Вы находитесь на странице: 1из 20

1 Rebar installation for block masonry should be minimum 12mm.

2 DFT test should be conducted after 8 hours of coating application.

3 Leak test should be conduct after 8 hours of soaking (water pouring) prior to coating.

4 Cold joint is happen during concrete pouring if one truck arrives at site after initial setting of concrete for that we
use Nito bond or other approved chemical.

5 There is difference between splicing of coated and uncoated rebar.

6 During vibrator application in concrete vibrator should be straight (vertical from bottom) as for as possible.

7 During block work after 4 layer of block installation rebar and cement grout should be poured.

8 Gravel, sand and/or marl materials-maximum size shall be 75mm for backfilling.

Note: If ½ of lift thickness is less than 75mm, the maximum sieve size allowed shall be equal to ½ of lift thickness.

10 Select fill are composed only of inorganic materials and are free of frozen lumps, trash, or other unsatisfactory
materials.

11 Maximum size of sand and gravel materials being received shall be 75mm diameter particles.

12 Whenever the presence of underground pipes, cables, vessels or structures is known or suspected, mechanical
excavations shall not be used until all such obstructions have been exposed by hand digging.

13 Mechanical excavators shall not be used within 3 meters (10 feet) of any obstruction.

14 Excavations adjacent to existing underground installations (e.g., foundations, piping, manholes, electrical and
duct banks) or sidewalks shall use bracing and shoring to protect them.

15 Any excavation or trench with a minimum depth of 1.2 m (4 ft) or when soil banks are greater than 1.5 m (5 ft),
shoring shall be installed or the sides shall be sloped or benched and treated as a confined space.

16 Clear space on all sides of excavation shall be at least 0.6 m Safe entry and exit to excavation/ trenches shall be
provided every 7.5m.

17 Fill material shall be placed in lifts not exceeding 200mm in loose depth, fill material shall be placed in lifts not
exceeding 100mm in loose depth for hand-operated compaction.

18 Fill and backfill adjacent to any type of structure shall not be compacted with heavy equipment; Hand operated
equipment shall be used within 1.2 meters of any structures.

19 Compaction shall begin only after the fill or backfill has been properly placed and the material to be compacted is
at the proper moisture content. +/- 3% of the optimum moisture content per ASTM D1557 or ASTM D698, whichever is
applicable?

20 When the backfill material cannot clearly be classified as cohesive or cohesion less both relative density and
Proctor density tests must be performed. The backfill shall then be compacted to the greater density.

21 The compaction requirement for base course shall not be less than 100% of the maximum laboratory dry density
as determined by ASTM D1557 or AASHTO T180.

22 The compaction requirement for sub base shall not be less than 95% of the maximum laboratory dry density as
determined by ASTM D1557 or AASHTO T180.

23 The depth of the test holes shall be no greater than 300mm (12 inches) deep. (ASTM D 2922, Sec. 1.1)

24 Cohesive fill under footings, grade beams, mats, buildings and process areas shall have been compacted to at
least 90% of Modified Proctor Density to ASTM D1557 or per project requirements, whichever is higher.
25 Fill under foundations with loads exceeding 320kPa (6500psf), vibrating or heavy equipment and pavements shall
have been compacted to 85% of relative density for Cohesion less soils or 95% of maximum density per ASTM D1557 or
per project requirements, whichever is higher.

26 Concrete fireproofing shall be either cast-in-place, precast or gunite with a minimum thickness of 50mm (2").

27 The fireproofing concrete shall be a dense (structural) concrete with 28 day design compressive strength shall
be 28 MPa (4000 psi).

28 All fireproofing concrete shall be chamfered as follows: Pipe Supports-50 mm, Beams- 5 mm, Columns (except
pipes): 25 mm, Angles:-25 mm

29 A clearance of 30 mm shall be maintained between the vessel surface and the fireproofing material on support
legs, skirts, and saddles.

30 A clearance of 30 mm shall be provided between a sliding surface and the fireproofing material on a sliding
support.

31 Concrete fireproofing shall be water cured by covering with wet burlap and 0.15mm plasticized sheet vapor
barrier.

32 Maximum total dissolved solids in water used for curing shall not exceed 1000 parts per million.

33 Water curing shall be continuous until compressive strength has reached 70% of the specified strength but not
less than 7 days after placement.

