INTERIOR FITOUT WORKS at ______________________

PREAMBLE TO BOQ
The description of an item shall be deemed to include all preambles, headings, sub-headings and references to other docu
description of work and materials, given in the Specification are not necessarily repeated in the Bill of Quantities.
The Preamble to the Bills of Quantities must be read with the Drawings, Conditions of Contract and the Specification and
deemed to have examined the Drawings, Specifications, Conditions of Contract and to have acquainted himself with the Work
way in which they are to be carried out. This preamble to the Bills of Quantities shall form part of the Contract.

The Tenderers are requested to inspect the site and obtain for themselves at their own expense all necessary information and
them to submit the tender.
The dimensions shown in the drawings shall have to be verified by the contractor at site before execution of the items and n
have to be made as per the actual dimensions available at site.
For the items of works having Basic rate of material, price adjustment will be made only on the actual quantity measured. W
shall be to Contractors account. Basic rate indicates loading unloading, transportation etc.
The contractor should refer to the tender drawings / 3D views / Technical specifications for details. In case of any discrepancy
precedence, unless specifically mentioned in the BOQ.
All pre-fabrication works wherever possible shall be carried outside the client's premises, only assembling and finishing work
the Site. This is specific to finishing works involving high VOC items which are not permissible to be executed within the pre
works will be mutually agreed during the kick off meeting.

Items of work provided in this schedule but not covered in the specifications shall be executed strictly as per instruction
charge/Project Manager.
Unless specifically mentioned otherwise in the contract, the tenderer shall quote for the finished items and shall provide
towards labour, materials, plant and machinery, operational costs, levies, taxes, transport, repairs, rectification, maintena
revenue expenses, contingencies, overheads, profits and all incidental items not specifically mentioned but reasonably imp
complete the works according to the contract.

The quantities of the various items mentioned in the schedule of items are approximate and may vary up to any extent or b
The quoted rates of each item shall remain firm for all works. The contractor, in his own interest, should get an indication of t
the work to be executed under any particular item in this schedule, before undertaking any preliminary and enabling work
out components related to the work.

Rates shall be quoted both in figures and in words in clear legible writing. No overwriting is allowed. All scoring and ca
countersigned by the tenderer. In case of illegibility, the interpretation of the engineer shall be final. All entries shall be in Eng

Engineer-in-charge's decision shall be final and binding on the contractor regarding clarifications of items in this schedule wit
sections of the Contract.
It may be noted that the total work or any part / parts of the same may be awarded as mentioned in this schedule of items.
The rates quoted shall be inclusive of all mock-ups (including necessary hardware), associated samples prior to any
procurement as per complete satisfaction of the Client and Architect. Inclusive of dismantling, demolishing and carting the
good of the surface.

Any debris generated out of the said work may please be cleared on priority basis from the Site
Day to day house keeping at site & providing professional cleaning services before handover.
Providing, erecting and maintaining temporary site office and store rooms as directed by the Project Manager for the duration
commencement until handover
Rates for all exposed Teak wood members and lipping / beading shall include cost of melamine finish. All edge binding works a
factory made. On site edge binding will not be accepted.
For Raised floor, Minimum two technicians required till the completion period for this job and they should equiped with all n
lifters, screw drivers, drill machines, zigsaw cutter machines, etc.
For Raised floor, Vendor has to carryout lazer level survey and level marking in the beginning of project. Protection of til
completion of job
Drawings are subject to change as per site conditions
Contractor to follow List of Approved Makes. No Deviation to the makes will be accepted. Contractor to submit NO DEVIATION
with the tender.
The Contractor shall be responsible for:
(a) Preliminary works such as marking / checking layout of structures on ground and reference lines and fixing temporary benc
(b) the accurate setting-out of the Works in relation to original points, lines and levels of reference given by the Employer in w
(c) the correctness, subject as above mentioned, of the position, levels dimensions and alignment of all parts of the Works.
(d) If, at any time during the execution of the Works, any errors appear in the position, levels, dimensions or alignment or a
the Contractor, shall at his own cost, rectify such error to the satisfaction of the Employer.

