BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE

(Ministry of Justice and Legal Affairs)

Item Description Amount

LATA PSO AND DPP OFFICE BUILDING

Summary

1 Preliminaries and General (4.5% of total cost)

2 Excavation $ 92,745.83

3 Concrete Work $ 808,234.35

4 Reinforcing Steel $ 408,419.58

5 Concrete Blockwork $ 67,886.52

6 Solid Plaster $ 53,029.37

7 Carpentry $ 1,180,407.98

8 Joinery $ 69,977.36

9 Roofing $ 75,128.76

10 Plumbing $ 68,532.22

11 Electrical Services $ 50,356.01

12 Tiling $ 76,472.54

13 Painting $ 95,027.98

14 Glazing $ 545,938.52

15 Siteworks $ 14,031.19

Subtotal $ 3,606,188.21
Preliminaries and General (4.5%) $ 162,278.47

Subtotal $ 3,768,466.68
Profit (10%) $ 376,846.67

Subtotal $ 4,145,313.35
WHT 7.5% $ 310,898.50

AMOUNT OF TENDER $ 4,456,211.85

SUMMARY Page 1
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

1 PRELIMINARIES AND GENERAL

Preambles

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2 Refer to the General and Special


Conditions of contract and Tender
and to the Preliminary and General
section of the Specification

The Contract will be based on the


Solomon Islands Government
Standard Form of Building Contract
with , Special Conditions of Contract
and Conditions noted in the Appendix

3 The scope of this Contract consists of


the construction of a new PSO and
DPP Office Complex for Ministry of
Justice and Legal Affairs, at Lata,
Temotu Province, together with
siteworks and services (all in a staged
manner) all as detailed on the
Drawings and Specification.

4 This Bill of Quantities has been


prepared generally in accordance with
NZS 4202:1995 Standard Method of
measurement of Building Works, but
no deviation from same shall form the
basis of a claim

5 Refer to the General Rules of the NZS


4202:1995 Standard Method of
Measurement of Building Works

1 PRELIMINARIES AND GENERAL Page 2


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

1 PRELIMINARIES AND GENERAL


6 The following metric abbreviations for
units have been used:

m3 : Cubic Metres
m2 : Square Metres
m : Linear Metres
mm : Millimetres
no : Number
kg : Kilogram
MPa : Megapascal

7 The prices and rates throughout the


Bill of Quantities shall, unless
otherwise stated, include all labour
and materials including necessary
nails, screws, spikes, plugs, glue etc.,
waste on materials, conveyance and
delivery, storage,unloading, return of
empty crates, preparation, site
assembly, hoisting, setting, fitting and
fixing in position, lapping of materials,
straight cutting and waste, taxes
payable, import duty and customs
charges. All expenses and conditions
payable to w/m

8 Allow for compliance with, and giving of 1 NOTE


notices required by any act of Parliament,
by regulation made thereunder, or by the
order or direction of any lawful authority,
and the paying of and indemnifying of
employer against any fees or charges
demandable by law thereunder unless
stated elsewhere

1 PRELIMINARIES AND GENERAL Page 3


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

1 PRELIMINARIES AND GENERAL


9 Allow for the obtaining of necessay 1 NOTE
approval from any relevant authority,
and the payment of fees payable to
such authority in respect of such
approvals or otherwise in relation to
the building works, unless stated
elsewhere

10 Allow provisional sum for insurance 1 NOTE

11 Allow provisional sum for signboard, 1 NOTE


together with details of sign writing

12 Allow provisional sum for setting out 1 NOTE


the works, and provision of all
instruments and labour required by
the contract documents for checking
of this work

13 Allow provision sum for water for the 1 NOTE


works and any necessary temporary
plumbing and storage, and onging
charges

14 Allow provisional sum for temporary 1 NOTE


electric power, including connection to
local supply authority main and
ongoing charges

15 Allow provisional sum for 1 NOTE


communication, for matters inrelation
to the project for the duration of the
project

16 Allow for Hoarding, gantries, screen, 1 NOTE


planked footways, rails and lighting,
for protection of the public

1 PRELIMINARIES AND GENERAL Page 4


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

1 PRELIMINARIES AND GENERAL


17 Allow for necessary access to the 1 NOTE
building site including temporary
footpath, crossing, roads and similar
services

18 1 NOTE
Allow for sheds, messrooms and
attendance , and offices for the site
and administration staff, provide
furniture, temporary power and water
connections as required

19
Allow for sanitary conveniences and
1 NOTE
keeping of the conveniences in clean
and orderly condition

20 1 NOTE
Allow for care and security of works

21 1 NOTE
Allow for management, supervision
and administration of the works by the
contractor

22 Allow for soil and concrete testing and 1 NOTE


submission of samples

23 1 NOTE
Allow for plants and tools required for
the excution of works

24 Allow for fire fighting equipment 1 NOTE

25
Allow provision for scaffolding, for
1 NOTE
exterior and interior works and for lifts
shaft

26 Allow for protection screens and other 1 NOTE


protection requirement

27 1 NOTE
Allow for protection of the works from
any wheather or any other cause

1 PRELIMINARIES AND GENERAL Page 5


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

1 PRELIMINARIES AND GENERAL


28 1 NOTE
Allow to remove temporary site
offices, sheds and any other
temporary buidling after completion of
work, dispose off debris from site.
Those material which are fit to reuse
shall be kept properly onsite.

AMOUNT OF PRELIMINARIES AND


GENERAL CARRIED TO SUMMARY

1 PRELIMINARIES AND GENERAL Page 6


BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/unit Wastage
2 EXCAVATION No allowance

General

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2 Refer to the General and Special


Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3 This Bill of Quantities has been


prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 All measurement of excavation and


subsequent disposal, filling and
backfilling has been measured net,
before excavation; allow for increase in
bulk or decrease in consolidation

6 Working space has been allowed for in


accordance with NZS 4202: 1995.
Should any further working space be
deemed necessary then tenderers
shall allow for it here, together with the
necessary backfilling

2. EXCAVATION Page 7
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/unit Wastage
2 EXCAVATION No allowance
7 The rates for excavation shall include
for excavating in any materials met
with, excepting hard rock, trimming
sides and forming batters and levelling
off, consolidating bottoms and any
necessary staging requred. Tenderers
should ascertain the nature of material
to be excavated

Clear Site and Surface Excavation

8 Clear site of all trees, shrubs etc.. And 299 m²


extract stumps

9 Excavate 100mm topsoil and remove 135 m3


from site

Foundation Excavation

10 Excavate 1225mm x 1225mm pad 47 m3


footing 0-1.500m deep, commencing
from ground level

11 Excavate 1000mm x 1000mm pad 23 m3


footing,1.500m deep, commencing
from ground level

12 Excavate 700mm x 300mm main 53 m3


building strip footing 0-0.50m deep,
commencing from ground level

13 Excavate 700mmx250mm main 7 m³


entrance strip footing, 0-0.50m deep
commencing from ground level

Stairs (Main and Back entrance stairs)

14
Excavate 700x300 strip footing, 0- 1 m3
600mm deep commencing from
ground level

2. EXCAVATION Page 8
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/unit Wastage
2 EXCAVATION No allowance
15 1.2 m²
Excavate 1076mm long x1100mm
wide, stairs ground landing slab, 0-
50mm deep commencing from ground
level

Cartaway, Backfilling & Blinding

16 400mm thick hardcore fill, ramped as 25 m3 $ 250.00


directed by Architect.

17 Approved backfill surplus excavated 91 m3


materials to sides of footing and
rammed as approved by Engineer

Filling

18 50mm thick sand blinding spread over 188 m2 $ 12.50


hardcore fill

Damp Proof membrane

19 Polythene DPC over 50mm thick sand 188 m2 $ 3.50


blinding

AMOUNT OF EXCAVATION WORK CARRIED TO


SUMMARY

2. EXCAVATION Page 9
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Material Labor Constant


Fixing Transport Sub-Total Standard Hours
1% 20% Hour/m³ Labor Tradesman Foreman
$ 8.00 $ 15.00 $ 30.00
Average Rate $25

2. EXCAVATION Page 10
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Material Labor Constant


Fixing Transport Sub-Total Standard Hours
1% 20% Hour/m³ Labor Tradesman Foreman

1 $ 25.00

1.1 $ 27.50

2.2 $ 55.00

2.2 $ 55.00

2.2 $ 55.00

2.2 $ 55.00

2.2 $ 55.00

2. EXCAVATION Page 11
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Material Labor Constant


Fixing Transport Sub-Total Standard Hours
1% 20% Hour/m³ Labor Tradesman Foreman
1.1 $ 27.50

$ 15.00 265.00 1 $ 8.00

1 $ 8.00

$ 0.13 $ 2.50 $ 15.13 1.00 $ 25.00

$ 0.04 $ 0.70 $ 4.24 0.05 $ 1.25

2. EXCAVATION Page 12
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Equipment Others
Excavator $1350/hr Overhead P&G Sub-Total
Sub-Total hrs rate Sub-Total 0% 0.00%

2. EXCAVATION Page 13
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Equipment Others
Excavator $1350/hr Overhead P&G Sub-Total
Sub-Total hrs rate Sub-Total 0% 0.00%

$ 25.00 $ - 0 $ -

$ 27.50 0.17 $ 1,350.00 $ 229.50 $ - $ - $ -

$ 55.00 0.13 $ 1,350.00 $ 175.50 $ - $ - $ -

$ 55.00 0.13 $ 1,350.00 $ 175.50 $ - $ - $ -

$ 55.00 0.13 $ 1,350.00 $ 175.50 $ - $ - $ -

$ 55.00 0.13 $ 1,350.00 $ 175.50 $ - $ - $ -

$ 55.00 0.13 $ 1,530.00 $ 198.90 $ - $ - $ -

2. EXCAVATION Page 14
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Equipment Others
Excavator $1350/hr Overhead P&G Sub-Total
Sub-Total hrs rate Sub-Total 0% 0.00%
$ 27.50 0.00 $ - $ - $ - $ -

Plate Compactor
$ 500.00
$ 8.00 0.17 $ 85.00 $ 14.45 $ - $ - $ -

$ 8.00 0.17 $ 85.00 $ 14.45 $ - $ - $ -

Plate Compactor
$ 500.00
$ 25.00 0.17 $ 85.00 $ 14.45 $ - $ - $ -

$ 1.25 $ -

2. EXCAVATION Page 15
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Rate Build up added Rate Cost

2. EXCAVATION Page 16
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Rate Build up added Rate Cost

$ 25.00 $ 25.00 $ 7,475.00

$ 257.00 $ 257.00 $ 34,695.00

$ 230.50 $ 230.50 $ 10,833.50

$ 230.50 $ 230.50 $ 5,301.50

$ 230.50 $ 230.50 $ 12,216.50

$ 230.50 $ 230.50 $ 1,544.35

$ 253.90 $ 253.90 $ 126.95

2. EXCAVATION Page 17
BILL OF QUANTITIES FOR MJLA'S BUILDING FOR PSO AND DPP OFFICE AT LATA, TEMOTU PROVINCE
(Ministry OF Justice and Legal Affairs)

Rate Build up added Rate Cost

$ 27.50 $ 27.50 $ 32.55

$ 287.45 $ 287.45 $ 7,186.25

$ 22.45 $ 22.45 $ 2,042.95

$ 54.58 $ 54.58 $ 10,260.10

$ 5.49 $ 5.49 $ 1,031.18

92,745.83

2. EXCAVATION Page 18
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK

General

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2 Refer to the General and Special


Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3 This Bill of Quantities has been


prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The rates for concrete shall include for


finishing surfaces to falls or to the
required specification and for curing
and protecting exposed surface

3. CONCRETE Page 19
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK
6 Rates for formwork shall include for
extra labour at narrow widths to
intersections etc… also for forming all
filletted or chamfered sailent angles.
Rate for formwork above ground as in
suspended beams suspended slab,
stairs and likes shall include for,
shores, stringer, joist, ledgers,
horizontal braces, vertical props, head
tree, cleats, fixing and other required
works for formwork

7 Rates for concrete shall include for


vibrating, as specified

8 Rates for concrete in slabs, walls,


footing, beams etc… shall include for
curing and for forming all control and
construction joints, as specified

9 Rates for concrete in slabs shall


include for all screeds and screeding
off and for paving in alternative
squares, as specified

10 Rates for damp proof course shall


include for penetration and taping for
all pipes etc

11 Allow to carry out all concrete tests 1.00 item


and pay all costs, as specified

SUBSTRUCTURE

20 Mpa strength concrete as specified


in :

3. CONCRETE Page 20
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK
12 1225mm x 1225mm x 300mm pad 10.00 m3 $ 1,450.00 $ 29.00
footing
13 450mm x 250 nib column external RC 3.00 m3 $ 1,450.00 $ 29.00
columns

14 450mmx250 nib column to main 1.00 m3 $ 1,450.00 $ 29.00


building corner RC columns

15 1000mmx1000mmx300mm pad 5.00 m3 $ 1,450.00 $ 29.00


footings

16 250mmx250mm nib cloumns 1.00 m3 $ 1,450.00 $ 29.00

17 700mmx300mm main building strip 13.3 m3 $ 1,450.00 $ 29.00


footing

18 700mmx250mm to ground floor main 1.17 m3 $ 1,450.00 $ 29.00


entrance strip footing

19 300mm x500mm deep ground beams 6.00 m3 $ 1,450.00 $ 29.00

20 100mm thick ground floor slab 18.00 m3 $ 1,450.00 $ 29.00

Stairs ( Main and Back entrance stairs)

20 700x300 strip footing to stairs midway 1.00 m3 $ 1,450.00 $ 29.00


support

21 1.00 m3 $ 1,450.00 $ 29.00


1076x1100x150 stairs ground landing
and 200mm x 300mm dept footing

22 Ground floor main entrance concrete 1.00 m3 $ 1,450.00 $ 29.00


steps

SUPERSTRUCTURE

23 20 Mpa strength concrete as


specified in :

3. CONCRETE Page 21
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK

24 450mm x 250mm column to external 9.20 m3 $ 1,450.00 29.00


wall

25 450mm x 250mm external corner 10.00 m3 $ 1,450.00 29.00


columns

26 250x250 RC columns 7.00 m3 $ 1,450.00 29.00

27 27.00 m3 $ 1,450.00 $ 29.00


125mm thick top floor suspended floor
slab in cluding top floor stairs landings

TOP FLOOR BEAMS

20 Mpa strength concrete as specified


in :
28 600mm x 250mm RC beam 26.00 m3 $ 1,450.00 29.00

29 700mm x 250mm RC beam to toilet 1.00 m3 $ 1,450.00 29.00


room and top back entrance landing

30 450mm x 250mm beam over ground 1.00 m3 $ 1,450.00 $ 29.00


floor main entrance

TOP FLOOR CEILING BEAMS

20 Mpa strength concrete as specified


in :
34 600mmx250mm ceiling RC Beam 28.00 m3 $ 1,450.00 29.00

STAIRS-(Back and Front stairs)

35 Stair midway support, landing and 5.64 m3 $ 1,450.00 29.00


treads to front entrance and back
entrance to top floor

FORMWORK

3. CONCRETE Page 22
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK
SUBSTRUCTURE 10%

36 Sides of pad footing, 0-300 high 53.00 m² $ 246.50 $ 24.65

37 Sides of nib columns to corners, 9.00 m² $ 246.50 $ 24.65


(1800mm girth)

38 Sides of exterior nib columns 30.00 m² $ 246.50 $ 24.65


(1400mm girth)

39 Sides of interior nib columns,(1000mm 20.00 m² $ 246.50 $ 24.65


girth)

40 Sides of strip footing, 0-250mm high 51.00 m $ 370.00 $ 37.00

41 Side of internal ground beams, 0- 22 m² $ 283.28 $ 28.33


500mm high

42 Side of slab, 0-100mm high 78.00 m $ 184.71 3.69


SUPERSTRUCTURE

43 Sides of corner columns, (1800mm 18.00 m² $ 246.50 24.65


girth)

