Manager
Manufacturing & Services and comprised of:-
Mission Statement
Timely delivery of Railway Carriages for safe, economical and
effective train operation.
63
Concrete sleeper Factories:
1. Pakistan Railways owns five Concrete Sleeper Factories,
located at Sukkur, Khanewal, Kohat Cantt, Shahinabad and
Kotri. The factory at Sukkur was established in 1967, first on
the Sub-Continent. Other four factories came up in 1979-80.
368 persons are working in CSF/Organization.
64
Pakistan Locomotive Factory, Risalpur:
The Pakistan Locomotive Factory was established at Risalpur in 1993 at
a total cost of Rs.2284 million. It is a modern factory and is equipped with
state of the art plant & machinery. This factory is spread over an area of
257 acres, out of which 100 acres are covered by the factory while on the
remaining 157 acres is the staff colony and service buildings.
A contract agreement has been signed with M/s CSR, China for the
supply/manufacturing of 05 D.E locos LC has been opened on
28-06-2013 and advance payment made on 21-08-2013. The
project is expected to be completed by December,2014.
65
Pakistan Locomotive Factory, Risalpur is also utilized for
development of spare parts for Pakistan Railways. Work orders
completed for Pakistan Railways are 1045 number amounting Rs
439.000 million, work orders completed for private sector are 34
number amounting Rs 55.875 million and work orders completed
for major repair of DE locomotives are 119 number amounting to
Rs. 194.000 million up till now.
Current Activities:
Presently, the "Project of 27 Nos. HGMU-30 Class Diesel Electric
Locomotives" is being executed in Locomotive Rehabilitation shop,
Moghalpura with collaboration of M/S EMD, (Electro-Motive
Diesel) Ltd, United Kingdom. The amount to the tune of Rs.
3100.000 Million was allocated for the Financial Year 2013-14,
whereas the total cost of the Project is Rs,
6284.000 Million. The 17 locomotives have been reached for
66
Rehabilitation in Loco Rehabilitation Shop, P.R. Moghalpura. The
preparation of foundation pad, installation of diesel engine, electric
cabinet, high tension/low tension wiring for initial 03 DE locomotives
have been completed under the technical assistance of
Service/Technical Experts of designated firm.
Future Plan:
The Project of "Rehabilitation of 27 Nos. (HGMU-30 Class) Diesel,
Electric Locomotives" is 48 months plan and its expected date of
completion is June, 2015.
Vision Statement:
To achieve excellence in Engineering Services with special
emphasis on Railway Sector while continuing to keep success and
profitability, as objective and focus.
Mission Statement:
To perform for our customers the highest level of quality services at
fair and market competitive prices.
67
Lahore : (Rupees in Million)
(i) Operation of Track Workshop at Raiwind 480.000
(ii) Operation of Track Machine Shops at Lahore 100.000
(iii) Track Machines Operation 4.800
(iv) Construction of 5 Bridges in connection with Doubling of Track
between Pattoki and Raiwind. 18.625
(v) Ballast Project Shershah 24.960
(vi) Ballast Project Shahinabad-III 15.698
(vii) Construction of Service building and level crossing between
Sahiwal and Pattoki in connection with Signalling project of PR 34.000
Total 644.083
Sukkur:
(i) Ballast Supply at Peerak 65.000
(ii) Ballast Supply at Kashmore 29.000
(iii) Construction of Bachelor Staff Hostel at Shah Abdul Latif University 42.000
(iv) IBA Central College, Kahirpur 55.000
(v) IBA Central Library 120.000
(vi) IBA Electric Sub-Station 11.577
(vii) IBA U/G Water Tank 7.636
(viii) Construction of Switch Yard Fence of 220 KV AIS Rohri Grid 7.490
(ix) Track Renewal (Deep Screening) 160.000
(x) Supply, stacking, loading of 2" Crushed stone Ballast to PR at
Daharki (8 lakh ct) 44.000
(xi) Supply, stacking, loading of 2" Crushed stone Ballast to PR at
Walhar (8 lakh ct) 36.000
(xii) Supply, stacking, loading of 2" Crushed stone Ballast to PR at
Padidan (8 lakh ct) 43.200
(xiii) Rehabilitation of Railway Track Embankment 5.125
Total 626.028
Karachi:
(i) Ballast Supply from Jangshahi Quarry-II 87.000
(ii) Rehabilitation and improvement of Rajwa, Kadhan distriburary more
minor and Sherwah large and Left Bank Canal 104.006
(iii) Construction of solid block masonry boundary wall at Jinnah in-
ternational Airport Boundary 38.870
(iv) Improvement of Shahway and Dokiyah left bank canal 47.353
Total 227.229
Islamabad:
(i) Construction of Girls Hostel at Fatima Jinnah Women University, 140.349
Rawalpindi
Total 140.349
68
3. Performance indicators during the financial year 2010-2014 are
as below:-
(Rupees in Million)
S.
