Вы находитесь на странице: 1из 2

VENDOR DATA REQUIREMENT DOCUMENT No.

FOR 6743-00-50-VR-5060 Rev. A


EMEREGENCY GENERATOR
PACKAGE Page 1 of 2

VENDOR DATA REQUIREMENT


EMERGENCY GENERATOR PACKAGE

Post Order
Sl.No Description With Bids For For Final
Review Record Documents
Vendor Drawing/Document Submission Schedule *
1. (EIL Format 1641-1923) *

List of deviations to specs and purchaser specified *


2. parameter in data sheet of MR, if any

3. -Completed data sheets * *

4. Details of excitation system * *

5. Details of cooling system * *

6. General arrangement drawing (Note-3) * *

7. Estimated capability curve * *

8. Open circuit characteristics * *

9. Short circuit characteristics * *

10. Short time under frequency operating limits * *

11. Control power requirements * *

12. List of recommended spares * *

13. Catalogues and brochures * *

14. Bill of materials *

15. Foundation/fixing arrangement drawings * *

16. Schematic/logic diagrams * *

17. Interconnection/wiring diagrams * *

A 29.01.08 ISSUED WITH MR PB HK NS


Rev. Prepared Checked Approved
Date Purpose
No by by by

Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
VENDOR DATA REQUIREMENT DOCUMENT No.
FOR 6743-00-DG-VDR-5060 Rev. A
EMERGENCY GENERATOR PACKAGE Page 2 of 2

Post Order
Sl.No Description With Bids For For Final
Review Record Documents
18. Cable Schedule & Cable Routing layout * Note-4 *

19. Earthing Layout *

20. Testing procedure * *

21. Operation & maintenance manual * *

22. Site storage requirements * *

23. Test certificates * *

* DATA REQUIRED.

Notes:

1. Unless otherwise agreed, the number of copies of various drawings and documents shall be as below:

a. With bids - Same as the number of copies of bids


b Post order submission - For Review/Records - Six copies
c. Final documents - Six prints and Two sets of CDs

Vendor shall furnish soft copy of all drawings in AutoCAD version 14.0/ 2000 and all documents in
MSOffice 2000 as part of the final documentation.

2. For further details vendor shall refer EIL std. 7-76-0101 `Instructions to vendor for quality data
requirement'.

3. Vendor shall note that GA drawings furnished alongwith bids shall have adequate information for
carrying out detailed engineering at Purchaser’s end; and as a minimum shall include overall
dimensions, foundation/ cut-out details etc. It shall also be ensured that these details are adhered to
after placement of order.

4. Vendor shall develop and submit for approval - post order - a list of all interconnecting power and
control conductors / cables giving scope demarcation for completeness of the DG package
commissioning..

Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved