Вы находитесь на странице: 1из 62

Section 7 - E L E C T R I C A L

PT. GLOBAL POWER SERVICES

SECTION 7

ELECTRICAL

Rev Date/Checked Date/Approved Date/Issued Notes


Orig Original Issue
Rev. A
Rev. B
Rev. C
Rev. D

PT. GLOBAL POWER SERVICES ©DOC2010 Page 1 of 62


Section 7 - E L E C T R I C A L

PT. GLOBAL POWER SERVICES

SECTION 7 ELECTRICAL

Index Page

Part I : Electrical Installation Specifications Testing and Check-out


7.1 General
7.2 Standards and General Instruction
7.3 Scope of Work
7.4 Technical Specification for Equipment Supplied by the Purchaser
7.5 Installation Details
7.6 Testing
7.7 Time Schedule
7.8 Drawing and Documents
7.9 Instruction for Tendering
7.10 Protection of Electrical Equipment
7.11 Location of Controls and Other Devices
7.12 Structural Modifications
7.13 Termination and Coding
7.14 Electrical Tags
7.15 Testing and Checkout Procedures
7.16 Grounding Conductor

Part II : Permit and Procedure for Initial Livening of Electrical Facilities

Appendix 1 : Isolation and Livening Permits for Use During Initial Livening of Electrical
facilities

Appendix 2 : Electrical System Energizing Procedure and Permit System

Appendix 3 : Step by Step Energizing Procedures

PT. GLOBAL POWER SERVICES ©DOC2010 Page 2 of 62


Section 7 - E L E C T R I C A L

Section 7

ELECTRICAL

Part I: ELECTRICAL INSTALLATION SPECIFICATIONS TESTING


AND CHECKOUT

7.1. General

The purpose of this section of specifications is to describe the ELECTRICAL


POWER INSTALLATION required for the Mill process electrification - all areas.

The Agreement, General Conditions of Contract, General Specifications and


Appendices govern all parts of the work and apply in full force to this
specification.

Deviations from this specification shall be specified separately and the reasons
for the deviations shall be explained. Their influence on the price shall be stated.

7.2 Standards and General Instruction

The installation and equipment shall comply with the laws and stipulations
currently in force in Indonesia.

The equipment shall comply with relevant IEC recommendations and local
standards; any exceptions shall be mentioned in the tender.

7.3. Scope of Work

7.3.1 General:

The scope shall include the following:

- Transfer from the storage area


- Erection and/or installation
- Connecting up
- Testing
- Putting to work in accordance with this specification of the equipment
specified in Section 4 and the accompanying Schedule of Equipment and List of
Drawings.

7.3.2 Installation:

The Contractor is invited to propose to the Purchaser any deviations from the
drawings and documents which he thinks might be an improvement or of

PT. GLOBAL POWER SERVICES ©DOC2010 Page 3 of 62


Section 7 - E L E C T R I C A L

some advantage to the Purchaser. However, he shall obtain the Purchaser's


approval for any deviation from this specification.

Before starting the work, the Contractor shall examine the site conditions
with other contractors so that cables, cable trays etc. can be installed properly
and appropriately, taking into consideration installation of other equipment.

If complete installation 'differs from the contract, the Contractor shall make the
necessary rectification without delay, at no charge to the Purchaser.

The Contractor shall use skilled staff for the installation work. It is expected
that foremen will have detailed information about the installation work included
in this inquiry specification.

The Contractor shall participate in meetings at the mill site which concern
electrical installation. The minutes of installation meetings shall form part of
the contract so that the changes agreed in these meetings shall be accepted by
the Purchaser and Contractor as being included in the contract.

7.3.2 Materials:

The Contractor shall measure installed cable lengths and mark them on the
cable list supplied by the Purchaser.

During the installation work the Contractor shall maintain a record of


material installed, using the same material denominations and units as in the
material lists.

This record shall indicate for each item the amount of material already
installed and the amount required completing the installation. This record shall
be updated weekly.

The material lists, the cable lists and the lists of additional and extra work
shall be handled in installation meetings. Any unclear matters shall be clarified
as soon as possible.

7.3.3 Completion:

When the installation work is complete the Purchaser and the Contractor will
compile a list for each installation package of the work done. These lists shall be
based on the material lists enclosed with this specification, with quantities
adjusted appropriately.

The basis for the above-mentioned lists shall be the following documents (all
documents must be approved between the Purchaser and the Contractor):

- cable lists
- material lists

PT. GLOBAL POWER SERVICES ©DOC2010 Page 4 of 62


Section 7 - E L E C T R I C A L

- "as built" drawings


- measurements results
- unit price lists
- minutes of installation meetings

The basis for cable tray installation shall be the direct cable ladder lengths
including necessary angles, T-pieces and cross-pieces. Only direct tray length
shall be counted as installed. This includes all necessary supports etc.

The basis for cable installation shall be the cable length from terminal to
terminal including installation and fastening materials.

After the installation work is finished a percentage of the cables and cable
ladder racks will be measured. The result will be compared to the Contractor's
corresponding length data and the total lengths will be adjusted accordingly.

The basis for the various material quantities in the electrical installation shall
be the quantities of equipment installed including all necessary additional material
(fixing materials, accessories, name plates, etc.) needed for such installation as
specified in this inquiry specification.

7.3.4 Additional Work:

Any work carried out by the Contractor which is not covered by the unit prices
shall be agreed in writing between the Purchaser and Contractor before the work
is commenced and shall be the subject of a separate order.

7.4 Technical Specification for Equipment Supplied by the Purchaser

7.4.1 6.6kV Switch gear:

The switch gear will be air insulated, metal clad with withdrawal vacuum
circuit breakers or contactors, Siemens type 8 BK 20.

7.4.2 Power Transformers:

The power transformers will be 3-phase oil immersed outdoor type of the
following ratings:

12.5 MV A 20/6.9 kV
6.3 MV A 30/6.9 kV
3150 kV A 20/0.693 kV
2000 kV A 20/0.4 kV
1000 kV A 20/0.4 kV
630 kV A 20/0.4 kV
630 kV A 660/400 kV

PT. GLOBAL POWER SERVICES ©DOC2010 Page 5 of 62


Section 7 - E L E C T R I C A L

The 12.5 MV A power distribution transformers will be delivered


without oil filling. The tanks are filled with pressurized nitrogen gas. Oil
conservator vessels, Buchholz relays and associated piping, bushings and
oil (in 170 kg drums) are delivered loose.

The Contractor’s scope of work shall include the mounting of the loose
transformers components and filling of the transformer with oil under
controlled full vacuum conditions as specified by the transformer
manufacturer (Siemens). The Contractor shall provide a suitable and
approved vacuum filling and oil treatment plant.

7.4.3 6.6k Bus duct:

Bus duct is provided to connect the transformers to the switch gear.

The bus duct consists of three insulated phase bars made of electrolytic
copper. The insulation consists of polyamide filled polyester resin.
Ratings are as follows:

6.6kV 1250A

The bus duct will be provided in sections which shall be connected


together and installed by the Contractor.

7.4.4 Neutral Earthing Resistors:

7.4.4.1 Resistors are provided to earth the neutral of the transformers of the 6.6kV
systems.

They will be of iron frame, sheet steel covered, floor standing, IP23.
Ratings arc as follows:

4.0kV 10A 15 sec

7.4.4.2 The 660 V system neutrals are earthed by resistors housed, together with
associated control components, in individual IP 23 panels for mounting on
top of the MCC incomers. Ratings are kV 2 A continuous.

7.4.5 660V and 380V MCC's:

Low voltage MCC's will be Siemens metal clad with withdrawal circuit breakers,
fuse combination starters and fuse feeders. They will be of modular construction,
floor standing.

7.4.6 660V Bus duct:

The 660V MCC's are connected to the transformers by means of bus duct
consisting of insulated phase conductors enclosed in a cast epoxy resin outer

PT. GLOBAL POWER SERVICES ©DOC2010 Page 6 of 62


Section 7 - E L E C T R I C A L

cladding. Ratings are as follows:

750V 3000A 1200A

The bus duct will be provided in Sections which shall be connected together and
installed by the Contractor.

7.4.7 Variable Speed Drive Cubicles:

These are ABB SAMI GS and SAMI STAR frequency converters, enclosed
type, for wall or floor mounting as indicated.

7.4.8 Miscellaneous Cubicles. Panels and Racks:

Cubicles, panels and racks will be supplied for various applications, mounted in
the electrical rooms or in the field. They will be of modular sheet steel
construction, floor standing, either individual or forming a suite.

7.4.9 Local Control Boxes:

These will be of sheet steel construction and shall be installed by the Contractor
in the field as indicated in the drawings.

7.4.10 Cable Trays:

Cable trays will be aluminum prefabricated ladder or Hat tray type consisting of
straights, bends, tees and other pieces as indicated in the cable tray drawings.

The Purchaser will supply the material for the supporting brackets, consisting of
mild steel channel or angle in standard lengths. The Contractor shall fabricate
the required supporting brackets from this material and shall paint same after
fabrication.

The supporting brackets shall be mounted at sufficient intervals (not exceeding


3 meters) to provide a rigid fixing and the installation shall be designed for a
distributed load of 80 kg per meter and spot load of 80 kg between supports with
a maximum deflection of 1/200.

Where cable trays enter cable rooms they shall be installed with a slight
downward slope (approximately 5%) to the outside.

7.4.11 Cables:

Cables will in accordance with the Cable Standard.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 7 of 62


Section 7 - E L E C T R I C A L

7.4.12 Installation Material:

The Purchaser will supply all cable glands, lugs, terminating materials, clamps,
and marker ties and fixing materials. The Contractor shall supply only
consumable items.

