WorkWise

PH- 30 Works status as on 07.07.2020

upto March '20


Short Name of

ALLOCATION

of Rly portion
Original Cost
(PB,LB,DRM)

Revised TDC
during 2020-
Expenditure

Expenditure

Expenditure
Modified for

progress of

progress of
Anticipated
Agency Rly

Balance till

TDC of Rly

REMARKS
%age Phy.

%age Phy.
Executing

2020-2021

upto date
Sanction

Division
PB Item

Agency
portion
Year of

Outlay
Work

2021

Date

Rly
SN

Bhilai Nagar-Durg Link


Block - Road over bridge
2013- PB- in lieu of level crossing CAO(CON S.Fund,R 31/12/20
2 2014 92 Raipur No.443 (Nehru Nagar) )/SECR RSK 114921 737 1 737 114183 18 100 100 ROB Commissioned on 22.02.2019.Railway portion of RUB completed.
Gunderdehi-Latabor -
Road under bridge in lieu DEN/II : Work completed. Final bill Passed. PVC not submitted by the Agency till date. Agency
2013- PB- of level crossing No.DD- S.Fund,R 31/08/20 31/07/20 ensured PVC bill to be submitted by 07.07.2020. After passing PVC bill the work will be
9 2014 96 Raipur 36 DRM/R RSK 28737 39316 500 0 39316 183 15 20 95 deleted. TDC for deletion revised up to 31.07.2020

Bilaspur-Gatora - Road S.Fund,R


2009- PB- over bridge in lieu of level CAO(CON RSK,EB 31/12/20 15/10/20 Work completed. After some rectification work, ROB opened for plying the road traffic over this
37 2010 77 Bilaspur crossing No.364 )/SECR R(PPP) 75736 78635 500 78635 15357 14 19 100 100 on dtd:15.10.2019.

BSP Div: Construction of


RUB (Limited Height Estimate No. 74/B/10. CA No. 78/11-12 (Brijesh Agrawal)
Subway) for LC No. 286 Sr.DEN/E : Work completed in Jan'15. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 31/03/20 associate accounts mentioned constraints regarding deletion of work. Deletion procedure under
38 2011 107 Bilaspur under SE/Works/RIG. DRM/BSP RSK 18560 17625 500 0 17625 574 15 100 finalisation with associate accounts.

BSP Div: Provision of Estimate No. 76/B/10. CA No. 78/11-12 CA No. 78/11-12 (Brijesh Agrawal)
RUB (Limited Height
Subway) for LC No. 294 Sr.DEN/E : Work completed in Mar'15. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 30/04/20 associate accounts mentioned contraints regarding deletion of work. Deletion procedure under
39 2011 111 Bilaspur under Sr DEN/East/BSP. DRM/BSP RSK 13466 5095 4000 0 5095 4496 15 100 finalisation with associate accounts.

"Estimate No. 75/B/10.


BSP Div: Provision of CA No. 78/11-12 (Brijesh Agrawal)
RUB (Limited Height
Subway) for LC No. 295 Sr.DEN/E : Work completed in Dec'14. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 31/03/20 associate accounts mentioned contraints regarding deletion of work. Deletion procedure under
40 2011 109 Bilaspur under Sr DEN/East/BSP. DRM/BSP RSK 16777 2348 5245 0 2348 9430 15 100 finalisation with associate accounts.

DTL-NGE: Re-building of
ROB - 95 on NH-78 at
Km. 955/9-10 bet. DTL-
NGE section on divertion Estimate No. 70/B/10. & Revised Estimate No.98/B/12. CA : 24/13-14 (JNPL).
2010- LB- by the side of existing S.Fund,R 30/06/20 31/05/20 Work has been completed 15 Jun'18, technical check of final bill completed on 05/06/2020, final
41 2011 105 Bilaspur ROB. DRM/BSP RSK 17515 24737 0 0 24737 0 18 18 100 80 variation to be processed for approval/ sanction.

Provision of LHS Road at Estimate No. 251/B/11. CA : 92/12-13 (JNPL).


Km.976/15-16 for closing DEN/Spl: Work completed Feb'15, final variation sanctioned on 30.04.2020. Final bill & PVC
of LC No.AB-46 at passed, reimbursement of GST bill pending.
2011- LB- Km.976/14-16 between S.Fund,R 31/12/20 TDC for deletion-30/06/2020.
42 2012 72 Bilaspur BRH-KTO. DRM/BSP RSK 19455 16993 100 2467 19460 2367 15 100

Provision of LHS Road at


Km.994/9-10 for closing
of LC No.AB-59 at
Km.994/4-5 & LC No.AB- "Estimate No. 255/B/11. CA : 92/12-13 (JNPL).
2011- LB- 60 at Km.995/3-5 S.Fund,R 31/12/20
43 2012 87 Bilaspur between KTO-SJQ. DRM/BSP RSK 22922 15892 500 0 15892 6774 15 100 Work completed Feb'15, final variation sanctioned on 30.04.2020, Work deleted..

Page 1 of 21 As on 17/07/2020
WorkWise

"Estimate No. 247/B/11. CA : 78/13-14


Construction of
Low/Limited height Sr.DEN/C : Physically work completed Feb'16. Due to fail ease of contractor in completing the
subway at Km.822/02-03 work, the contract has been terminated and SD, PG & EMD has been for fitted, party has
in lieu of closing of appeal in the Hon'ble High Court C.G. again the termination of contract demanding
unmanned level crossing appointment of arbitrator. The decision of Hon'ble High Court C.G. is not yet received. Hence,
2011- LB- No.BK-39 at Km.822/14- S.Fund,R 30/06/20 statuesque is to be maintained."
44 2012 173 Bilaspur 15 bet BSP-APR. DRM/BSP RSK 23458 21178 100 0 21178 2956 16 100

Bilaspur Yard - Limited


height subway on multi Estimate No. CE/Con/BSP/Subway/ Chuchiyapara/23/12-13, R.E.No. 111/B/15 & 104/B/17
line section in lieu of
2012- PB- Chuchiyapara level S.Fund,R 31/05/20 DEN/Siding : Contract awarded on 04.01.2018. Launching done. Work of approach road and
45 2013 89 Bilaspur crossing gate No.365 DRM/BSP RSK 46099 38727 1000 1000 39727 3305 20 100 cover shed completed. Sump and pump house work completed.

Provision of LHS for


elimination of unamnned "Estimate No. 101/B/12. CA : 87/12-13 (JNPL)
level crossing at DEN/Spl : Work completed Sep'15,LC closed. Final variation concurred & sanction by
2012- LB- Km.995/3-4 between S.Fund,R 31/12/20 competent authority. Bill pending due to test check issue."
47 2013 175 Bilaspur KTO-SJQ section. DRM/BSP RSK 31990 15943 8139 0 15943 0 15 100

"Estimate No. 114/B/12. CA : 35/13-14 (B.A.).

Sr.DEN/SPL : Work completed except drain and retaining wall. contract terminated due to very
Provision of LHS for slow progress balance work will be done through separate agencies. Final bill not pass due
closure of Manned Level contract in dispute. arbitration finalized railway challenged arbitration award in district court.
Crossing No AB - 16 at Policy from Hq is required to deal such case.
2012- LB- km 913/28-30 between S.Fund,R 31/01/20 "
49 2013 209 Bilaspur BATL-BJRI section. DRM/BSP RSK 24403 14066 100 0 14066 10391 17 100 1

"Estimate no 44/B/13. CA : 44/14-15 (J.Ramesh).

Provision of LHS at Work completed ,LC closed in Jan'16.


Unmanned Level
Crossing No AB - 25 F/B final bill passed on & PVC bill not received from contractor, letter served to contractor on
2013- LB- between UKR-BRND S.Fund,R 31/01/20 26/05/2020, policy is required from HQ to deal such cases. "
50 2014 84 Bilaspur section. DRM/BSP RSK 14921 10945 100 0 10945 4314 16 100 0

Nowrozabad : "Estimate No. 57/B/17.


Replacement of FOB DEN/North : C.A. No. 55/18-19, Contractor-Madhusudan Agrawal LOA issued on:
infringing intermediate 13.08.2018.Physically work completed. Nov'19. Final bill passed on 29.04.2020. TDC for work
trestle in between track closure: 29.07.2020
2017- LB- with through span FOB at S.Fund,R 31/12/20
61 2018 227 Bilaspur Nowrozabad. DRM/BSP RSK 19000 21338 620 175 21513 100 19 100 0

Karkeli : Replacement of
FOB infringing "Estimate No. 58/B/17.
intermediate trestle in DEN/North : C.A. No. 55/18-19, Contractor-Madhusudan Agrawal LOA issued on 13.08.2018.
between track with Physically work completed Sep'19. Final bill passed on 29.04.2020. TDC for work closure:
2017- LB- through span FOB at S.Fund,R 31/10/20 29.07.2020"
62 2018 229 Bilaspur Karkeli. DRM/BSP RSK 17000 14974 983 175 15149 100 19 100

Limited Height subway


(size 5m x 5m)at LC No.
CI-4(U/M) at Km 1263/6-7
2009- LB- Nagpur(S between on NGP-CWA CAO(CON S.Fund,R 31/01/20
78 2010 103 ECR) section(NG). )/SECR RSK 3717 14100 1102 14100 7 17 100 Work of LHS completed.

Proposed cons. of RUB of


size 4m x 3m (LHS at LC
No. CI-17 (U/M) at km.
1279/15 & at LC No. CI-
18 (U/M) at km. 1281/6-7
2009- LB- Nagpur(S in CWA-NGP section CAO(CON S.Fund,R 28/02/20
79 2010 101 ECR) (NG). )/SECR RSK 8759 24500 1300 24500 0 17 100 Work of LHS completed.

Page 2 of 21 As on 17/07/2020
WorkWise

Proposed cons. of RUB of


size 4m x 3m (LHS) at LC
No. CI-13 (U/M) at km.
1277/5-6 & at LC No. CI-
14 (U/M) at km. 1278/9-
2009- LB- Nagpur(S 10 in CWA-NGP section CAO(CON S.Fund,R 17/01/20
80 2010 99 ECR) (NG). )/SECR RSK 8675 24800 1 24800 60 17 100 LHS works completed.

Proposed construction of
LHS of size 4m x 3m at
LC No.CI-5 (U/M) at Km
1265/12-13 & at LC No.
2009- LB- Nagpur(S CI-6 (U/M) at Km. 1267/9- CAO(CON S.Fund,R 31/03/20
81 2010 93 ECR) 10 in CWA-NGP. )/SECR RSK 7425 17200 1300 17200 1 17 100 LHS work completed.

Proposed construction of
RUB of size 4m x 3m
(LHS) at LC No. CI-19
(U/M), Km. 1282/3-4 & LC
No. CI-92 (U/M), Km.
2009- LB- Nagpur(S 1371/11-12 in CWA-NGP CAO(CON S.Fund,R 31/05/20
82 2010 95 ECR) Section (NG). )/SECR RSK 7667 19400 0 19400 165014 17 100 Work of LHS completed.

Proposed construction of
RUB of size 4m x 3m
(LHS) at LC No. GJ-144
(U/M) at Km. 1213/2-3 &
LC No. GJ-145 (U/M) at
2009- LB- Nagpur(S Km. 1214/7 in G-JBP CAO(CON S.Fund,R 31/03/20
83 2010 97 ECR) Section. )/SECR RSK 7666 6503 0 6503 1163 16 95 0 Work completed. LHS commissioned. Final bill passed. SD released.