44 Sides of exterior columns (1400mm 60.00 m² $ 246.50 24.65


girth)

45 Sides of interior columns,(1000mm 36.00 m² $ 246.50 24.65


girth)

46 73.00 m 128.38 $ 2.57


Sides of top floor slab, 0-125mm high

47 Under side of top floor slab 182.00 m² $ 589.62 $ 11.79

First Floor Beams

48 Sides and soffit of suspended floor 264.00 m² $ 430.25 $ 8.61


beams

3. CONCRETE Page 23
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Ma


Rate/Unit Wastage
2%
3 CONCRETE WORK

First Floor Columns and Extended columns above ceiling beams


49 Sides of corner columns (1800mm 12.00 m² $ 246.50 4.93
girth)

50 Sides of exterior columns (1400mm 34.00 m² $ 246.50 4.93


girth)

51 Sides of interior columns,(1000mm 20.00 m² $ 246.50 4.93


girth)

STAIRS
52 Sides of stair footing, 0-300 high 13.00 m $ 81.00 1.62

53 Rises with (girth 0-185 high) 13.00 m $ 81.00 8.10

54 Soffits of stairs 8.00 m2 $ 250.00 25.00

55 Sides of landing, 0-150 high 9.00 m $ 72.00 7.20

56 Sides of treads 39.00 m $ 81.00 8.10

AMOUNT OF CONCRETE WORK


CARRIED TO SUMMARY

3. CONCRETE Page 24
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00
Average Rate 18.00

3. CONCRETE Page 25
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00

Estimate Average Labor Labour cost


hours to hour rate for 1 m³
work on
1m³

3. CONCRETE Page 26
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00
$ - $ 290.00 $ 1,769.00 1.30 $ 19.30

$ - $ 290.00 $ 1,769.00 1.50 $ 27.00

$ - $ 290.00 $ 1,769.00 1.50 $ 27.00

$ - $ 290.00 $ 1,769.00 1.50 $ 27.00

$ - $ 290.00 $ 1,769.00 2.25 $ 40.50

$ - $ 290.00 $ 1,769.00 1.75 $ 31.50

$ - $ 290.00 $ 1,769.00 1.75 $ 31.50

$ - $ 290.00 $ 1,769.00 1.75 $ 31.50

$ - $ 290.00 $ 1,769.00 1.30 $ 23.40

$ - $ 290.00 $ 1,769.00 1.75 $ 31.50

$ -
$ - $ 290.00 $ 1,769.00 1.75 $ 31.50

$ -
$ - $ 290.00 $ 1,769.00 1.3 $ 23.40

3. CONCRETE Page 27
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00

$ - $ 290.00 $ 1,769.00 2.90 $ 52.20

$ - $ 290.00 $ 1,769.00 2.9 $ 52.20

$ - $ 290.00 $ 1,769.00 2.90 $ 52.20

$ - $ 290.00 $ 1,769.00 4.00 $ 72.00

$ - $ 290.00 $ 1,769.00 2.45 $ 44.10

$ - $ 290.00 $ 1,769.00 2.45 $ 44.10

$ - $ 290.00 $ 1,769.00 2.45 44.1

$ - $ 290.00 $ 1,769.00 2.25 $ 25.00 $ 56.25

$ - $ 290.00 $ 1,769.00 2.25 $ 25.00 $ 56.25

3. CONCRETE Page 28
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00
2% 20%

$ 4.93 $ 49.30 $ 325.38 1.20 $ 21.60

$ 4.93 $ 49.30 $ 325.38 2.90 $ 52.20

$ 4.93 $ 49.30 $ 325.38 2.90 $ 52.20

$ 4.93 $ 49.30 $ 325.38 2.90 $ 52.20

$ 7.40 $ 74.00 $ 488.40 2.45 $ 44.10

$ 5.67 $ 56.66 $ 373.93 1.2 21.6

$ 3.69 $ 36.94 $ 229.04 0.33 $ 5.94

4.93 49.3 325.38 2.90 $ 52.20

4.93 49.3 325.38 2.90 $ 52.20

4.93 49.3 325.38 2.90 $ 52.20

$ 2.57 $ 25.68 $ 159.19 0.15 2.7

$ 11.79 $ 117.92 $ 731.13 4.00 $ 72.00

$ 8.61 $ 86.05 $ 533.51 2.45 $ 44.10

3. CONCRETE Page 29
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material LABPOUR
Fixing Transport Sub-Total Standard Hours
0% 20% Hours/m³ Labor Tradesman
$ 8.00 $ 15.00

$ 4.93 $ 49.30 305.66 2.90 $ 52.20

$ 4.93 $ 49.30 305.66 2.90 $ 52.20

$ 4.93 $ 49.30 305.66 2.90 $ 52.20

$ 1.62 $ 16.20 100.44 0.25 $ 4.50

$ 1.62 $ 16.20 106.92 0.33 $ 5.94

$ 5.00 $ 50.00 330.00 1.75 $ 31.50

$ 1.44 $ 14.40 95.04 0.25 $ 4.50

$ 1.62 $ 16.20 106.92 0.45 $ 8.10

3. CONCRETE Page 30
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00

3. CONCRETE Page 31
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00

3. CONCRETE Page 32
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00
$ 19.30 0.2 $ 100.00 $ 100.00

$ 27.00 0.2 $ 100.00 $ 100.00

$ 27.00 0.2 $ 100.00 $ 100.00

$ 27.00 0.2 $ 100.00 $ 100.00

$ 40.50 0.2 $ 100.00 $ 100.00

$ 31.50 0.2 $ 100.00 $ 100.00

$ 31.50 0.2 $ 100.00 $ 100.00

$ 31.50 0.2 $ 100.00 $ 100.00

$ 23.40 0.2 $ 133.30 $ 133.30

$ 31.50 0.2 $ 100.00 $ 100.00

$ 31.50 0.2 $ 100.00 $ 100.00

$ 23.40 0.2 $ 100.00 $ 100.00

3. CONCRETE Page 33
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00

$ 52.20 0.2 $ 100.00 $ 100.00

$ 52.20 0.2 $ 100.00 $ 100.00

$ 52.20 0.2 $ 100.00 $ 100.00

$ 72.00 $ -

$ 44.10 0.2 $ 100.00 $ 100.00


$ -
$ 44.10 0.2 $ 100.00 $ 100.00

$ -
44.1 0.2 $ 100.00 $ 100.00

$ 56.25 0.2 $ 100.00 $ 100.00

$ 56.25 0.2 $ 100.00 $ 100.00

3. CONCRETE Page 34
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00
No machine needed for this work

$ 21.60 $ - $ - $ -

$ 52.20 $ - $ - $ -

$ 52.20 $ - $ - $ -

$ 52.20 $ - $ - $ -

$ 44.10 $ -

$ -
$ 21.60

$ 5.94 $ -
$ -
$ -
$ 52.20 $ -

$ 52.20 $ -

$ 52.20 $ -

$ -

2.7

$ 72.00

$ 44.10

3. CONCRETE Page 35
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

ABPOUR Equipment
ours Vibrating machine: $500/30m³/Day
Foreman SUB-TOTAL Hrs/m³ Hourly Rate Sub-Total
$ 30.00 $ 500.00

$ 52.20 $ -

$ 52.20 $ -

$ 52.20 $ -

$ 4.50 $ -

$ 5.94 $ -

$ 31.50 $ -

$ 4.50 $ -

$ 8.10 $ -

3. CONCRETE Page 36
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

3. CONCRETE Page 37
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

3. CONCRETE Page 38
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

$ - $ - $ - $ 1,888.30 $ 1,888.30

$ - $ - $ - $ 1,896.00 $ 1,896.00

$ - $ - $ - $ 1,896.00 $ 1,896.00

$ - $ - $ - $ 1,896.00 $ 1,896.00

$ - $ - $ - $ 1,909.50 $ 1,909.50

$ - $ - $ - $ 1,900.50 $ 1,900.50

$ - $ - $ - $ 1,900.50 $ 1,900.50

$ - $ - $ 1,900.50 $ 1,900.50

$ - $ - $ - $ 1,925.70 $ 1,925.70

$ - $ - $ - $ 1,900.50 $ 1,900.50

$ - $ - $ - $ 1,900.50 $ 1,900.50

$ - $ - $ - $ 1,892.40 $ 1,892.40

3. CONCRETE Page 39
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

$ - $ - $ - $ 1,921.20 $ 1,921.20

$ - $ - $ - $ 1,921.20 $ 1,921.20

$ - $ - $ - $ 1,921.20 $ 1,921.20

$ - $ - $ - $ 1,841.00 $ 1,841.00

$ - $ - $ - $ 1,913.10 $ 1,913.10

$ - $ - $ - $ 1,913.10 $ 1,913.10

$ - $ - $ 1,869.00 $ 1,869.00

$ - $ - $ - $ 1,925.25 $ 1,925.25

$ - $ - $ - $ 1,925.25 $ 1,925.25

3. CONCRETE Page 40
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

$ - $ - $ - $ 346.98 $ 346.98

$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ - $ 532.50 $ 532.50

$ - $ -
$ 395.53 $ 395.53

$ - $ - $ 234.98 $ 234.98

$ -
$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ - $ 377.58 $ 377.58

$ - $ - $ 161.89 $ 161.89

$ - $ - $ 803.13 $ 803.13

$ - $ - $ 577.61 $ 577.61

3. CONCRETE Page 41
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Rate Buildup added Rate


Overhead P&G Sub-Total
0% 0.00%

$ - $ - $ - $ 357.86 $ 357.86

$ - $ - $ - $ 357.86 $ 357.86

$ - $ - $ - $ 357.86 $ 357.86

$ - $ - $ - $ 104.94 $ 104.94

$ - $ - $ - $ 112.86 $ 112.86

$ - $ - $ - $ 361.50 $ 361.50

$ - $ - $ 99.54 $ 99.54

$ - $ - $ - $ 115.02 $ 115.02

3. CONCRETE Page 42
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

3. CONCRETE Page 43
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

3. CONCRETE Page 44
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 18,883.00

$ 5,688.00

$ 1,896.00

$ 9,480.00

$ 1,909.50

$ 25,276.65

$ 2,223.59

$ 11,403.00

$ 34,662.60

$ 1,900.50

$ 1,900.50

$ 1,892.40

3. CONCRETE Page 45
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 17,675.04

$ 19,212.00

$ 13,448.40

$ 49,707.00

$ 49,740.60

$ 1,913.10

$ 1,869.00

$ 53,907.00

$ 10,858.41

3. CONCRETE Page 46
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 18,389.94

$ 3,398.22

$ 11,327.40

$ 7,551.60

$ 27,157.50

$ 8,701.65

$ 18,328.47

$ 6,796.44

$ 22,654.80

$ 13,592.88

$ 11,818.06

$ 146,169.44

$ 152,489.04

3. CONCRETE Page 47
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 4,294.32

$ 12,167.24

$ 7,157.20

$ 104.94

$ 112.86

$ 361.50

$ 99.54

$ 115.02

$ 808,234.35

3. CONCRETE Page 48
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

4 REINFORCING STEEL

General

1 Refer to the drawings and Specification


for full details and descriptions of
materials and workmanship

2 Refer to the General and Special


Conditions of the contract and tender and
to the Preliminary and General section of
the Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202:
1995 Standard Method of measurement
of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 Weights are calculated from standard


average weights given in the
Manufactures tables and no allowance
has been made for rolling margin

6 The rates shall include for all clips, tie


wire, stays, ties, hangers, spacers,
(including designated spacers to
foundation beams), placing and support
bars; plastic, mortar blocks or similar
supports; all cutting, bending, hooked
ends etc… and for supply unless
otherwise stated

7 The rates for starters shall include for


boring all formwork

8 The rates for rods shall include for long


lengths

4. REINFORCEMENT Page 49
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

4 REINFORCING STEEL

9 Mesh reinforcement has been measured


net overrall and the rates shall include for
laps, as specified

10 Items described as stirrups shall be


deemed to include stirrups, links, ties,
hoops, stools, binder, ligatures and the
like

11 All reinforced steel shall comply with NZS


3402p Grade 275, as specified

SUBSTRUCTURE

Column Pads

12 D10 bars 516.00 KG $ 13.50 $ 6,964.14

13 Galvanized Tie wire 20.00 KG $ 34.02 $ 680.40

Nib Columns

14 D16 bars in External Columns 302.00 KG $ 17.37 $ 5,246.04

15 Ditto but in Corner Columns 95.00 KG $ 17.37 $ 1,650.25

16 Ditto but in internal columns 172.00 KG $ 32.37 $ 5,567.81

17 Galvanized Tie wire 15.00 KG $ 37.44 $ 561.60

D10 Rings as specified in:-

14 External Columns 92.00 KG $ 17.46 $ 1,605.99

15 Corner Columns 34.00 KG $ 17.46 $ 593.52

16 Interior columns 59.00 KG $ 17.46 $ 1,029.93

Tie Wire

17 Galvanized Tie wire 3.00 KG $ 37.44 $ 112.32

Strip Footing

4. REINFORCEMENT Page 50
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

4 REINFORCING STEEL
18 D16 horrizontal bars 1072.00 KG $ 17.37 $ 18,621.71

19 R10 ties @ 200 centers 489.00 KG $ 18.12 $ 8,858.33

20 Galvanized Tie wire 30.00 KG $ 37.44 $ 1,123.20

300mmx500mm deep internal Ground Beam

23 D16 Horizontal bars 199.00 KG $ 167.37 $ 167.37

24 R10 ties at 200 Centers 134.00 KG $ 18.12 $ 18.12

Floor Slab

25 F62 Mesh 195.00 m2 $ 54.22 $ 10,571.93

SUPERSTRUCTURE

COLUMNS (Ground floor and Top floor)


26 D16 bars in external columns 335.00 KG $ 32.37 $ 10,844.29

27 Ditto but to corner columns 1065.00 KG $ 32.37 $ 34,475.12

28 Ditto but to internal columns 629.00 KG $ 32.37 $ 20,361.36

29 Galvanized Tie wire 25.00 KG $ 37.44 $ 936.00

Blockwork (Ground floor and Top floor)

30 D12 vertocal bars 290.00 KG $ 17.32 $ 5,023.44

31 D12 horrizontal bars 251.00 KG $ 17.32 $ 4,347.87

32 Galvanized Tie wire 6.00 KG $ 37.44 $ 224.64

Suspended Beam

33 D16 horrizontal bars 3919.00 KG $ 17.37 $ 68,076.95

34 D10 ties @ 150 centers 1083.00 KG $ 17.46 $ 18,905.28

35 Galvanized Tie wire 50.00 KG $ 37.17 $ 1,858.50

Suspended Floor Slab

4. REINFORCEMENT Page 51
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

4 REINFORCING STEEL

36 D16 run both ways @ 150 centers 4655.00 KG $ 17.37 $ 80,862.01

37 F72 mesh wire 194.00 m² $ 22.13 $ 4,293.03

38 Galvanized Tie wire 35.00 KG $ 37.44 $ 1,310.40

Roof Beams

39 D16 bars 3919.00 KG $ 17.37 $ 68,076.95

40 D10 ties @ 150 centers 1084.00 KG $ 18.12 $ 19,636.88

41 Galvanized Tie wire 27.00 KG $ 37.44 $ 1,010.88

STAIRS

Footing

42 D16 bars 21.00 KG $ 17.37 $ 364.79

43 R10 ties at 200 centers 15.00 KG $ 19.50 $ 292.50

44 Galvanized Tie wire 2.00 kg $ 52.44 $ 104.88

Column-Stairs Midway support

45 D16 bars 31.00 KG $ 17.37 $ 538.50

46 R10 ties 25.00 KG $ 18.12 $ 452.88

47 Galvanized Tie wire 3.00 KG $ 37.44 $ 112.32

Beam-Stairs midway support

48 D12 Steel rod 9.00 KG $ 17.32 $ 155.90

49 R6 Ties @ 150mm Centers 5.00 KG $ 20.35 $ 101.74

Landing, Soffit & Treads

4. REINFORCEMENT Page 52
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Rate Cost

4 REINFORCING STEEL
50 D12 bars 144.00 KG $ 17.31 $ 2,492.64

51 Galvanized Tie wire 5.00 kg $ 37.44 $ 187.20

AMOUNT OF REINFORCING STEEL $ 408,419.58


CARRIED TO SUMMARY

4. REINFORCEMENT Page 53
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage Fixing
5 CONCRETE BLOCKWORK
1% 5%

General

1
Refer to the drawings and Specification for
full details and descriptions of materials and
workmanship
Refer to the General and Special Conditions
2 of the contract and tender and to the
Preliminary and General section of the
Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202:
1995 Standard Method of measurement of
Building Works