7.5. Installation Details

7.5.1 Installation of Cable Trays and Cables:

a) The cable trays shall be supported at intervals not exceeding the maximum distance
specified by the manufacturer.

b) The location of cable tray droppers and field mounted items will not be shown on
the installation drawings. The Contractor shall observe that when locating these, he
shall not restrict future maintenance and operation of the equipment nor block transport
or walkways. He shall also try to utilize the same droppers for the requirements of the
instrument installation.

c) The Contractor shall cooperate with other trades regarding the location of cable tray
supports and droppers in order to avoid any interference.

d) The Purchaser reserves the right to request the Contractor to relocate any drop-out
which, in his opinion, does not comply with the general practice of the trade without
extra cost to the Purchaser. No horizontal sections of the drop-outs shall be located
lower than 2.1 meters above walking floor level.

e) Where cable trays pass under or over steam lines, heat proof barriers shall be
installed between the tray and the steam lines. A minimum of 150 mm clear space
between cable and the surface of pipes or pipe insulation shall be allowed.

f) Cables shall run on the trays to which they are assigned in the power layouts and cable
lists.

g) The estimated length of each cable will be shown on the cable schedules provided by
the Purchaser. The Contractor shall immediately inform the Purchaser if there is a
difference between the estimated and installed length.

h) Cables shall be run straight and parallel within the trays,

i) Single core AC cables shall be run in trefoil.

j) Where there is only one tray for both power and control cables, they shall be clearly
separated.

k) Ties shall be used for securing cables on ladders as follows:

i) all cables shall be tied on bends;

PT. GLOBAL POWER SERVICES ©DOC2010 Page 8 of 62


Section 7 - E L E C T R I C A L

ii) larger cables shall be spaced and shall be tied at intervals that will ensure maintenance of
the spacing called for in the standards;

iii) on horizontal runs, spaced cables only shall be tied. On vertical runs however, all cables
shall be tied. Maximum distance between ties shall be 60 cm;

iv) all cables shall be secured within 60 cm of terminating boxes or apparatus.

1) All cables and wires shall be installed in continuous lengths from one end of the circuit to
the other if not otherwise specified.

m) Power cables shall be installed in one layer only without spacing. Control cables shall be
installed in layers.

n) All cables shall be numbered at both ends in accordance with Crapp-m10, "Numbering
Procedure for Electrical Parts and Equipment".

o) The Contractor shall drill all gland plates as necessary to accept the correct size cable
gland.

p) All cables to field mounted equipment shall enter from below.

q) Where non-armored cables leave ladders outside electrical rooms, they shall be run in
galvanized welded steel conduit or otherwise mechanically protected.

r) All cables passing less than 1.5 meters above ground shall be protected from mechanical
damage.

s) It must be possible to energize part of MCC and control rack and take starters and modules
into operation while the cabling work for the remaining starters and modules goes on.

t) Induction motors will be supplied by the Purchaser. The motors will have a connection
box and terminals for cable connecting.

7.5.2 Earthing

All equipment required to be earthed by the Inspection Authority shall be earthed


whether specifically mentioned on the drawing or not.

Earthing wire for the main cable routes shall be 120 mm2 PVC insulated copper.

All earth conductors above ground shall be so located as to be readily visible for
inspection.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 9 of 62


Section 7 - E L E C T R I C A L

All earth conductors and armoring in cables shall be terminated at both ends
unless otherwise specified by using approved connectors.

All earth connections shall be made only after the surface is thoroughly
cleaned of pain and dirt. Earth wires shall not run parallel to single core cables.

The joints of the main earthing loop shall be of the thermal type.

In each cable room or MCC room there will be a number of approximately 1


meter long, 10 x 100 mm copper earthing bars.

Individual pieces of equipment shall be connected either by separate earthing


cable or by using one core of the supplying power cable.

7.6. Testing

7.6.1 General:

The Contractor shall carry out testing and all other services necessary to put
the electrical system in condition ready for service.

The Contractor shall provide all two-way radios, instruments, equipment and
personnel necessary for testing the electrical installation and shall make sure
that such personnel are available during final testing of the process system as
considered necessary by the Purchaser to make immediate adjustments.

The costs of all testing activities shall be included in the total price.

7.6.2 Cable Testing:

All cabling and wiring shall be tested for continuity, short circuits and earth
faults.

6.6kV cables shall be submitted to pressure testing after installation in the presence
of the Purchaser.

Before energizing, the Contractor shall carry out the following cable tests:
- tightening up the joints
- checking of the power cable connections
- checking of the control cable connections

Connections shall be checked by using a tester. "OK" sign shall be marked in pen
on the corresponding wiring diagrams. These marked copies shall be given to the
Purchaser's supervisors.

Megger tests shall be made on all power cables.

Megger tests shall be made on all motors prior to connection of power leads.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 10 of 62


Section 7 - E L E C T R I C A L

No electronic circuits shall be meggered.

It shall be the Contractor's responsibility to make certain the megger testing


does not damage electrical equipment or injure personnel.

7.6.3 Operation and Mechanical Tests:

The following tests shall be included by the Contractor:

- check and ensure the correct phase sequence;


- check control voltages;
- check motors and motor starters according to equipment lists;
- check and adjust thermal relays according to motor nominal current;
- check, test and adjust protective relays for breakers;
- check correct fuses are fitted;
- operation of the control circuit including function test of:
- safety switch
- local switch
- field devices '
- operation of the control circuit under tension, for correct function up to the
input/output units of the DCS 1/0 rack;
- check and ensure correct direction of rotation for motors;
- measure and record motor currents;
- Contractor shall record all results and settings of various protection relays after
testing of relays is over and submit the result to the Purchaser.

Immediately prior to energizing a motor for the first time, the Contractor shall
request the Purchaser to check out the motor for proper and adequate lubrication.

The Contractor shall submit the test result on a test report form supplied by the
Purchaser.

7.7. Time Schedule

The electrical installation work will take place simultaneously with civil
construction and pipe and machine installation. Therefore the Contractor should not
expect free and uninterrupted access at all times in all areas. The Contractor
shall take into consideration these other installation activities.

The Contractor shall ensure that lack of material or labor will not prevent the
installation from being done according to the time schedule.

7.8. Drawings and Documents

7.8.1 Installation Drawings:

The Purchaser will supply the following drawings and documents for electrical

PT. GLOBAL POWER SERVICES ©DOC2010 Page 11 of 62


Section 7 - E L E C T R I C A L

installation:

- one line diagrams;


- electrical circuit lists (i.e. motor lists);
- wiring diagrams;
- power layouts showing approximate location of equipment and cable trays;
- electrical room layouts;
- cable tray installation drawings (piping drawings);
- cable tray installation drawings for electrical rooms;
- cable lists;
- MCC and panel lists; '
- MCC and panel layouts and specifications;
- earthing layouts;
- earthing connection diagrams;
- rack room layouts;
- control room layouts

All other drawings and documents needed by the Contractor shall be provided by
him and approved by the Purchaser and a copy shall be given to the Purchaser.

All drawings used for electrical installation shall be approved by the Purchaser and
stamped accordingly.

7.8.2 Enquiry/Contract Drawings:

Drawings accompany this specification to describe the work and to supplement the
information contained in this specification. It shall be known and understood that
addition detail drawings may be prepared and issued during the course of the work to
modify or clarify this specification. Such drawings shall thereupon become part of
this specification.

7.8.3 Time Schedule for Drawings:

Below is the time schedule concerning the delivery of the final installation
documents (documents for various installation areas; the time is weeks before the
corresponding part of the work starts):

Cable tray drawings 2 weeks - final

Power cable lists, power layouts and 4 weeks - preliminary


equipment layout drawings 2 weeks - final

Control cable lists 2 weeks - final

Connection diagrams 2 weeks - final

The power cable lists and the control cable lists may be delivered at different times.
Non-receipt of the power cable lists shall not prevent lying of control cables and vice-

PT. GLOBAL POWER SERVICES ©DOC2010 Page 12 of 62


Section 7 - E L E C T R I C A L

versa.

7.8.4 As-Built:

When the installation work is finished the Contractor shall deliver two sets of
working drawings on which all "as-built" modifications are marked with red pen.

The installation will be accepted only after the above drawings have been handed
over.

7.9. Instruction for Tendering

7.9.1 The Contractor shall quote a lump sum price for the complete installation in
accordance with this specification and accompanying Schedule of Equipment.

This lump sum price shall be valid for changes to the final quantity of
plus/minus 15%.

7.9.2 To cater for changes to the final scope in excess of the plus/minus 15%, the
Contractor shall quote take-out/take-in unit prices for each and every type of item
listed in Appendix I.

7.9.3 The Contractor shall also quote hourly labor rates for:

- all classes of labor


- all normal and premium time rates.

7.10. Protection of Electrical Equipment

7.10.1 All electrical material, equipment, cables and all work during the installation and
acceptance periods shall at all times have adequate weather, moisture and
mechanical protection.

7.10.2 All Electrical Rooms and work areas must be kept in a clean, neat and tidy
condition at all times.

7.10.3 Care of the motors in storage shall conform to the Mechanical Equipment
Installation Specifications Section 10, #2.

7.11. Location of Controls and Other Devices

7.11.1 The general location of local and remote control stations and other wiring
devices shall be mounted in such a manner as to afford the maximum
protection from mechanical damage, moisture, chemicals and dirt.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 13 of 62


Section 7 - E L E C T R I C A L

7.12. Structural Modifications

7.12.1 Fastenings for attaching electrical cables, conduit, ducts and other electrical
equipment, if not cast-in-place with the concrete, shall be an expansion type as per
the Design standards.

7.12.2 All openings into Electrical Rooms, control consoles and other electrical
equipment shall be sealed to prevent moisture and foreign matter from entering.

7.12.3 All openings into exterior walls or roofs of buildings shall be flashed and
sealed in a manner consistent with their construction and, in the case of roofs,
shall be flashed and sealed to the approval of the contractor who installed it
and is guaranteeing the installation of the roofs.

7.13. Termination and Coding

7.13.1 Each cable shall be identified at each connection with the proper code number as
shown on the drawings or design standards; likewise each conductor shall also
be identified at each connection.

Each relay, control, or other devices shall also be identified as shown on


drawings or design standards. The type and manufacture of identification
material shall be shown on the drawings or design standards.

7.14. Electrical Tags

7.14.1 On completion of each portion of the electrical installation an "Electrical Tag"


shall be attached to each MCC of a piece of electrical equipment. The
"Electrical Tag" will be furnished by Riau Pulp and a copy of the tag is appended
in Section 6.