34 Concrete surfaces (such as acid waste neutralizing tanks) that have been in prolonged contact with acids require
a minimum soak of 24 hours at a pH of 6-8, agitating the solution during soaking.

35 A strip of pH Test Paper is dipped in the rinse water remaining on the surface. The pH reading obtained should
not be more than 1.0 pH units lower or 2.0 pH units higher than readings taken on the fresh water rinse before being
applied to the concrete surface.

36 After rinsing, force air dry surfaces for at least 24 hours prior to making any repairs to the concrete.

37 Coating shall not be applied when the substrate temperature is less than 10°C; or less than 3°C above dew point.

38 Coating shall not be applied when wind is strong enough to blow sand, salt spray, or other foreign matter onto the
surface being coated.

39 Surfaces with sharp corners and subject to immersion conditions shall be rounded by forming a fillet with
approximately 25 mm radius using an epoxy grout.

40 No rock shall protrude through the clean sand pipe bedding layer at the bottom of any pipe trench.

41 Sand pads or sand bags at 9 meters maximum spacing shall be placed at the bottom of the trench to support the
pipe 100mm off the prepared bottom.

42 The top of the pipe shall be below the level of the construction road by at least 100mm.

43 For piping installation the side of the fill shall not be steeper than 35 degrees.

44 The width of the sand pad shall be 3m in Sabkha areas and is required on only one side of the pipeline.

45 When the buried pipeline is installed through a river bottom, wadi or other places where water run-off occurs,
concrete coated pipe shall be used.

46 The bottom of the trench shall be free of rocks and other materials that can damage the pipe or its coating
material.
47 Slings for lifting pipe shall be nylon or similar material to prevent damage to the pipe surfaces; Wire rope slings
shall not be used.

48 Internally coated pipe shall be handled from the outside diameter (O.D.) only. Pipe shall not be rolled or dropped
off of trucks.

49 Open ends of pipe strings shall be capped to prevent entry of debris or animals and birds at the end of every day.

50 LPG Lines, gas lines and oil well flow lines in trenches shall have a minimum cover of 900mm, all others shall
have 600mm.

51 The top of the pipe shall be 100mm below finished grade in Sabkha area, Sabkha area is near the sea..

52 In active sand dune areas, the backfill shall be stabilized with marl of 152mm minimum depth, other stable
material, or weathered crude oil with a minimum of 13mm penetration.

53 Where the line passes through a sand dune, the width of leveled, stabilized right-of-way shall be 3m on each side
of the pipeline plus 1m for every 1m of dune height in both the "cut" and "fill" areas.

55 For standard units, in concrete masonry unite no overall dimension (width, height, and length) shall differ by more
than ±3.2mm from the specified dimensions.

56 For molded face units, no overall dimension (width, height, and length) shall differ by more than 3.2mm from the
specified dimensions.

57 For hot weather, when the ambient temperature exceeds 100°F (38°C), the temperature of mortar shall be
maintained below 120°F (49°C). Mortar shall not be used within 2 hours of initial mixing.

58 When the mean daily temperature exceeds 100°F (38°C), or exceeds 90°F (32°C) with a wind velocity greater
than 8 mph (13 km/h), newly constructed masonry shall be fog sprayed until damp at least three times a day until the
masonry is three days old.

59 Where bond beams are required, all cells of the last course of masonry below the bond beam shall be filled with
grout. The grout pour shall be stopped a minimum of 20mm below the top of the masonry.

60 Grout in concrete masonry unit shall be placed within 90 minutes from the introduction of water in the mixture and
prior to initial set.

61 The preferred roof systems for new flat roofs with a slope of less than 13mm (1/2inch) vertical to 305mm
(12inches) horizontal are.

62 For water proofing acceptable systems are 1.52 mm (0.060") thick EPDM (Ethylene Propylene Diene Monomer)
or 5 mm (0.2") Modified Bitumen membrane systems.

63 Ballasted roofs shall have a minimum of 19 mm (¾") washed gravel placed to a minimum thickness of 50 mm (2").

64 Installation of fully adhered EPDM sheets over the entire area shall have a minimum thickness of 1.52mm
(0.060") thick.