4
Refer to the General rules of the NZS 4202:
1995 Standard Method of Measurement of
Building Works

Measurement and Price

5 Rates for blockwork shall include for all


straight cutting at closers and junctions core
filling, forming junctions, cleaning down and
protection, as specified
6 Blockwork shall be laid in stretcher bond
unless otherwise stated

7 Rates for lintels shall include for centering


and its subsequent removal

Reinforcement for blockwork has been


included in this trade.Therefore, preambles
of Reinforcing Steel trades shall be equally
binding on this trade and should be read in
conjunction

SUBSTRUCTURE

5. BLOCKWORK Page 54
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage Fixing
5 CONCRETE BLOCKWORK
1% 5%
Strip Footing

200mm thick reinforced blockwork to 57 m² $ 162.50 $ 1.63 $ 8.13


Underside of Ground floor slab

External Wall (Ground and Top Floor)

8 200mm thick reinforced blockwork wall 85 m2 $ 162.50 $ 1.63 $ 8.13


plastered finish both sides

Internal Wall (Ground and Top floor)

11 200mm thick reinforced blockwork wall 50 m2 $ 144.00 $ 1.44 $ 7.20


plastered finish both sides

14 D12 vertical bars 152 kg $ 10.45 $ 0.10 $ 0.52

15 D16 bond beam bars 86 kg $ 10.64 $ 0.11 $ 0.53

Galvanized Tie wire 15 kg $ 27.00 $ 0.27 $ -

CONCRETE FILLING
Fill all cells of 200mm thick blockwork to 57 m2 116.45 1.16 5.8225
underside of GF slab with 17.5 Mpa
Strength concrete

16 Fill all cells of external 200mm thick 85 m2 $ 116.45 1.16 $ 5.82


blockwork wall with 17.5 Mpa Strength
concrete

17 Fill all cells of internal 200mm thick 50 m2 $ 115.45 1.15 $ 5.77


blockwork wall with 17.5 Mpa Strength
concrete
AMOUNT OF CONCRETE BLOCKWORK
CARRIED TO SUMMARY

5. BLOCKWORK Page 55
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

terial Labor
Transport Sub-Total Standard hours
20% Labor Tradesman Foreman
$ 8.00 $ 15.00 30

0.43 0.22
0.5 0.25
0.56 0.28

0.35

0.45
0.55

Standard Hours LH

5. BLOCKWORK Page 56
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

terial Labor
Transport Sub-Total Standard hours
20% Labor Tradesman Foreman
TRADESMAN LABOR TRADESMAN LABOR

$ 32.50 $ 204.75 0.56 0.28 $ 8.40 $ 2.24

$ 32.50 $ 204.75 0.56 0.28 $ 8.40 2.24

$ 28.80 $ 181.44 0.5 0.22 $ 4.00 3.30

$ 2.09 $ 13.17 0.03 0.22 $ 3.30 25.00

$ 2.13 $ 13.41 0.02 0.22 $ 3.30 25.00

$ 5.40 $ 32.67 0.2 0.2 $ 3.00 $ 1.60

23.29 $ 146.73 0.55 0.55 $ 8.25 8.25

$ 23.29 $ 146.73 0.55 0.55 $ 8.25 8.25

$ 23.09 $ 145.47 0.45 0.55 $ 8.25 8.25

5. BLOCKWORK Page 57
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

RAKING Equipment
Hourly rate hrs rate
Sub-Total TradesmaLabour Foreman Sub-total
$ 25.00 $ 8.00
25

Hrs/m2 hrs/m2 rate/m2 rate/m2

0.18 0.18 100mm

0.20 0.20 150mm


0.28 0.28 200mm

5. BLOCKWORK Page 58
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

RAKING Equipment
Hourly rate hrs rate
Sub-Total TradesmaLabour Foreman Sub-total

$ 10.64 0.28 0.28 7 $ 2.24 $ 9.24 $ - $ -

$ 10.64 0.28 0.28 $ 7.00 $ 2.24 $ 9.24 $ - $ -

$ 7.30 0.20 0.2 $ 5.00 $ 1.60 $ 6.60

$ 28.30 0.20 $ - $ - $ - $ -

$ 28.30 0.00 $ - $ - $ - $ -

$ 4.60

$ 8.25 $ - $ - $ - $ - $ - $ - $ -

$ 8.25 $ - $ - $ - $ - $ - $ - $ -

$ 8.25 $ - $ - $ - $ - $ - $ - $ -

5. BLOCKWORK Page 59
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate


Sub-Total Overhead P&G Sub-Total
0% 0.00%

5. BLOCKWORK Page 60
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate


Sub-Total Overhead P&G Sub-Total
0% 0.00%

$ - 0 0 0 $ 224.63 $ 224.63

$ - $ - $ - $ - $ 215.39 $ 215.39

$ - $ - $ - $ - $ 188.74 $ 188.74

$ - $ - $ - $ - $ 41.47 $ 41.47
$ -
$ - $ - $ - $ - $ 41.71 $ 41.71
$ -
$ 37.27 $ 37.27

$ -
$ - $ - $ - $ 154.98

$ 154.98

$ - $ - $ - $ - $ 154.98

$ 154.98

$ - $ - $ - $ - $ 153.72

$ 153.72

5. BLOCKWORK Page 61
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

5. BLOCKWORK Page 62
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

$ 12,803.91

$ 18,308.15

$ 9,437.00

$ 6,302.98

$ 3,586.75

$ 559.05

$ 8,833.69

$ 13,173.05

$ 7,685.85

$ 67,886.52

5. BLOCKWORK Page 63
BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
6 SOLID PLASTER 2%

Preambles

General

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2 Refer to the General and Special


Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3 This Bill of Quantities has been


prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The rates for plastering are to include


for all small quantities, working down
to different finishes, stripping to provide
key for slurry coats, well wetting and
cross scratching between coats,
cleaning down and protection as
specified

6 The rates for linear items are to include


for short lengths, ends, intersections
etc.

6. SOLID PLASTER Page 64


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
6 SOLID PLASTER 2%
7 The rates shall include for making
good around pipes, brackets and the
like, for making up to frames etc., and
for internal angles. External angles
have been measured

8 The rates shall include for all screeds


and formwork

9 Allow to protect adjacent finishes and


finished work including protecting
window frames and glass and cleaning
up around same on completion

10 The rates for plastering shall include


for an initial slurry dash coat, as
specified

EXTERIOR

15mm thick two coat 1:3 cement/sand


plaster with an approved plasticiser
added, finished with a smooth and
wood float finish, as specified in :

11 Concrete blockwalls 85 m2 ### $ 0.72

12 Sides of Corner column, 0 - 1850mm 24 m2 ### $ 0.72


girth

13 Sides of 250 x 250 Column, 0-1000mm 15 m2 ### $ 0.12


girth)

14 Sides of 450x250 columns, 0-1400mm 114 m2 ### $ 0.72


girth

15 Extra value for narrow width , 0-475 65 m2 ### $ 0.72


girth( sides of beams)

INTERIOR

6. SOLID PLASTER Page 65


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
6 SOLID PLASTER 2%
10mm thick two coat 1:3 cement/sand
plaster with an approved plasticiser
added, finished with a smooth and
wood float finish, as specified in :

16 Blockwork wall 185.00 m2 ### $ 0.72

17 Sides of 250 x 250 Column, 0-1000mm 58.00 m2 ### $ 0.72


girth

18 Extra value for narrow width , 0- 65.00 m2 ### $ 0.72


475mm girth( sides of beams)

19 Sides of columns, 0-1278mm girth 214.00 m2 ### $ 0.72

20 Side of RC floor slab 114.36 m ### $ 0.03

21 Soffit of floor slab 128.00 m2 ### $ 0.72

22 Stairs threades and raises, 0-485mm gir 20.00 m2 ### 0.72

23 Stairs sides, 0-250mm high 7.00 m² ### $ 0.72

AMOUNT OF SOLID PLASTER


CARRIED TO SUMMARY

6. SOLID PLASTER Page 66


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hour Tradesman Labor
$ 15.00 $ 8.00

0.5 0.25 wall noarrow width (m)


0.55 0.3 soffits (M)

6. SOLID PLASTER Page 67


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hour Tradesman Labor

wall 0.25 0.11


soffit 0.28 0.11

column 0.42 0.18


Beam 0.42 0.18

TRADESMAN LABOR TRADESMAN

$ 1.80 $ 7.20 $ 45.72 0.25 0.11 $ 3.75

$ 1.80 $ 7.20 $ 45.72 0.42 0.18 $ 6.30

$ 0.30 $ 0.42 $ 36.84 0.42 0.18 $ 6.30

$ 1.80 $ 7.20 $ 45.72 0.42 0.18 $ 6.30

$ 1.80 $ 7.20 $ 45.72 0.55 0.25 $ 8.25

6. SOLID PLASTER Page 68


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hour Tradesman Labor

$ 1.80 $ 7.20 $ 45.72 0.25 0.18 $ 3.75

$ 1.80 $ 7.20 $ 45.72 0.42 0.18 $ 6.30

$ 1.80 $ 7.20 $ 45.72 0.55 0.25 $ 8.25

$ 1.80 $ 7.20 $ 45.72 0.42 0.18 $ 6.30

$ 0.08 $ 0.30 $ 1.91 0.42 0.18 $ 6.30

$ 1.80 $ 7.20 $ 45.72 0.42 0.18 $ 6.30

1.8 7.2 45.72 0.55 0.3 $ 8.25

$ 1.80 $ 7.20 $ 45.72 0.55 0.30 $ 8.25

6. SOLID PLASTER Page 69


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

bor Raking Others


d Hours hrs rate Sub-Total Overhead P&G
Sub-Total

rrow width (m)

6. SOLID PLASTER Page 70


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

bor Raking Others


d Hours hrs rate Sub-Total Overhead P&G
Sub-Total

LABOR

$ 0.88 $ 4.63 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 2.00 $ 10.25 $ - $ - $ - $ - $ -

6. SOLID PLASTER Page 71


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

bor Raking Others


d Hours hrs rate Sub-Total Overhead P&G
Sub-Total

$ 1.44 $ 5.19 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 2.00 $ 10.25 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 1.44 $ 7.74 $ - $ - $ - $ - $ -

$ 2.40 $ 10.65 $ - $ - $ - $ - $ -

$ 2.40 $ 10.65 $ - $ - $ - $ - $ -

6. SOLID PLASTER Page 72


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost


Sub-Total

6. SOLID PLASTER Page 73


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost


Sub-Total

$ - $ 50.35 $ 50.35 $ 4,279.75

$ - $ 53.46 $ 53.46 $ 1,283.04

$ - $ 44.58 $ 44.58 $ 668.70

$ - $ 53.46 $ 53.46 $ 6,094.44

$ - $ 55.97 $ 55.97 $ 3,638.05

6. SOLID PLASTER Page 74


BOQ FOR PROPOSED OFFICE FOR PSO AND DPP OFFICE AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost


Sub-Total

$ - $ 50.91 $ 50.91 $ 9,418.35

$ - $ 53.46 $ 53.46 $ 3,100.68

$ - $ 55.97 $ 55.97 $ 3,638.05

$ - $ 53.46 $ 53.46 $ 11,440.44

$ - $ 9.65 $ 9.65 $ 1,103.00

$ - $ 53.46 $ 53.46 $ 6,842.88

$ - $ 56.37 $ 56.37 $ 1,127.40

$ - $ 56.37 $ 56.37 $ 394.59

$ 53,029.37

6. SOLID PLASTER Page 75


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
Hardware 1%
General

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2 Refer to the General and Special


Conditions of the contract and
tender and to the Preliminary and
General section of the Specification

Method of measurement

3 This Bill of Quantities has been


prepared generally in accordance
with NZS 4202: 1995 Standard
Method of measurement of Building
Works

4 Refer to the General rules of the


NZS 4202: 1995 Standard Method
of Measurement of Building Works

Measurement and Price

5 The rates shall include for all labour,


cutting, notching, boring or checking
for ventilation, framing to other
timbers, packings and wedges as
required, morticing, tenoning, arris
rounding, thicknessing or guaging
where required and all other
machinging

6 All finishing timbers or timber


described as 'dressed' shall include
for machine dressing and hand
finishing

7. CARPENTRY Page 76
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
7 The sizes given of thicknessed,
gauged or dressed timbers are
nominal sizes. Where finished sizes
are required these are described as
(fin)

8 Damp proof course shall be two ply


malthoid

9 All timbers shall be treated as


specified and strength grade F1
unless otherwise described

10 The rates shall include for all nails,


screws, plugs and other fixings.
Where timbers are screwed and / or
plugged they are described as such
and the rates shall include for the
screws and / or plugs.

11 Where timbers are bolted, the bolts,


Dynabolts or Ramset are measured
separately. The rates for bolts and
Dynabolts shall include for boring
the timber, for necessary nuts and
washers and for building in, casting
in and recessing heads as required

Structural Steel
Structural steel is included in this
section :-
12 Weights are calculated from
standard average weights given in
the Manufactures tables and no
allowance has been made for rolling
margin

12 The rates shall include for all labour,


supply, fabrication, delievery,
hoisting and erection

7. CARPENTRY Page 77
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
ROOF FRAMING

The follwing roof memberz erected


approximately 6.600m above
ground floor level

14 125 x 50 Purlin strapped in position 254.00 m $ 31.20 $ 3.12

15 125 x 50 stiffner to purlins 188.00 m $ 31.20 $ 3.12

16 150 UB 75 rafter anchor to concrete 1806.00 KG $ 200.00 $ 20.00


column with fish tail cleat and bolts

17 60.00 no $ 68.00 $ 6.80


M16 x 400mm U Bolts with nuts and
washer, cast into RC columns and
fixed to 150 UB 75 rafters

18 16mm dia x 150mm long anchor bolt 80.00 no $ 13.00 $ 0.13

19 450x50x6mm thick fish tail cleat with 62.00 no $ 226.00 $ 22.60


2 holes for M16 bolts

20 M16 bolts, nuts and washer 120 no $ 11.00 $ 0.11

21 450mmx250mmx20mm thick base 12 no $ 261.25 $ 2.61


plate drilled with 2 no. holes for M20
bolts

22 250mmx250mmx20mm thick base 18 no $ 152.25 $ 1.52


plate drilled with 2 no. holes for M20
bolts

23 M20x 400mm long bolts or 126 no $ 32.40 $ 0.32


equivalent fixed 20mm thk base
plate to RC column

7. CARPENTRY Page 78
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
24 Allow for 150x100x 10mm thk cleats 1.00 item $ 20,382.36 $ -
with associate cutting and drilling for
2 no 12mm dia holes, site welding
and M12 x75mm bolts to purlin and
rafter fixing. Refer to drawing for
detail and workmanship.