BTC-NIR: Construction of
LHS at Manned LC No.
GJ-63 at km. 1082/15-16
2010- LB- Nagpur(S and at unmanned LC CAO(CON S.Fund,R 31/03/20 Work of LHS at GJ - 69 completed. GJ - 63 box segment casted & approach road etc. work is
84 2011 115 ECR) no.GJ-69 at km. 1092/8-9. )/SECR RSK 8428 8400 27 8400 1 20 100 in progress.

BTC-NIR: Construction of
LHS at U/M LC No. GJ-44
at km. 1053/3 and at U/M
LC No. GJ-55 at km
2010- LB- Nagpur(S 1072/0-1 between BTC- CAO(CON S.Fund,R 31/01/20
85 2011 119 ECR) NIR section. )/SECR RSK 8428 9500 1307 9500 0 19 100 LHS at GJ -44 and 55 completed.

Construction of LHS at
U/M LC No. CI-113 at km.
1398/14-15 in NGP-CWA
section and at U/M LC
No. NC-9 at km 1136/12-
2010- LB- Nagpur(S 13 between CWA-NIR CAO(CON S.Fund,R 31/10/20 31/05/20
86 2011 117 ECR) section. )/SECR RSK 13229 15300 1300 15300 28 17 18 100 LHS at NC-9 & CI-113 completed.

LHS at LC No. CI-


78(U/M), Km. 1355/9-10
between KLOD (PH)-
SONR Station and LC No.
CI-96(U/M) Km. 1375/13-
2010- LB- Nagpur(S 14 between KPDK-PTS CAO(CON S.Fund,R 31/10/20
87 2011 145 ECR) stations. )/SECR RSK 7479 17600 1300 17600 20 15 100 Work at CI-78 completed & commissioned. CI-96 To be retained as manned in GC .

Page 3 of 21 As on 17/07/2020
WorkWise

LHS at LC No. CI-90


(U/M) km 1368/14-15
between SONR-PTS
stations and LC No. CI-91
(U/M) Km. 1370/9-10
2010- LB- Nagpur(S between SONR-PTS CAO(CON S.Fund,R 28/02/20
88 2011 147 ECR) stations. )/SECR RSK 8019 24900 1300 24900 50 17 100 LHS work completed & commissioned.

NGP-CWA: Construction
of LHS at Unmanned level
crossings No. CI-23 at
Km 1285/9-10 and CI-81
2010- LB- Nagpur(S at Km 1360/10-11 in CAO(CON S.Fund,R 31/03/20
89 2011 141 ECR) NGP-CWA section. )/SECR RSK 8422 25500 1300 25500 20 17 100 Work completed at CI-81 & CI-23 & commissioned.

NGP-CWA: Proposed
construction of Limited
Height Subway at U/M i) LC No. CI-106 is closed by Road diversion.
LCs No. CI-99 at km. ii) At CI-99- local villagers and people representative demanded bigger size LHS or ROB.
2010- LB- Nagpur(S 1381/3-4 and LC no.CI- CAO(CON S.Fund,R 30/09/20 Drainage is not available for height of LHS more than 4m and hence ROB is to be planned
90 2011 113 ECR) 106 at km. 1388/3-4. )/SECR RSK 8422 24000 1437 24000 80 17 100 instead of LHS at CI-99.Proposed for retention as manned LC till construction of LROB.

NIR-CWA: Construction
of at U/M LCs No.NC-19
at Km 1150/14 and at
Unmanned LC No.NC-38
2010- LB- Nagpur(S at Km 1175/5 between CAO(CON S.Fund,R 31/12/20 31/12/20
91 2011 127 ECR) NIR-CWA section. )/SECR RSK 8472 26410 1300 26410 0 17 18 100 100 LHS work completed at NC-19 & NC-38

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-43 at Km 1182/3 and
at Unmanned LC No. NC-
2010- LB- Nagpur(S 54 at Km 1204/5 between CAO(CON S.Fund,R 31/10/20 31/10/20
92 2011 129 ECR) NIR-CWA section. )/SECR RSK 8406 17610 1300 17610 0 16 18 100 LHS work at NC-43 c& NC-54 completed.

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-56 at Km 1208/5 and
at Unmanned LC No. NC-
76 at Km 1229/1-2
2010- LB- Nagpur(S between CWA-NIR CAO(CON S.Fund,R 31/12/20 31/01/20
93 2011 131 ECR) section. )/SECR RSK 8170 18810 1300 18810 0 16 19 100 LHS work at NC-56 & 76 completed.

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-77 at Km 1229/15 and
at Unmanned LC No. NC-
81 at Km 1237/11-12
2010- LB- Nagpur(S between CWA-NIR CAO(CON S.Fund,R 31/10/20 31/12/20 1) NC-77 LHS work completed.
95 2011 133 ECR) section. )/SECR RSK 8372 17639 1400 17639 0 16 19 100 2) NC-81 LHS work completed.

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-82 at Km 1238/6-7
and at Unmanned LC No.
NC-84 at Km 1240/9-10
2010- LB- Nagpur(S between CWA-NIR CAO(CON S.Fund,R 31/01/20 30/06/20 NC-82 Completed (Dec'17)
96 2011 137 ECR) section. )/SECR RSK 8481 21110 500 21110 0 17 19 100 NC-84 Completed (March'19).

Page 4 of 21 As on 17/07/2020
WorkWise

NIR-CWA: Construction
of LHS AT U/M LCs No.
NC-86 at Km 1242/9-10
and at Unmanned LC No.
NC-87 at Km 1243/13-14
2010- LB- Nagpur(S between CWA-NIR CAO(CON S.Fund,R 30/09/20 30/06/20 NC-86 Completed (Jan.'18).
97 2011 135 ECR) section. )/SECR RSK 8188 17700 0 17700 0 16 18 100 NC-87 Completed March'18

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-89 at Km 1246/6-7
and at Unmanned LC No.
NC-91 at Km 1248/14-15
2010- LB- Nagpur(S between CWA-NIR CAO(CON S.Fund,R 31/12/20 31/01/20 NC-89 LHS Work completed.
98 2011 139 ECR) section. )/SECR RSK 8234 24510 0 24510 0 16 19 100 NC-91 LHS Work completed.

NIR-MFR: Proposed
construction of Limited
height subway at
Unmanned level
crossings No. NM-4 at
2010- LB- Nagpur(S Km 1120/15-16 between CAO(CON S.Fund,R 30/06/20 30/06/20
101 2011 143 ECR) NIR-MFR section. )/SECR RSK 4489 10000 1 10000 199 17 17 100 Work of LHS completed.

Chhindwara-Nagpur -
Limited height subways i)Work completed at CI-07,08,15,16,21,22,26,27,41,43, 48,50,51,54,57,60,62,66,67,69,
by open cut method at 76,77,79,80, 85, 86, 89,93, 95, 97, 98, 101 ,102 , 109,110,112) (36 nos).
2011- PB- Nagpur(S unmanned level crossings CAO(CON S.Fund,R 31/10/20 ii) CI-01 & 88 retained as manned LC and CI- 73 & 74 closed by diversion.
103 2012 83 ECR) (40 Nos) )/SECR RSK 447223 5E+05 500 537500 -56000 18 100

Construction of LHS at
unmanned LCs No. CI- 20
at km 1282/10-11
2011- LB- Nagpur(S between CWA - NGP CAO(CON S.Fund,R 31/03/20
108 2012 149 ECR) section . )/SECR RSK 13154 16000 1 16000 99 17 100 LHS work completed.

Construction of Limited
Height Subway at
unmanned LC No.CI-24
2011- LB- Nagpur(S at km 1286/3-4 between CAO(CON S.Fund,R 31/01/20 CI-24 completed.
109 2012 154 ECR) CWA - NGP section . )/SECR RSK 13765 16000 0 16000 100 17 100

Construction of Limited
Height Subway at
unmanned LCs No. CI- 40
2011- LB- Nagpur(S at km 1311/6-7 between CAO(CON S.Fund,R 28/02/20
110 2012 156 ECR) CWA - NGP section . )/SECR RSK 13765 18000 1 18000 1360 17 100 - Work of LHS Completed and commissioned .

Construction of Limited
Height Subway at
unmanned LCs No. CI- 56
at km 1332/15-16
2011- LB- Nagpur(S between CWA - NGP CAO(CON S.Fund,R 31/12/20
111 2012 158 ECR) section . )/SECR RSK 13765 18060 0 18060 1300 17 100 Work of LHS completed.

Construction of Limited
Height Subway at
unmanned LC No.CI-42
2011- LB- Nagpur(S at km 1315/14 between CAO(CON S.Fund,R 31/03/20
112 2012 160 ECR) CWA - NGP section . )/SECR RSK 13765 16000 0 16000 1320 17 100 LHS work completed.

Construction of Limited
Height Subway at
unmanned LC No.CI-61
2011- LB- Nagpur(S at km 1336/1 between CAO(CON S.Fund,R 31/10/20
113 2012 162 ECR) CWA - NGP section . )/SECR RSK 13765 15920 0 15920 0 17 100 LHS work completed.

Page 5 of 21 As on 17/07/2020
WorkWise

Construction of Limited
Height Subway at
unmanned LC No. CI- 64
2011- LB- Nagpur(S at km 1337/15 between CAO(CON S.Fund,R 31/10/20
114 2012 163 ECR) CWA - NGP section . )/SECR RSK 13765 15900 0 15900 30 17 100 LHS work completed.

Construction of LHS at
unmanned LC No.CI-65
at km 1338/12-13
2011- LB- Nagpur(S between CWA - NGP CAO(CON S.Fund,R 30/09/20 Works of LHS completed.
115 2012 165 ECR) section . )/SECR RSK 13765 16140 0 16140 0 17 100

Construction of LHS at
unmanned LC No. CI- 75
at km 1351/10-11
2011- LB- Nagpur(S between CWA - NGP CAO(CON S.Fund,R 30/04/20
116 2012 167 ECR) section . )/SECR RSK 13765 16150 0 16150 0 17 100 Work of LHS completed.

Construction of LHS(size
4m x 5m) at LC No. CI-11
(U/M) at km 1273/5-6
2011- LB- Nagpur(S between CWA-NGP CAO(CON S.Fund,R 28/02/20
117 2012 169 ECR) section. )/SECR RSK 13781 15930 0 15930 0 17 100 Work of LHS completed.

Proposed construction of
normal height subway of
size 2 X 6.00m X 6.00m
at manned L/C No. GJ-45
2011- LB- Nagpur(S at km 1053/14-15 in CAO(CON S.Fund,R 30/11/20
119 2012 150 ECR) between G - JBP sec. )/SECR RSK 20667 24200 30 24200 0 18 100 Work of LHS completed.

Construction of LHS(size
6m x 6m) at LC No.CI-02
(U/M) at Km.1262/1-2
2012- LB- Nagpur(S between CWA-ITR line CAO(CON S.Fund,R 31/12/20
123 2013 189 ECR) (NG). )/SECR RSK 16662 13290 0 13290 0 16 100 LHS commissioned.

Construction of L H
Subway at M/LC No.CI-52
at Km.1328/13-14
between CWA-ITR line
(NG) under the
2012- LB- Nagpur(S jurisdiction of CAO(CON S.Fund,R 28/02/20
124 2013 191 ECR) ADEN/CWA. )/SECR RSK 18388 18200 1 18200 186 17 100 0 Work of LHS completed.

Construction of LHS(size
4.15m x 4.15m) at U/M
LC No.CI-39 at
2012- LB- Nagpur(S Km.1308/7-8 between CAO(CON S.Fund,R 30/11/20
125 2013 193 ECR) CWA-ITR line (NG). )/SECR RSK 17252 15800 1 15800 112 16 100 0 Work LHS completed.