No. Description 2010-2011 2011-2012 2012-2013 2013-2014
69
under the Companies Ordinance, 1984. It is governed by a Board
of Directors under the Chairmanship of Secretary/Chairman
Railways. The other members of the board include Member
Finance, General Manager/Operations, General Manager/M & S,
General Manager/ Development, Additional General
Manager/Infrastructure, Additional General Manager/Mechanical,
Additional General Manager/Traffic and Managing Director/PRACS.
Our Experience:
PRACS has completed 38 years of high quality performance in
numerous Railway related and general consultancy fields. It has
successfully completed over 200 assignments pertaining to Civil/
Mechanical Engineering, Commercial and Transportation disciplines;
including feasibility studies, project management, provision of
services, coordination of field surveys and consultancy services.
Area of Specialization:
PRACS can provide manpower and experts/consultants in various
fields such as Railway construction, maintenance, operations,
signaling and management. It can also assist in establishment of
new Railway/Road networks, workshops and transport systems.
Our international assignments during the period cover, Saudi
Arabia, Zimbabwe, Sudan, Senegal, Syria, Sri Lanka, Bangladesh
and Iran. PRACS is presently engaged in four Civil
Engineering Projects in the Kingdom of Saudi Arabia.
70
of Railways in October, 2010. PRACS has conducted a number of
chartered trips to Taxila and Khewra, Attock Khurd and Changa
Manga. The other destinations like, Kalabagh, Mangla, are also on
cards.
71
Commercial Wing:
The commercial wing of PRACS has two areas of responsibility
which are:-
72
3. Catering:
PRACS has taken over Dining Cars of the following trains, to
provide fresh and hygienic food to travelling public:-
1. Karakoram
2. Karachi Express
3. Tezgam
4. Jaffar Express
5. Akbar Express
PRACS IT Department:
PRACS IT Department was established in the year 2002, which is
playing an important role for the development of PRACS using
Information Technology in following department.
(i) Commercial/Passenger Department.
* Online Reservation and Ticketing System.
(ii) Accounts Department.
* Online E-Payroll System.
* Online Accounts and book keeping System.
Future Plan:
! Up-gradation of Reservation and Ticketing system in new
technology.
73
PRACS Mechanical Division:
Projects Completed:
S. Name of Project Value
No.
1. Manufactured and supplied 15 Nos. Bogie Tank Wagons US$ 2.00 Million
(BTOs) to Sri Lanka Railway.
2. Up gradation of Pakistan Railway's Carriage and Wagon Rs. 2.06 Million
Shops, Mughalpura.
3. Maintenance/Overhauling of 11 Nos. DG. Sets of Power Rs. 50.375 Million
Vans, of Pakistan Railway
Projects In Hand:
1. Manufacturing and supply of 03 Nos. Flat Wagons with Rs. 26.424 Million
Mobile Ramps, to Pakistan Army.
2. Supply and installation of 25 Nos. Distribution Transformers, Rs. 10.024 Million
to Pakistan Railway.
74
S.No. Name of Project Client Value
Project in Hand
8. Construction of Supervision of Bye Pass Track at Hofuf- Saudi Rs. 61.000
Al-Riyadh Section of Saudi Railway Organization. Railways Million
9. Replacement of existing Wooden Decking as per Pakistan Rs. 14.000
approved Design of Pakistan Railways including painting Railways Million
of all Bridge Steel Structure according to Pakistan
Railway's Standard Specifications of Kalabagh Railway
Bridge.