150x100x10mmthk cleat 121 no 98


M12 x75mm bolts nuts and washer 242 no 9.9
Drilling for m12 bolts 242 holes 4
Cutting 121 cuts 6
Welding rod 1 box 380

CEILING FRAMING

25 50 x 50 Nogging 291.00 m $ 14.96 $ 1.50

26 150 x 50 framing fixed to roof 299.00 m $ 37.57 $ 3.76


concrete beam

27 30 x 1.2 galvanised straps span as 50.00 m $ 11.93 $ 0.12


diagonal bracing

28 100x50 vasa timber wall framing 338.00 m $ 24.96 $ 2.50

WALL FRAMING (GL & L1)

29 100X50 hardwood top plate 68 m $ 28.46 $ 2.85

30 100x50 hardwood bottom plate 54 m $ 28.46 $ 2.85

31 100x50 studs and noggings 420 m $ 28.46 $ 2.85

EXTERIOR FINISHES

32 75 x 20 Eave battens 318.00 m $ 914.00 91.40

33 250 x 25 Fascia board 74.00 m $ 67.03 $ 6.70

7. CARPENTRY Page 79
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
34 Allow for fabricated steel lattice at 1 item $ -
front of building, inclusive of all site
fabrication, hoisting, erection and
fixing in position. Refer to drawing
for fabrication layout plan
100 SHS x 3.5mm thk 154 m $ 63.75 $ 3.19
Anti-rust paint 16 m² $ 50.00 $ 0.80
Welding rod 1 box $ 380.00 $ 19.00
M16x110 dyna bolt 112 pcs $ 12.20 $ 0.61
Driliing for M16 bolts 112 holes $ 4.00
Cutting for MS Plate 112 cuts $ 6.00
100x100x6mm thick base plate 36 pcs $ 29.30

35 1 item $ 21,837.80

Allow for 50 SHS stairs railings and


posts to main entry and 2 stairs to
topfloor . Including bottom posts
steel plates with associate drillings,
site fabrications and dyna bolts,
anti-rust painting and all other work
required to complete the stairs
railing work. Refer to stairs drawing
for detail.

50 SHS x3.5mm thk 154 m $ 63.75 $ 6.38

Anti-rust paint 32.4 m² $ 50.00 $ 1.62


Welding rod 1 box $ 380.00 $ 19.00

M12x75 dyna bolt 144 pcs $ 5.60 $ 0.28


Driliing for M12 bolts 144 holes $ 4.00
Cutting for MS Plate 72 cuts $ 6.00
100x100x6mm thick base plate 36 pcs $ 29.30

INTERIOR FINISHES (GL&L1)

36 1/4 Round Cornice to FC ceiling 50.20 m $ 0.42


lining $ 4.18

37 100 x 25 timber skirting fixed to 296.00 m $ 25.67 $ 2.57


bottom walls

7. CARPENTRY Page 80
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Desription Qty Unit M


Rate/Unit Wastage
7 CARPENTRY Timber 10%
38 6mm thick FC hard board to 38.00 m2 $ 59.00 $ 5.90
bath/toilet rooms ceiling linings and
stairs landing ceiling linings at top
floor

39 m² $ 4.30
10mm Gyprock to interior ceiling linin 324 $ 43.00

40 12mm Gyprock to interior walls 194.2 m² $ 68.00 $ 6.80


lining

41 Allow for gyprock accessories, 1 item $ 14,673.23 $ -


inclusive of cornice, paper tape,
adhesive, sander etc..
Gyprock cornice 274.8 m 27.78 $ 2.78
Paper tape 4 rolls 70 $ 7.00
Stud adhesive (5.5kg) 7 ptks 260 $ 26.00
Sand Paper large 3 pcs 141 $ 14.10
Board knife 2 pcs 310 $ 15.50
Corner tool 2 pcs 267 $ 26.70

42 6mm thick FC board internal wall 24.2 m² $ 59.03 $ 5.90


lining to kitchen area walls

Windows and Door frames


43 144x44 window frames 52 m $ 42.79 $ 4.28

44 144x44 door frames 92 m $ 42.79 $ 4.28

HARDWARE

45 Allow a PC Sum of $2000-00 (Two sum


thousand dollars) for the supply and
installation of all hardware

AMOUNT OF CARPENTRY
CARRIED TO SUMMARY

7. CARPENTRY Page 81
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman
5% 20% 8 $ 25.00

7. CARPENTRY Page 82
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman

7. CARPENTRY Page 83
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman

$ 1.56 $ 6.24 $ 42.12 0.12 $ 3.00

$ 1.56 $ 40.00 $ 75.88 0.12 $ 3.00

$ 10.00 $ 40.00 $ 270.00 0.20 $ 5.00

$ 13.60 $ 88.40 0.5 $ 12.50

$ 0.65 $ 2.60 $ 16.38 0.50 $ 12.50

$ 11.30 $ 45.20 $ 305.10 0.16 $ 4.00 $ -

$ - $ 2.20 $ 13.31 0.5 $ 12.50 $ -

$ - $ 52.25 $ 316.11 0.3 $ 7.50 $ -

$ - $ 30.45 $ 184.22 0.3 $ 7.50 $ -

$ - $ 6.48 $ 39.20 0.5 $ 12.50 $ -

7. CARPENTRY Page 84
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman
$ - $ - $ 20,382.36 0 $ - $ -

$ 19.60 $ 117.60 0.22 $ 5.50


$ 1.98 $ 11.88 0.02 $ 0.50
$ 0.80 $ 4.80 $ -
$ 1.20 $ 7.20 $ -
$ 76.00 $ 456.00 0.1 $ 2.50

$ 0.75 $ 2.99 $ 20.20 0.20 $ 5.00

$ 1.88 $ 7.51 $ 50.72 0.20 $ 5.00

$ 0.60 $ 2.39 $ 15.03 0.12 $ 3.00

1.248 4.992 $ 33.70 0.2 $ 5.00

$ 1.42 $ 5.69 $ 38.42 0.2 $ 5.00

$ 1.42 $ 5.69 $ 38.42 0.2 $ 5.00

$ 1.42 $ 5.69 $ 38.42 0.2 $ 5.00

$ 45.70 $ 182.80 $ 1,233.90 0.26 $ 6.50

$ 3.35 $ 13.41 $ 90.49 0.28 $ 7.00

7. CARPENTRY Page 85
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman
$ 20,640.94 $ 20,640.94

12.75 $ 79.69 0.23 $ 5.75


$ 10.00 $ 60.80 0.23 $ 5.75
$ 76.00 $ 475.00 $ -
$ 2.44 $ 15.25 0.50 $ 12.50
$ 4.00 $ -
$ 6.00 $ -
$ 5.86 $ 35.16 0.50 $ 12.50

$ 21,837.80

$ 12.75 $ 82.88 0.23 $ 5.75

$ 10.00 $ 61.62 0.23 $ 5.75


$ 76.00 $ 475.00 $ -

$ 1.12 $ 7.00 0.50 $ 12.50


$ 4.00 $ -
$ 6.00 $ -
$ 5.86 $ 35.16 0.50 $ 12.50

$ 0.21
$ 0.84 $ 5.64 0.12 $ 4.18

$ 1.28 $ 5.13 $ 34.65 0.26 $ 6.50

7. CARPENTRY Page 86
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard hours
5% 20% Hours Labour Tradsman
$ 2.95 $ 11.80 $ 79.65 0.60 $ 15.00

$ 2.15
8.6 58.05 0.6 $ 15.00

$ 3.40 $ 13.60 $ 91.80 0.6 $ 15.00

$ - $ - $ - 0 $ -

$ 5.56 $ 36.11
$ 14.00 $ 91.00
$ 52.00 $ 338.00
$ 28.20 $ 183.30
$ 62.00 $ 387.50
$ 53.40 $ 347.10

$ 2.95 11.806 $ 79.69 0.6 $ 15.00

$ 2.14 $ 8.56 $ 57.77 1.2 $ 30.00

$ 2.14 $ 8.56 $ 57.77 1 $ 25.00

7. CARPENTRY Page 87
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total
$ 30.00

7. CARPENTRY Page 88
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total

7. CARPENTRY Page 89
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total

$ 3.00 $ - $ - $ - $ - $ -

$ 3.00 $ - $ - $ - $ - $ -

$ 5.00 $ - $ - $ - $ - $ -

$ 12.50 0 $ -

$ 12.50 $ - $ - $ - $ - $ -

$ - $ 4.00 $ - $ - $ - $ - $ -

$ - $ 12.50 $ - $ - $ - $ - $ - $ -

$ - $ 7.50 $ - $ -

$ - $ 7.50 $ - $ -

$ - $ 12.50 $ - $ -

7. CARPENTRY Page 90
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total
$ - $ -

$ 5.50
$ 0.50
$ -
$ -
$ 2.50

$ 5.00 $ - $ - $ -

$ 5.00 $ - $ - $ -

$ 3.00 $ - $ - $ -

$ 5.00 $ - $ - $ - $ - $ - $ -

$ 5.00

$ 5.00

$ 5.00

$ 6.50 $ - $ - $ -

$ 7.00 $ - $ - $ -

7. CARPENTRY Page 91
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total
$ - $ - $ - $ -

$ 5.75
$ 5.75
$ -
$ 12.50
$ -
$ -
$ 12.50

$ 5.75

$ 5.75
$ -

$ 12.50
$ -
$ -
$ 12.50

$ 4.18 $ - $ - $ - $ - $ -

$ 6.50 $ - $ - $ - $ - $ -

7. CARPENTRY Page 92
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

abor Equipment Others


rd hours hrs rate Sub-Total Overhead P&G Sub-Total
Foreman Sub-Total
$ 15.00 $ - $ - $ - $ - $ -

$ - $ - $ - $ - $ -
$ 15.00 $ -

$ 15.00 $ - $ - $ - $ - $ - $ -

$ - 0 $ - $ - $ - $ - $ -

$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -
$ - $ - $ -

$ 15.00 0 $ - $ - $ - $ - $ -

$ 30.00

$ 25.00

7. CARPENTRY Page 93
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

7. CARPENTRY Page 94
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

7. CARPENTRY Page 95
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

$ 45.12 $ 45.12 $ 11,460.48

$ 78.88 $ 78.88 $ 14,829.44

$ 275.00 $ 275.00 $ 496,650.00

$ 100.90 $ 100.90 $ 6,054.00

$ 28.88 $ 28.88 $ 2,310.40

$ 309.10 $ 309.10 $ 19,164.20

$ 25.81 $ 25.81 $ 3,097.20

$ 323.61 $ 323.61 $ 3,883.35

$ 191.72 $ 191.72 $ 3,451.01

$ 51.70 $ 51.70 $ 6,514.70

7. CARPENTRY Page 96
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

$ 20,382.36 $ 20,382.36 $ 20,382.36

$ 123.10 $ 14,895.10
$ 12.38 $ 2,995.96
$ 4.80 $ 1,161.60
$ 7.20 $ 871.20
$ 458.50 $ 458.50
$ 20,382.36

$ 25.20 $ 25.20 $ 7,332.04

$ 55.72 $ 55.72 $ 16,660.13

$ 18.03 $ 18.03 $ 901.59

$ 38.70 $ 38.70 $ 13,079.25

$ 43.42 $ 43.42 $ 2,952.63

$ 43.42 $ 43.42 $ 2,344.73

$ 43.42 $ 43.42 $ 18,236.82

$ 1,240.40 $ 1,240.40 $ 394,447.20

$ 97.49 $ 97.49 $ 7,214.30

7. CARPENTRY Page 97
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

$ 20,640.94 $ 20,640.94 $ 20,640.94

$ 85.44 $ 13,157.38
$ 66.55 $ 1,064.80
$ 475.00 $ 475.00
$ 27.75 $ 3,108.00
$ 4.00 $ 448.00
$ 6.00 $ 672.00
$ 47.66 $ 1,715.76
$ 20,640.94

$ 21,837.80 $ 21,837.80 $ 21,837.80

$ 88.63 $ 13,648.25

$ 67.37 $ 2,182.79
$ 475.00 $ 475.00

$ 19.50 $ 2,808.00
$ 4.00 $ 576.00
$ 6.00 $ 432.00
$ 47.66 $ 1,715.76
$ 21,837.80

$ 9.82 $ 9.82 $ 493.11

$ 41.15 $ 41.15 $ 12,181.73

7. CARPENTRY Page 98
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

$ 94.65 $ 94.65 $ 3,596.70

$ 58.05
$ 58.05 $ 18,808.20

$ 106.80 $ 106.80 $ 20,740.56

$ -
$ - $ 14,673.23 $ 14,673.23

$ 36.11 $ 9,924.13
$ 91.00 $ 364.00
$ 338.00 $ 2,366.00
$ 183.30 $ 549.90
$ 387.50 $ 775.00
$ 347.10 $ 694.20
$ - $ 14,673.23

$ 94.69 $ 94.69 $ 2,291.51

$ 87.77 $ 87.77 $ 4,563.86

$ 82.77 $ 82.77 $ 7,614.52

$ 2,000.00 $ 2,000.00

$ 1,180,407.98

7. CARPENTRY Page 99
BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Materi
Items Description Quantity Unit

8 JOINERY Rate/Unit Wastage


Timber 5%
General Hardware 1%
1
Refer to the drawings and Specification
for full details and descriptions of
materials and workmanship

2
Refer to the General and Special
Conditions of contract and Tender and
to the Preliminary and General section
of the Specification

Method Of Measurement
3
This Bill of Quantities has been
prepared generally in accordance with
NZS 4202:1995 Standard Method of
measurement of Building Works, but no
deviation from same shall form the
basis of a claim

4 Refer to the General Rules of the NZS


4202:1995 Standard Method of
Measurement of Building Works

5 All timber shall be dressed and the sizes


stated are nominal except where
described as (fin) finished

6
The rates for joinery items, except
where otherwise described, shall
include for supply and delivery to site,
hanging,fixing or placing in position

7
The rates shall include for all nails,
screws, plugs and other fixings, framing
to other timbers, and all machining,
arris-rounding, grooving, sinking,
rebating, throating etc., and assembly
joints where required

8. JOINERY Page 100


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Materi
Items Description Quantity Unit

8 JOINERY Rate/Unit Wastage


Timber 5%
8
The rates shall include for re-assembly
or part assembly on site as necessary

9 The rates for joinery fittings shall


include for all necessary hardware

10 The rates shall include for one coat of


sanding sealer, as specified

DOORS
11 Doors and frame sizes are given in note
order of Height x Width

12 note
Flush doors shall have 6mm thick
hardwood clashing strips to all edge

Exterior & Interior


13
45mm thick solid core door, size
5 no. $ 1,320.00 $ 66.00
2.040m x 0.830m, both sides faced
timber facings (single door) with
approved hardware

GROND FLOOR
Kitchen sink Bench
14 1 item $ 3,265.23
Construct 2 meter long x 0.42meter
wide x 0.9meter high kitchen sink
bench unit from 15mm plywood with
plywood doors with conceal hinges and
hardwares, and intermediate shelving
bottom support constructed from 100 x
44 DAR vasa, complete with formica
laminated at top, commencing from
both ends of single stainless sink to
each end of bench.

