Ref.No.

TPF/D&C/PR-I/2019-20/26 Date- 28/11/2019


To,
M/S. Deshmukh And Company,
Surli Road,
At Post- Tembhurni,
Tal –Madha,
Solapur– 413211, Maharashtra (India)
Sub: - NHAI-PIU-NSK- Six Lanning of Pimpalgaon-Nashik-GondeSection of NH-03 from Km 380/00
to 440/00 in the state of Maharashtra – Authority Engineer/Supervision Consultant Services for PR
Works & O & M Works on Pimpalgaon-Nashik-Gonde Project on NH-3 – Regarding Balance work
completion of PR-I.
Dear Sir,
With reference to above mentioned subject we would like to bring to your attention that the
contract period of PR-I from Chainage 421+000 to 440+000 has ended on 25-08-2019. The EOT of
119 Days has been recommended by NHAI, PIU for further approval to competent authority.
However EOT of 119 days, as recommended by PIU, NHAI, Nashik is ending on 22.12.2019.
In view of the above & looking towards the time constraint you are hereby instructed to expedite
the balance work within your scope & BOQ items (enclosed below) at earliest within the schedule
time period.

Sr.N Component Item Description


o
1. Stone Pitching
Road 2. Dismantling Structural Pavement
1
Maintenance. a) Plain Concrete
1.33). Milling Of Distressed Bituminous Surface
Painting Higloss Synthetic enamel paint- on existing surface
2 Road Property
Painting All type MS /GI Railing
(a) Cats Eye/Pavement Marker (NMC nail Less)
(i) Providing and marking of hot applied thermoplastic
compound 2.5 mm thick
Safety
3 (ii) Construction of subgrade and earthen shoulders with
Improvement
approved material
(ii) Providing, laying and compacting wet mix macadum
( WMM) base course with approved materials
(iii)Providing, laying and compacting dense graded
bituminous macadam complete as per technical specification
clause no 505 including tack coat (increased 266*1.25% =
332.5)
(iv) Providing, laying and compacting and bituminous
concrete as per technical specification clause 508
...Continue Letter No. TPF/D&C/PR-I/2019-20/26 dated 28/11/2019… Page 2/2

Providing and laying tack coats with bituminous emulsion


(v).Cast in situ cement concrete M - 20 kerb
4.6) Supply of colour photographs in three copies and two
CDs complete
Incident
4 4.7) Supply of Video Cassette (CD) in three copies including
Management
videography of complete stretch at three stages in O&M
period
1. Dismantling Flexible Pavement
2. Raising and Repairing of Chamber with M20 grade of
Additional Items Concrete
(Non BOQ Items) 3. R.C.C.Chamber cover with frame Heavy Duty 225kg
5
Proposed for Road 4. Providing and laying in situ / ready mix M20 RCC of trap /
safety granite/ quartzite / gneiss metal for RCC work of ballast
walls, kerbs and box returns including scaffolding ,
compaction form work finishing and curing etc. Complete.

This is for your information and necessary action.

Yours faithfully,

For TPF GETINSA– EUROESTUDIOS S.L. in JV with TPF Engineering Pvt. Ltd.

Pankaj Mohabey
(Team Leader)

Cc: 1. The Project Director, NHAI, PIU Nashik


2. TPFEPL Head Office