10. Planning, Designing and Construction Supervision of Pakistan Rs. 0.225
the project "Renovation/Improvement" of Railway Victoria Railways Million
Bridge over River Jhelum (form rail to rail com road) at
Chak Nizam, Distt: Mandi Baha-Ud-Din
11. Vetting of Design in connection with construction of Pakistan Rs. 0.130
Malik Ahmed Khan (1 x 115'-0") FLY Over at Km-30/0-1 Railways Million
between Gujar-Garhi-Takht Bhai Stations on NSR-DRY
Section.
Projects in Pipeline:
PRACS has planned to make Rail Food courts at different
locations of Pakistan Railways as Joint Venture (partnership) i.e.
Chaklala Railway Station (Rawalpindi) placing two Nos. of
coaches designed/refurbished for Azadi Special Train and cafe
in two coaches, play land for kids and other entertainment
components; and at Margala Railway Station (Islamabad) by
offering a food park involving different food franchises like KFC,
McDonald's, Pizza Hut, fast food chains and traditional food
etc. PRACS also established a handcraft display which will be
based on Railway vocational center products.
75
CHAPTER-III
Welfare & Special Initiative Unit
The unit is headed by General Manager Welfare & Special
Initiative who is assisted by the following heads of the Departments
(Principal Officers).
Medical Department:
Medical Department of Pakistan Railways comprises of 172
Doctors headed by Chief Medical & Health Officer. General
Manager Welfare & Special Initiative is the Executive Head of the
Department.
76
! Opening of Satellite Clinic at different dispensaries for proper
Centre for Disease Control (CDC).
77
Education Directorate:
To improve the Education System on Pakistan Railways, Ministry of
Railways requested for an Educationist from Government of Punjab on
the direction of Federal Minister for Railways. As a result, Prof. Dr.
Farhan Ebadat Yar Khan an acclaimed Educationist, a full bright
scholar who has previously served as Principal Govt. Islamia College
Civil Lines, Lahore, Govt. M.A.O College, Lahore and Chairman, BISE,
Gujranwala, has a teaching and administrative experience of 27 years
to his credit was posted in Ministry of Railways as Director Education.
The following steps have been taken by the Director Education for
improvement of Railway Schools.
78
7. Plan to start Bachelors in Education B.ED Classes in the
evening under Self Finance Scheme at Lady Griffin
College. Affiliation Process with University of Education is
under process.
Railways Sports:
The Pakistan Railways Sports Board is a sole Institution of the
country which encourages, promotes, controls and arrange
coaching, training and competitions in various disciplines of sports
in the entire Pakistan Railways.
79
Games Controlled by the Pakistan Railways Sports Board:
Men
1. Athletics 13. Judo
2. Badminton 14. Karate
3. Body Building 15. Kabaddi
4. Boxing 16. Netball
5. Basketball 17. Rowing
6. Cycling 18. Taekwondo
7. Cricket 19. Table Tennis
8. Football 20. Tug of War
9. Gymnastic. 21. Volley ball
10. Golf 22. Weight Lifting
11. Handball 23. Wrestling
12. Hockey 24. Wushu
Women
1. Athletics 5. Judo
2. Badminton 6. Karate
3. Cycling 7. Table Tennis
4. Hockey 8. Taekwondo
International Achievements:
Mr. Rashad Mahmood Butt, Sports Officer/P.R. Sports Board.
(i) Appointed as Umpires Manager in 1st Men & Woman
Challenge Cap Hockey Tournament from 1st to 8th
September-2013 at Bangkok (Thailand).
80
* Mr. Najam-us-Saeed, Inspector Sport/P.R Sports Board,
appointed as Scorer by the Emirates Cricket Board/
International Cricket Council (ICC) to supervise the ICC
U-19 World Cricket Cup from 12-28 Feb-2014 at UAE.
Men Teams
Team
Games Gold Silver Bronze Total
Position
Athletics(W) 2 1 4 7 3rd
____________________________________________________________________________________________________________
Body Building 4 2 3 9 1st
____________________________________________________________________________________________________________
Boxing 0 1 1 2
_______________________________________________________________________________________________________
Canoeing 0 0 1 1
____________________________________________________________________________________________________________
Gymnastic 0 2 1 3 2nd
____________________________________________________________________________________________________________
Judo 3 2 4 9 2nd
____________________________________________________________________________________________________________
Karate 2 3 1 6 2nd
____________________________________________________________________________________________________________
Table Tennis (M) 1 0 0 1
____________________________________________________________________________________________________________
Table Tennis(W) 0 0 1 1 3rd
____________________________________________________________________________________________________________
Taekwondo(M&W) 4 14 9 27 2nd
____________________________________________________________________________________________________________
Tug of War 1 0 0 1 1st
____________________________________________________________________________________________________________
Total 17 25 25 67
81
National Achievements:
Results of National Championships (From July 13 to June,14).