Construction of LH
Subway at M/ LC No.GJ-
134 at Km.1195/5-6
between BTC-JBP (NG)
2012- LB- Nagpur(S under the jurisdiction of CAO(CON S.Fund,R 31/03/20 31/12/20
126 2013 195 ECR) ADEN/NIR. )/SECR RSK 17210 126 0 126 16885 16 16 98 Work completed. LHS commissioned. Final bill passed. SD released.

Construction of Limted
Height Subway of size
4.15mx4.05m at
Unmanned LC No. NC-
71at km.1225/4 between
2013- LB- Nagpur(S NIR-CWA line by GC CAO(CON S.Fund,R 31/12/20 30/06/20
133 2014 76 ECR) project. )/SECR RSK 12866 16400 17 16400 0 16 20 100 Cast in situ LHS. work of LHS completed

Page 6 of 21 As on 17/07/2020
WorkWise

Construction of Limted
Height Subway of size
4.15m x 4.05m at
Unmanned LC No. NC-74
at km.1227/4-5 between
2013- LB- Nagpur(S NIR-CWA line by GC CAO(CON S.Fund,R 31/01/20 31/12/20
135 2014 78 ECR) project. )/SECR RSK 13235 15800 1 15800 92 17 18 100 Work of LHS completed.

Construction of full height


subway of size 6m X 5m
at manned LC No. NC-21
at Km.1154/10-11
2013- LB- Nagpur(S between NIR-CWA line by CAO(CON S.Fund,R 31/03/20 30/04/20
136 2014 91 ECR) GC project. )/SECR RSK 20440 17000 1 17000 20 17 18 100 Work of LHS compled.
Nagpur-Chhindwara-
subways in lieu of level
2015- PB- Nagpur(S crossing No. 9, 12, 45, 47 CAO(CON S.Fund,R 31/05/20
137 2016 115 ECR) , 53 & 103 (6 Nos) )/SECR RSK 99445 1E+05 200 120500 -21256 18 100 Work completed at CI-09, 12, 45, 47 , 53 and 103. all are completed.
Kanhan-Ramtek - Light
Road over bridge (Br.No.
2016- PB- Nagpur(S 28-A) in lieu of level S.Fund,R Work completed and LC closed in Jun-19. Final bill passed. CR to be drawn.
148 2017 122 ECR) crossing No.KR-12 DRM/NAG RSK 26622 37862 1 656 38518 4459 100 100
Kanhan-Ramtek - Light
Road over bridge in lieu of KR-3 : Joint survey done with SDO/Ramtek for site survey for getting collector consent on
2016- PB- Nagpur(S level crossing No.KR-3 & S.Fund,R 01.02.17. No Collector consent . Not feasible. Work to be dropped.
149 2017 124 ECR) KR-8 (2 Nos.) DRM/NAG RSK 92137 36870 10000 5703 42573 45267 100 100 KR-8 : ROB commissioned for Road Traffic. Final bill passed.

Rajnandgaon -
Replacement of FOBs
having intermediate 2
legged trestles in between Work completed and FOB commissioned. Connection work of FOB with lift is in progress (after
2017- LB- Nagpur(S running lines at S.Fund,R 31/07/20 raising of door level of lift)
154 2018 249 ECR) Rajnandgaon. DRM/NAG RSK 15407 16791 100 2337 19128 5400 20 99

Tirora - Replacement of
FOB having intermediate
2 legged trestles in
between running lines at
2017- LB- Nagpur(S Tirora station in Durg- S.Fund,R 31/08/20 FOB work completed in Oct 2019. De-launching of old FOB work completed on 18.03.2020.
157 2018 247 ECR) Nagpur section DRM/NAG RSK 14978 23835 4400 0 23835 165 20 98 Now, cable shifting done but block not agreed due to Shramik special trains.

Nagpur Division:
Proposed construction of
limited height subway at
U/M LC No. TT-19 at km
2017- LB- Nagpur(S 1072/5-6 in Tumsar - S.Fund,R 31/03/20
159 2018 223 ECR) Tirodi branch line. DRM/NAG RSK 16012 6676 1614 0 6676 7722 20 100 Work completed. Final bill could not prepared due to contractor dispute.
ROB work is completed and commissioned by State PWD. This ROB work was executed by
Dadhapara-Belha - Road PWD on single entity basis. RUB work is executed by Railways. RUB work is completed and
2010- PB- over & under bridge at CAO(CON S.Fund,R 31/12/20 31/10/20 LC closed.As per MOU letter written and also reminder sent to state PWD/Bridge for take
178 2011 79 Raipur level crossing No.370 )/SECR RSK 54286 1E+05 3000 119081 4291 14 17 100 100 handing over of RUB for maintenance.

Tilda-Simga - Road under


& over bridge at level
crossing No.397 near
2010- PB- Tilda crossing (national CAO(CON S.Fund,R 31/12/20
179 2011 78 Raipur highway No.37) )/SECR RSK 63700 67800 100 67800 52951 14 100 100 Completed and Commisioned in Feb 19
Bhilai-Durg - Limited Sr.DEE(G)/R : work completed final bill passed, informed for deleation
height subway near level Sr.DEN-Line : RUB work in Railway portion completed. State portion road completed by PWD.
2011- PB- crossing No.443 (Nehru S.Fund,R 30/06/20 31/07/20 ROB works completed in Railway portion, PWD work for electrical fitting is in progress.
180 2012 81 Raipur Nagar Gate) DRM/R RSK 36717 61391 31200 159 61550 0 15 20 98 0 Installation of pump by Elect(G) and pipe line work completed.

Page 7 of 21 As on 17/07/2020
WorkWise

Balod-Kusumkasa- Light DEN/II :Work completed.Final bill passed. RUB commissioned. Agency has submitted PVC bill.
2016- PB- Road over bridge in lieu of S.Fund,R 31/07/20 PVC bill is under passing. After passing of PVC bill the work can be deleted. TDC for deletion of
189 2017 126 Raipur level crossing No. DD-55 DRM/R RSK 28873 28327 500 0 28327 5170 20 95 work revised up to 15.07.2020
Kumhari- C Cabin- Sr.DEE(G)/R : work completed Informed for deletion
2016- PB- Subway in lieu of level S.Fund,R 31/07/20 Sr.DEN-Line : Work completed. Final bill passed on 08.09.2019. PVC bill passed on
192 2017 119 Raipur crossing No.432 DRM/R RSK 58628 38698 20525 0 38698 21724 20 95 0 10.10.2019

Raipur-Durg- Subway in Sr.DEE(G)/R : Work complted. Final bill paid. inform for deletion.
2016- PB- lieu of level crossings S.Fund,R 31/07/20 Sr.DEN-Line : Sr.DEN-Line : Work completed. Final bill passed on 08.09.2019. PVC bill passed
193 2017 135 Raipur No.433 & 434 (1 No.) DRM/R RSK 54106 53425 520 0 53425 722 20 99 on 10.10.2019. Sr.DEE(G)/R : Work complted. Final bill paid. inform for deletion.
Latabor Yard - Closure of Sr.DEE(G)/R : Work completed . Final bill paid. informed for deletion.
2017- PB- manned level No.DD-45 31/07/20 DEN/II : Work completed. Final bill passed. PVC bill passed. Work proposed for deletion.
196 2018 141 Raipur by road under bridge DRM/R RRSK 42500 21875 20600 1710 23585 4537 20 99 Sr.DEE/G/R:- final bill under process

Urkura-Sarona - Road Sr.DEN-Line : Work completed by state PWD. LC Closed. Collector permission received on
under bridge in lieu of 01.06.16. Cost sharing letter received on 21.06.16. DE vetted on 04.05.18. DE for
2017- PB- manned level crossing 31/07/20 Rs.14,69,24,188/- Sent to HQ for vetting on 05.05.18. Railway Board letter received on
197 2018 142 Raipur No.424 (Gondwara Gate) DRM/R RRSK 36200 0 30000 0 0 6200 20 95 100 26.09.18 for compliance. Compliance of Railway Board sent to HQ on 04.10.18.

Dagori - Replacement of
existing through FOB at
Dagori station by
providing 3.0 mtr. wide
new FOB to remove Sr.DEE(G)/R : Work completed departmentally
2017- LB- infringement on safety S.Fund,R 31/07/20 Sr.DEN-Line : Sr.DEN-Line : Civil Work completed. Final bill passed on 15.06.2020. PVC bill
199 2018 235 Raipur Account. DRM/R RSK 15509 11102 4318 1341 12443 100 20 95 0 awaited. Sr.DEE(G)/R : Work completed departmentall

Belha - Replacement of
existing through FOB at
Belha station by providing
3.0 mtr. wide new FOB to Sr.DEN-Line : Sr.DEN-Line : Work completed, Final bill passed on 15.06.2020. PVC Bill
2017- LB- remove infringement on S.Fund,R 31/07/20 awaited. Sr.DEE(G)/R : work completed departmentally , final closure under process
200 2018 237 Raipur safety Account. DRM/R RSK 20586 19685 663 1397 21082 834 20 95 Sr.DEE(G)/R : work completed departmentally

Dadhapara -
Replacement of existing
through FOB at
Dadhapara station by
providing 3 mtr new FOB Sr.DEN-Line : Sr.DEN-Line : Work completed, Final bill recieved on 17.06.2020. Closure of
2017- LB- to remove infringement on S.Fund,R 31/07/20 contract is under process.
201 2018 239 Raipur safety Account DRM/R RSK 15701 13809 1811 155 13964 100 20 95 Sr.DEE(G)/R : work completed departmentally

Tilda - Replacement of
existing through FOB at
Tilda station by providing
3.0 mtr. wide new FOB to
2017- LB- remove infringement on S.Fund,R 31/07/20 Sr.DEN-Line : Sr.DEN-Line : Civil Work completed. Final bill passed on 10.06.2020.
202 2018 243 Raipur safety Account. DRM/R RSK 24002 17217 7389 1583 18800 100 20 95 Sr.DEE(G)/R : work completed, final closure under process

Kumhari - Replacement of
existing through FOB at
Kumhari station by
providing 3.0 mtr. new
FOB to remove
2017- LB- infringement on safety S.Fund,R 31/07/20 Sr.DEN-Line : Work completed. Final bill awaited.
203 2018 245 Raipur Account. DRM/R RSK 21070 26718 0 81 26799 182 20 95 Sr.DEE(G)/R : work completed departmentally , final closure under process

Page 8 of 21 As on 17/07/2020
WorkWise

PH- 30 Works status as on 07.07.2020

upto March '20


Short Name of

ALLOCATION

of Rly portion
Original Cost
(PB,LB,DRM)

Revised TDC
during 2020-
Expenditure

Expenditure

Expenditure
Modified for

progress of

progress of
Anticipated
Agency Rly

Balance till

TDC of Rly

REMARKS
%age Phy.

%age Phy.
Executing

2020-2021

upto date
Sanction

Division
PB Item

Agency
portion
Year of

Outlay
Work

2021

Date

Rly
SN

1 5 6 10 12 13 17 18 22 24 23 26 27 29 31 38 39 41
Bilaspur Yard - Road over
bridge in lieu of level GAD for width 12 meters has been adapted by Railway authorities and the same sent to state
2013- PB- crossing No.366 at CAO(CON S.Fund,R 31/03/20 govt. for make revised original drawing and design and alignment in RDSO standard. Estimate
1 2014 91 Bilaspur Tarbahar Naka )/SECR RSK 310629 737 1000 737 154446 16 will be prepare after signature on drawings both Railway and State authorities.
Bilaspur-Katni - Road
over & under bridge in lieu
2013- PB- of level crossing No.BK- CAO(CON S.Fund,R 30/06/20 31/03/20 RUB portion work will be executed by Railway for which tender awarded on 29.1.18.Work is in
3 2014 93 Bilaspur 37 near Gourela )/SECR RSK 128811 1E+05 11000 118503 -693 16 20 50 80 progress.