GENERAL NOTES
The rates for all tiles, slabs of marble, granite, Kota or any other stone should be inclusive of all materials, transport, loading
thereon as per Item Rate. Only tax will be paid extra. The rate mentioned is the maximum and in no way should exceed, the o

The door size mentioned is the overall opening size


The contractor should refer to the detailed drawings for details. All the rates so quoted should be inclusive of all hardware.
between drawing and Bill of Quantity the drawing supersedes, unless specifically mentioned in the BOQ.
Rates for all exposed wooden members and lipping shall include cost of melamine finish.
The rate of all units to be inclusive of matched locks for individual work space every drawer and shutter to be provided w
make
Details of the items under this schedule shall be read in conjunction with the corresponding specifications, drawings and othe

The work shall be carried out as per drawings, specifications, the description of the items in the schedule and / or architects in

Items of work provided in this schedule but not covered in the specifications shall be executed strictly as per instru
manager/architect
Unless specifically mentioned otherwise in the contract, the tenderer shall quote for the finished items and shall provide
towards labour, materials, plant and machinery, operational costs, levies, taxes, transport, repairs, rectification, maintena
revenue expenses, contingencies, overheads, profits and all incidental items not specifically mentioned but reasonably imp
complete the works according to the contract.

The quantities of the various items mentioned in the schedule in the schedule of items are approximate and may vary up
deleted altogether. The quoted rates of each item shall remain firm as long as the variation in the total value of the work
contract including extra items, if any, remain within + 10 (10 percent) of the tendered value of the works. The contracto
should get an indication of the probable extent of the work to be executed under any particular item in this schedule, be
preliminary and enabling work or purchasing bought out components related to the work.

Rates shall be quoted both in figures and in words in clear legible writing. No overwriting is allowed. All scoring and ca
countersigned by the tenderer. In case of illegibility, the interpretation of the engineer shall be final. All entries shall be in Eng

Project managers decision shall be final and binding on the contractor regarding clarifications of items in this schedule with
sections of the Contract.
It may be noted that the total work or any part / parts of the same may be awarded as mentioned in this schedule of items.
The rates quoted shall be inclusive of all mock-ups, associated samples prior to any mass production or procurement as per co
the Client and Architect. Inclusive of dismantling, demolishing and carting the material and making good of the surface.
MASONRY WALLS & PLASTER
For all 'hard flooring areas',(areas with Granite / marble/ceramic-vitrified tiles/etc,) only the 'laid area' (visible after complete l
paid for. No 'extra' shall be paid for cutting / wastage / etc.
All 'inlays' in the flooring shall be paid for as per relevant item(s) in RMT. If, as per design, any 'module' of the relevant inlay, (w
be executed at site and the same is not conforming to / with the specification(s), the rate shall be derived on a prorata basis fr

All stones mentioned in the tender shall be brought to site only from the lots pre-approved /selected by the architects.
For all items the basic rate of the stones are mentioned. This rate specifies the range in which the Architect shall choose the r
of variation in the basic rate mentioned and the procured rate, extra shall be payable to the contractor or the benefit woul
client based on the difference in the rate. Unless otherwise mentioned / specified, all statutory taxes/levies/duties shall not b
the 'Basic Rate' of stones/marble/tiles/etc., which please kindly note. However, if the same is so desired at the Client's end,
within the Basic Cost), instructions likewise shall / will be forwarded, as deemed necessary

