PROJECT : SM LIGHT RESIDENCES

LOCATION : BONI AVE. EDSA MANDALUYONG CITY

SUBJECT : PRODUCTIVITY RATE


SCOPE OF WORK : INTERIOR PAINTING OF UNITS
FINISH : SEMI-GLOSS (2 COATS)
PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FIRST COAT
- Application of Semi-Gloss
4. FINAL COAT
- Application of Semi-Gloss

PAINTING TO MASONRY WALL

FLOOR : 17TH FLOOR


UNIT NO. : 18
AREA :
2
UNIT 46.9 m
2
CR 8.86 m
2
55.76 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

TOTAL 37.75 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.6770

FLOOR : 17TH FLOOR


UNIT NO. : 19
AREA :
2
UNIT 46.9 m
2
CR 8.86 m
2
55.76 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 3.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

TOTAL 37.75 Man-Hrs


2
PRODUCTIVITY (Man-hr/m ) 0.6770

PAINTING TO MASONRY WALL

FLOOR : 17TH FLOOR


UNIT NO. : 37-38
AREA :
2
UNIT 93.8 m
2
CR 17.72 m
2
111.52 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter Surface Preparation - Putty Works 22 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 8.5 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 3 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 5.5 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
13-Nov Painter Final Coat - Application of Semigloss 12 Man-Hrs

TOTAL 61 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.5470

PAINTING TO MASONRY WALL

FLOOR : 8TH FLOOR


UNIT NO. : 21-22
AREA :
2
UNIT 93.8 m
2
CR 17.72 m
2
111.52 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter Surface Preparation - Putty Works 14 Man-Hrs
8-Nov Painter Surface Preparation - Putty Works 10 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 7.5 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 6 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 13 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
Painter Final Coat - Application of Semigloss 12 Man-Hrs

TOTAL 68.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.6142

AVERAGE PRODUCTIVITY (Man-hr/m2) 0.6288

FINISH : FLAT FINISH


PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FINAL COAT
- Final application of flat latex

PAINTING TO CONCRETE CEILING

FLOOR : 17TH FLOOR


UNIT NO. : 18
AREA :
2
UNIT 12.8 m
2
12.8 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 2 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 0.75 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter Final Coat - Application of flat latex 1.25 Man-Hrs

TOTAL 11.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.8984

FLOOR : 17TH FLOOR


UNIT NO. : 19
AREA :
2
UNIT 12.8 m
2
12.8 m

DATE MANPOWER ACTIVITY MANHOUR


6-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Sanding 2 Man-Hrs
7-Nov Painter 1 Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter 2 Primer - Application of Flat Latex 0.75 Man-Hrs
8-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter 1 Final Coat - Application of flat latex 1.25 Man-Hrs

TOTAL 11.5 Man-Hrs


2
PRODUCTIVITY (Man-hr/m ) 0.8984

FLOOR : 17TH FLOOR


UNIT NO. : 37-38
AREA :
2
UNIT 25.6 m
2
25.6 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter 1 Surface Preparation - Putty Works 5.5 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 6 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

TOTAL 19.5 Man-Hrs


PRODUCTIVITY (Man-hr/m2) 0.7617

FLOOR : 8TH FLOOR


UNIT NO. : 21-22
AREA :
2
UNIT 25.6 m
2
25.6 m

DATE MANPOWER ACTIVITY MANHOUR


7-Nov Painter 1 Surface Preparation - Putty Works 9 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 4 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

TOTAL 21 Man-Hrs
2
PRODUCTIVITY (Man-hr/m ) 0.8203

AVERAGE PRODUCTIVITY (Man-hr/m2) 0.8447


210 972.625
105 69.47321 0.330825
5 1 43.69
6 2
7 2
8 3
9 4
10 5
11 6