S. Medals Team
No. Event Gold Silver Bronze Position
1 Football
PFF "B" Division Football League 2013-14, 1 0 0 1st
On Nov-Dec-2013.
2 Body Building:
Mr. Pakistan & 62nd National C/Ship, 1-2 Feb, 2 2 3 2nd
2014 at Lahore.
3 Basket Ball
53rd National C/Ship, 2014 at Wah Cantt: from 0 0 0 3rd
1-8 Apr. 2014.
4 Athletics
All Pakistan National Relay Race (Men) at 0 0 1 2nd
Islamabad on 27-03-2014.
5 Hockey Women
28th National Championship at Karachi from 0 1 0 2nd
24-03-2014 to 04-04-2014.
6 Taekwondo
National Championship at Lahore from 11th to 7 8 9 2nd
13th April, 2014.
7 Gymnastic
All Pakistan Quid-e-Azam Trophy Championship 0 0 3 2nd
Karachi on 2nd 3nd March, 2014.
Total: 10 11 16
In Short Pakistan Railways Teams/Players on International and
National Level got following medals in the Sports Session (July-
2013 to April-2014).
Gold Silver Bronze
International 1 2 2
National Games 17 25 25
National Championships 10 11 16
Total: 28 38 43
82
CHAPTER-IV
Pakistan Railway Academy
1. Introduction:
In 1925, a small Railway Training School of the legendary North
Western Railway was originally established in Layallpur (now
Faisalabad). It was shifted to the present purpose-built
Walton campus named as Walton Training School. This institution
was named after Col. C.E. Walton, the Agent (as the General
Manager was then known) of the North Western Railways. In no
time, the Walton Training School became the hub of the suburb of
Lahore and the area became famous as "WALTON".
The Walton Training School took on the character and repute of its
parent organization, the North Western Railways; symbolizing the best
traditions of service, innovation, development and organizational
excellence. The performance standards of this institution received
international acclaim when, in 1954, its premises were selected by the
ECAFE (Economic Commission for Asia and Far East)- a United
Nations agency, to establish their regional Railway training centre for
training of Railway Officers and senior supervisors of Asia and the Far
East in Signaling and Advanced Railway Operations. Control of the
Center was transferred to the Government of Pakistan in January
1958. In July 1982, this academy was upgraded as the Pakistan Inter-
Regional Railway Training
College, while in May 1983, it was again renamed as Directorate of
Research and Training and finally in July 2000, it got the present
name as "Pakistan Railway Academy".
83
induction training, 43 promotion and 30 refresher Programes yearly
for Railway staff of all grades, disciplines and departments.
Officers inducted into various departments of the Pakistan Railways
through the Federal Public Service Commission as
Probationers also receive their initial training in the academy.
Short Management-training courses are also conducted from time
to time whenever required.
2. Mission:
To fulfill the growing and diversified training requirements of the officers
and staff of Pakistan Railways and the Afro-Asian member countries of
the ESCAP (Economic & Social Commission for Asia and Pacific) region,
through imparting good training in operation, maintenance and allied
technical services; and to inculcate in the officers and staff high sense of
public service, professional ethics, efficiency heuristic spirit, cost-
consciousness and productive management.
3. Vision:
To place this Academy as one of the world class Railway Training
Institute amongst the International Railway Training Institutes.
4. Objectives:
* To impart quality training for improving organizational
efficiency and cost-consciousness.
84
5. Organization:
The Academy is headed by a Director General who is assisted by
Joint Directors heading each of the engineering, disciplines viz,
Civil, Mechanical, Signaling & Telecommunications, Electrical/
Electronics Engineering and the Traffic (Operations and Commercial)
Departments.
7. Facilities:
35 well-equipped class rooms, including dedicated rooms for
special subjects. Model rooms equipped with life size and sale
working models, for hands on training networked computers Labs.
