Вы находитесь на странице: 1из 6

Piping Inspection Basics for the beginners

Written by Shyam Mohan in Mechanical,Piping Design and Layout,Piping


Interface,Piping Materials

Table of Contents
• What is the Inspection and Test Plan or ITP?
• Inspection of Piping and Component Materials
• Fit-Up Inspection
• Welding Inspection
• Piping Inspection Punch Lists
• Hydro-test Package
• Piping Inspection Flow Chart
• Codes and Standards for Piping Inspection
Sh are Share Whatsapp Tw eet Messenger Em ail

Piping Inspection is a comprehensive task that is performed following


client/company-specific inspection documents. The main aim of the piping
inspection is to ensure plant reliability reducing probable errors and thus safely
operating the plant throughout its design life.

All plants are designed for a pre-determined design life (normally 20 years for process
piping). Periodic inspection help plants to operate with safety and efficiency.

Even after attending and completing various courses related to piping most of the fresh
graduates/professionals face difficulties in understanding the procedures when it comes
to real-life jobs.

Considering the stigma, a simple way to understand the basic unique procedures that
are to be followed during the fabrication and installation of carbon steel pipes are
discussed in this article.

When it comes to piping it’s the Piping and Instrumentation Diagram or P & ID is
the bible for an Engineer to execute his work.

For performing piping inspections there should be a client-approved Inspection


and Test Plan or ITP in place prior to commencement of any job activities. This
shall be prepared with reference to the piping design code and project
specifications.

Piping design codes like ASME B 31.3 PROCESS PIPING, will be the design code for
designing of piping by the engineering team for the project.

Different types of design codes are available as per the project and product
requirements. Understanding the codes and standards along with the particular project
specification will provide basic ideas regarding the scope of work being executed.

Unrestricted
According to the requirements of the design code, the drawings will be developed and
the same design code will be reflected in the drawings. All the construction procedures
will be shortlisted with different intervention points as shown in the below Fig.1

Fig. 1: List of Piping Inspection Points

What is the Inspection and Test Plan or ITP?


An ITP covers all the construction activities that are being carried out during and
after the construction. Learning and understanding ITP along with the construction
procedures and Method of statement for specific activities will give a wide range of
understanding regarding the job being executed. The Inspection and Test Plan must
meet the requirements of the design code (ASME B 31.3 for process piping).

Welding procedure specification or WPS shall be approved by the client prior to the
commencement of any welding jobs. CSWIP and AWS certified inspectors are preferred
as inspectors or quality engineers for the inspection related jobs. Further to the approval
of WPS welder qualification tests will be carried out based on the project requirements
on welding process, type and positions. Only these welders who successfully pass the
qualification test based on visual and RT reports can be used for all the project related
welding activities. Welder ID’s signed by all parties shall be prepared and issued to the
welder that shall be available with the welder during the working hours.

Various certifications like API 570, API 650, Bgas, NACE, Level 3 courses are available
in the market to strengthen the requirements of a professional for a company.

Initially, after the approval of the above-said documents by the client, inspections shall
be performed based on the ITP. No inspections or documents will be generated other
than the ones mentioned in the ITP.

Unrestricted
Inspection of Piping and Component Materials
Piping and Component Material inspection is the next step of inspection normally done
by the quality personal when a material related to project is received at site. The below
points as a minimum are to be checked during the material inspection:

1. Material purchased is from the client approved manufacturer or vendor


2. Material specification, grade, thickness, size.
3. Any mechanical damages.
4. Heat numbers provided in the materials are matching with the Material Test
Certificates provided prior to the inspection.
5. Quantity of the material with reference to purchase order and delivery note.
6. Reviewing of Material Test certificates with reference to project specification, design
code, and drawings.
7. Proper stacking of the materials.
Material inspection reports shall be generated with all the requested data’s like Material
grade and type, quantity, Heat number, Material certificate number, inspection status.

Once the materials are approved by client it can be issued for construction.

Fit-Up Inspection
Initially, the piping activities will commence with the fit-up inspection. This shall be
carried out based on the approved isometric/weld map generated from the P & ID.

During the fit-up inspection, the joint number, date, spool number, drawing number, and
sheet with revision shall be checked. The heat number of the material shall be noted for
preparing the fit-up report. Taper gauge, Hi-lo gauge, cam gauge, and measuring tape
will be used for checking the fit-up gap between the joints and for checking the
dimension of spools. Further to the acceptance of fit-up the spool or joint can be
released for welding.

Welding Inspection
Mostly GTAW and SMAW welding techniques are most commonly used for pipe
welding. The welding inspections will be carried out in different stages by a certified
welding inspector and the reports shall be generated with material grade and
specification, heat number, drawing number with sheet number and revision, joint type,
welding process, welder number, dates.

Once the joints are completed will proceed for the RT i.e, radiography testing as per the
percentage of NDE recommended in design code and project specification.

Unrestricted
Piping routing consist of elbows and fittings. Other than the weld joints flanged joints will
be available based on the engineering requirements considering the stress analysis.
Pipe supports and wear pads along with any other attachment’s shown in the drawings
shall be checked twice.

Piping Inspection Punch Lists


Once the welding activities and installation of piping spools or the system are completed
a pre-hydro walkthrough will be conducted in order to find the balance/pending jobs.
These are normally considered as punches that are commonly grouped into two types,
punch A & punch B. Punch A items consist of direct welding items, and punch B can be
closed after the hydro tests. No direct welding shall be done in the piping system after
the completion of hydro testing.

Hydro-test Package
After attending the punch A items, the spools can be released for hydro testing. A test
package shall be prepared, not limited with the below listed items.

Fig. 2: Piping Hydro Test


Package Items

Unrestricted
The test pressure and holding time will be confirmed subject to the project specification
and design code.

Water will be filled into the pipe spools with a pump connected through a test manifold
with pressure gauges, safety relief valves, and proper venting facilities. Water test
certificate shall be attained prior to the filling of water along with the blind checklist, i.e.
the list of blind flanges that are being used for hydro testing.

Understanding the above list will provide a basic idea regarding the hydro test.

Note that hydro test is done in order to confirm the weld joints integrity and to ensure
that the parent material is free of any leakage.

Bolt tightening with torque wrench shall be done for the flanged joints. After draining the
water, flushing of the lines with water and air blowing shall be done in order to dry the
lines.

Note that valves are not installed prior to the hydro test, inline valves are installed after
the hydro test and cleaning process as the testing pressure and design code for valves
are different.

The spools or piping system can now be released for blasting and painting as per the
project requirements. A final walkthrough shall be conducted in order to confirm the
installation of all the valves and instruments in the piping system are in place as per the
P & ID.

Piping Inspection Flow Chart


The following figure shows a sample piping inspection flow chart.

Unrestricted
Fig. 3: Piping Inspection Flow Chart

Codes and Standards for Piping Inspection


There are various international codes and standards that provides guidelines for piping
inspection. Few of those codes and listed below for reference:

• API 570, Piping Inspection Code


• API RP 574, Inspection Practices for Piping System Components
• API RP 577 Welding Inspection and Metallurgy
• API RP 578, Material Verification for New and Existing Alloy Piping
• API RP 583, Corrosion Under Insulation and Fireproofing
• ASME PCC-2, Repair of Pressure Equipment and Piping
• ASTM STP 880, Corrosion of Metals Under Thermal Insulation
• API RP 571 Damage Mechanism Affecting Fixed Equipment in the Refining Industry
Hope, the above-mentioned details will provide some basic ideas to the beginners
regarding the sequence and structure of piping inspection.

Unrestricted

Вам также может понравиться