7.14.2 The "Electrical Tag" on a MCC for a piece of electrical equipment shall relate
to that piece of equipment and to all cable supplying power to the equipment
including the connection of the cable to the preceding piece of equipment.

7.14.3 Each portion of the installation shall then be tested and "checked out" in the
sequence and in the manner described in Chapter 7.

7.14.4 On completion of each stage of the testing and checkout, the contractor's
Superintendent shall satisfy himself that the stage is complete and shall date and
sign the tag. He shall then advise the Area Electrical Engineer of the completion
of the stage, and request the Engineer's approval before going on to the next
stage.

7.14.5 In the case of motors, there will be an "Equipment Tag" mounted on the piece of
equipment to be driven by the motor. The installation of the motor shall be tested
and checked out as set out in the appropriate stages of the Equipment Installation
Check out Procedure. The Contractor's Superintendent, when satisfied that each

PT. GLOBAL POWER SERVICES ©DOC2010 Page 14 of 62


Section 7 - E L E C T R I C A L

stage has been properly completed, shall date and sign the Equipment Tag and
shall advise the other Contractor who is responsible for the installation of the
driven equipment that the installation of the motor has been properly completed.
When the other Contractor is satisfied that the motor installation is completed and
does not interfere with the alignment of the equipment, he will sign the
Electrical Tag in the space provided.

7.15. Testing and Checkout Procedures

7.15.1 Stage 1
Installation ready for Testing and Check out (Visual check to see if the following is
completed)

7.15.1.1 The whole assembly is clean inside and outside. No loose cables
hanging free. Ground wires clear of bus work and properly
grounded.

7.15.1.2 The unit is adequately grounded.

7.15.1.3 The main bus is the proper phasing.

7.15.1.4 All equipment is correctly identified, using at least 2 1/2 cm figures,


front and back.

7.15.1.5 Each starter is identified with correct drive number, drive title and
power rating.

7.15.1.6 Feeder cables, if single conductors are used, that the load end of the
cables are insulated from the enclosure and from one another, the
connecting gland or clamp should also be insulated with plastic
electrical tape. This is to prevent shock from sheath voltage.

7.15.1.7 All cables leaving Electrical Equipment have proper cable clamps
or glands.

7.15.1.8 All unused holes are adequately plugged.

7.15.1.9 All openings are sealed to prevent steam and other foreign matter
from entering.

7.15.1.10 Relay sections are properly identified.

7.15.1.11 Equipment and the immediate area is clean and tidy.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 15 of 62


Section 7 - E L E C T R I C A L

7.15.1.12 Motors and connected units have been properly fastened down to
the base, and aligned. (Signatures affixed by others to the
alignment stage of Mechanical Check-out Tag, 2S-20.01).

7.15.2 Stage 2-
Insulation Resistance Test

7.15.2.1 Take megger test and record for all control circuits, motor leads,
feeders, etc. on equipment up to and including 5000 volts. Do not
megger static devices, tachometer or pulse generators, check with
ohm meter.

7.15.2.2 DC hi-pot test feeders 15 kV and higher voltage to manufactures


recommended test voltages as noted in the Design Standards.

7.15.2.3 Megger test motor and cable as one unit.

7.15.2.4 Stress cones must be completed and be in accordance with the design
standards, prior to the DC Hi-pot test. Pig-tails are not to be added or
connected to stress cones at load and if length is less than 130m.

7.15.2.5 Transformer windings are to be megger tested only, between windings


and grounding.

7.15.2.6 When cables are re-connected they are to be in the proper phase
sequence.

7.15.3 Stage 3-
For each type of equipment, check as noted.

7.15.3.1 High voltage Switch gear - check the following:


1. Main supply bus is the proper phasing. That is front to back 1,2
and 3. Supply to and from breakers, facing back of cells, left to
right is 3-2-1.

2. All interconnections between cells are properly made and


insulated.

3. DC supply is complete with automatic charger and battery is fully


charged.

4. Batteries are suitably stored, and all connections are well made
with no chance of loose connections. Vaseline has been applied
over all terminals and connection points.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 16 of 62


Section 7 - E L E C T R I C A L

5. Outgoing cables are installed in accordance with Riau Pulp


design standards or manufacturing drawings. Terminals must be
insulated and cables supported.

6. Stress cones are adequate and all pig-tails are connected with
the ground lead and must be returned back through the ground
fault current transformer and then grounded.

7. If a pothead is used, it must be insulated from the frame with a


ground connection, returned back through the ground fault
current transformer and then grounded.

8. All relays and protection devises are wired correctly and are
tested, such testing procedure will be available from the
Engineer.

9. Each cell is identified in the front as per design standards, and


the back using at least 2.5 cm figures.

10. All instruments and relays are identified for their use.

11. All cells are clean including the whole electrical room. Concrete
floors should be painted if possible before the units are
energized. This is to prevent concrete dust from entering the
cells.

12. The top of cells are sealed with silicone rubber caulking
compound or the equivalent to prevent water, etc., from entering
the cells if switch gear is not located in an air conditioned room.
This is particularly important between 'cells and extension
sections added to the rear for extra cable, etc.

13. A single line diagram of the primary supply and feeder system
shall be wall mounted as close to the cells as possible.

14. Spare breaker (or breakers) should be cleaned, checked, tested


and then protected with a clear plastic sheet ready for instant
use.

15. Emergency lighting units are installed.

16. If more than one supply is provided, phase relationship and


phase angle must be proven before any attempt to parallel is
made. The Engineer will supply the necessary procedure for this
testing.

17. Interlock device on breaker unit panels must be proven in proper


working order.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 17 of 62


Section 7 - E L E C T R I C A L

18. Arc chutes arc properly installed.

19. All PT fuses are correct rating and properly fitted.

20. If additional equipment relays, meters, CT's or PT's have been


added in the field, see specific check list for added items.

21. Each breaker, including the main, should be operated three times
to prove operating condition of the breaker and also that the
protection devices are ready for operation.

Note: When early breaker is to be racked-in for the first time,


alignment of slabs shall be checked. It is required that the
racking-in of the breaker be by hand with careful checks.

22. All unused future feeder terminals are taped.

7.15.3.2 Power Generator - Check the following

1. Generator supply terminals are correctly connected Tl to phase


A, T2 to B, T3 to C.

2. Generator Bus, to high voltage switch gear is connected to


correct phases. (See high voltage switch gear check list).

3. Terminals T4, 5 and 6 are properly connected (and insulated) to


the Storable Current Transformers with the polarity marks as per
drawings.

4. Secondary connections from SCTs are properly connected.

5. Differential CT’s are correctly connected with polarity marks as


per drawings.

6. Grounding resistors is properly mounted using insulator legs and


connections are tight.

7. The CT's between ground resistor and ground to be properly


installed and connected with polarity mark facing the resistor.

8. Connections to Power Potential Transformer for exciter are of


correct phasing.

9. Capacitors and lightning arresters are correctly connected.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 18 of 62


Section 7 - E L E C T R I C A L

10. The secondary connection from the PT's are correctly


connected.

11. All electrical components at the generator are properly protected


from weather and personnel.

12. Static exciter and regulator are correctly connected and properly
grounded.

13. RTD's are connected and tested as a complete system.

14. Check differential CT's in main breaker cell to assure the


polarity marks are facing away from the generator.

15. Generator bus connection at main switch gear for proper


phasing be insulated correctly to avoid corona.

16. Assist to check relays, meters and other devices forming part of
this generator system as shown on the drawings.

17. Check all remote controls, meters and other devices forming
part of this generator system as shown on the drawings.

7.15.3.3 Power Transformers - Check the following

1. Transformer Oil level.

2. Take oil sample top and bottom, check dielectric strength.


Should be 22 kV or higher for standard oil, 30 kV or higher for
Askarel.

3. Note: If oil is to be passed through filter papers for removing


water etc., the oil may acquire an electrostatic charge; this will
transfer back to the transformer windings. To avoid this
hazardous condition, ground all transformer terminals, tank and
oil filtering equipment.

4. Visual examinations for oil leaks, etc.

5. Connection between neutral insulator and grounding resistor is


insulated.

6. Sudden pressure switch and relay and other alarm points are
working properly. See manufacturer's instructions for details.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 19 of 62


Section 7 - E L E C T R I C A L

7. Low voltage terminal bushings are clean and connections tight.

8. If flex connections are used, be sure sufficient space or


insulation is provided.

9. Check for drain hold in low voltage enclosure.

10. Primary switch and/ or connections are adequate and workable.

11. Ground connections of transformer, neutral resistor, enclosure


fence, etc.

12. Tap changer switch should be set in center position unless


advised otherwise.

7.15.3.4 Medium Voltage Switch gear - Check the following:

1. The main bus is in the proper phasing.

2. Contacts are clean, with proper tension, and all moving parts are
free and properly aligned.

3. All terminals are tight and properly made.

4. Check overload elements, fuses or breakers for correct sizes in


accordance with design standards.

5. If motor is synchronous, check field contactor and discharge


resistors. Remove field lead test discharge resistor and contactor
as one unit for continuity. At this time test field leads and motor
field for continuity.

6. Operate contactor in test position to prove all controls,


interlocks, etc., are functioning as described on the drawings and
design standards.

7. Arc chutes are properly installed.

8. All PT fuses are correct rating and properly fitted.

9. If mechanical check-out tag has been completed and signatures


are affixed indicating motor is ready for rotation check; place
contactor in operate position and "jog" motor for rotation. If
rotation is wrong change connections at starter. Sign check-out
Tag for rotation stage after completion.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 20 of 62


Section 7 - E L E C T R I C A L

7.15.3.5 Low Voltage Switch gear - Check the following:

1. The main bus is the proper phasing.

2. Contacts are clean, with proper tension, and all moving parts are
free and properly aligned.

3. All terminals are tight and properly made.

4. Check overload elements, fuses or breakers for correct sizes in


accordance with design standards.

5. Operate breaker in test position to prove all controls, relays, etc.,


are functioning as described on the drawings and design
standards.

