Академический Документы
Профессиональный Документы
Культура Документы
SYNOPSIS About 40 million cum of sand was dredged and pumped for the construction of the new International
Airport at Changi. The second runway, taxiway and high speed turnoffs are to be located on the reclaimed sand
fill which had a relative density between 40% and 80%. Despite the care exercised during reclamation, the fill
had entrapped fines especially below the mean sea level. In order to achieve the specified degrees of compaction
of the fill a suitable means of densifying the fill was required. After a careful study of the nature of the
fill and various compaction methods available and after carrying out a pilot test the technique of applying high
energy impacts (Dynamic Consolidation) was chosen as the most appropriate method. A series of tests was then
carried out to investigate the proper choice of the operational parameters of this technique. The results obtain-
ed from these studies enabled a better understanding of the factors involved in densifying hydraulic sand fill
with the application of high impact energy.
INTRODUCTION the runway and taxiways requires a subgrade with a
A major reclamation project was undertaken in 1976, relative density of the order of 90%. In order to
by the Port of Singapore Authority, along the north- minimise the settlement of the runway due to the air
eastern shoreline of the Republic of Singapore for the traffic and associated vibrations a minimum relative
construction of an international airport at Changi. density of 75% is desired for the hydraulic fill. It
A 3.4 km long runway and the terminal buildings are to was, therefore, necessary to compact the 6.5 m thick
be situated on the reclaimed land. The first runway hydraulic fill underlying the runway, and its associa-
and its supporting facilities are located on the main ted turnoffs and taxiways covering an area of about'
land. About 40 million cum of suitable fill material 460,000 sq. m. After carefully considering the various
was dredged from the sea bed 4 km away from the shore- factors involved in compacting a hydraulic fill the
line and pumped through floating pipe lines to the application of high energy impacts, known as Dynamic
reclamation site. Five cutter suction dredges, each Consolidation, was chosen as the most appropriate
with a capacity of 5,000 to 10,000 H.P., were deployed method. This paper reports a field test conducted to
for these operations. Fig. 1 shows the layout plan of study the densification of the hydraulic fill by means
the proposed runway, the shoreline, reclamation site of Dynamic Consolidation.
and the borrow area.
GEOLOGY
Soil investigation and seismic reflection surveys
carried out over the reclamation site and the borrow
areas revealed the existence of a shallow stratum of
loose sand and gravel overlying a cemented sandstone
and shale of the Pleistocene period. Deep buried
channels cut in the sandstone are infilled with bluish
grey marine clay belonging to the marine member of
Kallang Formation deposited during Holocene period.
Marine clay varies in thickness from 2 m to 40 m below
the sea bed and is found to be interbedded with layers
of firm to stiff silty clay and occasional peat layers.
Buried channels of marine clay run through the north
and south ends of the runway and across the middle of
the borrow area. The central portion of the runway
and the southern and northern ends of the borrow area
are covered with loose sand, deposited on sandstone
which is weathered to a depth of about 20m.
Fig. 1 Layout Plan DREDGING AND RECLAMATION
The dredges operated mainly in loose, uncemented sur-
It has been reported that the relative density of face sand and weathered sandstone having a standard
hydraulic fills vary widely between 40% and 80% penetration test value less than 70 blows per foot.
(Whitman, 1970). Tests carried out during reclamation The maximum dredged depth was 22 m below mean sea
confirmed the above findings. The pavement design for level. Dredging was difficult because of the abrasive
137
11/6
dredged and pumped through the floating pipe line was ~80
0
Envel~pe for
discharged in the reclamation area. Fines accumulated !f 70
..... mate:na.l between
at the toe of the fills whose slopes averaged about ~ 60
6 m "nd 8 m
below ground
1:40. Upto 2 m thick accumulations of silt were Vi te:ve:l
noticed at the merging boundaries of the five dis- lf) 50
charge areas and these were partially removed by
flushing them with water directed from the pipe lines.
11.
w 40
~
. .:'?
Subsequently these areas were also surcharged.