65 All completed flat roofs shall be subjected to a flood test for a period of no less than 24 hours.

66 The top of concrete shall be a minimum of 150mm above finished grade.

67 The design concrete compressive strength of concrete shall be 27.6MPa (4000psi) at 28 days

68 High Strength Anchor Bolts shall conform to ASTM A193 Grade 105. (105000 psi)
69 All Columns Base Plates shall be designed with a minimum of 4 anchor bolts except for posts under 300lbs
(136kg).

70 The structure shall be plumbed, leveled, and braced before any final bolted or welded connections are made

71 Gypsum wallboard or gypsum plaster shall not be used in any exterior surface where such gypsum construction
will be exposed directly to weather.

72 Gypsum wallboard shall not be used when there will be direct exposure to water or continuous high humidity
conditions.

73 Room temperature shall be maintained at not less than 4°C during application of gypsum board except when
bonding of adhesive is used

74 When a temporary heat source is used during gypsum board installation, the temperature shall not exceed 35°C
in any given room area

75 Adequate ventilation shall be maintained in the working area during installation and curing period during gypsum
board installation

76 Gypsum board shall be protected from direct exposure to rain, snow, sunlight, or other excessive weather
conditions

77 In gypsum board stud spacing (16” 400mm) and 24" (600mm) spicing

78 Wood supports for lath or gypsum board, as well as wood stripping or furring shall not be less than 51mm (2")
nominal thickness in the least dimension.

79 Metal lath runners and furring shall not be less than 19.1mm (3/4") in least dimension. Metal lath and lath
attachments shall be of corrosion-resistant material for gypsum board.

80 Plastering gypsum plaster or cement plaster shall not be less than three coats where applied over metal lath or
wire fabric lath and not less than two coats where applied over other bases.

81 The finished thickness of gypsum plaster shall be 16mm (5/8") minimum where applied to metal plaster base,
13mm (1/2")

82 The finished thickness of Portland cement plaster shall be 22mm (7/8") minimum where applied to metal plaster
base & metal plaster base over solid base 16mm

83 A maximum of 5 defective tiles out of every 80 received shall permit acceptance of any lot of tiles; 6 or more
defective tiles out of 80 shall be the basis for rejection of the entire lot of tiles delivered.

84 Maximum variation from required plane surfaces shall be 6mm in 3m for subfloors, wall and ceiling surfaces.

85 Door to resident sleeping units shall have a clear width of not less than 711 mm and height shall be 1930

86 Means of egress doors shall provide a clear width of not less than 813 mm. The maximum width of swinging door
leaf shall be 1,219 mm. nominal. The height of doors shall not be less than 2,032 mm.

87 During tiles installation maximum variation from required plane surfaces shall be 6mm in 3m for subfloors, wall
and ceiling surfaces.

88 Standard intermediate types shall be used for openings not exceeding 5.57 m2, with neither dimensions
exceeding 3.05 m

89 Residential-type windows shall be used for openings not exceeding 1.98 for either dimension.
90 Maximum size openings for hollow metal plate steel windows shall be as follows, Single window: 1.52 x 1.52m.
Multiple windows: 2.13 x 3.05 m.

91 Hangers in ceiling for carrying channels or main runners are spaced 4 ft. (1200 mm) on centers.

92 For all glazing types in handrails and guards, the minimum nominal thickness shall be 1/4 inch (6.4mm).

93 All column base plates have a minimum of four anchor bolts per IFC Drawings. (NOTE: This excludes posts,
which weigh less than 300 pounds/136 kg.)

94 Minimum thickness of grout shall be 25mm and it have ratio of cement sand and hydrate lime (1:3:0.5).

95 The top of concrete foundation shall be a minimum of 150 mm above finished grade.

96 Structural alignment during erection the variation in straightness shall be equal to or less than 1/1000

97 High-strength bolts, 3/4 inch (20 mm) in diameter, shall be used in all bolted structural connections, unless
otherwise noted in the contract documents

98 For color code of gypsum these colors and their functions are used Blue----Normal gypsum, Green----Water
resistant gypsum. Red---- Fire resistant gypsum

99 The thicknesses of gusset and stiffener plates are 10 mm (3/8 inch) minimum.

100 Ratio of course and fine aggregates and ratio of water are the factor that affects the workability of mix design.

101 Water cement ratio size of course, aggregates, grading of fine aggregates and mixing property are the important
factor in strength increase of mix design.