8. Lodging:
There are seven hostels with accommodation for more than 500
trainees including an exclusive hostel for the International Students
with air-conditioned and fully furnished rooms. Free mess facilities
are provided to all trainees.
9. Health Care:
A resident medical officer with a dispensary for emergency medical
cover has been provided in the Campus.
85
10. Recreation:
Academy provides for indoor, outdoor sports and games such as
football, hockey, cricket, basketball and badminton.
86
CHAPTER-V
Railway Inspectorate
Federal Government Inspector of Railways (FGIR):
1. Brief History:
Prior to 1908, control over Railways was exercised by Government
through consulting Engineers. However, in 1908 a new system of
Governmental control of Railway was introduced and the
Government Inspectors were appointed at Calcutta, Lucknow,
Lahore, Bombay and Madras and were placed under the
administrative control of the Railway Board (India).
87
Two Inspectorate Circles were established in Pakistan one in west
and other in East Pakistan and were placed under Ministry of
Communications. The East Pakistan Circle was subsequently
abolished due to "economy campaign" and since then there is only
one Government Inspector of Railways in Pakistan.
3. Major Responsibility:
The duties and functions of the Federal Government Inspector of
Railways as laid down in the Railway Act, focus mainly on the
safety aspect of Railway constructions, maintenance and operation.
While inspecting track structures, rolling stock, signaling and
interlocking installation while examining station records operational
staff, repair facilities, etc. and while holding enquiries into
accidents, the safety aspect is always borne in mind and the
reports and recommendations are based on this aspect.
The function of FGIR further encircles:-
88
(ii) Approval of plans and other works
The Federal Government Inspector of Railways performs
the function of scrutiny and formal sanction of yard
remodeling plans, signal diagrams, working rules and all
other new Engineering, Mechanical and Signaling works
concerning lines used by passenger trains.
89
CHAPTER-VI
Vigilance Directorate
Revival of Vigilance:
The present Directorate of Vigilance was revived in April/2012, by
entrusting with certain functions and powers.
Functions of Vigilance:
The functions/duties of Vigilance are of perpetual nature and
encompass all spheres of activities over Pakistan Railways such as
to identify non-adherence of rules, procedure and instructions.
The function of Vigilance Directorate is to mounitor and report to
concerned department and MOR about like.
Examine Records
Call employee for statement/questioning
Examine premises to carry out search
Carry out desired enquiries
90
Manpower:
Vigilance Wing is manned by the serving employees (officers & staff)
of Pakistan Railways, with its Head Office at Railway Headquarters,
Lahore and regional directorates at all the Divisional Headquarters.
91
CHAPTER-VII
Railway Estate Development & Marketing Company:
Pakistan Railway owns a very large land bank. Some of land is surplus
to its operational use. Taking cognizance of this opportunity, a
Directorate of Marketing was established in Ministry of Railways in
2000, which was given the task of commercial exploitation of surplus
Railway land, franchising, awarding and selling rights to international
brands and advertizing/Bill boards over Pakistan Railway net work.
The revenue so generated from these non-core resources of Pakistan
Railways was envisaged to support railway operations.
92
The Directors from private sector are eminent professionals.
REDAMCO is a private company where no invitation is issued to
the Public to subscribe for any share of the company.
All shares are under the control of board of directors and are
allotted on terms and conditions specified by the Board.
93
A similar exercise has been initiated in other Divisions of Pakistan
Railways too and prequalification of the consultants is underway.
94
CHAPTER-VIII
Internal Auditor
Establishment of CIA Office
Office of Chief Internal Auditor was established in 1999 headed by
a BS-20 officer Prior to this, the office was working under the
administrative control of FA&CAO (Modernization).
95
Backlog of Internal Audit Inspection Reports.
There are 2096 outstanding Internal Audit Inspection Reports
relating to the period from 1983-84 to 2012-13.
Issue-Based Audit as per Annual Audit Plan for the Year 2013-14
In the current Annual audit Plan 2013-14, this office has planned to
conduct Issue-based Internal Audit rather than traditional audit
inspection. This office has increased its scope of audit activities,
changed audit approach and reporting style. This office main
concern is to give top management a well defined and immediate
accountability tool for effective governance to the significant issues
that are likely to effect operations of the department.
96
PRINTED AT THE P.R. PRESS, MUGHALPURA
BY
2013-2014