Bhilai Power House-


Bhilainagar - Road over &
under bridge in lieu of
2013- PB- manned level crossing CAO(CON S.Fund,R 31/12/20
4 2014 99 Raipur No.442 (Supela Gate) )/SECR RSK 144055 737 50001 737 93317 18 GAD under approval

All the 86 nos Piles, 13 nos Pile Caps, 13 nos Piers and 13 nos Pier caps have been
casted.Sub-structure work completed.
Work of shuttering for RCC T-beams & deck slab, construction of RE wall at both the UP and
Bijuri Yard - Road over Down side approaches and manufacturing of steel/composite girders for 18.3m & 30.5m
2013- PB- bridge in lieu of level CAO(CON S.Fund,R 31/03/20 31/03/20 ready for launching. Application for launching for Girders sent to CRS for sanction on
5 2014 94 Bilaspur crossing No.AB-18 )/SECR RSK 249555 91569 31500 91569 126485 16 20 53 50 17.12.2019.

Sr.DEE(G)/R : LOA issued on date 14.08.2017.material approval given , work short closed due
to engg. site clearance execution work can be done departmentally or by quotation after engg.
site clearance
Sr.DEN-Line : Work transferred from Construction organization to open line on 05.08.2015.
Bhilai - Full height subway State share recieved on 18.05.16 Tender opened on 02.06.16 LOA issued on 12.11.16 Heldup
2013- PB- in lieu of level crosing S.Fund,R 31/12/20 31/01/20 for S&T clearance which was received on 05.02.2019. (Non availability of cables) Work
6 2014 97 Raipur No.439 (Sirsa Gate) DRM/R RSK 66053 39114 35550 6510 45624 15737 16 21 40 awarded on Nov 16. Three location

Sr.DEN-Line : Work transferred from Construction organization to open line on 05.08.2015.


State cost sharing consent received on 01.05.2018. GAD approved on 09.07.2019.DE
submitted to finance on 24.09.2019. File returned from finance on 17.10.19.File resubmitted to
Sarona-Kumhari - Full finance on 21.10.19. File returned from finance on 04.11.19 with observations. File resubmitted
2013- PB- height subway in lieu of S.Fund,R 31/03/20 30/06/20 to finance on 15.11.19. Revised cost is RS. 16.67 Cr due to change in GAD (Twin box,
7 2014 102 Raipur level crosing No.429 DRM/R RSK 43889 4442 1000 0 4442 38447 17 21 0 0 diversion of road, retaining wall length etc. *File s

Sr.DEE(G)/R : LOA Issued on Date 05.01.2018 awaiting for Engg. site Clearance.
Sr.DEN-Line : Work transferred from Construction organization to open line on
05.08.2015.Signed MOU received on 23.07.2016.State share received on 24.12.16.Revised
Durg Yard - Full height estimate sanctioned on 02.03.2017.LOA issued on 12.07.2018 for LHS.LC physically
2013- PB- subway in lieu of level S.Fund,R 31/12/20 31/03/20 closed.Estimate of 13.7 Lakhs received from Nagar Nigam on 22.11.2019. Submitted to PWD
8 2014 98 Raipur crosing No.445 DRM/R RSK 36694 12819 25700 1131 13950 10074 16 21 15 0 on 23.11.2019. Upside approach- Nagar Nigam water pipe line to be shifted.Sheet piling

Sr.DEE(G)/R : LOA Issued on date 12.10.2018 work to be started awaiting engg.site clearence.
Sr.DEN-Line : Work transferred from Construction organization to open line on 05.08.2015.
Saraswatinagar-Sarona - Signed MOU recieved on 07.05.18. State share recieved on 22.05.18. LOA issued on 21.11.18.
Full height subway in lieu Work held up initially by locals for service road which was not feasible due to land constraints.
2013- PB- of level crossing No.421 S.Fund,R 31/03/20 31/01/20 MLA & DRM visited site on 29.05.19. PWD advised to provide service road. Approach road
10 2014 95 Raipur (Dumartalab Gate) DRM/R RSK 35055 11416 4505 3122 14538 19134 17 21 40 80% completed on both sides. For thrust
Bilaspur-Durg - Limited
height subway in lieu of Sr.DEN-Line : LOA issued on 13.03.18. 14 no. boxes launching completed. Approach road yard
2013- PB- level crossing near G- S.Fund,R 31/12/20 31/07/20 side completed and village side approach road raft completed, retaining wall completed. Shed-
11 2014 100 Raipur cabin DRM/R RSK 28564 20802 12100 2267 23069 787 15 20 75 0 fabrication started. 34 no truss erected at yard side. 80 mtr wearing coat completed.

Page 9 of 21 As on 17/07/2020
WorkWise

Estimated investment
through EBR(Partnership)
for works on Indian
Railways on cost share
2018- PB- basis incl deposit from EBR(PP
12 2019 145 State Government etc P) 1300000 0 1250000 0 50000 .

Bilaspur-Raipur -
Elimination of level
crossing No.398 in Tilda
Yard by provision of road
over bridge & road under
bridge S.Fund,R
2018- PB- (Supl.No.2/December CAO(CON RSK,EB
13 2019 148 Raipur 2018) )/SECR R(PPP) 748100 0 50010 0 254190 GAD under preparation

Pendra Road-Harri -
Construction of road over
& road under bridges for
closure of manned level
crossing No.BK-38
2018- PB- (Supl.No.4/December CAO(CON RRSK,E 31/03/20 Joint survey with state govt. done for distribution of work and feasibility study. Geo tech
14 2019 150 Bilaspur 2018) )/SECR BR(PPP) 453200 0 1000 0 225600 22 0 0 investigation is in progress. GAD under preparation

Mandhar-Urkura -
Elimination of level
crossing No.414 in Urkura
Yard by provision of road
over bridge & road under
bridge S.Fund,R
2018- PB- (Supl.No.3/December CAO(CON RSK,EB
15 2019 149 Raipur 2018) )/SECR R(PPP) 775400 0 50010 0 266790 GAD under preparation

Kotarlia-Raigarh - Road
over bridge with subway
in lieu of level crossing
No.287 S.Fund,R
2018- PB- (Supl.No.8/December CAO(CON RSK,EB Work dropped from this year budget of State Govt..State Govt. has moved a case for re-
16 2019 154 Bilaspur 2018) )/SECR R(PPP) 302200 0 1000 0 150100 approval.Will be executed on single entity basis by PWD/Chhattisgarh.

Champa-Gevra Road -
Elimination of level
crossing No.CG-28 by
provision of road over
bridge with subway
2018- PB- (Supl.No.13/December CAO(CON RRSK,E
17 2019 159 Bilaspur 2018) )/SECR BR(PPP) 260400 0 5000 0 125200 Work will be executed on single entity basis by PWD/Chhttiagarh..

Champa-Gevra Road -
Elimination of level
crossing No.CG-20 in
Urga Yard by provision of
road over bridge with
subway
2018- PB- (Supl.No.11/December CAO(CON RRSK,E
18 2019 157 Bilaspur 2018) )/SECR BR(PPP) 289200 0 5000 0 139600 GAD under preparation

Champa-Bilaspur - Road
over bridge at level
crossing No.360 on
Jairam Nagar Yard S.Fund,R
2018- PB- (Supl.No.6/December CAO(CON RSK,EB
19 2019 152 Bilaspur 2018) )/SECR R(PPP) 397200 0 2000 0 196600 GAD under preparation by PWD, it will be executed by PWD on single entity basis

Page 10 of 21 As on 17/07/2020
WorkWise

Bhupdeopur-Robertson -
Elimination of level
crossing No.303 by
construction of road over
bridge with subway S.Fund,R
2018- PB- (Supl.No.10/December CAO(CON RSK,EB
20 2019 156 Bilaspur 2018) )/SECR R(PPP) 272000 0 6000 0 130000 GAD under preparation

Bhupdeopur-Robertson -
Elimination of level
crossing No.301
(Naharpali) by
construction of road over
bridge S.Fund,R Work will be executed on single entity basis by SECR/Con,GAD approved for the ROB. DPR
2018- PB- (Supl.No.9/December CAO(CON RSK,EB submitted by PWD to Government approval process. State Govt sanctioned the work.
21 2019 155 Bilaspur 2018) )/SECR R(PPP) 226000 0 6000 0 107000

Bilaspur-Uslapur -
Construction of road
under bridge for closure
of manned level crossing Estimate No. 69/B/19.
No.BK-03 Sr.DEN/Central : GAD approved by CBE on 17/10/19. Detailed estimate vetted on 20.03.2020.
2018- PB- (Supl.No.5/December RRSK,E 30/06/20 Vetted estimate sent to PWD/CG govt. on 01.04.2020. For deposition of 50%
22 2019 151 Bilaspur 2018) DRM/BSP BR(PPP) 94600 0 1 0 0 47299 21 0 0 (Rs.5,76,03,258/-) share cost & acceptance of estimate.

Rasmara-Durg - Road
under bridge in lieu of
level crossing No.450 S.Fund,R
2018- PB- Nagpur(S (Supl.No.1/December RSK,EB 30/06/20 Tender awarded in Mar-20, but work could not started due to lockdown (Covid-19). Also, state
23 2019 164 ECR) 2018) DRM/NAG R(PPP) 141200 0 6000 0 0 69600 21 0 0 govt. has not yet deposited his 50% cost sharing amount.

Raipur Division - Road


under bridge in lieu of
level crossing No.373 at Sr.DEN-Line : GAD approved on 21.08.19.DE vetted on 18.11.19. MOU sent to State PWD on
Belha Yard S.Fund,R 19.11.19. 2nd Reminder letter sent to State PWD on 13.03.2020. 3rd Reminder letter sent to
2018- PB- (Supl.No.7/December RSK,EB 31/10/20 State PWD on 20.05.2020. After receipt of signed MOU and state government share tender to
24 2019 153 Raipur 2018) DRM/R R(PPP) 173800 0 1001 0 0 90899 22 0 be floated.

Champa-Jharsuguda -
Elimination of level
crossing No.320 (Temar
Gate) by provision of road
over bridge with subway S.Fund,R
2018- PB- (Supl.No.15/December CAO(CON RSK,EB
25 2019 161 Bilaspur 2018) )/SECR R(PPP) 311200 0 6000 0 149600 GAD under preparation

Champa-Gevra Road -
Elimination of level
crossing No.CG-26
between Korba-Urga Yard
by provision of road over
bridge with subway
2018- PB- (Supl.No.12/December CAO(CON RRSK,E
26 2019 158 Bilaspur 2018) )/SECR BR(PPP) 179400 0 5000 0 84700 GAD under preparation

Champa-Jharsuguda -
Elimination of level
crossing No.313 in
Kharsia Yard/West End
by provision of road over
bridge and subway S.Fund,R
2018- PB- (Supl.No.16/December CAO(CON RSK,EB
27 2019 162 Bilaspur 2018) )/SECR R(PPP) 321200 0 2000 0 158600 Work will be executed on single entity basis by PWD/Chhttiagarh

Page 11 of 21 As on 17/07/2020
WorkWise

Raigarh-Kirodimalnagar -
Elimination of level
crossing No.289 (Kotara
Gate) by construction of
road over bridge with
subway S.Fund,R
2018- PB- (Supl.No.14/December CAO(CON RSK,EB
28 2019 160 Bilaspur 2018) )/SECR R(PPP) 408200 0 250010 0 -45910 Work will be executed on single entity basis by PWD/Chhttiagarh

South East Central


Railway - Construction of
2019- PB- road over/under bridges RRSK,E
29 2020 165 (Umbrella Work 2019-20) BR(PPP) 2385438 0 50000 0 1750000 .

