Академический Документы
Профессиональный Документы
Культура Документы
PROCEDURE
TABLE OF CONTENTS
Page
1.0 SCOPE…………………………………………………….………………...3
2.0 REFERENCES……………………………………………………………...3
3.0 RESPONSIBILITIES……………………………………………………….3
8.0 ATTACHMENT/APPENDIX……………………………………………...10-21
FLANGE MANAGEMENT
PROCEDURE
1.0 SCOPE
This procedure covers the basic requirements for flange management including
proper storage, inspection, tightening to be performed by subcontractors under JG
SUMMIT STAGE 1, EXPANSION PROJECT in SIMLONG, BATANGAS CITY,
PHILIPPINES.
2.0 REFERENCES
1) ASME B31.3: ASME Design code for Process Piping
2) ASME B16.5: ASME Pipe Flanges and Pipe Fittings
3) ASME B16.47: Large Diameter Steel Flanges: NPS 26 through NPS 60 Metric/Inch
Standard
4) ASME PCC-1: Guidelines for Pressure Boundary Bolted Flange Joint Assembly
6.0 PROCEDURE
6.1.1 Flanges shall be stored above the ground on pallets or in packing crates.
6.1.2 Flanges that are stored by stacked, subcontractor shall provide cardboard,
plywood or wooden battens between each layer to protect gasket mating
surfaces.
6.1.3 All Stainless-Steel Flanges shall be separated from all carbon steel flanges.
6.1.4 All Flanges shall have covers to protect faces from damage during
handling and storage.
6.1.5 Gasket shall be stored in containers, on racks and segregated by gasket
type and item code number for easy identifications.
6.1.6 All gaskets should be stored away from direct sunlight/heat and humidity.
Store away from water, oils and chemicals.
6.1.7 Hanging gaskets is prohibited to avoid distortions in the rings shape.
6.1.8 Bolts shall be stored in such away to prevent thread damage. Bolts shall
be segregated by type for easy identifications.
6.1.9 Stainless steel bolts shall be stored separately from carbon steel bolts.
6.1.10 Receiving and Releasing of Items shall always be monitored.
6.1.10 Good Housekeeping shall be maintained at all time.
6.2.5 Subcontractor shall ensure that gasket to be installed are new, not damage.
6.2.6 Subcontractor shall ensure correct gasket, bolt & nuts are used.
6.2.7 Marking shall be done on the bolts to indicate that the flange joint has been
tightened to the required value.
START
no
ACCEPTED Issue Flange Management
checklist (rejected)
yes
END
FLANGE MANAGEMENT
PROCEDURE
6.3.20 If a bolt tensioning is going to be employed on the joint the bolt length shall
be exposed a minimum of one bolt diameter beyond one nut to allow for
tensioning device.
6.3.21 Subcontractor shall prepare the flange management checklist ensuring all
items installed are correct and shall be signed/approved by QA/QC
representative of the contractor before any final bolt tightening commence.
6.3.22 Piping supervisor shall update all flange management done on flange
management monitoring log to ensure proper monitoring of the
completeness of system flange management.
6.3.23 Torque tightening of pipe flange bolts shall be performed with calibrated
manual and hydraulic wrenches or bolt tensioning equipment. Spanners
shall be used for smaller pipe flanges of low rating to prevent over tightening
and damage to the gasket. Use of adjustable spanners is totally not allowed.
6.3.24 After finishing the final bolt tightening following the correct procedures and
bolt sequence. Subcontractor shall prepare the Flange management
Report and shall be signed by QA/QC representative of the contractor who
witness the bolt tightening.
6.3.25 Piping supervisor shall update all flange undergone acceptable final bolt
tightening.
6.3.26 In case a flange undergone flange management and final bolt tightening is
disassembled. It shall be inspected again follow the same procedure and
make sure old gaskets are been replaced by a new gasket and bolt threads
are been inspected.
6.5.1 Two bolts shall be installed diametrically opposite to each other, one bolt
tighten halfway for retaining the gasket. The nut shall then be engaged.
6.5.2 The gasket shall be inserted and centered between the flanges and ensure
the use of correct gasket. Nuts shall be hand tightened to hold the gasket
in place. Monitor that the gasket between flanges is properly seated on the
seating surfaces. Install bolt in opposite direction for bolts no. 3,4.5 & 6 as
per sample figure below.
FLANGE MANAGEMENT
PROCEDURE
6.5.3 The remaining bolts and nuts shall be installed, and hand tightened at the
opposite direction following the bolt sequence. Care shall be taken to
assure proper seating and centering of the gasket. Nuts shall be positioned
on the stud bolts such that all nut threads are fully engaged when assembly
is completed.
6.5.4 Do a preliminary pass, set a torque value of 25 % of the final torque.
6.5.5 2nd pass shall be carried out at a torque value of 50 % of final torque.
6.5.6 3rd pass shall be carried out at a torque value of 75% final torque.
6.5.7 Final pass shall be carried out at 100% torque value.
6.5.8 Continue tightening the bolts following a circular clockwise pattern until no
further nut rotation occurs at the target torque value.
6.5.9 In case there will be other bolting sequence or method proposed other than
those patterns stated on ASME PCC-1 (see appendix F of ASME PCC-1
for alternative patterns), it shall be reviewed and approved first before
commencing of work.
8.0 Attachments/Appendix