6. Arc chutes are properly installed.

7.15.3.6 Motor Control Centers and Starters - Check the following:

1. The main bus is the proper phasing

2. Contacts are clean with proper tension, and all moving parts are
free and properly aligned.

3. All terminals are tight and properly made.

4. Remove overload elements, then energized starter to prove all


controls, interlocks, etc., are functioning as described on the
drawings and design standards.

5. Check overload elements, fuses or breakers for correct sizes in


accordance with design standards.

6. Replace overload elements and 'jog' motor for rotation, if


mechanical check-out Tag has a signature affixed indicating
ready for rotation check. If rotation is wrong change connections
as starter. Sign check-out tag after completion.

7. All devices, other than starters are identified and will operate as
the drawings indicate.

7.15.3.7 AC Motors

Check the following in conjunction with appropriate stages of


Mechanical Specifications:

PT. GLOBAL POWER SERVICES ©DOC2010 Page 21 of 62


Section 7 - E L E C T R I C A L

1. Rotors are free.

2. If motor is synchronous, check that slip rings are clean and


brushes are free with adequate pressure.

3. If motor is totally enclosed, remove drain plugs to check for


water.

4. With motor running check for vibration or indication of bearing


problems.

7.15.4 Stage_4 -Test Run

7.15.4.1 These checks are required if any of the following is


encountered during the initial operation of the equipment:

1. Motor trips from overload heater.

2. Motor runs hot.

3. Breaker trips or fuse blows.

7.15.4.2 If breaker trips or fuse blows, re-megger motor leads and check
amperes reading and voltage at motor terminal box.

7.15.4.3 Motor runs hot or trips from overload heater, check amperes reading,
and voltage at motor terminal box.

7.15.4.4 Record amperage taken and report any abnormal conditions


immediately to the Engineer.

7.15.4.5 Notify Preventative Maintenance Department in advance as a


vibration analysis report is required prior to accepting the motor.

7.15.5 Stage 5 - Installation Completed

7.15.5.1 Each piece of equipment shall, upon completion of all the required
check-out stages the Electrical and Mechanical Check-out Tags, secure
the approval of the Area Engineer on the installation completion.

7.15.5.2 Any field changes made to original plans shall be recorded on a set
of 'as built drawings' and forwarded to Owner Plant Superintendent
upon completion of the installation.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 22 of 62


Section 7 - E L E C T R I C A L

7.15.5.3 Work areas and storage area shall be clear of surplus


materials, tool cribs, etc.

7.15.5.4 All damaged equipment and material has been repaired or replaced.

7.16 Grounding Conductor

The grounding conductor of the wiring system shall be No. 4/0 AWG bare
copper conductor. Except where conductor may be in direct contact with
aluminum, conductor shall have a green insulated jacket.

7.16.1 Installation of Grounding Conductors

The 4/0 grounding conductor will run around the perimeter of each building to
form a ground grid. The conductor shall be outside the foundation wall.

Run shall be continuous, splices required will be by copper welding or


compression fitting.

Loops shall be provided at each corner of buildings for bolted connection of


ground cable to building steel and future connections.

Loops shall be provided at each electrical room and transformer slab location and
provision shall be made to run ground conductor to each piece of electrical
equipment as detailed on the electrical room and transformer slab layout drawings.

Grounding conductor shall be connected to ground plates mounted on the outside


face of the foundation wall. Ground plates will be located adjacent to
grounding electrodes as noted on the mill grounding layout drawing.

Grounding conductor shall be installed and connected between each building


grid to form the overall mill grid. Ground conductor shall be buried a minimum
of 1 meter, grade marked at each end where entering into grade, and shall be
protected with a treated plank covering.

7.16.2 Grounding Electrodes

2 cm diameter x 3m long copper weld rod electrodes shall be installed at


location as noted on the mill grounding layout drawing. These should be
assembled in a group of three (3) or more if required, to have a combined resistance
to ground not greater than 1 OHM. Ground conductor from electrodes shall be
connected to ground plate for testing purposes.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 23 of 62


Section 7 - E L E C T R I C A L

Rules and Inspections

Upon completion of installing ground conductors in foundation form work,


contractor shall obtain the Electrical Superintendents written approval prior to pouring
concrete.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 24 of 62


Section 7 - E L E C T R I C A L

Part II: PERMIT AND PROCEDURE FOR INITIAL LIVENING OF


ELECTRICAL FACILITIES

Contents:

1. Introduction

2. Responsible Persons

2.1 The Construction Representative


2.2 The Energizing Coordinator
2.3 The Responsible Commissioning Engineer, Electrical
2.4 The Energizing Controller

3. Permit and Procedures

3.1 Permit
3.2 Procedure
3.3 Principles Incorporated into the Procedure
3.4 Actions Covered by Procedure

4. Livening Circuits for Bump Testing of Motors

5. Safety Locks and Keys

5.1 Construction Representative Locks (Red)


5.2 Responsible Commissioning Engineer Locks (Blue)
5.3 Energizing Controller Locks (Gold - unpainted)

6. Operational Activities Covered by Procedures

7. Switching Requests

Appendix 1: Isolation/Livening Permit

Appendix 2: Electrical System Energizing Procedure and Permit System

Appendix 3: Step-by-step Permit Procedure

Appendix 4: Typical Switching Request

PT. GLOBAL POWER SERVICES ©DOC2010 Page 25 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL


LIVENING OF ELECTRICAL FACILITIES

1. Introduction

This document addresses the livening of electrical facilities during the initial
energization program.

1.1 Definitions:

Energizing refers to making a system "Live" or electricity being put on to a system after
that system has been commissioned and is approved.
Livening refers to electricity being put on to a system for the "First Time" only.

2. Responsible Persons

To exercise direction and control over energization and carry out all necessary
switching operations under permit control, four officials are required. Their
responsibilities and duties are defined in detail in the permit procedure, Appendices 2 and
3.

The following gives a summary of the responsibilities and duties of the respective
officials.

2.1 Construction Representative:

There are a number of defined construction areas within the project, each having
its own electrical supervisor who is in charge of electrical construction work or in
charge of subcontractors doing the work. The electrical supervisors will be the
Construction Representatives (CR) for the livening of electrical facilities in their
respective areas. The Construction Representative will advise the Energizing
Coordinator which facilities are ready for livening, having confirmed the completion of
checkout of the facilities, the category 1 punch items and the withdrawal of all
construction personnel from the facilities. In the case of electrical facilities within sub-
stations, he will hand over control of entry into the building premises to the
Responsible Commissioning Engineer, Electrical, subject to the issue of an Interim
Acceptance Certificate for the sub-station building and on the signing of a "Ready
for Commissioning" (RFC) Certificate for the substation.

2.2 Energizing Coordinator (Area Electrical Representative):

The Energizing Coordinator (ECR) acting on behalf of and in support of


construction will initiate permits and switching requests and the preparation of
these in writing. He will coordinate the safe and orderly livening of facilities in a
manner that will ensure the prevention of exposure to inadvertent livening of
facilities still being worked on by construction.

He will ensure that energization of facilities takes place without hindrance to

PT. GLOBAL POWER SERVICES ©DOC2010 Page 26 of 62


Section 7 - E L E C T R I C A L

construction in progress.

He will prepare and submit detailed switching requests to the Responsible


Commissioning Engineer, Electrical, for review, approval and execution and will keep
detailed status records of the complete network and all isolation permits issued.

2.3 Responsible Commissioning Engineer, Electrical Horst Unger):

The Responsible Commissioning Engineer, Electrical (RCEE) will take over control of
facilities to be livened, lock up facilities to prevent unauthorized access or accidental
contact with live conductors and take all necessary steps to ensure safety of personnel
and plant equipment.

He will review and approve all switching requests before sanctioning these and passing
them on to the Energizing Controller for execution. The Responsible Commissioning
Engineer, Electrical will be the senior Operations Electrical Engineer carrying legal
appointment as fee official in overall charge of the permanent power distribution
network.

2.4 Energizing Controller (Name):

The Energizing Controller (EC) will be an Operations Representative nominated by


the Responsible Commissioning Engineer, Electrical and authorized to carry out all
switching required to energize or isolate facilities. The Energizing Controller will not
carry out any switching without recourse to an approved switching request, issued by the
Energizing Coordinator and passed on to him by the Responsible Commissioning
Engineer, Electrical, with whom he will review and agree to the switching request
before proceeding with switching.

3. Permit and Procedure

The permit and procedure are to secure permission to proceed with livening.

3.1 Permit:

The format of the permit which will be used is illustrated in Appendix 1.

3.2 Procedure:

The procedure for the initial livening of electrical facilities is detailed in Appendix 2.
It is consistent with Riau's practice and incorporates the minimum requirements to ensure
effective control for safe and orderly livening.

3.3 Principles Incorporated into the Procedure:

For clarity of how the procedure is structured and applied the following describes
the main principles and terminology incorporated into the procedure.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 27 of 62


Section 7 - E L E C T R I C A L

a) The facility (Circuit) to be livened must be identified. Following checkout of all items of
equipment making up the facility and completion of Category 1 punch items, livening
of any section of a power distribution network or facility may only proceed after the
Construction Representative has notified the ECR that the electrical construction is
complete and the facility is ready to liven.

b) To make a circuit safe it must be electrically isolated from the source of supply. This
is accomplished by opening the feeder circuit breaker and isolating the switch.

c) To establish control over livening of facilities the Energizing Coordinator will,


prior to initial livening, prepare and issue switching requests to isolate all circuits
in the facility, both incoming and outgoing and all tie breakers (bus-couplers), and
will cause all feeder circuit breakers and tie breakers to be opened, locked out and
permitted out. He will initiate the isolation permit with the Responsible
Commissioning Engineer, Electrical, for incoming feeders and tie breakers. (These will
be locked out by the Responsible Commissioning Engineer, Electrical and the
Energizing Controller, each with his own lock.) The party to whom the permit is
issued becomes the permit holder.

d) A circuit under permit control is referred to as "permitted out". The permit holder
puts his own lock on the circuit breaker for the period of time he holds the permit,
to prevent anyone from inadvertently closing the circuit breaker and livening the
feeder.