South East Central


Railway - Construction of
road over/under bridges
on golden quadrilateral /
2019- PB- golden diagonal routes
30 2020 166 (Umbrella Work 2019-20) S.Fund 4900000 0 260000 0 4640000 .

Champa Yard - Road S.Fund,R


2007- PB- over & under bridge in lieu CAO(CON RSK,EB 31/10/20 30/06/20 Railway track Portion,Sub-Structure completed. work is in progress in Super structure and
35 2008 75 Bilaspur of level crossing No 337 )/SECR R(PPP) 72967 32059 28100 32059 12808 16 20 42 85 approach.
Champa-Naila - Road 1-Both the Approach spans completed with PSC girder and deck slab
over bridge in lieu of level S.Fund,R 2-Track portion 2 Span completed out of 3 span. Work is in progress for 3rd span. CRS
2007- PB- crossing No 342 (Khoksa CAO(CON RSK,EB 31/03/20 30/06/20 sanction is awaited for launching of girder of Railway span.
36 2008 74 Bilaspur level crossing) )/SECR R(PPP) 69324 81392 15500 81392 12359 14 20 85 100 .

Bilaspur-Katni - Road
over & under bridge / Sr.DEN/N : Work is to be executed by state govt-MPRDC Bhopal. Work sanctioned on cost
limited height subway in sharing basis. Railway portion work sanctioned. Work pertaining to State Govt. is not yet
2012- PB- lieu of level crossing S.Fund,R 31/03/20 sanctioned.
46 2013 88 Bilaspur No.BK-66 DRM/BSP RSK 148794 0 1000 0 0 147794 21 0 0

Provision of Limited "Estimate No. 123/B/12.


Height Subway in lieu of DEN/N : C. A. No. 77/17-18 Contractor: Shrestha buildcon LOA issued on: 04.10.2017 LC
closing of manned LC No. closed in June'18. Stone pitching work completed. Pump house at BK-65 roof slab casted on
BK-68 at Km.888/13-15 28.06.2020 plastering work remaining TDC: 25.07.2020.
2012- LB- between AAL-BUH S.Fund,R 31/07/20 "
48 2013 205 Bilaspur section DRM/BSP RSK 23083 14589 10000 0 14589 35 20 95

Uchchabati - Road over S.Fund,R


2014- PB- bridge in lieu of level CAO(CON RSK,EB
51 2015 103 Bilaspur crossing No.293 )/SECR R(PPP) 175000 0 2000 0 173000 Joint survey has been done by the state PWD and open line. GAD is under preparation.
Katora-Surajpur- Re- Estimate No. 162/B/15. LOA-17/12/16, 66/B/17 (Madhusudan Agrawal)
Construction of Road over DEN/Spl : Scope of work- Rob of span- 1*18m and 7.5 m wide, approach road-200m. Phy.pro-
2015- PB- bridge in lieu of level S.Fund,R 30/06/20 31/12/20 Girder launching completed in Sept'19.Deck slab casted, 100m approach road completed,
52 2016 107 Bilaspur crossing No. 205 DRM/BSP RSK 33229 23868 4000 4697 28565 7098 20 19 82 earth work for balance work is done, concreting work is in progress.

Estimate No. 83/B/15 Sr.DEN/C :Private land acquisition involved. Notification in Gazette for
Tarbahar Bilaspur- special project has been declared. Nomination of Land Acquisition officer received from
subway in lieu of level Collector. File sent to HQ for Gazette notification of Land acquisition officer. Now land detailed
crossing No. 366B under sent to state govt. authority for verification for further action on 04.04.2020. Joint programme
2015- PB- bypass line & up lead line 31/03/20 with patwari is planed on 09.06.2020 as per the SDM /BSP
53 2016 114 Bilaspur to BCN Depot DRM/BSP RRSK 79444 0 1000 0 0 84125 21 0

Page 12 of 21 As on 17/07/2020
WorkWise

E. No. 111/B/16, 141/B/17 (R). DEN/Siding : 02 LCs: BOX casting in progress (335, 356). 1 LC:
BK-33 LHS proposal changed to LROB due to rocky strata. GAD for LROB approved. Revised
estimate with division finance. Finance has returned the estimate with observations.
Compliance is being done. LC No. BK-44,54,55,58,60 (05 LC) box casting done, launching is
Champa-Bilaspur- planned. June 2020: Launching of BK-44,54,55,58 & 60 completed. Launching of all LHS
Anuppur- Subways in lieu completed. BK 33- Revised estimate sent to Finance after compliance. Again returned by
2016- PB- of level crossings (25 S.Fund,R 31/03/20 Finance with observations, compliance is being done. LC Closed till date:-365, BK-19, BK-21,
54 2017 136 Bilaspur Nos.) DRM/BSP RSK 1015980 3E+05 250000 37358 342855 460483 21 45 BK-47,BK-29,BK-24
Estimate No. : 20/B/16.
Chhada-Singhpur- Light DEN/North : C.A. No. 70/18-19 Jhajharia Nirman Limited LOA issued on: 21.08.18. Tender
2016- PB- Road over bridge in lieu of S.Fund,R 31/01/20 awarded to JNL on 20.08.2018. Girder at site, launching scheme sent for CRS sanction on
55 2017 121 Bilaspur level crossing No.BK-70 DRM/BSP RSK 79052 2326 30000 1991 4317 55003 21 20 0 29/05/2020, RE wall casting started.

"Estimate No. 52/B/16. LOA-30/11/17, CA-73/B/17-18 (M/S Mhamaya Engineers)


Bilaspur Division:
Construction of approach Scope of work- AB14- 600 m road, drain 150 m, pitching work. Ab16- 50 m
road, Drain, Retaining retaining wall, 50 m road. Ab-62-100 m retaining wall and 200 m drain.
2016- LB- wall at LC No.AB-14, AB- S.Fund,R 30/11/20 31/03/20 AB- 67- 500 m hume pipe laying. Phy.Pro- AB14- Road work completed, drain
56 2017 80 Bilaspur 16, AB-67 & AB-62. DRM/BSP RSK 20742 9655 13904 1197 10852 100 20 19 60 work in progress, 50% pitching work done, TDC- 30/11/2020

Naila Yard - Closure of


2017- PB- level crossing No.345 by CAO(CON S.Fund,R Joint survey conducted by open line and State PWD. GAD is under Preparation. The work is
57 2018 137 Bilaspur road over & under bridge )/SECR RSK 334902 0 2000 0 332902 not sanctioned by state PWD.

DE No. 06/B/17. LOA-13/06/18, CA:22/B.18(Subham Infrastructure)


Name of the work shows 4 LCs. But, only 3 LCs are sanctioned under this work.
Anuppur-Ambikapur - launching of all three LHS done in April 2019.
Elimination of manned AB-8: Work completed and LC closed in July.
level crossings by full AB-05 : Work completed and LC closed in November.
height/limited height AB-43: Boxes launched, scope of work- 200m road and 200 m U truff, 600 m drain. WBM for
2017- PB- subways/road under 31/12/20 31/03/20 road work done, earth work for U truff done, Earthwork for drain work is in progress, concreting
58 2018 144 Bilaspur bridges (4 Nos) DRM/BSP RRSK 108700 51332 20000 951 52283 20544 20 20 80 of approach road started.

"Estimate No. 56/B/17.


Anuppur: Replacement of DEN/North : C.A. No. 91/18-19, Contractror:- Madhusudan Agrawal LOA issued on:
existing through FOB at 03.10.2018.Launching of girders (2 span) done in 1st week of Mar'20.Structural steel work
Anuppur station by completed in both span. Casting of lattice & staircase of one span completed & one span under
providing new FOB to progress. Work in progress. TDC: 10.09.2020
2017- LB- remove infringement. (To S.Fund,R 31/08/20 "
59 2018 231 Bilaspur avoid surface crossing) . DRM/BSP RSK 18987 15359 6632 3759 19118 100 20 80

Brajrajnagar - "Estimate No. 74/B/17. (SC)


Replacement of FOB Sr.DEN/East : Work awarded in Nov'19. Foundation work under progress.
infringing intermediate Fund allotted in 2020-21: 2.4 Cr
trestle in between track TDC: 28.02.2021
2017- LB- with through span FOB at S.Fund,R 28/02/20
60 2018 221 Bilaspur Brajrajnagar (colony side). DRM/BSP RSK 23582 0 22000 0 0 2073 21 15

Bilaspur Division - "Estimate No. 75/B/17.


Improvement to drainage
of existing LHS by Sr.DEN/East : Work awarded on 15.06.2018 to Tirupati Construction. Work at 4 out of 5 LCs
providing effective completed (286, 294, 295 & CG-7). Sump and connecting drain work at CG-1 in progress.
drainage system at LC
2017- LB- No. 286, 294, 295, CG-1 S.Fund,R 30/11/20 Fund required: 15 lakhs. TDC 30.11.2020"
63 2018 211 Bilaspur & CG-7. DRM/BSP RSK 14992 7853 7020 0 7853 119 20 85 0

Improvement to drainage "Estimate No. 86/B/17. C.A. 23/D-B/19-20


of existing LHS by Sr.DEN/C: Tender opened on 12.09.2018 & awarded on 14.12.2018. Contract terminated, due
providing effective to non submission of PG. Tender refloated and opened on 03.03.2019 & awarded on
drainage system at LC 06.06.2019. Work is in progress in LC No.332 (completed), BK-39 (50%) work of sump and
BK-11,BK -39,332 &346 pump house completed and drain of length 100 mtrs is under progress , BK-11 (30%) work of
2017- LB- between Champa- S.Fund,R 31/07/20 sump completed pump house and drain of length 300 mtrs is under progress, . LC No. 346
64 2018 213 Bilaspur Bilaspur-Anuppur. DRM/BSP RSK 11811 6738 7 0 6738 100 20 80 (40%) , work of sump a

Page 13 of 21 As on 17/07/2020
WorkWise

"Estimate No. 87/B/17. C.A No 33/D-B/19-20 (Escab Technoxpart)

Champa-Naila - Sr.DEN/Central : work awarded on 11.04.2019. RCC Box size of 4 mtrs X 2.5 mtrs barrel
Construction of LHS for length 32.77 mtrs. Thrust bed design approved by HQ in Nov-19' . Thrust bed under
closing of manned LC construction. Due to frequent rain work interrupted due to low laying area. and not yet started
2017- LB- No.343 at between S.Fund,R 31/03/20 due to covid-19."
65 2018 215 Bilaspur Champa-Naila. DRM/BSP RSK 23660 0 23934 0 0 475 21 0 0

Jairamnagar -
Replacement of FOB
infringing intermediate "Estimate No. 129/B/17.
trestle in between track Sr.DEN/Central : Tender awarded on 19.09.2018 to Suresh Kumar Agrawal. Launching done
2017- LB- with through span FOB at S.Fund,R 31/10/20 on 18.05.2020. scope 3 span of size 24.05,24.1 & 29 mtrs width 3mtrs.
66 2018 233 Bilaspur Jairamnagar station. DRM/BSP RSK 22099 9775 12000 0 9775 293 20 48 0

Bilaspur Division -
Provision for dismantling
of old ROB 95 and 205
2019- LB- under the jurisdiction of 30/06/20 Estimate No. 97/B/19. Detailed estimate sanctioned on 13.04.2020.
67 2020 85 Bilaspur Sr.DEN/Spl(W)/Bilaspur. DRM/BSP RRSK 2648 0 2648 0 0 0 21 0

GAD approved by State Govt & Railway. Combined revised estimate submitted to Railway
Board for sanction on 27.02.2015.Revised estimate sanctioned vide Railway Boards letter No.
2015/CE-IV/Estt./6(ROB) dt 19.9.2016. Tender for civil work awarded and work started. Out of
Tumsar - Road over 29 piles, casting of 27 piles completed. Out of 33 precast box segments, casting of 33 nos box
2006- PB- Nagpur(S bridge in lieu of level CAO(CON S.Fund,R 31/12/20 31/03/20 segments completed. 3 pier out of 4 completed & 4th completed up to bed block & works in
77 2007 73 ECR) crossing No 532 )/SECR RSK 69111 71600 41000 71600 68800 17 20 70 30 progress.Super structure balance to complete.