102 By adding chemicals (admixture) high early strength of 3 days can be achieved.

103 Concrete is not expected to resist high direct tensile stress because of its low tensile strength and brittle nature.
Tensile strength is of importance with regard to crack formation.

104 Chemicals reaction resulting hydration cause the rise in temperature and it is controlled by using chilled water or
ice.

105 Increase in size of course aggregates to concrete affect the workability and cause the segregation.

106 The test to determine the initial setting time is done by vikatus apparatus.

107 The form of sodium chloride and calcium sulphate are common form chloride and sulphate that are found in
aggregates.

108 Concrete without rebar in presence of chemicals cause expansion in concrete mass which cracking the structure.

109 Mixing truck will be checked on sit by this way. Ticket checked for signature & slump value at plant, Revolution
rd
counter, Timing from batch plant to the site, Insure that 3 party inspector is present at sit; slump and temperature value
of concrete at site, 4 cylinders should be taken per 115 cubic meter.

110 Type of cement is this 1. Rapid hardening cement. 2. Low heat cement. 3. High alumina cement.
4. Quick setting cement. 5. Expanding cement. 6. White Portland cement. 7. Colored cement. 8. Super
sulphated cement. 9. Pozzoulanic cement. 10. Sulphate resistance cement. 11. Air entertaining cement.

111. Foreign chemical in aggregate make reaction that can cause expansion & cracking.

112. For proper curing of concrete with water needs 2 men to placing burlap and vapor barrier.

113. 75mm bottom cover is required for all type foundation and 50mm for side of walls columns and foundation.
114. Paving slop to catch basin or trench should have minimum 1.5% or 1:65 ratio

115. DFT mean dry film thickness. This should be 400 to 600 micron for concrete structure and 175 to 260 micron for
rebar or other metallic structure.

116. Types of documents. Level 1. Quality Plane. Level 2. Quality procedure. Level 3. Work
instruction, inspection and test plans. Level 4. Quality record.

117 Different type of schedules Schedule B Job specification. Schedule G Material tool &
equipment. Schedule Q Quality assurance, control, inspection and testing.

118 Brackish water ? Water with total dissolved solids of 10000 ppm or more is called brackish water.

119 Clean sand? Soil meeting the following graduation, containing less than 3% weight of organic material
or clay. Sieve size Percentage of passing
¼ inches (6.25mm) 100%
No 10 (2.00mm) 90-100%
No 200 (0.075mm) 10% or less.

120 Clear space of 600mm shall be maintained extra on the all side of excavation when trench reach more than 1.2m.

121 When soil bank are greater than 1.5 m shoring shall be installed or sides shall be sloped or benched and trench is
treated as confined space.

122 A safe mean of entry or exit shall be providing for all excavation and trenches at every 7.5m distance.

123 No excavation is permitted under the existing foundation

124 Excavation are not allowed to intersect a 45 degree plane extending downward from bottom edge of existing
foundation, unless an engineered support system is in place prior to start work or excavation is in stable rock.

125 The maximum size of fill material shall be ½ of the lift thickness or 75mm.Fill material shall be free of frozen
lumps, organic matters, chunk of high plastic clay or other unsatisfactory matter

126 Select fill material shall be composed only of inorganic material and shall have 100% passing 2 inch (50mm)
sieve. Liquid limit and plastic limit tests are not required for select fill with 15% passing the sieve no 200.

127 Water need for compaction of fill material shall be reasonably free of salt, oil, acids, alkalis, organic matters
deleterious substance. Use water with a TDS of 10000 ppm such as brackish water.

128 For capping layer only cohesive material passing 11-35% of No 200 sieve and the capping material shall have
maximum liquid limit of 35 and maximum plasticity index of 12.

129 For FDTunder all foundation one tests every 90m/square of each lift. Under area of paving one test 180 m/square.
Road base and sub-base one test 90m/square. Backfilling of linear trench one test shall be conducted 15m length.

130 Carbonation? Carbonation is the process of carbon dioxide reacting with calcium hydroxide within the cement
neutralizing it to form calcium carbonate.