15mm plywood 2 sheets $ 385.00 $ 19.25


44x44 timber 20 m $ 14.48 $ 0.72
Self taping screw 3 pkt $ 28.00 $ 1.40
Formica 1 sheets $ 360.00 $ 18.00

8. JOINERY Page 101


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Materi
Items Description Quantity Unit

8 JOINERY Rate/Unit Wastage


Timber 5%
Conceal Hinges 4 pairs $ 68.00 $ 0.68
Handle 4 pcs $ 64.00 $ 0.64
Forica glue 1 l $ 53.00 $ 2.65
4" Jolt head nail 1 kg $ 20.00 $ 1.00
2" Jolt head nail 1 kg $ 20.00 $ 1.00
75x44 6.5 m $ 22.47 $ 1.12

Storage Room Shelf


15 1 item $ 25,420.87

Construct Storage shelf unit of overal


length of aprox. 4.9m long by 0.42m
wide and 1.64m long by 0.42m wide
along wall in storage room as shown in
the drawing from 75x44 and 44x44
dressed hardwood timber and 15mm
plywood with self-tapping screws and
wood glue and other appropriate
fixtures. With intermediate bottom
support constructed from 100x44 dar
vasa. Apply varnish to finishing and
make good. Refer to drawing for layout
plan

15mm plywood 12 shts $ 385.00 $ 19.25


44x44 hardwd timber 51 m $ 14.48 $ 0.72
75x44 hardwd timber 92 m $ 22.47 $ 1.12
Self taping screw 3 pkt $ 28.00 $ 0.28
Clear varnish 97 m² $ 102.00 $ 5.10
4" Jolt head nail 4 kg $ 20.00 $ 0.20
2" Jolt head nail 4 kg $ 20.00 $ 0.20
3" jolt head nail 4 kg $ 20.00 $ 0.20
Sand paper fine 3 pcs $ 45.00 $ 0.45
Sand paper rough 3 pcs $ 45.00 $ 0.45
Wood glue 4 liter $ 102.00 $ 1.02
Vanish brush 4 pcs $ 24.00 $ 0.24

Reveption Counter

8. JOINERY Page 102


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Materi
Items Description Quantity Unit

8 JOINERY Rate/Unit Wastage


Timber 5%
Construct reception counter 1.8m long 1 item $ 2,281.25
by 0.5m wide with 100x44 timber,
18mm plywood, complete with formica
laminated to tall sides, top and under .
Allow for fixing and other necessary
items required to finisf this part of
work. Complete with good finishing

15mm ply 2 sheets $ 435.00 $ 21.75


100x44 timber 6 m $ 28.46 $ 1.42
Formica 2 sheets $ 240.00 $ 12.00
4'' JH nail 1 kg $ 20.00
3'' JH nail 1 kg $ 20.00
Formica glues 1 bottle $ 46.00 $ 2.30
Self tapping screw 1 pkt $ 30.00 $ 0.30
Sanding belt 1 no $ 40.00

TOP FLOOR
Library Bookshelf
16 1 item $ 16,891.79
Construct book shelf unit of overal
length of aprox. 6.9m long by 0.3m
wide by 2m high along wall in library as
shown in the drawing from with 18mm
plywood with self-tapping screw and
wood glue. With intermediate bottom
support constructed from 100x50 dar
vasa. Apply varnish to finishing and
make good. Refer to drawing for layout
plan

18mm plywood 14 sheets 435 $ 21.75


90x44 timber 20 m 22.47 $ 1.12
Self taping screw 6 pkts 28 $ 0.28
Wood glue 8 lietrs 102 $ 5.10
Varnish 90 m² 50 $ 2.50
4" Jolt head nail 2 kg 24 $ 1.20
2" Jolt head nail 4 kg 20 $ 1.00
3" jolt head nail 4 kg 20 $ 1.00
Sanding belt 1 no

17 Ditto but 2 no. 1.9m by 0.3m wide 1 item $ 10,085.49


book shelf. Refer to drawing for layout
plan
18mm plywood 8 sheets $ 435.00 $ 21.75

8. JOINERY Page 103


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Materi
Items Description Quantity Unit

8 JOINERY Rate/Unit Wastage


Timber 5%
90x44 timber 10 m $ 22.47 $ 1.12
Self taping screw 5 pkts $ 28.00 $ 0.28
Wood glue 4 liters $ 102.00 $ 5.10
Varnish 43 m² $ 50.00 $ 2.50
4" Jolt head nail 2 kg $ 24.00 $ 0.24
2" Jolt head nail 3 kg $ 20.00 $ 0.20
3" jolt head nail 3 kg $ 20.00 $ 0.20
Sanding belt 1 belt $ 40.00 $ 0.40

Kitchen Sink Bench


18 Construct 2 meter long x 0.42meter 1 item $ 3,265.23
wide x 0.85meter high kitchen sink
bench unit from 15mm plywood with
plywood doors with conceal hinges and
hardwares, and intermediate shelving
bottom support constructed from 100 x
44 DAR vasa, complete with formica
laminated at top, commencing from
both ends of single stainless sink to
ends of bench .

15mm plywood 2 sheets $ 385.00 $ 19.25


44x44 timber 20 m $ 14.48 $ 0.72
Self taping screw 3 pkt $ 28.00 $ 1.40
Formica 1 sheets $ 360.00 $ 18.00
Conceal Hinges 4 pairs $ 68.00 $ 0.68
Handle 4 pcs $ 64.00 $ 0.64
Forica glue 1 l $ 53.00 $ 2.65
4" Jolt head nail 1 kg $ 20.00 $ 1.00
2" Jolt head nail 1 kg $ 20.00 $ 1.00
75x44 6.5 m $ 22.47 $ 1.12
Sanding belt 1 no $ 40.00 $ -

AMOUNT OF JOINERY CARRIED TO SUMMARY

8. JOINERY Page 104


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Constant

Fixing Transport Sub-Total Standard hours


5% 20% Hours Labour Tradsman Foreman
5% 20% Average rate $ 25.00

8. JOINERY Page 105


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Constant

Fixing Transport Sub-Total Standard hours


5% 20% Hours Labour Tradsman Foreman

$ 66.00 $ 264.00 $ 1,716.00 1.5 $ 37.50

$ 3,265.23

$ 19.25 $ 77.00 $ 500.50 1.2


$ 0.72 $ 2.90 $ 18.82 0.12
$ 1.40 $ 5.60 $ 36.40 0.1
$ 18.00 $ 72.00 $ 468.00 1

8. JOINERY Page 106


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Constant

Fixing Transport Sub-Total Standard hours


5% 20% Hours Labour Tradsman Foreman
$ 3.40 $ 13.60 $ 85.68 0.5
$ 3.20 $ 12.80 $ 80.64 1
$ 2.65 $ 10.60 $ 68.90 0.4
$ 1.00 $ 4.00 $ 26.00 0.05
$ 1.00 $ 4.00 $ 26.00 0.05
$ 1.12 $ 4.49 $ 29.21 0.12

$ 25,420.87

$ 19.25 $ 77.00 $ 500.50 1.2 $ 30.00


$ 0.72 $ 2.90 $ 18.82 0.12 $ 3.00
$ 1.12 $ 4.49 $ 29.21 0.12 $ 3.00
$ 1.40 $ 5.60 $ 35.28 0.4 $ 10.00
$ 5.10 $ 20.40 $ 132.60 0.13 $ 3.25
$ 1.00 $ 4.00 $ 25.20 0.3 $ 7.50
$ 1.00 $ 4.00 $ 25.20 0.3 $ 7.50
$ 1.00 $ 4.00 $ 25.20 0.3 $ 7.50
$ 2.25 $ 9.00 $ 56.70 1 $ 25.00
$ 2.25 $ 9.00 $ 56.70 0.3 $ 7.50
$ 5.10 $ 20.40 $ 128.52 1 $ 25.00
$ 1.20 $ 4.80 $ 30.24 1 $ 25.00

8. JOINERY Page 107


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Constant

Fixing Transport Sub-Total Standard hours


5% 20% Hours Labour Tradsman Foreman
$ 2,281.25

$ 87.00 $ 543.75 1.2 $ 30.00


$ 5.69 $ 35.58 0.12 $ 3.00
$ 48.00 $ 300.00 1.2 $ 30.00
$ 4.00 $ 24.00 0.3 $ 7.50
$ 4.00 $ 24.00 0.3 $ 7.50
$ 9.20 $ 57.50 0.3 $ 7.50
$ 6.00 $ 36.30 0.2 $ 5.00
$ 8.00 $ 48.00 1 $ 25.00

$ 16,891.79

$ 21.75 $ 87.00 $ 565.50 1.2


$ 0.06 $ 4.49 $ 28.14 0.12
$ 1.40 $ 1.80 $ 31.48 0.4
$ 0.26 $ 20.40 $ 127.76 0.13
$ 2.50 $ 10.00 $ 65.00 0.2
$ 4.80 $ 30.00 0.3
$ 4.00 $ 25.00 0.3
$ 4.00 $ 25.00 0.3

$ 10,085.49

$ 21.75 $ 87.00 $ 565.50 0.20 $ 5.00

8. JOINERY Page 108


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Constant

Fixing Transport Sub-Total Standard hours


5% 20% Hours Labour Tradsman Foreman
$ 1.12 $ 4.49 $ 29.21 1.00 $ 25.00
$ 1.40 $ 5.60 $ 35.28 1.00 $ 25.00
$ 5.10 $ 20.40 $ 132.60 1.00 $ 25.00
$ 2.50 $ 10.00 $ 65.00 0.80 $ 20.00
$ 1.20 $ 4.80 $ 30.24 0.5 $ 12.50
$ 1.00 $ 4.00 $ 25.20 0.5 $ 12.50
$ 1.00 $ 4.00 $ 25.20 0.6 $ 15.00
$ 8.00 $ 48.40 1 $ 25.00

$ 3,265.23

$ 19.25 $ 77.00 $ 500.50 1.20 $ - $ - $ -


$ 0.72 $ 2.90 $ 18.82 0.12 $ - $ - $ -
$ 1.40 $ 5.60 $ 36.40 0.10 $ - $ - $ -
$ 18.00 $ 72.00 $ 468.00 1.00 $ - $ - $ -
$ 3.40 $ 13.60 $ 85.68 0.50 $ - $ - $ -
$ 3.20 $ 12.80 $ 80.64 1.00 $ - $ - $ -
$ 2.65 $ 10.60 $ 68.90 0.40 $ - $ - $ -
$ 1.00 $ 4.00 $ 26.00 0.05 $ - $ - $ -
$ 1.00 $ 4.00 $ 26.00 0.05 $ - $ - $ -
$ 1.12 $ 4.49 $ 29.21 0.12 $ - $ - $ -
$ - $ - $ - 0.00 $ - $ - $ -

8. JOINERY Page 109


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

nstant Equipment Others

hours hrs rate Sub-Total Overhead P&G


Sub-Total 10% 4.50%

8. JOINERY Page 110


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

nstant Equipment Others

hours hrs rate Sub-Total Overhead P&G


Sub-Total 10% 4.50%

$ 37.50

$ 30.00
$ 3.00
$ 2.50
$ 25.00

8. JOINERY Page 111


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

nstant Equipment Others

hours hrs rate Sub-Total Overhead P&G


Sub-Total 10% 4.50%
$ 12.50
$ 25.00
$ 10.00
$ 1.25
$ 1.25
$ 3.00

$ 30.00 0 0 0
$ 3.00 0 0 0
$ 3.00 0 0 0
$ 10.00 0 0 0
$ 3.25 0 0 0
$ 7.50 0 0 0
$ 7.50 0 0 0
$ 7.50 0 0 0
$ 25.00 0 0 0
$ 7.50 0 0 0
$ 25.00 0 0 0
$ 25.00 0 0 0

8. JOINERY Page 112


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

nstant Equipment Others

hours hrs rate Sub-Total Overhead P&G


Sub-Total 10% 4.50%

$ 30.00
$ 3.00
$ 30.00
$ 7.50
$ 7.50
$ 7.50
$ 5.00
$ 25.00

$ 30.00
$ 3.00
$ 10.00
$ 3.25
$ 5.00
$ 7.50
$ 7.50
$ 7.50

$ 5.00

8. JOINERY Page 113


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

nstant Equipment Others

hours hrs rate Sub-Total Overhead P&G


Sub-Total 10% 4.50%
$ 25.00
$ 25.00
$ 25.00
$ 20.00
$ 12.50
$ 12.50
$ 15.00
$ 25.00

$ 30.00 $ - $ - $ - $ - $ -
$ 3.00 $ - $ - $ - $ - $ -
$ 2.50 $ - $ - $ - $ - $ -
$ 25.00 $ - $ - $ - $ - $ -
$ 12.50 $ - $ - $ - $ - $ -
$ 25.00 $ - $ - $ - $ - $ -
$ 10.00 $ - $ - $ - $ - $ -
$ 1.25 $ - $ - $ - $ - $ -
$ 1.25 $ - $ - $ - $ - $ -
$ 3.00 $ - $ - $ - $ - $ -
$ - $ - $ - $ - $ - $ -

8. JOINERY Page 114


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost

Sub-Total

8. JOINERY Page 115


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost

Sub-Total

$ 1,753.50 $ 1,753.50 $ 8,767.50

$ 3,265.23 $ 3,265.23 $ 3,265.23

$ 530.50 $ 1,061.00
$ 21.82 $ 436.48
$ 38.90 $ 116.70
$ 493.00 $ 493.00

8. JOINERY Page 116


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost

Sub-Total

$ 98.18 $ 392.72
$ 105.64 $ 422.56
$ 78.90 $ 78.90
$ 27.25 $ 27.25
$ 27.25 $ 27.25
$ 32.21 $ 209.37
$ 3,265.23

$ - $ 25,420.87 $ 25,420.87 $ 25,420.87

$ 530.50 $ 6,366.00
$ 21.82 $ 1,113.02
$ 32.21 $ 2,963.41
$ 45.28 $ 135.84
$ 135.85 $ 13,177.45
$ 32.70 $ 130.80
$ 32.70 $ 130.80
$ 32.70 $ 130.80
$ 81.70 $ 245.10
$ 64.20 $ 192.60
$ 153.52 $ 614.08
$ 55.24 $ 220.96
$ 25,420.87

8. JOINERY Page 117


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost

Sub-Total

$ 2,281.25 $ 2,281.25 $ 2,281.25

$ 573.75 $ 1,147.50
$ 38.58 $ 231.45
$ 330.00 $ 660.00
$ 31.50 $ 31.50
$ 31.50 $ 31.50
$ 65.00 $ 65.00
$ 41.30 $ 41.30
$ 73.00 $ 73.00
$ 2,281.25

$ 16,891.79 $ 16,891.79 $ 16,891.79

$ 595.50 $ 8,337.00
$ 31.14 $ 622.87
$ 41.48 $ 248.88
$ 131.01 $ 1,048.04
$ 70.00 $ 6,300.00
$ 37.50 $ 75.00
$ 32.50 $ 130.00
$ 32.50 $ 130.00
$ 16,891.79

$ 10,085.49 $ 10,085.49

$ 570.50 $ 4,564.00

8. JOINERY Page 118


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Others Total Rate Cost

Sub-Total

$ 54.21 $ 542.11
$ 60.28 $ 301.40
$ 157.60 $ 630.40
$ 85.00 $ 3,655.00
$ 42.74 $ 85.48
$ 37.70 $ 113.10
$ 40.20 $ 120.60
$ 73.40 $ 73.40
$ 10,085.49

$ 3,265.23 $ 3,265.23 $ 3,265.23

$ - $ 530.50 $ 1,061.00
$ - $ 21.82 $ 436.48
$ - $ 38.90 $ 116.70
$ - $ 493.00 $ 493.00
$ - $ 98.18 $ 392.72
$ - $ 105.64 $ 422.56
$ - $ 78.90 $ 78.90
$ - $ 27.25 $ 27.25
$ - $ 27.25 $ 27.25
$ - $ 32.21 $ 209.37
$ - $ - $ 3,265.23

$ 69,977.36

8. JOINERY Page 119


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
9 ROOFING 1%

General

1 Refer to the drawings and Specification for full


details and descriptions of materials and
workmanship

2
Refer to the General and Special Conditions of
the contract and tender and to the Preliminary
and General section of the Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202: 1995
Standard Method of measurement of Building
Works

4 Refer to the General rules of the NZS 4202:


1995 Standard Method of Measurement of
Building Works

Measurement and Price

5 All roofing, building papers, netting etc. have


been measured net with no allowance made
for side or other laps

6 All sealants shall be of an approved type and


compatible with the roof coverings

7 The rates for flashings and gutters shall


include for folding and bending to shape, laps,
joints, expansion joints, soakers, clips,
packers, forming junctions with other flashings
and shaping at angles and ends