NIR-CWA: Construction
of LHS at U/M LCs No.
NC-57 at Km 1210/1-2
and at U/M LC No. NC-79
2010- LB- Nagpur(S at Km 1235/5-6 between CAO(CON S.Fund,R 30/11/20 31/03/20 (1) NC-57 Cast in situ. Bottom raft casting RCC box completed & sidewall in progress.
94 2011 125 ECR) NIR-CWA section. )/SECR RSK 8116 24900 1300 24900 0 16 20 95 (2) NC-79 Cast in situ. Work of LHS completed jun'2018.

NIR-JBP: Construction of
LHS at Manned LC
No.GJ-110 at Km 1154/7-
8 and U/M LC No.GJ-130
2010- LB- Nagpur(S at Km 1188/11-12 CAO(CON S.Fund,R 31/03/20 31/03/20
99 2011 123 ECR) between NIR-JBP section. )/SECR RSK 11192 4717 2000 4717 4204 16 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

NIR-JBP: Construction of
LHS at U/M LCs No.GJ-
128 at Km 1185/6-7 and
at U/M LC No.GJ-129 at
2010- LB- Nagpur(S Km 1186/13-14 between CAO(CON S.Fund,R 31/03/20 30/04/20
100 2011 121 ECR) NIR-JBP section. )/SECR RSK 11978 15085 0 15085 11136 16 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Casting of pre-cast box segment completed at 27 locations GJ-38, 39, 40, 41, 42, 46, 47, 49,
50, 51, 52, 53, 54, 56, 58, 59, 61, 70, 73, 74, 76, 77, 80, 81, 82, 87, 89 = 27 Nos).
"i) Work completed at 17 nos. of LCs (LC-no. GJ-38, 39, 40, 41, 42, 46, 47, 52, 59, 61,70, ,73,
Balaghat-Nainpur - 74,76, 77, 87 & 89 )
Limited height subways ii) Launching, construction of return wall and road approaches work is in progress at 5 nos of
by open cut method at LC (LC-no. GJ-50, 51, 53, 56, 58).
2011- PB- Nagpur(S unmanned level crossings CAO(CON S.Fund,R 31/03/20 iii) GJ-49 & 81 is to be manned.
102 2012 84 ECR) (27 Nos) )/SECR RSK 301876 3E+05 500 341400 -14750 20 80 iv) GJ-54, 80 & 82 diverted.

Page 14 of 21 As on 17/07/2020
WorkWise

Nainpur-Chhindwara - i) Total LHS at 20 LCs at NC-1, 3,4,6,11, 15, 16, 17, 18,20, 22, 23, 24, 26, 27, 29, 32 , 33, 34 &
Limited height subways 36 (LROB) .
by open cut method at ii) Box segment casted and Launched at 3 LCs (NC-3,6 & 11) & approach is in progress.
2011- PB- Nagpur(S unmanned level crossings CAO(CON S.Fund,R 31/12/20 30/06/20 iii) LHS completed 17 LHS (NC-1,4, 15, 16, 17, 18, 20, 22, 23, 24, 26, 27, 29, 32 , 33, 34 & 36
104 2012 82 ECR) (20 Nos) )/SECR RSK 223612 2E+05 500 249352 -6522 16 20 92 (LROB) completed.

Nainpur-Jabalpur -
Limited height subways
by open cut method at
2011- PB- Nagpur(S unmanned level crossings CAO(CON S.Fund,R 31/03/20
105 2012 85 ECR) (13 Nos) )/SECR RSK 145347 61082 1000 61082 74922 16 20 0 Work completed. LHS commissioned. Final bill passed. SD released.

Nainpur-Mandla Fort - 15 LHS at locations (NM-2, 7, 9, 11, 14, 24, 25, 27, 30, 31, 33, 35, 38, 39 & 40) .
Limited height subways i) LHS completed at 12 LC (LC no. 2, 7, 9, 11, 14 ,24,25 27, 30, 31, 33 & 39 )
by open cut method at ii) Launching completed & return wall and approaches is in progress at 2 nos of LC (LC-no.
2011- PB- Nagpur(S unmanned level crossings CAO(CON S.Fund,R 31/10/20 30/06/20 NM- 35 & 38 ).
106 2012 86 ECR) (15 Nos) )/SECR RSK 167709 2E+05 15000 182800 -15095 17 20 85 iii) LROB is under progress at LC No. NM-40.

Construction of LHSW at
unmanned LCs No. GJ-92
, GJ-96 and GJ-97
between NIR - PDE
2011- LB- Nagpur(S section under the CAO(CON S.Fund,R 31/03/20
107 2012 152 ECR) jurisdiction of ADEN/NIR. )/SECR RSK 22575 1964 0 1964 25739 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Construction of Limited
Height Subway of size
6.80m X 5.0m at
unmanned LC No. GJ-
121 at km 1175/1-2 in
2011- LB- Nagpur(S between Gondia - CAO(CON S.Fund,R 31/03/20
118 2012 171 ECR) Jabalpur section (NG) . )/SECR RSK 13729 1123 0 1123 16137 15 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Proposed construction of
full height subway of size
6.8mX5.0m at manned
LC No. GJ-99 at ch 12060
2012- LB- Nagpur(S (TP 1131/0-1) in between CAO(CON S.Fund,R 31/03/20
120 2013 179 ECR) NIR -JBP section (NG). )/SECR RSK 21159 3921 1834 3921 21831 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Proposed construction of
full height subway of size
6.8mX5.5m at manned
LC No. GJ-113 at ch 5525
2012- LB- Nagpur(S (TP 1159/1-2) in between CAO(CON S.Fund,R 31/03/20
121 2013 207 ECR) NIR -JBP section (NG). )/SECR RSK 24484 126 0 126 28140 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Proposed construction of
full height subway of size
6.8mX5.0m at U/M LC
No. GJ-116at ch 157 (TP
2012- LB- Nagpur(S 1162/11-12) in between CAO(CON S.Fund,R 31/03/20
122 2013 181 ECR) NIR -JBP section (NG). )/SECR RSK 24271 126 0 126 27792 15 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Provision of LH Subway
for elimination of U/M LC
No.GJ-150 at Km.1220/7-
2012- LB- Nagpur(S 8 in KEQ-GRG section CAO(CON S.Fund,R 31/12/20 29/02/20
127 2013 197 ECR) under DEN(N)/NGP. )/SECR RSK 20328 126 0 126 24115 14 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Page 15 of 21 As on 17/07/2020
WorkWise

Provision of L H Subway
for elimination of manned
LC in BG at ch222786m
in KEQ - GRG section
2012- LB- Nagpur(S under jurisdiction CAO(CON S.Fund,R 31/12/20 29/02/20
128 2013 199 ECR) DEN(N)Nagpur. )/SECR RSK 22032 126 0 126 27754 14 16 Work completed. LHS commissioned. Final bill passed. SD released.

Proposed construction of
limited ht subway of size
4.15mX3.75m at manned
LC No. GJ-109 at ch 247
2012- LB- Nagpur(S (TP 1153/8-9) in between CAO(CON S.Fund,R 31/03/20
129 2013 183 ECR) NIR -JBP section (NG). )/SECR RSK 18788 126 0 126 26945 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Proposed limited span &


width ROB of size
9.1mX7.0m at location of
proposed M/LC at ch6584
2012- LB- Nagpur(S between PDE-GNS sec of CAO(CON S.Fund,R 31/03/20
130 2013 185 ECR) G-JBP GC project. )/SECR RSK 23552 126 0 126 29751 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Construction of L H
Subway at M/ LC No.NC-
85 at Km.1242/3-4
between NIR-CWA line
(NG) under the
2012- LB- Nagpur(S jurisdiction of CAO(CON S.Fund,R
131 2013 187 ECR) ADEN/CWA. )/SECR RSK 17044 0 0 0 17043 0 Closed. ROB by NHAI commissioned. Work to be dropped from IRPSM.

Proposed construction of
FHSW of size 6.8mX5.0m
at M/LC No. GJ-95 at ch
5519 (TP 1124/5-6) in
2012- LB- Nagpur(S between NIR -JBP section CAO(CON S.Fund,R 31/03/20
132 2013 177 ECR) (NG). )/SECR RSK 22768 607 0 607 27995 16 0 0 Work completed. LHS commissioned. Final bill passed. SD released.

Construction of Limted
Height Subway of size
4.15m x 4.05m at
unmanned LC no. NC-55
at Km.1205/11 between
2013- LB- Nagpur(S NIR-CWA line by GC CAO(CON S.Fund,R 31/10/20 30/06/20
134 2014 74 ECR) project. )/SECR RSK 14485 18400 21 18400 61 16 20 50 Cast in situ. Work is in progress

Subways in lieu of level


crossings Nos
63,52,23,64 & 68 on i) NM-23 Completed.
2015- PB- Nagpur(S Nainpur subdivision (5 CAO(CON S.Fund,R 30/06/20 ii) GJ-64 & GJ-68 completed.
138 2016 112 ECR) Nos) )/SECR RSK 95578 78000 35000 78000 -17423 20 62 iii) NC-63 & 52 works in progress.

Gondia-Chandafort- Light
2015- PB- Nagpur(S Road over bridge in lieu of S.Fund,R 31/08/20 Approach RE wall work completed. Crash barrier and road work is in progress.
139 2016 106 ECR) level crossing No. 134 DRM/NAG RSK 68338 42711 20000 8431 51142 5627 20 80 72
LAO issued on 26.02.2018, but Contract terminated due to slow progress. Re tendering for
Gondia-Chandafort- Light balance work done, opened on 25.4.19, but discharged due to technical ground. Fresh tender
2015- PB- Nagpur(S Road over bridge in lieu of S.Fund,R 31/03/20 invited and awarded in Dec-19. Pile Foundations completed, Substructure work is in
140 2016 109 ECR) level crossing No. 88 DRM/NAG RSK 64435 6712 43920 200 6912 13803 21 42 progress .