131 Environmental conditional condition during coating application 1. Relative humidity should less than 85%.
2. Surface temperature should be less than 10C. 3. Atmospheric temperature must be greater than 3C.90
4. Surface should be tested for dryness test after rain water blasting or heavy overnight fog. 5. Wind
condition should be such as to prevent dust and dirt accumulation on the surface to be coated.

132 Prior to coating the surface to remove any protrusions and sharp edges by using abrasive brick power grinder or
power brushing. Check overall surface soundness by scratching a screw driver or pocket knife across surface. If material
object rides over surface without loosening any particles and leaves only shiny mark then surface is sound otherwise
continues scouring.
133 Surface contaminates such as laitance and form oils, grease must be removed by steam cleaning with water
emulsifiable detergent added.

134 Laitance can be removed by wire brushing hydrochloric acid is used for etching and it should be diluted 10/90 to
20/80 with water.

135 Acid etching is applied at the rate of 1.0 rate/meter square. Let the acid react with concrete surface for 5 to 10
minutes flush water while scrubbing, then let the surface be dried completely before applying any coating.

136 Environmental conditional condition during coating application 1. Relative humidity should less than 85%.
2. Surface temperature should be less than 10C. 3. Atmospheric temperature must be greater than 3C.
4. Surface should be tested for dryness test after rain water blasting or heavy overnight fog. 5. Wind
condition should be such as to prevent dust and dirt accumulation on the surface to be coated.

137 Area subject to spills, wash, fire water and side walk shall be paved with minimum thickness of 100 mm with
reinforced concrete of 150 x150 MW9XMW9 welded wire fabric.

138 If sulfate content is less than 1500ppm the chloride is more than 500ppm then type 1 cement and FBE coated
rebar shall be applied.

139 Welded wire fabric shall conform to SASO, SSA 224 (cold drawn) wire with minimum yield strength of 240 Mpa.

140 Care should be taken to avoid any damage to the coated rebar’s during shipment handling fabrication and
placement of in structure.

141 Equipment made of aluminum alloy shall not be used for pump lines, or chutes used to discharge concrete from
truck mixer.

142 Racking shall not be used for movements of concrete after placement and vibrator shall not be used to move
concrete inside.

143 Retampering of concrete are prohabitated after placement of concrete.

144 50mm of blinding or vapor barrier plastic sheet of 0.15mm thickness should be placed beneath slab on grade.
Outdoor, side walk are exempted from this requirement.

145 The minimum thickness of grout should be 25mm from top of concrete foundation to the bottom steel base plate.

146 Where the existing sub-grade material have CBR of 5, a sub-base with minimum CBR of 15 shall be provided with
minimum thickness of 200mm.

147 Asphalt for foaming shall be supplied at temperature not less than 175C and more than 200C and stabilizing work
shall be undertaken only when ambient temperature is above 15C.

148 Moisture content of in-situ material shall be tested not more than one week in advance of the asphalt foaming
operation.

149 A minimum 1 line of sample shall be taken at 2.0meter interval across the road width and every 500 meter in
linear length. Check shall be conducted when wet weather occur between initial testing and work commencing.

150 Prime coat of 2 types are used in ARAMCo projects such as MC-70 and MC-250 for its atmospheric temperature
should be minimum 16 c or more.

151 For MC-70 temperatures should be between 50 to 80 centigrade, and pressure distribution at the rate between
0.65 to 1.75 liter/meter square.

152 For MC-250 the temperature should be between 65 to 105 centigrade and pressure distribution at the rate 0.65 to
1.75 liter/meter square.
153 Tack coat shall be of RC-250 or RC-800; tack coat shall be applied on paved surface and vertical surface.

154 Hot mix asphalt concrete shall be placed only when the atmospheric temperature is 4 C or above and when
weather is not fogy or rainy and when existing surface is free of moisture, and all compaction shall be completed before
temperature drop the 90 C of asphalt concrete.

155 Concrete slab or paving adjacent to the foundation shall have minimum 12mm isolation joint around the
foundation using approved elastic joint filler with sealant on top.

156 In the event that foundation size is greater than 1.20meters thickness is required for stability rigidity or damping
the minimum reinforcing steel may as recommended in ACI-207.2R with suggested minimum reinforcement of 22 mm
bars at 300mm on centre.

157 Design shall be such that buried cables, pipes, etc will not be incorporated in foundation and be protected from
the influence of foundation stress.

158 Main reinforcement in pier shall not be less than 1% nor more than 8% of the cross area of the piers.

159 Minimum tie size of pier shall be 12mm and maximum spacing in piers shall be smallest of 8 bars diameter, 24 tie
diameter, or 1/3 the least dimension of the pier.

160 Slab with the thickness of 500mm or more shall be provided with shrinkage and temperature reinforcement in
accordance with ACI-318.

161 For concrete foundation the weight of foundation for reciprocating equipment shall not be less than 5 times and
for rotary equipment shall not be less than 3 times of the weight of the machinery. Unless analysis demonstrates that a
lesser value will perform adequately.

162 Minimum thickness of the concrete foundation for machinery shall not be less than 600mm.

163 For block foundation for reciprocating machine (compressor and so forth) should have minimum of 50% of block
thickness embedded in soil. Unless otherwise specified by equipment user.

164 For grouting total dissolved solid for mixing and curing water shall not exceed 500ppm and minimum compressive
strength shall not be less 5000psi (34.5Mpa).

165 When type of grout is not specified by equipment manufactures then cementitious grout shall be applied for these
conditions for rotating equipment. (1) Driver horse power less than 500 (373KW). (2) 3600 rpm or less.
(3) Combined weight of machine, driver and base plate up to 2270kg (5000 ibs)

166 Solvent cement and primer for thermoplastic and RTR piping should not be stored if no expiration date is clearly
specified on the container.

167 The depth of trench shall be dug deep enough to provide a minimum ground cover above the top of pipe as
required that should be 300mm minimum.

168 Ground bed below the bottom of pipe should be provided at least 150 mm of clean sand.

169 Plastic pipe such as PVC, UPVC, CPVC, RTRP, HDPE, PP etc shall be protected from contact with concrete by
wrapping tap.

170 4 cylinder are taken out of 115 meter cubic during pouring 1 is tested after 3 days, 2 is tested after 7days and
remaining 2 are tested after 28 days. After 7 days compressive strength should be minimum 70% of 28 days.

171 The type of soils (1) Gravelly or sandy soil with some stone fragments. (2) Silty or Clayey gravel and
sand. (3) Sand dunes. (4) Silty soil. (5) Clayey soil.

172 For backfilling not more than 3% organic or decomposable material and particles size of 75mm or half of lift.
173 For relative density results should be like that. (1) Traffic area 85%. (2) Non Traffic area 70%.

174 Proctor density result should be like that. (1) Traffic area 95%. (2) Non Traffic area 90%

175 Length of one rebar strip is 12m and it could be 5 mm plus or minus.

176 foundations shall be found on either undisturbed soil or compacted fill and at least 600mm below the existing
finish grad surface.

177 The minimum over tune stability ratio for service load combination including wind load shall be 1.5 for foundation
design and open frame structure where the dead load factor 0.6 the minimum over tune stability ratio shall be 1.0.

178 Select fill material should have passing at least 100% passing of 50mm sieve and 0 to 20 % passing # sieve 200.

179 Plasticity index is not required if material has less 15% fines passing # 200 sieve.

180 Overlaps in vapor barrier (plastic sheet) should be 150 mm and thickness should be 0.15mm minimum.

181 The rough gradation under slabs and footing shall be to minimum tolerance of 0.00 mm or -38mm and fine
grading where required shall be performed to a tolerance of 0.00 or -25mm.

182 When backfill material cannot be defined either cohesive or cohesion less then both relative density and proctor
density test are conducted.

183 Compaction by water jetting is not permitted but flooding may be used if material is cohesionles freely drained
sand.

184 No compaction should be allowed on slop greater than 1:5.

185 pH value of mixing water should be 6-8 this test is conducted to check the values of acid and alkalis in water.

186 Dead load is the actual weight of material forming the structure foundations and all permanent attached
appurtenances.

187 Live load is those entire gravity load produced by the use and occupancy of the structure this include all move
able load.

188 Surface contaminates such laitance and form soil must be removed by steam cleaning with water emulsifying
detergent added and laitance shall be removed by wire brushing.

189 Perimeter of columns must extend 1200mm.

190 Minimum size of high strength bolts should be 20mm of diameter.

191 Where foundation protrudes through the paving 12 mm diameter reinforcement bars having length minimum
800mm should be place diagonally in the paving at all interior corners.