METAL ROOFING

8 Roof shall be 0.48mm thick BMT Trimdeck


colorbond steel roofing in single length sheets
fastened to purlins with roofing screw No. 10 x
50 Type 17 screws with total cyclonic
assembly, as:

9. ROOFING Page 120


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
9 ROOFING 1%

Maximum 7.08m Above Ground Floor Level

9 Color Bond Roofing Iron sheets fixed to timber 220 m² 139.84 1.40
purlins with 75mm galv. Roofing screws

FLASHING

10 0.48mm thick trimdeck flashing folded to


profile fixed with roof screws complete with
silicone rubber sealant, as specified

11 22 m $ 49.30 $ 0.49
300x380 Galvanized flashing to roof front.
Refer to drawing section for fixing detail

INSULATION

12 Double sided sisilation 453 laid over bird wire 220 m2 $ 9.10 0.09
netting

13 Galvanised wire mesh netting 220 m2 $ 12.80 0.13

DOWNPIPES AND GUTTERS

14 Storm cloud marley gutter 26 m $ 65.00 0.65

15 100 dia PVC downpipe fixed to reinforced 28 m $ 120.00 1.20


concrete wall with brackets and clips

16 Extra value for 100 dia bends 8 no $ 80.00 0.80

17 Extra value for gutter jointers 4 no $ 74.00 0.74

18 Extra value for gutter stop ends 8 no $ 81.00 0.81

19 Extra value for rain water head 4 no $ 102.00 1.02

20 Connect 100 dia downpipe to 150 dia 8 no $ 124.00 1.24


stormwater pipework

21 Allow clips, Solvent cement and other 1 item $ 500.00 $ 5.00


necessary items required to finish
guttering works

9. ROOFING Page 121


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
9 ROOFING 1%

AMOUNT OF ROOFING CARRIED TO SUMMARY

9. ROOFING Page 122


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equip


Fixing Transport Sub-Total Hourly Rate $ 25.00 hrs
5% 20% Men Labour Tradesman Foreman Sub-Total
Average Rate $ 25.00

9. ROOFING Page 123


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equip


Fixing Transport Sub-Total Hourly Rate $ 25.00 hrs
5% 20% Men Labour Tradesman Foreman Sub-Total

6.992 27.968 176.20 1.99 $ - $ 49.75 $ - $ 49.75 $ -

$ 2.47 $ 9.86 $ 62.12 1.6 $ 40.00 $ 40.00 $ -

0.455 1.82 11.47 0.3 $ 7.50 $ 7.50 0

$ 0.64 $ 2.56 $ 16.13 0.5 $ 12.50 $ 12.50

$ 3.25 $ 13.00 $ 81.90 1.8 $ 45.00 $ 45.00

$ 6.00 $ 24.00 $ 151.20 1.7 $ 42.50 $ 42.50

$ -
$ 4.00 $ 16.00 $ 100.80 0.2 $ 5.00 $ 5.00
$ -
$ 3.70 $ 14.80 $ 93.24 0.2 $ 5.00 $ 5.00
$ -
$ 4.05 $ 16.20 $ 102.06 0.2 $ 5.00 $ 5.00
$ -
$ 5.10 $ 20.40 $ 128.52 0.2 $ 5.00 $ 5.00
$ -
$ 6.20 $ 24.80 $ 156.24 0.5 $ 12.50 $ 12.50

$ -
$ 25.00 $ 100.00 $ 630.00 8 $ 200.00 $ 200.00

9. ROOFING Page 124


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equip


Fixing Transport Sub-Total Hourly Rate $ 25.00 hrs
5% 20% Men Labour Tradesman Foreman Sub-Total

9. ROOFING Page 125


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Rate Cost


rate Sub-Total Overhead P&G Sub-Total
10% 4.50%

9. ROOFING Page 126


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Rate Cost


rate Sub-Total Overhead P&G Sub-Total
10% 4.50%

$ - $ - $ - $ - $ 225.95 $ 49,708.65

$ - $ - $ - $ - $ - $ 102.12 $ 2,246.60

0 0 0 0 0 $ 18.97 $ 4,172.52

$ 28.63 $ 6,298.16

$ 126.90 $ 3,299.40

$ 193.70 $ 5,423.60

$ 105.80 $ 846.40

$ 98.24 $ 392.96

$ 107.06 $ 856.48

$ 133.52 $ 534.08

$ 168.74 $ 1,349.92

$ 830.00 $ 830.00

9. ROOFING Page 127


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Rate Cost


rate Sub-Total Overhead P&G Sub-Total
10% 4.50%

$ 75,128.76

9. ROOFING Page 128


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%

General

1
Refer to the drawings and Specification
for full details and descriptions of
materials and workmanship

2 Refer to the General and Special


Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3 This Bill of Quantities has been


prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The rates for pipework shall include for


running joints in the length, for all
holdfasts, straps, brackets, hangers,
clips, etc., and for supporting and fixing
at the centres specified.

6 The rates for pipework less than 25


diameter shall include for all bends,
elbows, tees, junctions, cleaning eyes
and the like.

7 The rates for tees and junctions shall


include for any bends necessary for the
required sweep. The rates for irregular
tees and junctions shall include for any
necessary reducers

10. PLUMBING Page 129


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%
8 The rates for pipework shall include for
sleeving and running pipes through
concrete, blockwork, linings and the
like and for caulking and for all wall and
cover plates and penetration flashings

9 All pipe diameters given are internal,


unless otherwise stated

10 The rates for pipework shall include for


expansion joints

11 The rates for pipework in chases shall


include for filling chase around
pipework with cement mortar on
completion

12 The rates shall include for priming and


painting ferrous metals as specified

13 The rates for pipe insulation shall


include for cutting and trimming around
equipment fixings, valves and the like

14 The rates for insulation to all pipework


shall include for all bends, elbows,
tees, junctions, cleaning eyes, valves
and the like

15 The rates for all flashings and the like


shall include for laps, ends, junctions,
angles, fixing clips and the like

10. PLUMBING Page 130


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%
16 The rates for excavation and trenching
shall include for clearing away all
obstructions, depositing excavated
materials in temporary spoil heaps,
returning, filling and removing surplus
(unless stated otherwise), well ramming
bottom of trenches and keeping free
from water by pumping or approved
methods, including the provision of any
temporary drainage and its subsequent
removal

17 The rates for pipework in ground shall


include for bedding and protection as
specified

18 Allow for labelling and identifying all


pipework, valves, equipment and the
like as specified

19 Allow for providing fire collars to


pipework penetrating fire rated walls,
floors, ceilings, etc., as required by the
installation and as specified

Water Supply

20 Allow for 20mm dux pipe with all


required connections, brackets, and
fittings

21 Allow for 15mm dux pipe, with all 145 m $ 25.20 $ 1.26
required connections, brackets, and
fittings

22 Hand Wash Basin mounted to concrete 4 item $ 830.00 $ 41.50


block wall

23 Waste pipe

24 40mm waste pipe from kitchens to soak 10 m $ 26.00 $ 1.30

25 S-Trap-40mm to 32mm 4 no $ 85.00 $ 4.25

10. PLUMBING Page 131


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%

Sewer pipe

26 100mm dia pipe from ground floor and 12 m $ 105.00 $ 5.25


top floor WCs to septic

27 100mmØ T join 1 no $ 48.00 $ 2.40

28 100mmØ Elbow 6 no $ 58.00 2.9

29 100mmØ Y-Junction 2 no $ 53.00 2.65

30 50mm vent pipe with cap exposed 5 m $ 28.00 1.4


above roof level

31 75mm Ø PVC pipe from inspection box to 6 m $ 90.00 $ 4.50


soak away

32 100mmØ PVC waste pipe from septic to 3.18 m $ 105.00 $ 5.25


soak away

SANITARY FITTINGS

Supply and fix the following:-

33 W.C. pan, secured to concrete floor 4 items 1,508.00 75.40


and connect to 100 pvc drainpipe and
complete with WC cistern

34 Approved seat and cover 4 no. 110.00 5.50

35 Allow Hand Wash Basins mounted to 4 items 1,065.00 53.25


block wall with approved taps, s-trap
and unversal wastes

36 Kitchen double stainless sink 2 no $ 450.00 $ 22.50

37 Kitchen sink tap 2 no $ 95.00 $ 4.75

38 Hand wash basin tap 4 no $ 95.00 0.2

Septic tank, Soakaway & Gully trap

10. PLUMBING Page 132


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%
39
Reinforcement, blockwork and
excavation have been included in the
following section of work.Therefore,
preambles of Reinforcing Steel trade,
blockwork trade and excavation trade
shall be equally binding on the
following works and should be read in
conjunction wastage
1%
SI Standard Type 3 septic and soakaway
40 Excavation for septic and soakaway 37 m³ 0

41 20 Mpa concrete in slab and air tight 3 m³ $ 1,450.00 $ 72.50


and manhole concrete lids (Septic and
soakhole)

42 D12 reinforce Steel vertical bars in 59 kg $ 10.51 $ 0.11


block wall (septic and soakaway)

43 D12 reinforce steel horrizontal bars in 47 kg $ 10.51 $ 0.11


block wall (septic and soakaway)

44 D16 reinforcement steel in soakaway 36 kg 10.55 $ 0.11


base slab, run both ways at 200
centers with 75mm concrete cover

45 D12 steel rod bars in septic base and 123 kg 10.51 $ 0.11
cover slab and soakaway cover slab,
run both ways at 200 centers with
50mm concrete cover

46 Galvanized tie wire (Septic and soakawa 3 kg $ 30.00 $ 0.30

47 200 mm block work (septic and soakawa 27 m² $ 162.50 $ 8.13

48 Fill in 200mm block cells with 17 Mpa 3 m³ $ 970.00 $ 48.50


concrete and mortar bed and plastering
(septic and soakaway)

49 Allow for formwork and other temporary 1 item $ 8,015.64 0


support work required for septic and
soakaway constructions, large stones
and small stones back fill to side of
soakhole and air tight and manhole lid
handles

10. PLUMBING Page 133


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
10 PLUMBING 5%

Form plywood 2 sheets $ 412.00 $ 20.60


2" JH nails 3 kg $ 24.00 $ 1.20
2"x2" timber 18 m $ 11.00 $ 0.55
Large stone 5 m³ $ 250.00 $ 12.50
Small stones 14 m³ $ 250.00 $ 12.50
R10 Steel rod for cover handle 2 m $ 5.83 $ 0.29

AMOUNT OF PLUMBING CARRIED


TO SUMMARY

10. PLUMBING Page 134


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman
Average rat $ 25.00

10. PLUMBING Page 135


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman

10. PLUMBING Page 136


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman

$ 0.25 $ 5.04 $ 31.75 0.15 $ 3.75

$ 8.30 $ 166.00 $ 1,045.80 0.15 $ 3.75

$ 0.26 $ 5.20 $ 32.76 0.2 $ 5.00

$ 0.85 $ 17.00 $ 107.10 0.3 $ 7.50

10. PLUMBING Page 137


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman

$ 1.05 $ 21.00 $ 132.30 0.4 $ 10.00

$ 0.48 $ 9.60 $ 87.00 0.15 $ -

0.58 11.6 $ 87.00 0.15 $ 3.75

0.53 10.6 $ 86.00 0.15 $ 3.75

0.28 5.6 $ 46.00 0.20 $ 5.00

$ 0.90 $ 18.00 $ 113.40 0.21 $ 5.25

$ 1.05 $ 21.00 $ 132.30 0.20 $ 5.00

15.08 1,598.48 3,196.96 2.20 $ 55.00

1.1 22 138.60 0.20 $ 5.00

10.65 213 1,341.90 2.00 $ 50.00

$ 4.50 $ 90.00 $ 567.00 3.00 $ 75.00

$ 0.95 $ 19.00 $ 119.70 0.20 $ 5.00

$ 0.95 $ 19.00 $ 115.15 0.20 $ 5.00

10. PLUMBING Page 138


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman

fixing transport
1% 20%

0 0 $ - 2.20 $ 55.00

$ 14.50 $ 290.00 $ 1,827.00 1.75 $ 43.75

$ 0.11 $ 2.10 $ 12.82 0.25 $ 6.25

$ 0.11 $ 2.10 $ 12.82 0.25 $ 6.25

$ 0.11 $ 2.11 $ 12.87 0.25 $ 6.25

$ 0.11 $ 2.10 $ 12.82 0.25 $ 6.25

$ 0.30 $ 6.00 $ 36.60 0.2 $ 5.00

$ 1.63 $ 32.50 $ 204.75 0.84 $ 21.00

$ 9.70 $ 194.00 $ 1,222.20 0.55 $ 13.75

0 0 $ 8,015.64 $ - 0 0 0

10. PLUMBING Page 139


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
1% 20% Hours/Unit Labour Tradesman Foreman

$ 4.12 $ 82.40 $ 519.12 0.5 $ 12.50


$ 0.24 $ 4.80 $ 30.24 0.3 $ 7.50
$ 0.11 $ 2.20 $ 13.86 0.2 $ 5.00
$ 2.50 $ 50.00 $ 315.00 1 $ 25.00
$ 2.50 $ 50.00 $ 315.00 1 $ 25.00
$ 0.06 $ 1.17 $ 7.35 0.5 $ 12.50

10. PLUMBING Page 140


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

10. PLUMBING Page 141


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

10. PLUMBING Page 142


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

$ 3.75 $ 35.50 $ 35.50 $ 5,147.79

$ 3.75 $ 1,049.55 $ 1,049.55 $ 4,198.20

$ 5.00 $ 37.76 $ 37.76 $ 377.60

$ 7.50 $ 114.60 $ 114.60 $ 458.40

10. PLUMBING Page 143


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

$ 10.00 $ 247.30 $ 379.60 $ 4,555.20

$ - $ 87.00 $ 87.00 $ 87.00

$ 3.75 $ 90.75 $ 90.75 $ 544.50

$ 3.75 $ 89.75 $ 89.75 $ 179.50

$ 5.00 $ 5.00 $ 5.00 $ 25.00

$ 5.25 $ 118.65 $ 118.65 $ 711.90

$ 5.00 $ 137.30 $ 137.30 $ 436.61

$ 55.00 $ 3,251.96 $ 3,251.96 $ 13,007.84

$ 5.00 $ 143.60 $ 143.60 $ 574.40

$ 50.00 $ 1,391.90 $ 1,391.90 $ 5,567.60

$ 75.00 $ 642.00 $ 642.00 $ 1,284.00

$ 5.00 $ 124.70 $ 124.70 $ 249.40

$ 5.00 $ 120.15 $ 120.15 $ 480.60

10. PLUMBING Page 144


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

$ 55.00 $ 55.00 $ 55.00 $ 2,035.00

$ 43.75 $ 1,870.75 $ 1,870.75 $ 5,612.25

$ 6.25 $ 19.07 $ 19.07 $ 1,125.26

$ 6.25 $ 19.07 $ 19.07 $ 896.39

$ 6.25 $ 19.12 $ 19.12 $ 688.36

$ 6.25 $ 19.07 $ 19.07 $ 2,345.88

$ 5.00 $ 41.60 $ 41.60 $ 124.80

$ 21.00 $ 225.75 $ 225.75 $ 6,095.25

$ 13.75 $ 1,235.95 $ 1,235.95 $ 3,707.85

0 0 $ 8,015.64 $ 8,015.64

10. PLUMBING Page 145


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Total Rate Cost

Sub-Total

$ 12.50 $ 531.62 $ 1,063.24


$ 7.50 $ 37.74 $ 113.22
$ 5.00 $ 18.86 $ 339.48
$ 25.00 $ 340.00 $ 1,700.00
$ 25.00 $ 340.00 $ 4,760.00
$ 12.50 $ 19.85 $ 39.70
$ 8,015.64
$ 68,532.22

10. PLUMBING Page 146


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
11 ELECTRICAL SERVICES 5%

General

1 Refer to the drawings and Specification for full


details and descriptions of materials and
workmanship

2 Refer to the General and Special Conditions of


the contract and tender and to the Preliminary
and General section of the Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202: 1995
Standard Method of measurement of Building
Works

4 Refer to the General rules of the NZS 4202: 1995


Standard Method of Measurement of Building
Works
Measurement and Price

5 The rates for sub-circuiting shall include for


conduit systems and accessories, timber battens,
outlets and metal flush boxes, mounting blocks,
cables, fixings and connections only. Switches,
plug sockets, etc. have been measured

6 The rates for sub-circuiting shall include for


providing an earth wire to all outlets

7 The rates shall include for fittings such as roses,


holders, flex and the like

8 Except where otherwise described, all subcircuit


cabling shall be TPS run concealed, and where
within masonry walls shall be TPS enclosed in
rigid PVC conduit

9 The rates for cable connections shall include for


all terminal glands and accessories appropriate to
the type and size of cables

11. ELECTRICAL Page 147


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
11 ELECTRICAL SERVICES 5%
10 The rates shall include for fixing in the structure,
forming all holes and pockets and making good

ELECTRICAL WORK
Mains Supply

11 Allow to supply incoming mains cable from Local 20 m 56.00 2.80


Power Authority Network to new building
complete with all necessary cables, fittings,
connections etc..