Gondia-Chandafort- Light Structural drawing approved in Jun-19. Pre-casting of RE wall panels in progress. Piling work
2015- PB- Nagpur(S Road over bridge in lieu of S.Fund,R 31/03/20 completed. Work of pile caps and Abutments in progress.
141 2016 105 ECR) level crossing No. 20 DRM/NAG RSK 67432 5834 46849 0 5834 14749 21 35 15
Tumsar-Tirodi- Light Road
2015- PB- Nagpur(S over bridge in lieu of level 31/10/20 Foundation and abutment completed. Also, Girder launching done. RE wall work in progress.
142 2016 110 ECR) crossing No. 2 DRM/NAG RRSK 46527 32805 7025 0 32805 6697 20 70 75

Page 16 of 21 As on 17/07/2020
WorkWise

Nagpur-Durg- subways in "LC No. 565 - Tender awarded in Dec-19. S&T cable shifting in progress.
2015- PB- Nagpur(S lieu of level crossing No. S.Fund,R 31/03/20 LC No. 566 - Box pushing and road work completed. LC closed. Protection works are in
143 2016 118 ECR) 565 & 566 (2 Nos) DRM/NAG RSK 81300 11319 60206 3119 14438 9775 21 55 60 progress.
Nagpur-Durg- subways
manned in lieu of level "LC No. 526 - LHS commissioned and LC closed.
2015- PB- Nagpur(S crossing No. 526 & 530 (2 S.Fund,R 31/12/20 LC No. 530 - Thrust bed casted. Box casting was in progress. But work stopped due to
144 2016 111 ECR) Nos) DRM/NAG RSK 77300 32888 6600 6289 39177 37812 20 50 0 lockdown (covid-19) for one and half month. Work started 2 boxes out of 3 under progress.

Nagpur Division :-
Rebuilding of RUB No.33
DN (1 x 12.2 M) at
Km.1113/18-20 in
between Kanhan &
2015- LB- Nagpur(S Kamptee stations on S.Fund,R 31/03/20 Casting of pre-cast RCC boxes completed. But box insertion can be done only after diversion
145 2016 82 ECR) Durg-Nagpur Gr.'A' route DRM/NAG RSK 14539 14464 2786 0 14464 0 21 60 0 of National highway through new bridge over Kanhan river which is expected by Dec-20.

"LC No. 569 - LC closed, approach road work on south side is in progress, Drain work in
progress. LC No. 568 -Construction of
ROB along with two subways will be executed by State Govt . GAD of ROB approved. Also, all
Kalumna-Nagpur- work will be funded & executed by State Government.
2016- PB- Nagpur(S Subways in lieu of level S.Fund,R 31/12/20 Structural drawing awaited from PWD.
146 2017 128 ECR) crossing No. 568 & 569 DRM/NAG RSK 76236 12125 46860 1519 13644 17251 20 80 80

One side approach road work can be constructed only after diversion of road traffic of NH-7 to
the new bridge under construction by PWD(NH division), which is expected in Dec-20.
Further, Land acquisition involved in other approach. Land owner is not agreeing to sell his
land. Collector is being pursued to help.

Kamptee-Kanhan-
Subway in lieu of level "
2016- PB- Nagpur(S crossing No. 560 & 561 S.Fund,R 31/03/20
147 2017 131 ECR) (01 No.) DRM/NAG RSK 63373 9252 1000 0 9252 53121 21 50 0

LC No. 531 - Collector has not given


consent for closure of LC by construction of LHS, but agrees to give consent after construction
of ROB. Hence, work to be processed for dropping.
Tumsar Road-Gondia- LC No. 525 - Excavation work for thurst bed completed. Casting of thurst bed and RCC Box
2016- PB- Nagpur(S Subways in lieu of level S.Fund,R 31/12/20 was in progress. But work stopped due to lockdown (covid-19) for one and half month. Work
150 2017 120 ECR) crossing No. 531 & 525 DRM/NAG RSK 70065 3651 13000 801 4452 53414 20 5 0 restarted. One box out of 3 under progress.
Balaghat Yard - Road
over bridge at level
2017- PB- Nagpur(S crossing No.GJ-36 at CAO(CON
151 2018 140 ECR) Gondia end )/SECR RRSK 231866 0 1000 0 230866 GAD to be prepared by state Govt.
Tharsa-Chacher - Road
2017- PB- Nagpur(S over bridge at level CAO(CON S.Fund,R As per the MOU with state Govt., this ROB shall be executed by State Govt on single entity
152 2018 139 ECR) crossing No.554 )/SECR RSK 199500 0 2000 0 197500 0 0 basis. Estimate under preparation.
Dongargarh-Paniajob -
Limited height subway in
2017- PB- Nagpur(S lieu of level crossing S.Fund,R 31/12/20 Box pushing (twin box) completed. Also one side approach ready. Land acquisition involved for
153 2018 143 ECR) No.474 DRM/NAG RSK 109800 75220 25000 905 76125 35522 20 70 52 down side approach.

Gondia - Replacement of
FOBs having intermediate
2 legged trestles in 02 nos FOB girder have been launched. Landing work is in progress. But stopped due to
2017- LB- Nagpur(S between running lines at S.Fund,R 31/08/20 lockdown. Now work restarted.
155 2018 241 ECR) Gondia. DRM/NAG RSK 24882 4860 14000 2276 7136 6022 20 80

Gondia - Chandafort -
Provision of Drain &
protection works at LHS Work awarded on 08.08.2018. Work completed at four LC's(GCF-11, 53, 57 & 116). Work at
2017- LB- Nagpur(S (9 Nos) in Gondia- S.Fund,R 31/12/20 LC no. GCF-35 is in progress. But in slow progress due to unavailability of material and labour
156 2018 89 ECR) Chandafort section. DRM/NAG RSK 24954 16854 2893 0 16854 5207 20 60 0 due to lockdown (Covid-19)

Page 17 of 21 As on 17/07/2020
WorkWise

Tumsar Road -
Replacement of FOB
having intermediate 2
legged trestles in between
running lines at Tumsar Work of FOB foundation completed. Girder fabrication in progress. But work at site hampered
2017- LB- Nagpur(S Road station in Durg- S.Fund,R 31/10/20 due to lockdown(Covid-19)
158 2018 219 ECR) Nagpur section. DRM/NAG RSK 24396 6478 18000 185 6663 1736 20 50 S&T : Cable already Cleared.

Salwa-Kanhan - Road
over bridge at level S.Fund,R
2018- PB- Nagpur(S crossing no.559 CAO(CON RSK,EB As per the MOU with state Govt., this ROB shall be executed by State Govt on single entity
160 2019 147 ECR) (PB#157/2018-19/SECR) )/SECR R(PPP) 323064 0 2000 0 164532 basis. Estimate under preparation.

Durg-Nagpur - Road over


bridge at level crossing S.Fund,R
2018- PB- Nagpur(S no.548 (PB#157/2018- CAO(CON RSK,EB As per the MOU with state Govt., this ROB shall be executed by State Govt on single entity
161 2019 146 ECR) 19/SECR) )/SECR R(PPP) 535860 0 2000 0 270930 basis. Estimate under preparation.

Gondia-Amgaon -
Subway in lieu of manned Casting of thrust bed completed. Road work , Drainage work and Pre-casting of Boxes in
2018- PB- Nagpur(S level crossing No.497 S.Fund,R 31/12/20 progress.
162 2019 163 ECR) (PB#157/2018-19/SECR) DRM/NAG RSK 91492 5529 6000 13921 19450 44217 20 30 40

Durg-Dallirajhara - Road Work in Progress on Single entity by State. The launching of girders on railway span is
2012- PB- over & under bridge at CAO(CON S.Fund,R completed. CRs application has been sent to CRS on 29.01.2018 ROB commissioned on
181 2013 87 Raipur level crossing No.DD-10 )/SECR RSK 168154 15474 1 15474 152679 06.10.18 and RUB construction not started till date.

Sr.DEE(G)/R : LOA Issued on Date 05.01.2018 .,30% schedule item supplied, awaiting Engg.
site Clearance.
Sr.DEN-Line : Work transferred from Construction organization to open line on 05.08.2015.
Signed MOU received on 31.05.2017. Letter written to state PWD for submitting the state share
Raipur Naka - Limited on Dt. 16.06.2017 but state share yet not received. Last reminder written on 29.08.2019.LOA
2012- PB- height subway in lieu of S.Fund,R 31/12/20 31/03/20 issued on 03.04.18.4 boxes- All box casted. 45mtr road raft casting completed. 20mtr first lift
182 2013 90 Raipur level crossing No.444 DRM/R RSK 37055 23687 2600 377 24064 21210 16 21 45 0 retaining wall both si
Bilaspur-Durg- Road over The GAD has been signed by DRM/Raipur and sent to CBE for approval on 01.12.2017 and
bridge & Road under returned with observations. The same has been forwarded to State PWD for compliance and
2015- PB- bridge in lieu of level CAO(CON S.Fund,R resubmitted on 19.12.2017. The compliance is still awaited from state PWD. The State govt.
183 2016 108 Raipur crossing No. 391 )/SECR RSK 213061 0 50001 0 163060 has sanctioned the work . Estimate under sanction.

Sr.DEE(G)/R : LOA Issued on date 03.06.2019.work to be started awaiting Engg.site clearence


Sr.DEN-Line : Work transferred from Construction organization to open line on 05.08.2015.
Bhatapara-Nipania- Road GAD approved on 27.02.18 Signed MOU recieved on 14.11.17 State share recieved on
under bridge in lieu of 28.12.17 LOA issued on 30.11.18. Work stopped before monsoon due to unsafe condition for
2015- PB- manned level crossing S.Fund,R 31/01/20 adjacent ROB foundation. DN line side 105 mtr retaining wall completed and approach road
184 2016 104 Raipur No. 383 DRM/R RSK 32893 11950 7552 0 11950 13391 21 25 0 105 mtr completed. Thrust bed casting completed. DN line s
Raipur-Durg- Road under
bridge in lieu of level
2015- PB- crossing No. 438 near D- S.Fund,R 31/03/20 Sr.DEN-Line : LOA issued on 11.03.2020. Work to be started.
185 2016 113 Raipur Cabin DRM/R RSK 96213 183 2000 0 183 94030 21 0 0 Sr.DEE(G)/R : tender to be floated

Sr.DEE(G)/R : LOA Issued on Date 05.04.2018 cable shifted work done, contractor not turn up
Bhilai-Bhilai Nagar- Road Sr.DEN-Line : State Govt sanctioned received on 29.03.2016. Signed MOU received on
under bridge in lieu of 31.05.2017.DE sanctioned on 16.06.2017.State share received on 16.11.2017.LOA issued on
manned level crossing 16.02.2018.Work delayed due to infringement of pipe line and Electrical & S&T cable.Box
2015- PB- No. 441 (Bhilai Power S.Fund,R 31/07/20 pushing completed.BSP side & Z road both side approach road completed. Retaining wall
186 2016 116 Raipur House) DRM/R RSK 36921 17396 3900 179 17575 15625 20 80 0 completed. Both side steel structure erected. Z road side wear

Page 18 of 21 As on 17/07/2020
WorkWise

Bilaspur-Raipur- Road Sr.DEE(G)/R : Awaiting engg.site clearence, Issued to M/s Sagar Sharma on 13.04.2017.
under bridge in lieu of Sr.DEN-Line : GAD approved on 01.09.2017. Initially on Railway cost. With increase in TVU,
2015- PB- manned level crossing S.Fund,R 28/02/20 cost sharing demanded from state govt. Consent for cost sharing not received yet. PWD
187 2016 117 Raipur No. 385 DRM/R RSK 52202 7159 31004 0 7159 14039 22 0 informed that it will be included in next year budget.
Urkura-Sarona- Road
over bridge in lieu of level
2016- PB- crossing No.425 with CAO(CON S.Fund,R
188 2017 127 Raipur subway )/SECR RSK 224283 0 60000 0 164283 0 0 Work executed by State Govt,Work yet to start.