192 for precast and water retaining structure the 28 days compressive strength should be 5000psi (35 Mpa), and
142.185 psi is equal to 1 Mpa.

193 When we prepare RFI for rebar material inspection the following documents should be attached (1) Delivery
notes. (2) Quality assurance certificates. (3) Mill Test reports.

194 Admixtures are chemical in liquid form which is used in order to improve or change some properties of fresh or
hardened concrete. These are the some types of admixtures. (1) Retarders (2) Plasticizers. (3) Retarding
plasticizers. (4) Super plasticizer. (5) Air entertaining Agent.

195 Retarders these chemical delay the initial setting time of concrete to give more time for transporting, placing,
compaction and surface finishing.
196 Plasticizer is water reducing admixture, it can reduce water demand in mix by 12% obviously that can be used in
2 different way (1) to reduce water content at the same slump. (2) To increase slump at the same water content.

197 Retarding plasticizer these admixture combine retarding and water reducing properties in one material.

198 Super plasticizer this type admixture can reduce the water demand in mix by up to 40%. There by facilitating
extremely low W/C ratio they can be used in the same two ways like normal plasticizer.

199 Marl: It is the wide variety of calcareous soil material found in Saud Arabia which may vary from clay or
gravel size and often include cobble and boulders size pieces.

200 Fill material: It consist of gravel sand or marl. The maximum size of fill material should be one half of the lift
thickness or maximum 75mm. Fill material shall be composed only of in organic material shall have 100% passing of
50mm sieve and 0.00 to 20% passing of sieve # 200.

201 Top 150mm of any area to receive fill, foundation, pavement, are the area to be used in future to support structure
load shall be scarified and recompose and compact.

202 Capping material shall have a maximum size of one half lift thickness approximately 75mm and should have
passing 11 to 35% of sieve #200.

203 Slope steeper than 1:5 (20%) may require erosion protection such as cohesive marl (Plasticity index greater than
12).

204 In place density and moisture content of soil shall be tested (determined) by sand cone method. ASTM D 1556,
nuclear method, ASTM D 2922 and rubber balloon method as per ASTM D 2167.

205 Greater than 1530 mps which required blasting or pneumatic rock breaker to facilitate excavation.

206 Solvent and paint shall not be applied to surface warmer more than 80C. Solvent shall not be flushed in to
container that is hotter than 50C.

207 The pull off of coating should be 175psi or exceed for immersion service and 260 psi for industrial floors.

208 New concrete surface must have moisture content of 4% or less before the coating application commencing.

209 Crack less than 10mm wide and holes not exceeding 10mm in diameter shall be filled using a qualified epoxy filler
of grout before applying primer / sealer.

210 Maximum drop to catch basin from high point of paving shall be 200m and its ratio is 1.5% or 1:65

211 If sulfate content is less than 1500ppm and chloride is more than 500ppm the type 1 cement and FBE rebar are
used.

212 Conduit, pipe and other items made from aluminum shall not be embedded in structural concrete unless
effectively coated to prevent aluminum reaction with concrete.

213 Paving or slab construction joints not specified on the drawings shall be located at column s centre line and
intermediate intervals.

214 Water stopper shall be provided in joints where water tight construction is required.

215 Release strength for pre-stressed unit shall be 24.10 Mpa (3500psi).

216 Concrete cover for precast concrete exposed to earth or weather = 75mm. Wall panels =25mm. Slab and joints =
40mm. Beam and columns =50mm. Concrete exposed to sea water or sewage =75mm.

217 Maximum acid soluble chloride ions and sulfates as SO3 in concrete shall not exceed 0.25% and 4% by weight of
cement.
218 Metallic sleeve are not allowed and anchor bolt should not contact with reinforcing steel.