The official responsible for switching (Energizing Controller) also places his lock on
the circuit breaker to prevent unauthorized closure of the circuit breaker. A copy of the
isolation permit is fixed to the circuit breaker and the circuit is then referred to as
"locked out, permitted and tagged".

e) The withdrawal of a permit (referred to as the "Permit Release") will be necessary to


allow a circuit to be made live.

No circuit may be made live unless the permit, against which it was isolated and
taken out of service, has been cleared.

The permit release thus becomes the main safeguard to control safe livening of
circuits as the permit release can only be affected by the holder's endorsement of the
Energizing Coordinator's master copy. The Energizing Coordinator will not issue a
switching request for the livening of a circuit until he is in possession of the cleared
permit.

f) The closing of any circuit breaker may only be done against a switching request issued
by the Energizing Coordinator and approved by the Responsible Commissioning
Engineer and this is the second safeguard to controlling safe livening.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 28 of 62


Section 7 - E L E C T R I C A L

3.4 Actions Covered by Procedure:

There are only four different actions allowed for in the procedure, these being:

a) The issue of a switching request to isolate a circuit, together with the permit to cover
the isolation of a circuit to be locked out, prior to being energized for the first time.

b) The issue of a switching request to isolate a circuit, together with the permit to cover
the isolation of a circuit to be taken out of service after it has been energized and placed
into service.

c) Release (withdrawal) of a permit and issue of the switching request to return a


circuit to a "Ready for Service" condition (not energized).

d) Release (withdrawal) of a permit and issue of the switching request to return a


circuit to an "In Service" condition (energized).

4. Livening Circuits for Bump Testing of Motors

The procedure makes provision for a temporary release of the isolation/livening


permit to allow:

a) bump testing and uncouple test running a motor where its feeder circuit is isolated
and locked out under an initial isolation permit; and

b) access to a motor starter cubicle in order to complete construction work, necessitating


temporary removal of locks without livening of the circuit where the circuit is
isolated and locked out under permit.

5. Safety Locks and Keys

For the purpose of locking out feeders, three sets of locks will be necessary (one
set for each of the officials designated in paragraphs 2.1, 2.3 and 2.4). A
combination of only two locks applied simultaneously to a feeder circuit breaker
by two of the designated officials will be necessary to secure lockout in
accordance with the procedure.

Each official will retain control over the keys for his own set of
locks and it is proposed that the key combination for the locks be
arranged as follows: '

5.1 Construction Representative Locks (Red):

The Construction Representative will have a set of locks for his own area. Ideally,
each lock will have the same key (for different areas the locks must have different
key combinations).

PT. GLOBAL POWER SERVICES ©DOC2010 Page 29 of 62


Section 7 - E L E C T R I C A L

5.2 Responsible Commissioning Engineer. Electrical. Locks (Blue):

These locks should be keyed alike to obviate the need to carry around large
bunches of keys.

5.3 Energizing Controller Locks (Gold):

These locks should be keyed alike but with a different key combination to those
of the Responsible Commissioning Engineer set.

6. Operational Activities Covered by Procedures

The step-by-step procedural activities to be taken by each of the designated officials


and covering all possible operations, with which they will be faced, are tabulated in
Appendix 3. The following operations are covered:

a) Procedure No 1: To ensure that all feeder breakers (incoming and outgoing) and all
bus-section (tie) circuit breakers are isolated and locked out and to initiate permit
control over livening of facilities (prior to livening the facility under consideration for
the first time). Compliance with this procedure is essential to set up and place the permit
system in operation.

b) Procedure No 2: To take an energized feeder circuit out of service.

c) Procedure No 3: To take an incoming breaker or tie breaker out of service.

d) Procedure No. 4: To release a feeder circuit for service without energizing.

e) Procedure No. 5: To release and energize a circuit for service.

f) Procedure No. 6: To liven a feeder temporarily for construction testing and to isolate it
again on completion of the tests.

g) Procedure No. 7: To temporarily remove locks from motor starter cubicles, which are
isolated and locked out to allow access for completion of construction work?

h) Procedure No. 8: To release and energize an incoming breaker or tie breaker.

7. Switching Requests

Switching requests will be prepared by the Energizing Coordinator and issued to the
Responsible Commissioning Engineer, Electrical, for review and approval to cover each
and every livening or isolating operation which is necessary to execute. Appendix 4 is
a typical example of a switching request.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 30 of 62


Section 7 - E L E C T R I C A L

SECTION 7

APPENDIX 1

ISOLATION AND LIVENING PERMITS FOR USE DURING


INITIAL LIVENING OF ELECTRICAL FACILITIES

PT. GLOBAL POWER SERVICES ©DOC2010 Page 31 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 1 of 8

Permit and Procedure for Initial Livening of Electrical Facilities

Serial No.: __________________

Identification Details of Circuit

Circuit/Service : ____________________
Located in Sub-Station No. : ______________________
Switch gear Location - Tag No.: ________ Cubical No.: __________

Permit Initiated by : ____________________


Energizing Coordinator/Signature

Permit Issued by : ___________________


Responsible Commissioning Engineer/Signature

Section 1 - Certificate of Isolation of Circuit

Reason for isolation of circuit : ______________________

______________________

Serial Number of switching instruction to isolate: _______________________

We, the undersigned, certify that the circuit has been isolated and locked out. We have each
applied our own lock and mutually agree that the circuit may be safely worked on to complete
the specified work.

Energizing Controller: _______________ _______ _____


Name (block letters) Signature Date
Construction _______________ _______ _____
Representative: Name (block letters) Signature Date

Circuit taken out of service: ___________ ______


Date Time

Issue and Acceptance of Permit to Carry Out Work Identified Above

Permit to work received by: _______________ _______ _____


Name (block letters) Signature Date

PT. GLOBAL POWER SERVICES ©DOC2010 Page 32 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 2 of 8

Section 2 - Clearance of Isolation Certificate

I, the undersigned permit holder, release the permit and notify completion of construction
work. All construction workmen have been withdrawn from the workplace.

________________ _______________ _______ ________


Name (block letters) Signature Date Time

Clearance of permit noted, release note No.: ____________

Issued by: Engineering Coordinator: ____________ _______


Signature Date

Approved by:
Responsible Commissioning Engineer: ______________ _________
Signature Date

We the undersigned certify that the feeder circuit breaker has been correctly identified
and confirm removal of the Construction Representatives lock and permit from the
circuit isolator.

Construction Representative: _____________________


Signature
Energizing Controller: _____________________
Signature

PT. GLOBAL POWER SERVICES ©DOC2010 Page 33 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 3 of 8
Section 3 - Permit to Liven

The isolation permit has now been released.

Switching request No.: ________ issued to liven.

Initiated by:
Energizing Coordinator: _____________ _______ ______
Signature Date Time

Approved by: _______________ ________ _______


Signature Date Time

Switching Executed by:


Energizing Controller: _______________ _________ ________
Signature Date Time

Checked and Witnessed by:

_______________________ ______________ ________


Designation Name (block letters Date

PT. GLOBAL POWER SERVICES ©DOC2010 Page 34 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 4 of 8
Temporary Permit Release

Release to Remove Locks from Equipment No.: _________________

Isolation/Livening Permit No.: ____________________________

I, the permit holder, request that the feeder be released to allow access to the equipment.

Construction Representative: ______________ ______ ______


Name (block letters) Signature Date

Switching Request No.: _________ Issued

Energizing Coordinator: _____________ _______ _____


Name (block letters) Signature Date

Approved by:

Responsible Commissioning Engineer: ___________ ____


Signature Date

I certify that all necessary steps have been taken to cover any exposed live conductors
and accept full responsibility for supervision of all work on the equipment. Only qualified
electricians will be assigned to do this work and they have been instructed not to operate the
circuit isolator under any circumstances.

Construction Representative: _______________ ________ ______


Name (block letters) Signature Date

Locks removed and switch in open position as per above referenced switching request.

Energizing Controller: _____________ ________ ______


Name (block letters) Signature Date

PT. GLOBAL POWER SERVICES ©DOC2010 Page 35 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 5 of 8
Release to Bump Test Motor Plant Equipment No.:

Isolation/Livening Permit Serial No.:

I, the permit holder, request that the feeder be made temporarily live to allow test running.

Construction ______________ _________ ________


Representative: Name (block letters) Signature Date

Switching Request No.: ________ issued (with copy routed via Area Process
Superintendent for information and approval).

Energizing Coordinator: _______________ ________ _______


Name (block letters) Signature Date

Approved by:
Responsible Commissioning Engineer: _____________ __________
Signature Date

I certify that all necessary steps have been taken to ensure safety of persons and plant and
accept full responsibility for supervision of the live circuit, the tests and isolation of the
circuit on completion of the tests. I have confirmed correct identification of the circuit and
witnessed completion of the megger and trip tests and switching as requested.

Construction
Representative: ____________ _______ ______
Signature Date Time

Locks removed and switching completed as per above referenced switching request, the
circuit having been megger tested and motor protection trip tested before livening.

Energizing Controller: _________ ________ ______


Signature Date Time

PT. GLOBAL POWER SERVICES ©DOC2010 Page 36 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Page 6 of 8
Notification of Completion of Work/Test Run

I herewith request that the circuit be re-isolated and locked out. Construction

Representative: _________________
Signature

Switching Instruction No.: ________ Issued.

Energizing Coordinator: ________________


Signature

Circuit re-isolated and locked out by: ____________ __________


Date Time

Energizing Coordinator: ___________________


Signature

Witnessed and Certified Correct by:

Construction Representative: __________________


Signature

PT. GLOBAL POWER SERVICES ©DOC2010 Page 37 of 62


Section 7 - E L E C T R I C A L

Isolation of Feeders as Per Initial Livening Procedure

PT. GLOBAL POWER SERVICES ©DOC2010 Page 38 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 1
Attachment 2

Livening Feeders as Per Initial Procedures

PT. GLOBAL POWER SERVICES ©DOC2010 Page 39 of 62


Section 7 - E L E C T R I C A L

Section 7

Appendix 2: Electrical System

Energizing Procedure and Permit System

PT. GLOBAL POWER SERVICES ©DOC2010 Page 40 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 1 of 10

Permit and Procedure for Initial Livening of Electrical Facilities

1. Introduction

The electrical system energizing procedure and permit system is structured to achieve
two goals, namely:

- to provide maximum safety for all personnel during the energization of the
electrical system; and

- to avoid any delays to the completion of the construction program.