13 Meter Box

12 Allow to supply approved type meter box from 1 no 950 47.5


Local Power Authority completed with all
necessary fitting, etc .

Main Switch Boards

13 Approved type meter board complete with fuses, 1 no 2660 133.00


switches, cables etc all required by Local Power
Authority

Earthing MEN

14 Approved size Earthing cable, electrode and clip, 1 item 297.6 14.88
and allow for drillings of holes from main switch
board to sub-main board

GROUND FLOOR

Circuit Wiring

15 All approved cables from the switch board to 102 m 8.5 0.425
ceiling mounted lights

16 All approved cables from the switch board to the 1 item 858 42.9
general purpose outlets (GPO), and Socket
outlets.

Allow for approved conduit pvc pipe with 1 item 420 21


brackets, Tees, bends and all other necessary
items required for coduit installation work

11. ELECTRICAL Page 148


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
11 ELECTRICAL SERVICES 5%

22 The outlets fittings

17 Approved 1200mm ceiling fluorescent lamp with 31 no 210 10.5


36watts and fittings

18 Allow to install approved single gang 1 way light 8 no 40 2


switch with bracket & fitting fix to wall

19 Single gang 2 way light switch with bracket & 5 no 48 2.4


fitting fix to wall

1 item $ 1,255.00 $ 62.75


Allow for approved 1200mm ceiling mounted fan
with one way fan switch and regulator fixed to
wall

Power point fittings

20 Double gang power outlet with bracket and fitting 13 no 105 5.25
fix to wall

TOP FLOOR

21 Circuit Wiring

22 All approved cables from the switch board to 108 m 8.5 0.425
ceiling mounted lights

23 All approved cables from the switch board to 1 item 950 47.5
general purpose outlets (GPO) and Socket
outlets

24 Allow for approved conduit pvc pipe with 1 item 480 24


brackets, Tee, bends and all other necessary
items required for coduit installation work

25 1 item $ 1,255.00 $ 62.75


Allow for approved 1200mm ceiling mounted fans
with one way fan swicth and regular fixed to wall

The outlets fitting

26 Approved 1200mm ceiling fluorescent lamp with 34 no 210 10.5


36watts and fittings

11. ELECTRICAL Page 149


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
11 ELECTRICAL SERVICES 5%
27 Allow to install approved single gang 1 way light 14 no 40 2
switch with bracket & fitting fix to wall

Power point fittings

29 Double gang power outlet with bracket and fitting 10 no 105 5.25
fix to wall

OTHERS

30 Allow for accessories, timber battens outlets and 1 item 860 43


metal flush boxes, mounting blocks, cables,
fixings and connectionS. Switches, plug sockets
and all hardware.

AMOUNT OF ELECTRICAL CARRIED TO SUMMARY

11. ELECTRICAL Page 150


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standard Hours hrs rate
2% 20% Hours Labour Tradesman Foreman Sub-Total
Average Rate $ 25.00

11. ELECTRICAL Page 151


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standard Hours hrs rate
2% 20% Hours Labour Tradesman Foreman Sub-Total

1.12 11.2 71.12 1.5 $ 37.50 $ 37.50 0.00 0.00

19 190 1206.5 4 $ 100.00 $ 100.00 0.00 0.00

53.2 532 3,378.20 4 $ 100.00 $ 100.00 0.00 0.00

5.952 59.52 377.952 1.5 $ 37.50 $ 37.50 0.00 0.00

0.17 1.7 10.795 1.5 $ 37.50 $ 37.50 0.00 0.00

17.16 171.6 1089.66 1.5 $ 37.50 $ 37.50 0.00 0.00

8.4 84 533.4 1.8 $ 45.00 $ 45.00 0.00 0.00

11. ELECTRICAL Page 152


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standard Hours hrs rate
2% 20% Hours Labour Tradesman Foreman Sub-Total

4.2 42 266.7 0.9 $ 22.50 $ 22.50 0.00 0.00

0.8 8 50.8 1.1 $ 27.50 $ 27.50 0.00 0.00

0.96 9.6 60.96 1.2 $ 30.00 $ 30.00 0.00 0.00

$ 25.10 $ 251.00 $ 1,593.85 2 $ 50.00 $ 50.00 0.00 0.00

2.1 21 133.35 1.2 $ 30.00 $ 30.00 0.00 0.00

0.17 1.7 10.795 1.5 $ 37.50 $ 37.50 0.00 0.00

19 190 1206.5 1.5 $ 37.50 $ 37.50 0.00 0.00

9.6 96 609.6 1.8 $ 45.00 $ 45.00 0.00 0.00

$ 25.10 $ 251.00 $ 1,593.85 2 $ 50.00 $ 50.00 0.00 0.00

4.2 42 266.7 0.9 $ 22.50 $ 22.50 0.00 0.00

11. ELECTRICAL Page 153


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standard Hours hrs rate
2% 20% Hours Labour Tradesman Foreman Sub-Total
0.8 8 50.8 1.1 $ 27.50 $ 27.50 0.00 0.00

2.1 21 133.35 1.2 $ 30.00 $ 30.00 0.00 0.00

17.2 172 1092.2 5 $ 125.00 $ 125.00 0.00 0.00

11. ELECTRICAL Page 154


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate Cost


Sub-Total Overhead P&G Sub-Total
10% 4.50%

11. ELECTRICAL Page 155


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate Cost


Sub-Total Overhead P&G Sub-Total
10% 4.50%

0.00 0.00 0.00 0.00 0.00 $ 108.62 $ 2,172.40

0.00 0.00 0.00 0.00 0.00 $ 1,306.50 $ 1,306.50

0.00 0.00 0.00 0.00 0.00 $ 3,478.20 $ 3,478.20

0.00 0.00 0.00 0.00 0.00 $ 415.45 $ 415.45

0.00 0.00 0.00 0.00 0.00 $ 48.30 $ 4,926.09

0.00 0.00 0.00 0.00 0.00 $ 1,127.16 $ 1,127.16

0.00 0.00 0.00 0.00 0.00 $ 578.40 $ 578.40

11. ELECTRICAL Page 156


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate Cost


Sub-Total Overhead P&G Sub-Total
10% 4.50%

0.00 0.00 0.00 0.00 0.00 $ 289.20 $ 8,965.20

0.00 0.00 0.00 0.00 0.00 $ 78.30 $ 626.40

0.00 0.00 0.00 0.00 0.00 $ 90.96 $ 454.80

0.00 0.00 0.00 0.00 0.00 $ 1,643.85 $ 1,643.85

0.00 0.00 0.00 0.00 0.00 $ 163.35 $ 2,123.55

0.00 0.00 0.00 0.00 0.00 $ 48.30 $ 5,215.86

0.00 0.00 0.00 0.00 0.00 $ 1,244.00 $ 1,244.00

0.00 0.00 0.00 0.00 0.00 $ 654.60 $ 654.60

0.00 0.00 0.00 0.00 0.00 $ 1,643.85 $ 1,643.85

0.00 0.00 0.00 0.00 0.00 $ 289.20 $ 9,832.80

11. ELECTRICAL Page 157


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ment Others Total Rate Cost


Sub-Total Overhead P&G Sub-Total
10% 4.50%
0.00 0.00 0.00 0.00 0.00 $ 78.30 $ 1,096.20

0.00 0.00 0.00 0.00 0.00 $ 163.35 $ 1,633.50

0.00 0.00 0.00 0.00 0.00 $ 1,217.20 $ 1,217.20

$ 50,356.01

11. ELECTRICAL Page 158


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
12 TILING 5%

General

1 Refer to the drawings and Specification for


full details and descriptions of materials
and workmanship

2 Refer to the General and Special


Conditions of the contract and tender and
to the Preliminary and General section of
the Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202:
1995 Standard Method of measurement of
Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The rates shall include for thoroughly


cleaning and preparing surfaces

6 The rates shall include for all straight


cutting and cutting and making good
around openings, pipes, sleeves, floor
wastes and the like

7 The rates shall include for setting in


colours and patterns as directed

8 The rates shall include for protecting of


tiled surfaces and cleaning down on
completion

9 Mortar beds shall be of 1:3 cement to sand


ratio laid over 'Cemstik' to concrete floors

12. TILING Page 159


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
12 TILING 5%
10 Grouting shall be completed with ABA
Epoxy Grout

GROUND FLOOR

Floor Tiles
Vinyl Tiles

11 300 x 300mm Vinyl tiles, selected 164 m2 $ 102.00 $ 5.10


adhesive fixed on 20mm thick mortar bed

Mosaic Tiles-Bathroom floor

12 50 x 50mm mosaic tiles, adhesive fixed 8 m2 262.2 13.11


with ABA super tileset adhesive on 20mm
thick mortar bed. Point with approved
flexible grout on completion

Wall Tiles

Ceramic Tiles -Bathroom walls

13 150 x 150mm glazed ceramic tiles with an 44 m2 155.6 7.78


approved adhesive fixed to plastered
blockwork wall. Point with matching grout
on completion

Ceramic Tiles-Kicthen sink wall


14 150x150 ceramic tiles with an approved 1.5 m² 155.6 7.78
adhesive fixed to FC lining-Point with
matching grout on completion

TOP FLOOR

Vinyl Tiles

15 300 x 300mm Vinyl tiles, selected 164 m2 $ 133.33 $ 6.67


adhesive fixed on 20mm thick mortar bed

Mosaic Tiles-Bathroom floor

12. TILING Page 160


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
12 TILING 5%
16 50 x 50mm mosaic tiles, adhesive fixed 8 m2 262.2 13.11
with ABA super tileset adhesive on 20mm
thick mortar bed. Point with approved
flexible grout on completion

Wall Tiles

Ceramic Tiles -Bathroom walls

17 150 x 150mm glazed ceramic tiles with an 44 m2 155 7.75


approved adhesive fixed to plastered
blockwork wall. Point with matching grout
on completion

Ceramic Tiles-Kicthen sink wall


18 150x150 ceramic tiles with an approved 1.5 m² 155.6 7.78
adhesive fixed to FC lining-Point with
matching grout on completion

19 Allow for glue, spacers,tiles adhesive etc.. 1 item 1220 61

AMOUNT OF TILING CARRIED TO SUMMARY

12. TILING Page 161


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standar Hours hrs
2% 20% Hours Labour TradesmanForeman Sub-Total
Average Rat $ 25.00

12. TILING Page 162


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standar Hours hrs
2% 20% Hours Labour TradesmanForeman Sub-Total

$ 2.04 $ 20.40 $ 129.54 0.2 $ 5.00 $ 5.00

5.244 52.44 332.99 0.5 $ 12.50 $ 12.50

3.112 31.12 197.61 0.6 $ 15.00 $ 15.00

3.112 31.12 197.612 0.5 $ 12.50 $ 12.50

$ 2.67 $ 26.67 $ 169.33 0.2 $ 5.00 $ 5.00

12. TILING Page 163


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor Equipment


Fixing Transport Sub-Total Standar Hours hrs
2% 20% Hours Labour TradesmanForeman Sub-Total
5.244 52.44 332.99 0.5 $ 12.50 $ 12.50

3.1 31 196.85 0.5 $ 12.50 $ 12.50

3.112 31.12 197.612 0.5 $ 12.50 $ 12.50

24.4 244 1549.4 7 $ 175.00 $ 175.00

12. TILING Page 164


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Total Rate


rate Sub-TotalOverhead P&G Sub-Total
10% 4.50%

12. TILING Page 165


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Total Rate


rate Sub-TotalOverhead P&G Sub-Total
10% 4.50%

$ 134.54 $ 134.54

$ 345.49 $ 345.49

$ 212.61 $ 212.61

$ 210.11 $ 210.11

0 0 0 $ 174.33 $ 174.33

12. TILING Page 166


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Total Rate


rate Sub-TotalOverhead P&G Sub-Total
10% 4.50%
$ 345.49 $ 345.49

$ 209.35 $ 209.35

$ 210.11 $ 210.11

$ 1,724.40 $ 1,200.00

12. TILING Page 167


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

12. TILING Page 168


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

$ 22,064.56

$ 2,763.95

$ 9,354.93

$ 315.17

$ 28,589.97

12. TILING Page 169


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

$ 2,763.95

$ 9,211.40

$ 208.61

$ 1,200.00

$ 76,472.54

12. TILING Page 170


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit M


Rate/Unit
13 PAINTING

General

1 Refer to the drawings and


Specification for full details and
descriptions of materials and
workmanship

2
Refer to the General and Special
Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3
This Bill of Quantities has been
prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The rates shall include for surface


preparation, rubbing down surfaces
between coats, cutting in different
colours and / or textures, narrow
widths and stopping all nail holes,
splits, etc. with putty

EXTERIOR

All concrete surface apply one coat


Luxury concrete sealer and 2 coats of
exterior paint on:-

6 Concrete blockwalls and block US of 98 m2 $ 19.31


slab

13. PAINTING Page 171


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit M


Rate/Unit
13 PAINTING
7 Sides of Corner column,( 0 - 1500mm 44 m2 $ 36.00
girth)

8 Sides of 450 x 250 Column, ( 0- 99 m2 $ 36.00


750mm and 1400m girth)

9 Sides of 250x250 columns, 0- 14 m2 $ 36.00


1000mm girth

10 Extra value for narrow width ,( 0-475 65 m2 $ 36.00


girth sides of beams)

Extra value for sides of ground floor m $ 4.20


11 slab (0-100mm high) 60

12 Extra value for sides of top floor slab 60 m $ 4.50


(0-125mm high)

Three coats exterior paint, on ;

13 75 X 20 Eave battens 24 m² $ 35.00

14 250 x 25 Fascia board 74 m² $ 35.00

Anti-rust paint
16 Allow to apply antirust paint on 1 item
Fabricated steel lattice at fron of
building and 50x50 SHS stairs railing
and posts

INTERIOR

Three coats of Concrete sealer paint


and 2 coats interior paint, on ;

17 Blockwork wall 185.00 m2 $ 42.53

18 Sides of 250 x 250 Column, 0- 58.00 m2 $ 42.53


1000mm girth

19 Extra value for narrow width , 0- 65.00 m2 $ 42.53


475mm girth( sides of beams)

20 Sides of columns, 0-1278mm girth 214.00 m2 $ 42.53

13. PAINTING Page 172


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Item Description Qty Unit M


Rate/Unit
13 PAINTING

21 Side of RC floor slab 114.36 m $ 4.80

22 Soffit of floor slab 128.00 m2 $ 42.53

Apply Three (3) coats interior paint, on


;