Rates quoted for items of counter,etc. shall be inclusive of making necessary cutouts for sinks, basins and inclusive of polishin
profile as indicated on the drawings, to the entire satisfaction of the supervising architects.
All masonry and plastering works shall be sufficiently cured, to the entire satisfaction of the supervising architects, before taki
on the same.
Rates quoted for the treads of the staircases shall be deemed to be inclusive of making all necessary cutouts,for railing balustr
'workmanlike manner,and, to the entire satisfaction of the supervising architects
All Samples of tiles, fittings etc.shall be presented after ensuring that the necessary quantities of the relevant item(s) for which
are available, (ex-stock, or otherwise) and shall be approved by the architect before placing of mass orders.
All the Dado and/ Flooring shall include rates of the 2-4mm thk spacers as per architect's approval with colour matching grout
matching color of the dado wherever the walls are in right angles, as per instructions / related specifications towards the sam
consulting architects

All appointed agencies are required to ensure that their scope of works are undertaken in an absolutely professional and work
furthermore, to ensure that 'housekeeping' activities are undertaken , at the site / premises in question in such a manner that
materials/etc. are retained at site in a disorderly manner, failing which, the Clients/Architects shall be at liberty to take remed
cost(s) and consequences of the appointed contracting agency

CIVIL WORKS & Generic

The rates for all tiles, slabs of marble, granite, Kota or any other stone should be inclusive of all materials, transport, loading
thereon as per Item Rate. Only tax will be paid extra. The rate mentioned is the maximum and in no way should exceed, the o
The contractor should refer to the detailed drawings for details. All the rates so quoted should be inclusive of all hardware.
between drawing and Bill of Quantity the drawing supersedes, unless specifically mentioned in the BOQ.
Rates for all exposed wooden members and lipping shall include cost of melamine finish.
The rate of all units to be inclusive of matched locks for individual work space every drawer and shutter to be provided w
make

Details of the items under this schedule shall be read in conjunction with the corresponding specifications, drawings and othe

The work shall be carried out as per drawings, specifications, the description of the items in the schedule and / or architects in
Items of work provided in this schedule but not covered in the specifications shall be executed strictly as per instru
manager/architect
Unless specifically mentioned otherwise in the contract, the tenderer shall quote for the finished items and shall provide
towards labour, materials, plant and machinery, operational costs, levies, taxes, transport, repairs, rectification, maintena
revenue expenses, contingencies, overheads, profits and all incidental items not specifically mentioned but reasonably imp
complete the works according to the contract.

The quantities of the various items mentioned in the schedule in the schedule of items are approximate and may vary up
deleted altogether. The quoted rates of each item shall remain firm as long as the variation in the total value of the work
contract including extra items, if any, remain within + 10 (10 percent) of the tendered value of the works. The contracto
should get an indication of the probable extent of the work to be executed under any particular item in this schedule, be
preliminary and enabling work or purchasing bought out components related to the work.

Rates shall be quoted both in figures and in words in clear legible writing. No overwriting is allowed. All scoring and ca
countersigned by the tenderer. In case of illegibility, the interpretation of the engineer shall be final. All entries shall be in Eng
Project managers decision shall be final and binding on the contractor regarding clarifications of items in this schedule with
sections of the Contract.
It may be noted that the total work or any part / parts of the same may be awarded as mentioned in this schedule of items.
The rates quoted shall be inclusive of all mock-ups, associated samples prior to any mass production or procurement as per co
the Client and Architect. Inclusive of dismantling, demolishing and carting the material and making good of the surface.

FLOORING, COUNTERS & CLADDING WORKS


Granite / Marble / Kota / Tiles shall be free from colour variation
The sample of tiles/slabs to be submitted to the Architect/Engineer for approval prior to procurement and execution.

For floor tiles, all edges to be sorted for straight edges before laying. The tile will be laid after approval from the Architect / En
The rate to include all mirror machine polishing for granite and wax mirror polishing or Titanium polishing for Kota stone. Th
as per Architects instructions.

The cost of tile/stone mentioned below is the maximum cost and is the delivered cost at site. In no circumstances it sh
mentioned in the respective items and is inclusive of all material cost, transportation, Octroi if applicable, loading-unloading a
as applicable.