The procedure was developed from proven permit systems. From these proven permit
systems the basic safety elements have been incorporated and the administrative parts have
been simplified to satisfy the Riau situation.

The procedure is structured to be compatible with, and provide a smooth transition


to, the Riau Operations procedures as these are phased in to replace this procedure.
There will be no additional safety risk exposure during any turnover period.

The procedure is designed to function quickly and efficiently, as the steps involved
have been simplified and condensed to a minimum required while maintaining complete
safety.

Administration has been simplified to two operational documents and two database
records of those documents.

2. Documentation

2.1 Operation Documents

- Electrical Isolation/Livening Permit: This document serves two functions. In the first
instance, it provides a method to allow personnel to work safely on a portion of the
system which could be energized. Secondly, it provides a method to ensure agreement
that a portion of a system is ready and safe to energize and will be switched with the
required checks and in the proper sequence.

- Switching Request: This document provides a method to ensure that required safety
checks, equipment checks and switching operations are completed in the correct
sequence. The document provides a check to the switching operation and eliminates a one
man judgment condition.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 41 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 2 of 10
2.2 Database Records

- System Status Record: This record provides a current complete picture of the electrical
system status as it is progressively energized. At any time it can be determined what
parts of the system are energized, de-energized and under permit or de-energized but
available for service. The information source for this record is the completed switching
request.

- Permit Status Record: This record provides a quick source of information to determine
at any time that has the permit for any one circuit or what circuits are permitted out to
any one individual. The information source for this record is the permits.

3. Responsible Persons and Duties

3.1 Construction Representative (CR)

The Construction Representative is THE RESPONSIBLE INDIVIDUAL DIRECTLY


IN CHARGE OF THE WORK BEING PERFORMED. This individual will need to
be appointed in writing.

For the Riau Project, the Construction Representative is either the Electrical
Supervisor in charge of the construction work or the Senior Electrical Supervisor of
the subcontractors doing the work within a defined construction area on the project. It is
the responsibility of the Construction Representative to ensure that any work to be
done on the electrical installation which could become energized, is done under
PERMIT control.
The Construction Representative in each construction area will have to appoint a backup
representative who can perform these duties in his absence.

The Construction Representative in each construction area will ensure that the project
safety standards are enforced for any work on the electrical installation.

The Construction Representative will:

- Initiate the request to obtain PERMITS for circuits where work is to be


performed and signs as recipient of these PERMITS.

- Initiate the requests to release PERMITS when the work is completed and the
circuit may be energized.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 42 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 3 of 10

- Install a lock on any FEEDER circuit breaker of circuits where the work is
to be performed.

- Remove the lock on any FEEDER circuit breaker of the circuit where the
work has been completed.

- Place a lock on all FEEDER breakers which he has taken out under permit
and retain the keys.

- Confirm that the correct feeder circuits have been taken out of service and
certify the PERMITS accordingly.

- Confirm that the correct feeder circuits have been released for service and
approve the PERMIT RELEASE.

- Confirm that the correct circuits have been energized when the circuits are
placed into service.

- Ensure that any electrical circuit or equipment to be energized is clear of


personnel and safe to energize.

3.2 Energizing Coordinator

The Energizing Coordinator is THE OFFICIAL IN CHARGE OF


CONTROLLING RECORDS AND SWITCHING REQUESTS FOR THE
ENERGIZATION OF THE ELECTRICAL SYSTEM. This individual will need
to be appointed in writing (Area Electrical Representative).

The Energizing Coordinator will have to appoint a backup representative who can
perform these duties in his absence.

The Energizing Coordinator will:

- Prepare all requests and releases of PERMITS and initiate isolation, lockout
and permitting out of all circuits comprising any defined section of the power
distribution network scheduled for livening.

- Provide the detail SWITCHING REQUESTS to energize any part of the


electrical system.

- Submit all permits and switching requests to the Responsible Commissioning


Engineer, Electrical for review, approval and execution.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 43 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 4 of 10
- Keep a record of what the total system energized condition is.

- Keep a record of what circuits are permitted out and who the permit was
issued to.

- Ensure that an updated hard copy of the data base is maintained.

- Be the only party allowed "up-date" capability access to the data base. 3.3

3.3 Responsible Commissioning Engineer, Electrical (Horst Unger)

The Responsible Commissioning Engineer, Electrical, is THE RESPONSIBLE PERSON


APPOINTED IN OVERALL CHARGE OF THE PLANT OWNER DISTRIBUTION
NETWORK AND ELECTRICAL FACILITIES AND OPERATIONS THEREOF. The
Responsible Commissioning Engineer, Electrical, will take over control of all facilities to
be livened on being advised by Construction that construction of the facility is complete
and on confirmation that all category 1 punch items have been corrected.

He will cause all facilities to be locked up to prevent unauthorized access and all
circuits to be electrically isolated to prevent accidental contact of persons with live
conductors. He will take all necessary steps to ensure safety of personnel and plant
equipment prior to allowing livening of facilities to commence.

The Responsible Commissioning Engineer, Electrital will have to appoint a backup


representative who can perform his duties in his absence. He reviews and approves all
permits and switching requests.

The Responsible Commissioning Engineer, Electrical is required to:

- Place a lock on all incoming breakers and tie breakers which have been taken
out under permit. (Blue Locks)

- Confirm that the correct incoming/tie breakers have been taken out of service
and signs for the PERMITS as the recipient (permit holder) of these.

- Confirm that the incoming/tie breakers have been released for service and
approves the PERMIT RELEASES.

- Confirm that the correct circuits have been energized when the circuits are placed
into service.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 44 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 5 of 10

3.4 Energizing Controller (Name)

The Energizing Controller is THE RESPONSIBLE INDIVIDUAL IN CHARGE OF


PERFORMING THE SWITCHING REQUIRED TO ENERGIZE THE ELECTRICAL
SYSTEM. This individual will need to be appointed in writing.

The Energizing Controller will have to appoint a backup representative who can
perform these duties in his absence.

The Energizing Controller will:

- Perform the switching to energize or de-energize a circuit according to the


switching requests approved and passed on to him by the Responsible
Commissioning Engineer, Electrical and conform execution of all switching
requests and certify permits accordingly.

- Make entries in sub-station log books to reflect intended switching (prior to actual
switching), completion of successful switching and date and time of each entry.

- Place a lock on all incoming breakers, tie (Bus coupler) breakers and feeder
breakers which have been taken out under permit. (Gold Locks)

- Post copies of initial isolation permits on feeders which have been permitted out
and ensure that each circuit is tagged to reflect full details of the permit holder's
name, location of his base office, supervisor's name and telephone number.

- Place an ENERGIZED (In Service) tag on each breaker placed into service.

- Confirm that the correct incoming/tie breaker and feeder breaker circuits have
been taken out of service and certify the PERMITS accordingly.

- Remove copies of initial isolation/livening permits from feeder circuits


released for service.

- Confirm that the incoming/tie breaker and feeder breaker circuits have been
released for service and certify the PERMIT RELEASES accordingly.

- Confirm that the correct circuits and loads have been energized when the
circuits are placed into service.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 45 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 6 of 10

4. Permit Procedures

4.1 Permit to Request that a Circuit he Taken Out of Service Prior to the Circuit Being
Energized for the First Time

Initially, upon construction completion of each sub-station, all circuit breakers will
be OPENED, TAGGED (with a copy of the isolation permit) and LOCKED OUT.

a) Feeder Breakers

- A PERMIT will be issued by the Responsible Commissioning Engineer,


Electrical to each Construction Representative for the feeder breaker of
circuits feeding facilities within the areas of the plant in which they are
in charge of construction work.

- The Energizing Controller will contact the Construction Representative


and each will place their locks on the feeder circuit breakers under
PERMIT

- The Energizing Controller and the Construction Representative will each


sign the PERMIT for the feeder circuit taken out of service certifying
execution of all relevant switching instructions and return the PERMIT
to the Energizing Coordinator for record.

- The Energizing Controller will place a 6opy of the PERMIT on the


breaker which has been opened under permit and locked out.

b) Incoming and Tie Breakers

- A PERMIT will be issued by the Responsible Commissioning


Engineer, Electrical to the Responsible Commissioning Engineer,
Electrical (as permit holder) for the incoming and tie breakers in each
sub-station.

- The Energizing Controller will contract the Responsible


Commissioning Engineer, Electrical and each will place their locks on
the incoming and tie circuit breakers isolated under PERMIT.

- The Energizing Controller and the Responsible Commissioning


Engineer, Electrical will each sign the PERMIT for the incoming and
tie breakers taken out of service, certify switching is completed and
return the permit to the Energizing Coordinator for record.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 46 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 7 of 10

- The Energizing Controller will place a copy of the PERMIT on the


incoming and tie breakers which have been taken out of service and
locked out.

4.2 Permit to Request that a Circuit be Taken Out of Service After a Circuit Has Been
Energized and Placed in Service

a) Feeder Breakers

- The Construction Representative requiring the feeder breaker circuit out of


service contacts the Energizing Coordinator who will initiate the
PERMIT and prepare the required switching request and submit these to the
Responsible Commissioning Engineer, Electrical for review and
approval. The latter will issue these to the Energizing Controller.

- The Energizing Controller will contact the Construction Representative and


proceed to the sub-station where the Energizing Controller will switch
the feeder breaker for the circuit requested out of service.

- The Energizing Controller and the Construction Representative will each


place their locks on the feeder circuit breakers under PERMIT.

- The Energizing Controller and the Construction Representative will each


sign the PERMIT for the feeder circuit taken out of service and return it to
the Energizing Coordinator for record.

- The Energizing Controller will place a copy of the PERMIT on the


feeder breaker which has been taken out of service and locked out.

b) Incoming and Tie Breakers

- The Energizing Coordinator when requiring an incoming or tie breaker taken


out of service initiates the PERMIT and prepares the required switching
request. He submits both for review and approval to the Responsible
Commissioning Engineer, Electrical.