23 Gyprock cornice 63 m $ 3.40

24 100 x 25 timber skirting fixed to 78 m $ 3.55


concrete blockwork wall

25 Gyprock internal wall lining 227 m² $ 42.53

26 Gyprock internal ceiling lining 308 m² $ 42.53

DOORS & FRAMES

INTERIOR

Three coats of paint on:-

27 45mm thick solid core flush door 20 m2 $ 42.53


(girth)

28 144x44 door frames 92 m $ 4.00

29 144x44 window frames 52 m $ 4.00

AMOUNT OF PAINTING CARRIED


TO SUMMARY

13. PAINTING Page 173


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material
Wastage Fixing Transport Sub-Total Stan
5% 1% 20% Hours Labour
Average Rate

$ 0.97 $ 0.19 $ 3.86 $ 24.33 0.33

13. PAINTING Page 174


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material
Wastage Fixing Transport Sub-Total Stan
5% 1% 20% Hours Labour
$ 1.80 $ 0.36 $ 7.20 $ 45.36 0.42

$ 0.12 $ 0.30 $ 0.42 $ 36.84 0.42

$ 1.80 $ 0.36 $ 7.20 $ 45.36 0.42

$ 1.80 $ 0.36 $ 7.20 $ 45.36 0.55

$ 0.21 $ 0.04 $ 0.84 $ 5.29 0.15

$ 0.23 $ 0.05 $ 0.90 $ 5.67 0.15

1.75 $ 0.35 $ 7.00 $ 44.10 0.45

1.75 $ 0.35 $ 7.00 $ 44.10 0.45

$ 2.13 1% $ 8.51 $ 53.17 0.25 0.18

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.42 0.18

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.55 0.25

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.42 0.18

13. PAINTING Page 175


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Material
Wastage Fixing Transport Sub-Total Stan
5% 1% 20% Hours Labour

$ 1.40 $ 0.05 $ 0.96 $ 7.21 0.42 0.18

$ 0.43 $ 0.43 $ 8.51 $ 51.89 0.42 0.18

0.17 $ 0.03 $ 0.68 $ 4.28 0.23 $ 5.75

0.18 $ 0.04 $ 0.71 $ 4.47 0.23 $ 5.75

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.23

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.23

$ 2.13 $ 0.43 $ 8.51 $ 53.59 0.23


$ 5.75

$ 0.20 $ 0.04 $ 0.80 $ 5.04 0.23 $ 5.75

$ 0.20 $ 0.04 $ 0.80 $ 5.04 0.23 $ 5.75

13. PAINTING Page 176


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Labor Equipment
Standard Hours hrs rate Sub-Total
Tradesman Foreman Sub-Total Tools
$ 25.00

$ 8.25 $ 8.25

$ -

13. PAINTING Page 177


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Labor Equipment
Standard Hours hrs rate Sub-Total
Tradesman Foreman Sub-Total Tools
$ 10.50 $ - $ 10.50 $ - $ - $ -

$ -
$ 10.50 $ - $ 10.50 $ - $ - $ -

$ -
$ 10.50 $ - $ 10.50 $ - $ - $ -

$ -
$ 13.75 $ - $ 13.75 $ - $ - $ -

$ -
$ 3.75 $ 3.75

$ 3.75 $ 3.75

$ 11.25 $ 11.25

$ 11.25 $ 11.25

$ - $ - $ - $ - $ - $ -

$ - $ - $ - $ - $ - $ -

$ - $ - $ - $ - $ - $ -

$ - $ - $ - $ - $ - $ -

13. PAINTING Page 178


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Labor Equipment
Standard Hours hrs rate Sub-Total
Tradesman Foreman Sub-Total Tools

$ - $ - $ - $ - $ - $ -

$ - $ - $ - $ - $ - $ -

$ 5.75

$ 5.75

$ 0.23

$ 0.23

$ 5.75

$ -
$ 5.75
$ -
$ 5.75

13. PAINTING Page 179


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Total Rate


Overhead P&G Sub-Total

$ - $ - $ - $ 32.58 $ 32.58

13. PAINTING Page 180


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Total Rate


Overhead P&G Sub-Total

$ - $ - $ - $ 55.86 $ 55.86

$ - $ - $ - $ 47.34 $ 47.34

$ - $ - $ - $ 55.86 $ 55.86

$ - $ - $ - $ 59.11 $ 59.11

$ 9.04 $ 9.04

$ 9.42 $ 9.42

$ 55.35 $ 55.35

$ 55.35 $ 55.35

$ 5,210.00

$ - $ - $ - $ 53.17 $ 53.17

$ - $ - $ - $ 53.59 $ 53.59

$ - $ - $ - $ 53.59 $ 53.59

$ - $ - $ - $ 53.59 $ 53.59

13. PAINTING Page 181


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Others Total Rate


Overhead P&G Sub-Total

$ - $ - $ - $ 7.21 $ 7.21

$ - $ - $ - $ 51.89 $ 51.89

$ 10.03 $ 10.03
$ -
$ 10.22 $ 10.22

$ 53.82 $ 53.82

$ 53.82 $ 53.82

$ 59.34 $ 59.34

$ 10.79 $ 10.79

$ 10.79 $ 10.79

13. PAINTING Page 182


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 3,192.90

13. PAINTING Page 183


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 2,457.84

$ 4,686.66

$ 782.04

$ 3,842.15

$ 542.52

$ 565.20

$ 1,328.40

$ 4,095.90

$ 5,210.00

$ 9,836.91

$ 3,108.09

$ 3,483.21

$ 11,467.79

13. PAINTING Page 184


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry Of Justice and Legal Affairs)

Cost

$ 824.31

$ 6,641.48

$ 632.14

$ 797.39

$ 12,216.64

$ 16,575.88

$ 1,186.76

$ 992.68

$ 561.08

$ 95,027.98

13. PAINTING Page 185


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
14 GLAZING 10%

General

1 Refer to the drawings and Specification for


full details and descriptions of materials
and workmanship

2 Refer to the General and Special


Conditions of the contract and tender and
to the Preliminary and General section of
the Specification

Method of measurement

3 This Bill of Quantities has been prepared


generally in accordance with NZS 4202:
1995 Standard Method of measurement of
Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 All glass shall be of specified glazing


qualities

6 Irregular shaped panes have been


measured to the nearest rectangle

7 The rates for glazing shall include for back


bedding in putty and sprg fixing to frame,
as specified

DOORS

8 Standard single aluminum frames door 11 no 5796 579.60


with 480mmx840mmx6mm thick clear float
glass, beaded into hardwood timber door
frame. Complete with approved hardware

14. GLAZING Page 186


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
14 GLAZING 10%
9 Double door aluminum frames with 6mm 2 items $ 18,000.00 1800.00
thick obscure glass, fixed to timber door
frames, complete with approved hardware

Windows

10 6mm thick clear float glass, with aluminum 15 no 11000 1100.00


frames beaded into concete overall size of
3.15m wide and 1.8m high with aluminum
frames between. Refer to drawing for detail

11 9mm thick obscurw float glass with 2 no 4500 450.00


aluminum frames, beaded into timber
window frame, size 1.80m x 1.475m. Refer
to window schedule drawing for detail

12 9mm thick obscurw float glass with 4 no 4010 401


aluminum frames, beaded into timber
window frame, size 1.00m x 1.475m. Refer
to window schedule drawing for detail

13 9mm thick obscurw float glass with 14 no 5100 510


aluminum frames, beaded into timber
window frame, size 1.80m x 2.00m. Refer
to window schedule drawing for detail

14 9mm thick obscure float glass with 2 no 3200 320


aluminum frames, beaded into timber
window frame, size 1.80m x 0.72m. Refer
to window schedule drawing for detail

Reception

15 1800mm wide x 1.7mm high opening at 1 no 7600 760


recception counter-Provide sliding glass
window with alumimnum frames and
appropriate fixings

Mirrors above HWB

14. GLAZING Page 187


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
14 GLAZING 10%

16 450mm wide x 600mm high x 6mm thick 4 no 500 50.00


Pilkingtons fully tropicalised polished
plates float glass mirror, with bevelled and
polished edges and silvered reflecting
back, fixed to wall with c.p. dome headed
mirror screw with rubber spacer

AMOUNT OF GLAZING CARRIED TO


SUMMARY

14. GLAZING Page 188


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hours Labour Tradesman Foreman
Average rate $ 25.00

289.8 115.92 6781.32 1.5 $ 37.50

14. GLAZING Page 189


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hours Labour Tradesman Foreman
900 3600 24300.00 3 $ 75.00

550 2200 14850.00 1.5 $ 37.50

225 900 6075.00 1.5 $ 37.50

200.5 802 5413.5 1.5 $ 37.50

255 1020 6885 1.5 $ 37.50

160 640 4320 1.5 $ 37.50

380 1520 10260 2 $ 50.00

14. GLAZING Page 190


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
5% 20% Hours Labour Tradesman Foreman

25 100 675.00 1.6 $ 40.00

14. GLAZING Page 191


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others
hrs rate Sub-Total Overhead P&G
Sub-Total 0 0% 0.00%

$ 37.50 0 0 0 0

14. GLAZING Page 192


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others
hrs rate Sub-Total Overhead P&G
Sub-Total 0 0% 0.00%
$ 75.00 0 0 0 0 0

$ 37.50 0 0 0 0 0

$ 37.50 0 0 0 0 0

$ 37.50 0 0 0 0 0

$ 37.50 0 0 0 0 0

$ 37.50 0 0 0 0 0

$ 50.00 0 0 0 0 0

14. GLAZING Page 193


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others
hrs rate Sub-Total Overhead P&G
Sub-Total 0 0% 0.00%

$ 40.00 0 0 0 0 0

14. GLAZING Page 194


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ers Total Rate Cost


Sub-Total

$ - $ 6,818.82 $ 6,818.82 $ 75,007.02

14. GLAZING Page 195


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ers Total Rate Cost


Sub-Total

0 24375.00 $ 48,750.00 $ 97,500.00

0 $ 14,887.50 $ 14,887.50 $ 223,312.50

0 $ 6,112.50 $ 6,112.50 $ 12,225.00

0 $ 5,451.00 $ 5,451.00 $ 21,804.00

0 $ 6,922.50 $ 6,922.50 $ 96,915.00

0 $ 4,357.50 $ 4,357.50 $ 8,715.00

0 $ 10,310.00 $ 7,600.00 $ 7,600.00

14. GLAZING Page 196


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

ers Total Rate Cost


Sub-Total

0 $ 715.00 $ 715.00 $ 2,860.00

$ 545,938.52

14. GLAZING Page 197


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
15 SITEWORKS 5%
1%
General

1
Refer to the drawings and Specification
for full details and descriptions of
materials and workmanship

2 Refer to the General and Special


Conditions of the contract and tender
and to the Preliminary and General
section of the Specification

Method of measurement

3
This Bill of Quantities has been
prepared generally in accordance with
NZS 4202: 1995 Standard Method of
measurement of Building Works

4 Refer to the General rules of the NZS


4202: 1995 Standard Method of
Measurement of Building Works

Measurement and Price

5 The preambles of Concrete Work,


Reinforcing Steel, Solid Plaster,
Blockwork and Carpentry trades shall be
equally binding on this trade and should
be read in conjunction

FOOTH PATH

6 Excavation for footing 0.6 m³

7 20 Mpa strength concrete in walkway 3 m3 $ 1,200.00 $ 60.00


slab and footing

8 25mm thk Sand blinding on compacted fill 20 m² $ 6.60 $ 0.33

9 DPC on sand blinding 20 m² $ 3.50 $ 0.18

10 F62 Mesh and pvc mesh support 20 m2 $ 33.00 $ 1.65

15. SITEWORKS Page 198


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Item Description Qty Unit Material


Rate/Unit Wastage
15 SITEWORKS 5%

11 D12 bars horrizontal bars in footing 35 kg $ 10.51 $ 0.11

12 D12 starter bars @ 600 centers cast 45 kg $ 10.51 $ 0.11


600mm in concrete slab

13 Galvanized tie wire 3 kg $ 30.00 $ 0.30

Formwork

14 Allow for forwrok Sides of footh path 1 item $ 5,120.97


slab and footing and proper curing of
concrete

Form plywood 6 sheets 412 20.6


2"x2" timber 41 m 11 0.55
2" JH nails 2 kg 24 1.2
4" JH nails 2 kg 20 1
Water (free-fee included in 0
preliminaries)
Empty sack (Copra bag) 50 no 10.00

Planter
Allow for construction of concrete 1 item 520 26.00
planters with 200mm block, concrete,
reinforcement etc..

AMOUNT OF SITEWORK CARRIED


TO SUMMARY

15. SITEWORKS Page 199


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
2% 20% Hours Labour TradesmaForeman Sub-Total
1% Average Rat $ 25.00

2.2 $ 55.00 $ 55.00

$ 24.00 $ 240.00 $ 1,524.00

$ 0.13 $ 1.32 $ 8.38 1 $ 25.00 $ 25.00

$ 0.07 $ 0.70 $ 4.45 0.05 $ 1.25 $ 1.25

$ 0.66 $ 6.60 $ 41.91 0.25 $ 6.25 $ 6.25

15. SITEWORKS Page 200


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Material Labor
Fixing Transport Sub-Total Standard Hours
2% 20% Hours Labour TradesmaForeman Sub-Total

$ 0.11 $ 2.10 $ 12.82 0.25 $ 6.25 $ 6.25


$ -
$ 0.11 $ 2.10 $ 12.82 0.25 $ 6.25
$ 6.25

$ 0.30 $ 6.00 $ 36.60 0.5 $ 12.50 $ 12.50

$ 5,120.97

8.24 82.4 523.24 0.88 $ 22.00 $ 22.00


0.22 2.2 13.97 0.4 $ 10.00 $ 10.00
0.48 4.8 30.48 0.3 $ 7.50 $ 7.50
0.4 4 25.4 0.3 $ 7.50 $ 7.50

2 12.00 0.1 $ 2.50 $ 2.50

10.4 104 660.40 4 $ 100.00 $ 100.00

15. SITEWORKS Page 201


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Total Rate


hrs rate Sub-Total Overhead P&G Sub-Total
10% 4.50%

Wheel barrow $ 25.00


Graw bar $ 10.00
spade/shavel $ 10.00
$ 45.00 $ 45.00 $ 100.00 $ 100.00

$ 1,524.00 $ 1,524.00

0 0 0 0 0 0 $ 33.38 $ 33.38

0 0 0 0 0 0 $ 5.70 $ 5.70

0 0 0 0 0 0 $ 48.16 $ 48.16

15. SITEWORKS Page 202


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Equipment Others Total Rate


hrs rate Sub-Total Overhead P&G Sub-Total
10% 4.50%

0 0 0 0 0 0 $ 19.07 $ 19.07

0 0 0 0 0 0 $ 19.07 $ 19.07

0 0 0 0 0 0 $ 49.10 $ 49.10

$ 5,120.97 $ 5,120.97

$ 545.24 $ 3,271.44
$ 23.97 $ 982.77
$ 37.98 $ 75.96
$ 32.90 $ 65.80
$ - $ -

$ 14.50 $ 725.00
$ 5,120.97

$ 860.40 $ 860.40

15. SITEWORKS Page 203


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

$ 60.00

$ 4,572.00

$ 667.64

$ 113.90

$ 963.20

15. SITEWORKS Page 204


BOQ FOR PROPOSED OFFICE BUILDING FOR PSO AND DPP AT LATA-TEMOTU PROVINCE
(Ministry of Justice and Legal Affairs)

Cost

$ 667.53

$ 858.25

$ 147.30

$ 5,120.97

$ 860.40

$ 14,031.19

15. SITEWORKS Page 205