For staircase treads and risers, the stone shall be in one piece. The contractor to measure the dimensions at site before orderi
All bull nosing, polishing etc for sills, frames and staircase treads should be factory finished.
All the flooring material shall be free from any cracks / deformities / damages colour variations.
Tile Should be of the first Quality
Tiles should be cut with diamond type blades only, any cut tiles having chipping will be rejected
Prior fixing the floor tiles / stone, on site by-products such as Plaster of Paris dust & particles, Saw-dust, brick & aerated bloc
with sand bed shall strictly not be permitted
After laying the floor, thoroughfare shall be restricted for a period of 24 hours after which the floor shall be protected b
micron plastic sheet.
The Cost of Flooring/ skirting shall be inclusive of grouting with matching colour of grout or as specified.
Cost should be inclusive of Breaking the plaster on existing walls to flush the skirting it should also include the cost of jad fi
groove
The Cost should be inclusive of wastage, cartage & hauling stone slab/ Floor Tiles up to the desired floor.
For all 'hard flooring areas',(areas with Granite / marble/ceramic-vitrified tiles/etc,) only the 'laid area' (visible after complete l
paid for. No 'extra' shall be paid for cutting / wastage / etc.
All 'inlays' in the flooring shall be paid for as per relevant item(s) in RMT. If, as per design, any 'module' of the relevant inlay, (w
be executed at site and the same is not conforming to / with the specification(s), the rate shall be derived on a prorata basis fr
All stones mentioned in the tender shall be brought to site only from the lots pre-approved /selected by the architects.

For all items the basic rate of the stones are mentioned. This rate specifies the range in which the Architect shall choose the r
of variation in the basic rate mentioned and the procured rate, extra shall be payable to the contractor or the benefit woul
client based on the difference in the rate. Unless otherwise mentioned / specified, all statutory taxes/levies/duties shall not b
the 'Basic Rate' of stones/marble/tiles/etc., which please kindly note. However, if the same is so desired at the Client's end,
within the Basic Cost), instructions likewise shall / will be forwarded, as deemed necessary.
Rates quoted for items of counter,etc. shall be inclusive of making necessary cutouts for sinks, basins and inclusive of polishin
profile as indicated on the drawings, to the entire satisfaction of the supervising architects.
All masonry and plastering works shall be sufficiently cured, to the entire satisfaction of the supervising architects, before taki
on the same.
Rates quoted for the treads of the staircases shall be deemed to be inclusive of making all necessary cutouts,for railing balustr
'workmanlike manner,and, to the entire satisfaction of the supervising architects
All Samples of tiles, fittings etc.shall be presented after ensuring that the necessary quantities of the relevant item(s) for which
are available, (ex-stock, or otherwise) and shall be approved by the architect before placing of mass orders.

All the Dado and/ Flooring shall include rates of the 2-4mm thk spacers as per architect's approval with colour matching epoxy
Guards of matching color of the dado wherever the walls are in right angles, as per instructions / related specifications toward
provided by the consulting architects . Cost to include U /L/ H / SS profiles / edge finish etc. as per design details .

All appointed agencies are required to ensure that their scope of works are undertaken in an absolutely professional and work
furthermore, to ensure that 'housekeeping' activities are undertaken , at the site / premises in question in such a manner that
materials/etc. are retained at site in a disorderly manner, failing which, the Clients/Architects shall be at liberty to take remed
cost(s) and consequences of the appointed contracting agency.
Other notes

All floor surfaces receiving the appropriate flooring material(s) need to be thoroughly cleaned prior to installation of the desire
No allowances shall be made to undertake rectification works if the same are so desired to be undertaken for improper adher
recommended application procedures / standards.
All joints, wherever necessary, shall be undertaken after prior approval of the same from the Architects.

All finished flooring surfaces shall be free from bubbles/scratches/stains/etc. prior to final hand- over of the activity at the des
All materials utilised shall be as per tender recommendations and shall be applied according to manufacturer's specifications.
The rate shall be inclusive of heavy duty plastic sheet ( 2 layers) to protect the tiling/stone/flooring/dado works till instructed t
by the PMC/architect.