- The Energizing Controller will contact the Responsible Commissioning


Engineer, Electrical and proceed to the sub-station where the Energizing
Controller will switch the incoming or tie breaker requested out of service.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 47 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 8 of 10

- The Energizing Controller and the Responsible Commissioning Engineer,


Electrical will each place their locks on the incoming or tie breaker taken out
of service.

- The Energizing Controller and the Responsible Commissioning Engineer,


Electrical will each sign the PERMIT for the incoming or tie breaker taken
out of service and return the PERMIT to the Energizing Coordinator for
record.

- The Energizing Controller will place a copy of the PERMIT on the incoming
or tie breaker which has been taken out of service and locked out.

4.3 Release of a Permit and Return of a Circuit to a "Ready for Service Condition" (Not
Energized)

a) Feeder Breakers

- Upon construction completion of a circuit the Construction Representative


contacts the Energizing Coordinator and advises him that the PERMIT
taking the circuit out of service may be released.

- The Energizing Coordinator prepares and submits a release note to the


Responsible Commissioning Engineer, Electrical for review and approval.

- The Responsible Commissioning Engineer, Electrical authorizes the release


of the PERMIT and issues it to the Energizing Controller.

- The Energizing Controller will contact the Construction Representative and


proceed to the sub-station where the Energizing Controller will supervise the
removal of the locks and tags.

- The Construction Representative will remove his locks on the feeder circuit
breaker released for return to service.

- The Energizing Controller will leave his lock in place until such time as he
receives an energizing request and switching instructions from the
Responsible Commissioning Engineer, Electrical.

- The Energizing Controller and the Construction Representative will each


sign the PERMIT for the feeder circuit returned to service and return the
permit to the Energizing Coordinator for record.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 48 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 9 of 10

- The Energizing Controller will remove the copy of the PERMIT on the feeder
breaker which has been released for service.

4.4 Release of a Permit and Return of a Circuit to an In-service Condition (Energized)

a) Feeder Breakers

- Upon construction completion of a circuit the Construction Representative contacts


the Energizing Coordinator and advises him that the PERMIT taking the circuit out
of service may be released.

- The Energizing Coordinator prepares and submits a release note and switching
request to the Responsible Commissioning Engineer, Electrical for review and
approval.

- The Responsible Commissioning Engineer, Electrical authorizes the release of


the PERMIT and issues it, along with the required switching request to place the
circuit into service, to the Energizing Controller.

- The Energizing Controller will contact the Construction Representative and


proceed to the sub-station where the Energizing Controller and the Construction
Representative will remove their locks and tags on the feeder circuit breaker
released for return to service.

- The Energizing Controller will switch the feeder breaker circuit into service
according to the switching request issued by the Responsible Commissioning
Engineer, Electrical.

- The Energizing Controller and the Construction Representative will each sign the
PERMIT for the feeder circuit returned to service and return the PERMIT to the
Energizing Coordinator for the records.

- The Energizing Controller will remove the copy of the PERMIT on the feeder
breaker which has been released for service.

b) Incoming and Tie Breakers

- The Energizing Coordinator, upon requiring an incoming/tie breaker returned to


service, prepares the permit release and switching request and submits these to the
Responsible Commissioning Engineer, Electrical for review and approval. The
Responsible Commissioning Engineer, Electrical authorizes the release of the
PERMIT and issues it, along with the required switching request to place the
breaker into service, to the Energizing Controller.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 49 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 2
Page 10 of 10

- The Energizing Controller will contact the Responsible Commissioning Engineer,


Electrical and proceed to the sub-station where they will remove their locks and
tags on the incoming/tie breaker circuit breaker released for return to service.

- The Energizing Controller will switch the feeder breaker circuit into service
according to tile’s switching request given by the Responsible Commissioning
Engineer, Electrical.

- The Energizing Controller and the Responsible Commissioning Engineer,


Electrical will each sign the PERMIT RELEASE for the incoming/tie breaker
returned to service and return the PERMIT RELEASE to the Energizing
Coordinator for record.

- The Energizing Controller will remove the copy of the PERMIT on the feeder
breaker which has been released for service.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 50 of 62


Section 7 - E L E C T R I C A L

Section 7

Appendix 3: Step by Step Energizing Procedures

PT. GLOBAL POWER SERVICES ©DOC2010 Page 51 of 62


Section 7 - E L E C T R I C A L

Section 7
Appendix 3
Page 1 of 1

Energize Procedure No. 1 - Page 1 of 1


Proceed to Ensure that all Incoming and Outgoing Feeders and Bus Section Switches
are Isolated and Locked out to Initiate Permit Control Over Livening of Facilities

Construction Related Activities Operations Related Activities


Step Construction Representative (CR) Energizing Coordinator (EC) Responsible Commissioning Engineer, Energizing Controller (EC)
Electrical
l Advises the Energizing
Coordinator that the sub-station
has reached construction
completion and is ready for
commissioning
2 Initiates PERMITS and
SWITCHING REQUESTS to place
all circuits out of service
3 Sends the PERMITS and Reviews and approves the
SWITCHING REQUESTS (o Hie SWITCHING REQUEST. Instructs the
Responsible Commissioning Energizing Controller to proceed.
Engineer, Electrical
4 Contacts the respective Construction
Representative and Responsible
Commissioning Engineer to witness the
switching

5 With the Energizing Controller, With the Energizing Controller, With the Construction Representative
confirms that the feeder circuits to confirms that the incoming/lie and Responsible Commissioning
be switched out of service are breakers to be switched out of service Engineer to witness the switching
correctly identified. are correctly identified.
6 Approves the PERMITS and Approves the PERMITS Switches the circuits out of service
keeps a copy of each PERMIT. and signs each Permit to certify that
Witnesses switching and signs circuit has been isolated.
each permit to certify circuit
isolation.
7 Puts construction locks on all the Puts Responsible Commissioning Puts Energizing Controller locks on all
feeder breakers of the circuits Engineer, Electrical locks on all of the of the breakers of the circuits taken out
taken out of service. The CR incoming and tie breakers taken out of of service. The EC keeps his keys.
keeps his keys and signs service. The RCEE keeps his keys
acceptance of and keeps a copy and signs for acceptance of the
of, each permit relevant permit as the permit holder.
8 Attaches a copy of the relevant
PERMITS to each breaker of the
circuits taken out of service

9 Records the switching action on Returns the original PERMITS and


the SYSTEM STATUS "Completed" SWITCHING
RECORD. Records the PERMIT REQUESTS to the Energizing
information on the PERMIT Coordinator
STATUS RECORD

PT. GLOBAL POWER SERVICES ©DOC2010 Page 52 of 62


Section 7 - E L E C T R I C A L

Section 7

APPENDIX 4

EXAMPLE OF TYPICAL SWITCHING REQUEST

PT. GLOBAL POWER SERVICES ©DOC2010 Page 53 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL


FACILITIES

OPERATING INSTRUCTIONS TO:

SWITCHING REQUEST REVIEWED AND APPROVED: _____________ _______


Signature Date

Operating Sequence Switching Description Completed Remarks

SWITCHING COMPLETED BY ENERGIZING CONTROLLER

______________ __________ __________


Signature Date Time

Witnessed by: ________________ _____________


Name Signature

PT. GLOBAL POWER SERVICES ©DOC2010 Page 54 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Take an Energized Feeder Circuit Out Of Service
Energize Procedure No.2
Page 1 of 1
CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES
STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISINGCONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Requests the energizing coordinator to take a circuit out of
service to perform work on that circuit.
2 Confirm circuit to be switched out of service and prepares the
SWITCHING REQUEST for that circuit.
3 Initiates a PERMIT to take the circuit out of service. Sends Reviews and approves the SWITCHING
the PERMIT with SWITCHING REQUEST to the Responsible REQUEST Approves the PERMIT and
Commissioning Engineer, Electrical. instructs the Energizing Controller to proceed..

4 Contracts the Construction Representative to witness and


confirm the switching.
5 With the Energizing Controller, confirms that the With the Construction Representative, confirm that the
circuit to be switched out of service is correctly circuit to be switched out of service is correctly identified.
Identified.
6 Witnesses switching and certifies Isolation of the SWITCHES THE CIRCUIT OUT OF SERVICE and signs
circuit then signs the PERMIT and keeps a copy of the permit to certify that circuit has been isolated.
PERMIT (as permit holder)
7 Puts a Construction Representative lock on the Puts an Energizing Controller lock on the breaker of the circuit
breaker of the circuit taken out of service. The CR keeps the taken out of service. The EC keeps the key in his possession
in his possession.
8 Attaches a copy of the PERMIT to the breaker of the circuit
taken out of service.
9 Records the switching action on the SYSTEM STATUS Returns the original PERMIT and the "Completed"
RECORD. Records the PERMIT information on the SWITCHING REQUEST to the Energizing Coordinator.
PERMIT STATUS RECORD.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 55 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure To Take An Energised Feeder Circuit Out Of Service
Energise Procedure No.3

Page 1 of 1
CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVATES
STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Determines that a circuit needs to be taken out of service to support Determines that a circuit needs to be taken
the construction programmed. out of service to support system operating
conditions.
2 Confirms circuit to be switched out of service and prepares Requests The Energizing coordinator to take a
the SWITCHING REQUEST for that circuit. circuit out of service.
3 Initiates a PERMIT to take the circuit out of service. Sends the Reviews and approves the SWITCHING
PERMIT with SWITCHING REQUEST to the Responsible REQUEST. Instructs the Energizing
Commissioning Engineer, Electrical. Controller to proceed.
4 Contacts the Responsible Commissioning Engineer, Electrical,
to witness and confirm the switching.
5 With the Energizing Controller, confirms that the With the Responsible Commissioning Engineer, Electrical
circuit to be switched out of service is correctly confirms that the circuit to be switched out of service is correctly
identified. identified.
6 Approves the PERMIT. Witnesses switching Switches the circuit out of service and signs PERMIT to certify
and certifies isolation of the circuit and signs that circuit has been isolated.
for acceptance of the permit as the permit
holder.

