ENGINEERING SPECIFICATION
Rev.
Issued Endorsed Appr’d
No. Date Description
By By By
Signature
1. GENERAL .......................................................................................................................... 3
2. DESIGN PARAMETERS.................................................................................................. 3
3. FACTORY TESTS............................................................................................................. 5
4. DOCUMENTATION ......................................................................................................... 5
5. SPARE PARTS................................................................................................................... 5
Page 2 of 6 ENG-TS-X-SP-0012.doc
1. GENERAL
The transformer shall be sized, designed and equipped with adjustment features to permit the
rectifier to deliver the specified output under all operating conditions.
2. DESIGN PARAMETERS
The units shall comply with the following general and particular specification requirements.
Input power will be obtained from the ‘Delta’ connected secondary of a down hole pump
transformer with varying nominal voltages which are subject to ± 15% manual tap changer
adjustment. Equipment shall be designed for the following primary voltages :
Nominal Voltage Range
2400 Volts, 3 phase 2040 – 2760 Volts
1200 Volts, 3 phase 1020 – 1380 Volts
1000 Volts, 3 phase 850 – 1150 Volts
800 Volts, 3 phase 680 – 920 Volts
3. FACTORY TESTS
Each MVTR unit shall be subjected to the manufacturer's standard tests as well as those which
are outlined in the applicable ANSI standards. Tests shall include, but not be limited to, the
following :
• Power frequency voltage tests
• Insulation tests
• Performance and functional tests
• Output polarity tests
• Load and no load tests
Supplier shall provide a detailed listing, including reference standards, of proposed testing in
his quotation.
Purchaser reserves the right to have inspections carried out and/or witness factory tests by a
third party or his own representative. Supplier shall notify the Purchaser at least 6 weeks prior
to the commencement of all factory tests.
Certified test reports shall be submitted to the Purchaser prior to the date of shipment from the
factory.
4. DOCUMENTATION
Supplier shall be responsible for the submission of 3 (three) sets of each of the following
technical documentation :
• Outline Drawings
• Wiring Diagrams
• Operations and Maintenance Manuals, including all test reports, detailed component and
spare parts’ listings.
Documentation shall further comply with the Vendor Data Requirements’ List appended to the
purchase order.
5. SPARE PARTS
Supplier shall include within his quotation a complete priced listing of all necessary spare parts.
The spare parts shall be identical to those which are supplied in the original MVTR unit. This
listing should include, but not be limited to, the following minimum components :
Page 6 of 6 ENG-TS-X-SP-0012.doc