The sequence of reclamation was dictated by the con-
'Z 30
w
a! 20
: \:J ~ ~~~~r.•,
·. ::.::· . .:.·.:/
for
bttw••n Om
struction programme for the airport development. ~ . ........ · / "nd 6m b<low
Areas for the terminal building, next to the existing ·.':.'·,··.',·.. :.'.;;/ ground l<vtl
shoreline, and the runway, about ~ km away from the 0.1 10
shoreline, were therefore reclaimed first followed by
the area in between them. Finally the new beach area
to the east of the runway was reclaimed. During the
last stages of reclamation it was noticed that the
ground water level under the runway had risen up from Fig. 2 Gradation Envelopes of Fill Sand
1.6 m A. C. D. to about 4.5 m A. C. D., just about 1 metre
below the fill surface. The average depth of the fill values as high as 140 kg/cm 2 were observed at 2 m
at the runway stood at 6.5 m. depths but the cone penetration varied widely with the
penetration depth indicating both variation in the
SOIL PROPERTIES OF THE RUNWAY FILL particle size and density.
The hydraulic fill is required to sustain the loading COMPACTION REQUIREMENT OF THE FILL
from the runway, taxiway and high speed turnoffs.
During the dredging operations great care was exercised It has been reported (D'Appolonia, 1970) that granular
to fill this area with good quality material comprising soils are prone to liquefaction or densification as a
sand and gravel. Fig. 2 shows the envelopes of grada- result of vibrations and that for small strains of the
tion curves of all samples tested from the fill. Most order to lo-5 to lo-3 the minimum relative density to
of the material in the fill was sub-round to sub- prevent liquefaction should be about 70% and that fine
angular quartz in the medium to coarse sand region. sand with a relative density less than 50% is subject
The laboratory tests have indicated that the maximum to liquefaction during ground motions with accelera-
and minimum dry densities of the sand determined accor- tions in excess of O.lg. In order to avoid excessive
ding to ASTM were about 1.78 Mg;m3 and 1.54 Mgjm3 fill settlement and to satisfy the requirements·of
respectively. runway pavement design, the degree of compaction speci-
fied was 75% relative density below and 90% above
The insitu properties of the fill were determined by the permanent water level which was assumed to be
the standard penetration test (SPT) and Dutch Cone about 3m to 4 m below the pavement level. The grada-
penetration test (CPT). The results, before and after tion curve of the fill material appears to be similar
treatment, are shown in Fig. 3. Before treatment, an to that of the coarse sand used by Gibbs and Holtz
average N value of 8 to 10 was observed between 1.5 m (1957). Their empirical relationship between relative
and 3m below the fill surface. Values of N as low as density and N value with respect to effective over
3 to 4 were measured below the mean sea level. CPT burden pressure was therefore adopted for the determi-
~4
0
~
E3
-1
138
11!6
139
11/6
4
REFERENCES
Bhandari, R.K.M. (1978), "Deep Compaction of Ground
0u 3 by Vibroflotation", Geotechnical Engineering, Vol. 9,
... No.1, pp. 13-27 .
5 2 D'Appolonia, E. (1970), "Dynamic Loading", J.S.M.F.D.,
z A.S.C.E., Vol. 96, No. SMl.
1
2 Gibbs, H.J. and W.G. Holtz (1957), "Research on
J Determining the Density of Sands by Spoon Penetration
...~ 0
Testing", Proc. 4th Int. Conf. S.M.F.E., London,
-1
Vol. 1, pp. 35-39.
:--~-
Menard, L. andY. Braise (1975), "Theoretical and
Practical Aspects of Dynamic Consolidation",
Ptlut W(t) H(m) B (;(m) E(tm/ml)
Geotechnique, Vol. 25, pp. 3-18.
-3
[J1
3
15 6
15-6
15-6
15
15
15
8
8
6
8 l
83
6.0
45.)
45.3
65.0 =155.i;
Whitman, R.V. (1970), "Hydraulic Fills to Support
Structural Loads", J.S.M.F.D., A.S.C.E., Vol. 96,
n.o No. SMl.
D~
10 11 8-l 38-3
n-o 10 11 8-3 38·3
15-6 15 6 6.0 65.0 =141.6
140