7 Puts a Responsible Commissioning Puts an Energizing Controller lock on the breaker of the circuit
Engineer, Electrical, and lock on the breaker of taken out of service. The EC keeps the key in his possession.
the circuit taken out of service. The RCEE
keeps the key in his possession.

8 Attaches a copy of the PERMIT to the breaker of the circuit


taken out of service.
9 Records the switching action on the SYSTEM STATUS RECORD. Returns the original PERMIT and "Completed"
Records the PERMIT information on the PERMIT STATUS SWITCHING REQUEST to the Energizing Coordinator.
RECORD.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 56 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Release a Feeder Circuit For Service (Without Energizing)
Energize Procedure JN'o.4
Page 1 of 1

CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES


STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Advises the Energizing coordinator that a circuit is
complete and may be put into service, by signing
permit release.
2 Confirms that the circuit released is ready for service and may
be made available for exercitation.
3 Initiates a PERMIT RELEASE to remove the PERMIT. Sends Approves the PERMIT and instructs the
the PERMIT RELEASE to the Responsible Energizing Controller to proceed.
Commissioning Engineer, Electrical.
4 Contacts the Construction Representative to remove the
PERMIT.
5 With the Energizing Controller, confirms that the With the Construction Representative, confirms that the circuit
circuit to be released is correctly identified. to be released is correctly identified.
6 In the presence of the Energizing Controller removes the In the presence of the Construction Representative
Construction Representative lock on the breaker of the removes the copy of the PERMIT reached to the breaker
circuit to be made available for service, and certifies of the circuit to be made available for service.
removal of his lock.
7 Keeps the Energizing Controller lock on the breaker of the
circuit to be made available until a SWITCHING
REQUEST to put the circuit into service received
8 Records the availability action on the SYSTEM STATUS Returns the original PERMIT RELEASE to the
RECORD. Records the PERMIT RELEASE Information on Energizing coordinator.
the PERMIT STATUS RECORD.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 57 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Release and Energize a Circuit for Normal Operation
Energize Procedure No.5

Page 1 of 1
CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES
STEP CONSTRUCTION REPRESENT ATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Requests the Energizing coordinator to release a
circuit to Operations.
2 Confirms that the circuit is available and ready to energies.

3 Prepares the SWITCHING REQUEST for the circuit. Sends the Reviews and approves the SWITCHING
SWITCHING REQUEST to the Responsible Commissioning REQUEST. Obtains an approval to energies
Engineer, Electrical. from the process area superintendent.
Instructs the Energizing Controller to proceed.

4 With the Energizing Controller, confirms that the With the Responsible Commissioning Engineer, Electrical,
circuit to be energized is correctly identified and confirms that the circuit to be energized is correctlyidentified.
clear of personnel.
5 Places ENERGISED (in service) tags on the equipment tobe
energized.
6 Remove the Energizing Controller lock on the breaker of the
circuit to be energized.
7 SWITCHES THE BREAKER "ON", Energizing the circuit.

8 With the Energizing Controller, confirms that the With the Responsible Commissioning Engineer, Electrical,
load placed into service is energized and confirms that the load placed into service is energized and
operational. operational.
9 Places the circuit under the normal Operations Returns the original SWITCHING REQUEST to the Energizing
permit control. Coordinator.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 58 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Energize a Feeder Circuit for Construction Testing
And Re-Isolation on Completion of the Tests
Energize Procedure No.6
Page 1 of 1

CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES


STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Advises the Energizing Coordinator that a circuit is Confirms that the circuit released is ready for service and can
complete and requests that the circuit be energized for be energized.
testing.
2 Signs temporary permit release requesting that feeder be Initiates a TEMPORARY PERMIT RELEASE for
made temporarily live. testing. Prepares a SWITCHING REQUEST for the circuit
to be energized. Request to include details of tests and safety
precautions prior to livening.

3 Sends the TEMPORARY PERMIT RELEASE and the Approves the TEMPORARY PERMIT
SWITCHING REQUEST to the Responsible RELEASE. Obtains approval to energies from
Commissioning Engineer, Electrical. the process area superintendent.
4 Reviews and approves the SWITCHING
REQUEST. Instructs the Energizing
Controller to proceed.
5 Contacts the Construction Representative to remove locks
and to witness and confirm the switching.
6 With the Energizing Controller, confirms that the With the Construction Representative, confirms that the
circuit to be released and clear of personnel. circuit to be released and energized is correctly identified.

7 Signs the TEMPORARY PERMIT RELEASE Places ENERGISED (In Service) tags on the
accepting responsibility for supervision of the live equipment to be energized.
circuit and keeps a copy of the TEMPORARY
PERMIT RELEASE.
8 Attaches a copy of the TEMPORARY PERMIT
RELEASE to the breaker of the circuit to be energized.
9 Removes the Construction Representative lock on the Removes the Energizing Controller lock on the circuit
circuit breaker of the circuit to be energized. breaker of the circuit to be energized.
10 Megger tests circuit, trip tests electrical protection and
SWITCHES THE BREAKER "ON", ENERGISING THE
CIRCUIT.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 59 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Energize a Feeder Circuit for Construction Testing
And Re-Isolation on Completion of the Tests
Energize Procedure No. 6
Page 1 of 1
CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES
STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER. ELECTRICAL (RCEE)
11 With the Energizing Controller, confirms that the load With the Construction Representative, confirms that load
placed into service is energized and operational. placed into service is energized and operational.
»
12 Note : Responsibility rests on the Construction Records the switching action on the SYSTEM STATUS Certifies that circuit is live and returns the original
Representative to initiate re-isolation and lockout of RECORD.Records the PERMIT RELEASE information on TEMPORARY PERMIT RELEASE and the
circuit immediately on completion of testing. To effect the PERMIT STATUS RECORD. SWITCHING REQUEST to the Energizing Co-
re-isolation follow steps 13 onward. ordinator.
13 Immediately on livening of the circuit advises Opens the feeder breaker and isolates and locks out the
Energizing Coordinator and the Energizing circuit with his lock witnessed by the Construction
Controller of anticipated time of completion of the tests Representative. Removes the copy of the temporary
and makes suitable arrangements to ensure that release for testing from the circuit feeder and signs it to certify
Energizing Controller or his deputy will be available to re-isolation of the circuit.
re-isolate and lock out the circuit on completion of the
test.
14 On completion of tests contacts Energizing Controller and Issues switching request to re-isolate to Energizing Representative at the sub-station housing the circuit feeder
requests that the circuit be re-isolated and locked out and Controller. and collects switching request to re-isolate from Energizing
advises Energizing Coordinator, Coordinator..
15 Witnesses the switching and signs notification of Opens the feeder breaker and isolates and locks out the
completion of test run section of temporary release for circuit with his lock witnessed by the Construction
testing. Representative. Removes the copy of the temporary release
for testing from the circuit feeder and signs it to certify re-
isolation of the circuit.
16 Records the switching action on the SYSTEMS STATUS Return signed off copy of temporary release (endorsed by
RECORDS. Records the permit information on the PERMIT Construction Representative notifying completion of test run)
STATUS RECORDS. to Energizing Coordinator.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 60 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure for Temporary Removal of Locks from Motor Starter
Cubicles for Completion of Construction Work
Energize Procedure No.7
Page1 of 1

CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES


STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Advises the Energizing Coordinator that access is
required for completion of construction work.
2 Signs temporary permit release requesting removal of Initiates a temporary permit release for removal of locks only.
locks, to allow access to starter cubicle for
completion of construction work.
3 Advises Responsible Commissioning Engineer, Electrical, or Reviews request and signs approval of
request and arranges for approval. request.
4 Identifies circuit in the presence of the Energizing Advises Construction Representative and Energizing Verifies that circuit has been correctly identified,
Controller and removes his lock. Controller that approval has been granted and arranges for removes his lock and signs permit temporary release.
removal of locks and signing of temporary release by both
parties.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 61 of 62


Section 7 - E L E C T R I C A L

PERMIT AND PROCEDURE FOR INITIAL LIVENING OF ELECTRICAL FACILITIES


Procedure to Release and Energize an Incoming Feeder/Tie Breaker
Energize Procedure No.8
Page 1 of 1
CONSTRUCTION RELATED ACTIVITIES OPEARATIONS RELATED ACTIVITIES
STEP CONSTRUCTION REPRESENTATIVE (CR) ENERGISING CO-ORDINATOR (ECR) RESPONSIBLE COMMISSIONING ENERGISING CONTROLLER (EC)
ENGINEER, ELECTRICAL (RCEE)
1 Requests a circuit be energized and
placed into service.
2 Initiates a PERMIT RELEASE to remove the PERMIT. Approves the PERMIT RELEASE.
Prepares a SWITCHING REQUEST for the circuit to be
energized.
3 Sends the PERMIT RELEASE and the SWITCHING Reviews and approves the SWITCHING
REQUEST to the Responsible Commissioning Engineer, REQUEST. Instructs the Energizing
Electrical. Controller to proceed.
'4 Contacts the Responsible Commissioning Engineer,
Electrical, to remove the PERMIT and to witness the
switching.
5 With the Energizing Controller, confirms that With the Responsible Commissioning Engineer,
the circuit to be released and energized Electrical, confirms that the circuit to be released and
is the correct circuit. exercised is the correct circuit.
6 Places ENERGISED (In Service) tags on the
equipment to be energized.
7 Removes the copy of the PERMIT attached to the breaker
of the circuit to be energized.
8 Removes the Responsible Commissioning Removes the Energizing Controller lock on the circuit
Engineer, Electrical, lock on the breaker of the breaker of the circuit to be energized
circuit to be energized.
9 SWITCHES THE BREAKER "ON", EXERCISING THE CIRCUIT.

10 With the Energizing Controller, confirms that With the Responsible Commissioning Engineer,
the circuit placed into service is energized and Electrical, confirms that the circuit placed into service is
operational. energized and operational.
11 Records the switching action on the SYSTEM STATUS Returns the original PERMIT RELEASE and
RECORD. Records the PERMIT RELEASE information on "Completed" SWITCHING REQUEST to the
the PERMIT STATUS RECORD. Energizing Coordinator.

PT. GLOBAL POWER SERVICES ©DOC2010 Page 62 of 62

Вам также может понравиться