Sr.DEN-Line : State cost sharing consent received on 07.05.2018. GAD revised from single to
twin box. Approved on 17.07.19. DE sanctioned on 11.10.2019. Vetted detailed estimate and
MOU sent to state PWD on 04.10.2019. 1st Reminder letter sent to State PWD on
Bilaspur-Durg- Subway in 16.12.2019.2nd reminder letter sent to State PWD on 14.01.2020.3rd reminder letter sent to
2016- PB- lieu of level crossing No. S.Fund,R 31/03/20 State PWD on 13.02.2020.4th reminder letter sent to PWD on 18.03.2020.5th reminder letter
190 2017 130 Raipur 417 (Khamtrai) DRM/R RSK 53146 0 2000 0 0 51146 21 0 0 sent to PWD on 25.04.2020. 6th reminder letter sent to PWD

Sr.DEE(G)/R : Awaiting engg.site clearence, LOA Issued to M/s Sagar Sharma on 13.04.2017.
Bilaspur-Raipur- Road Sr.DEN-Line : LC physically closed. Site infringement (pipe line, pole tree) cleared on March
under bridge in lieu of 2019. Collector consent for diverting traffic received on 27.08.18. Box pushing completed.
2016- PB- level crossing No. 384 in S.Fund,R 31/07/20 Approach road completed. Sheeting work and sump well work in progress. DN line side stair
191 2017 134 Raipur Bhatapara Yard DRM/R RSK 54051 45630 625 5970 51600 10345 20 75 0 work is in progress. UP line side stair work is in progress.

DEN/Line- 1. Being done by state government(single entry) 2. Revised Estimate from 11 Cr. to
Raipur-Mandirhasaud - 34 Cr.due to change of box size from 2x6.0 m x5.0 m to 2 x 8.5 m x 5.5 m and increase barrel
Road under bridge in lieu length from 25 Mtr to 36.16 Mtr. 3. DE under sanction at Railway Board since May 2019. Last
2016- PB- of level crossing No. RV-1 31/12/20 compliance of Railway Board observation sent on 06.03.2019.
194 2017 132 Raipur at Waltair Gate DRM/R RRSK 58557 0 20600 0 0 37957 20 10 SDSTE/R : DE submitted. Sr.DEE(G)/R : awaiting of sanctioned estimat

Durg-Dallirajhara -
Closure of manned level GAD has been approved. The work has been allotted to state PWD for execution as single
crossing No.DD-4 by road entity basis. The detailed estimate has been sanctioned on 17.09.18. MOU has been signed by
2017- PB- over bridge with limited CAO(CON State Govt. and CE/C/II/BSP TDC for ROB/RUB both is 31.12.2019. ROB work in progress and
195 2018 138 Raipur height subway )/SECR RRSK 181400 0 30000 0 151400 RUB work not started.

Bilaspur - Durg - Provision


of shed over approaches Sr.DEE(G)/R : LOA issued on 12.11.2018 and work to be started after engg. site clearance
of LHS of LC No.388 & Sr.DEN-Line : Civil-LOA issued on 27.07.18. LC 388- Work completed. LC 420- 86 no. RCC
2017- LB- LC No.420 in Bilaspur - S.Fund,R 31/08/20 column completed. 86 no. steel column erection completed. 43 no. truss created. Balance work
198 2018 217 Raipur Durg section. DRM/R RSK 14983 9654 4889 2838 12492 100 20 70 0 in progress.

Page 19 of 21 As on 17/07/2020
WorkWise

PH- 30 Works status as on 07.07.2020

upto March '20


Short Name of

ALLOCATION

of Rly portion
Original Cost
(PB,LB,DRM)

Revised TDC
during 2020-
Expenditure

Expenditure

Expenditure
Modified for

progress of

progress of
Anticipated
Agency Rly

Balance till

TDC of Rly

REMARKS
%age Phy.

%age Phy.
Executing

2020-2021

upto date
Sanction

Division
PB Item

Agency
portion
Year of

Outlay
Work

2021

Date

Rly
SN

1 5 6 10 12 13 17 18 22 24 23 26 27 29 31 38 39 41

Bilaspur-Gatora - Road S.Fund,R


2009- PB- over bridge in lieu of level CAO(CON RSK,EB 31/12/20 15/10/20 Work completed. After some rectification work, ROB opened for plying the road traffic over this
37 2010 77 Bilaspur crossing No.364 )/SECR R(PPP) 75736 78635 500 78635 15357 14 19 100 100 on dtd:15.10.2019.

BSP Div: Construction of


RUB (Limited Height Estimate No. 74/B/10. CA No. 78/11-12 (Brijesh Agrawal)
Subway) for LC No. 286 Sr.DEN/E : Work completed in Jan'15. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 31/03/20 associate accounts mentioned constraints regarding deletion of work. Deletion procedure under
38 2011 107 Bilaspur under SE/Works/RIG. DRM/BSP RSK 18560 17625 500 0 17625 574 15 100 finalisation with associate accounts.

BSP Div: Provision of Estimate No. 76/B/10. CA No. 78/11-12 CA No. 78/11-12 (Brijesh Agrawal)
RUB (Limited Height
Subway) for LC No. 294 Sr.DEN/E : Work completed in Mar'15. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 30/04/20 associate accounts mentioned contraints regarding deletion of work. Deletion procedure under
39 2011 111 Bilaspur under Sr DEN/East/BSP. DRM/BSP RSK 13466 5095 4000 0 5095 4496 15 100 finalisation with associate accounts.

"Estimate No. 75/B/10.


BSP Div: Provision of CA No. 78/11-12 (Brijesh Agrawal)
RUB (Limited Height
Subway) for LC No. 295 Sr.DEN/E : Work completed in Dec'14. Processed for deletion on arbitration grounds, however
2010- LB- by Box pushing method S.Fund,R 31/03/20 associate accounts mentioned contraints regarding deletion of work. Deletion procedure under
40 2011 109 Bilaspur under Sr DEN/East/BSP. DRM/BSP RSK 16777 2348 5245 0 2348 9430 15 100 finalisation with associate accounts.

DTL-NGE: Re-building of
ROB - 95 on NH-78 at
Km. 955/9-10 bet. DTL-
NGE section on divertion Estimate No. 70/B/10. & Revised Estimate No.98/B/12. CA : 24/13-14 (JNPL).
2010- LB- by the side of existing S.Fund,R 30/06/20 31/05/20 Work has been completed 15 Jun'18, technical check of final bill completed on 05/06/2020, final
41 2011 105 Bilaspur ROB. DRM/BSP RSK 17515 24737 0 0 24737 0 18 18 100 80 variation to be processed for approval/ sanction.

Provision of LHS Road at Estimate No. 251/B/11. CA : 92/12-13 (JNPL).


Km.976/15-16 for closing DEN/Spl: Work completed Feb'15, final variation sanctioned on 30.04.2020. Final bill & PVC
of LC No.AB-46 at passed, reimbursement of GST bill pending.
2011- LB- Km.976/14-16 between S.Fund,R 31/12/20 TDC for deletion-30/06/2020.
42 2012 72 Bilaspur BRH-KTO. DRM/BSP RSK 19455 16993 100 2467 19460 2367 15 100

Provision of LHS Road at


Km.994/9-10 for closing
of LC No.AB-59 at
Km.994/4-5 & LC No.AB- "Estimate No. 255/B/11. CA : 92/12-13 (JNPL).
2011- LB- 60 at Km.995/3-5 S.Fund,R 31/12/20
43 2012 87 Bilaspur between KTO-SJQ. DRM/BSP RSK 22922 15892 500 0 15892 6774 15 100 Work completed Feb'15, final variation sanctioned on 30.04.2020, Work deleted..

"Estimate No. 247/B/11. CA : 78/13-14


Construction of
Low/Limited height Sr.DEN/C : Physically work completed Feb'16. Due to fail ease of contractor in completing the
subway at Km.822/02-03 work, the contract has been terminated and SD, PG & EMD has been for fitted, party has
in lieu of closing of appeal in the Hon'ble High Court C.G. again the termination of contract demanding
unmanned level crossing appointment of arbitrator. The decision of Hon'ble High Court C.G. is not yet received. Hence,
2011- LB- No.BK-39 at Km.822/14- S.Fund,R 30/06/20 statuesque is to be maintained."
44 2012 173 Bilaspur 15 bet BSP-APR. DRM/BSP RSK 23458 21178 100 0 21178 2956 16 100

Page 20 of 21 As on 17/07/2020
WorkWise

Estimate No. CE/Con/BSP/Subway/ Chuchiyapara/23/12-13, R.E.No. 111/B/15 & 104/B/17


Bilaspur Yard - Limited
height subway on multi DEN/Siding : Contract awarded on 04.01.2018. Launching done. Work of approach road and
line section in lieu of cover shed completed. Sump and pump house work completed. All works completed. LHS
2012- PB- Chuchiyapara level S.Fund,R 31/05/20 started on 15/5/2020. LHS will be handed over to open line on 20/7/2020. Final bill under
45 2013 89 Bilaspur crossing gate No.365 DRM/BSP RSK 46099 38727 1000 1000 39727 3305 20 100 preparation.

Provision of LHS for


elimination of unamnned "Estimate No. 101/B/12. CA : 87/12-13 (JNPL)
level crossing at DEN/Spl : Work completed Sep'15,LC closed. Final variation concurred & sanction by
2012- LB- Km.995/3-4 between S.Fund,R 31/12/20 competent authority. Bill pending due to test check issue."
47 2013 175 Bilaspur KTO-SJQ section. DRM/BSP RSK 31990 15943 8139 0 15943 0 15 100

"Estimate No. 114/B/12. CA : 35/13-14 (B.A.).

Sr.DEN/SPL : Work completed except drain and retaining wall. contract terminated due to very
Provision of LHS for slow progress balance work will be done through separate agencies. Final bill not pass due
closure of Manned Level contract in dispute. arbitration finalized railway challenged arbitration award in district court.
Crossing No AB - 16 at Policy from Hq is required to deal such case.
2012- LB- km 913/28-30 between S.Fund,R 31/01/20 "
49 2013 209 Bilaspur BATL-BJRI section. DRM/BSP RSK 24403 14066 100 0 14066 10391 17 100 1

"Estimate no 44/B/13. CA : 44/14-15 (J.Ramesh).

Provision of LHS at Work completed ,LC closed in Jan'16.


Unmanned Level
Crossing No AB - 25 F/B final bill passed on & PVC bill not received from contractor, letter served to contractor on
2013- LB- between UKR-BRND S.Fund,R 31/01/20 26/05/2020, policy is required from HQ to deal such cases. "
50 2014 84 Bilaspur section. DRM/BSP RSK 14921 10945 100 0 10945 4314 16 100 0

Nowrozabad : "Estimate No. 57/B/17.


Replacement of FOB DEN/North : C.A. No. 55/18-19, Contractor-Madhusudan Agrawal LOA issued on:
infringing intermediate 13.08.2018.Physically work completed. Nov'19. Final bill passed on 29.04.2020. TDC for work
trestle in between track closure: 29.07.2020
2017- LB- with through span FOB at S.Fund,R 31/12/20
61 2018 227 Bilaspur Nowrozabad. DRM/BSP RSK 19000 21338 620 175 21513 100 19 100 0

Karkeli : Replacement of
FOB infringing "Estimate No. 58/B/17.
intermediate trestle in DEN/North : C.A. No. 55/18-19, Contractor-Madhusudan Agrawal LOA issued on 13.08.2018.
between track with Physically work completed Sep'19. Final bill passed on 29.04.2020. TDC for work closure:
2017- LB- through span FOB at S.Fund,R 31/10/20 29.07.2020"
62 2018 229 Bilaspur Karkeli. DRM/BSP RSK 17000 14974 983 175 15149 100 19 100

Page 21 of 21 As on 17/07/2020