219 Calcium chloride as admixture should not be used in precast and pre-stress and pre- cast concrete.

220 The rebar for pre-cast and pre-stress concrete shall be acceptable under the ACI 318M.

221 For rebar minimum yield (compressive) strength should be 422Mpa or 60ksi (60000psi). Welder wire with
minimum strength of 240Mpa or 34.8 ksi (35000psi)

222 Curing compound shall not be used for curing of pre-cast or pre-stress concrete elements.

223 Sample of pre-cast shall be prepared as 400mmx400mmx40mm.

224 Cement based grout shall be free of hydrogen gas producing, oxidizing catalysts and inorganic accelerators.

225 When water cement ratio is 0.40 or less the concrete shall be continuously water cured for minimum 7 days.

226 Epoxy grout shall be applied only when surrounding temperature is between 15C to 32C.

227 If grouts pour is 100mm or deeper then grout manufacture recommendation for installing reinforcement rebar shall
be followed.

228 The corner of mounting plate shall be rounded to at least a 50mm radius where feasible to prevent crack
producing stress raiser in the grout.

229 Pedestal is not located with 150mm of a paving joint. The minimum ring wall width shall be 300mm.

230 When required the additional 3mm corrosion allowance should be applied. To calculated anchor bolt diameter.

231 Anchor bolt subject to up lift or vibration shall be equipped with an additional nut to serve as lock nut to ensure
against loosening.

232 Vibrator should be applied in concrete after each 500mm to 600mm, each place it should work 30 second.

233 During pouring concrete should be casted in layers and each layer s thickness should be 450mm.

234 pH value of water using for concrete should be 6-8 and pH value mean the quantity of acids and alkalis.

235 For back filling or filling liquid limit or plastic limit test are not required if material has less than 15% passing the
sieve # 200.

236 Concrete fireproofing shall be either cast in place or gun-tie with a minimum thickness of 50mm.

237 A clearance of 300mm shall be placed the vessel surface and fire proofing material on support legs, skirts, and
saddles

238 vessel support legs shall be fire proofed from grad up to level 30mm blew the contact line, surface between legs
and vessels.

239 All kind foundations structure the top of concrete shall be minimum 150mm high above the finish grade.

240 Finished thickness of gypsum plaster shall be 16mm and finish thickness of Portland cement shall be 22mm.

241 Door to resident sleeping unit shall be clear width of not less than 711mm and 1930 minimum height.

242 The maximum width of swing door shall not be less than 1219mm and minimum height 2032.

243 For precast concrete slump should not exceed 75mm.

244 Course aggregates should be washed prior to concrete batching with water not exceeding 3500ppm of TDS.
245 The concrete surface shall be subjected to final curing with free water maintained on their surface at all time a
temperature of 23 plus minus 2C.

246 Variation in dimension between the centers of adjacent bolt group shall be equal or less than 3mm.

247 The vertical tolerance on longitudinal reinforcing bar placement shall be no more than 6mm.

248 Tolerance on other embedded items location shall be 25mm plus or minus.

249 Irregularities in surface of form work shall be less than 3mm. Tolerance on formwork cross section shall be 6mm
and 4mm plus minus.

250 In case the rate of application of curing compound is not specified, apply the liquid membrane at the rate of
5meter square per liters.

251 A 6mm chamfered corner shall be used on the all longitudinal corners or fence post members.

252 The maximum amount of repaired damaged rebar coating shall not exceed 1% of total surface area in each
300mm of bar. This limit not includes the sheared or cut ends.

253 All ready mix concrete shall be delivered to the site with a batch ticket listing the following Name of ready
mix company, Serial number of truck, Truck number, date, Name of purchaser, Name of job and location, Saudi Aramco
mix design number, Amount of concrete in cubic meters, Time of loading, Checking the revolution counter, Type brand,
amount of cement, micro silica, aggregates, admixtures, mix water, Mass of fine and course aggregates and size of
aggregates.

254 Epoxy grout shall be applied only when surrounding temperature is 15 to 32C and its sample for testing are mad
50x50x50 cubes

255 Standard specification for structural bolts, steel, heat treated 120/105 Ksi( 830 Mpa) minimum tensile strength.

256 In RFI mostly we writes: RFI number, date of inspection, name of inspectors of contractor and consultant, location
of work and description or work.

257 To get weight of rebar of 1 meter following formula should be applied: DxD/162.162.

258 Distance between 2 layer of rebar should be bigger one value of following 3 option. Minimum 25mm, equal to size
of aggregates, equal to the size of diameter of rebar.

259 Before pouring concrete existing surface of concrete should be chipped and wet by concrete bonding agent.

260 Slab using for vehicular traffic should not be less than 150mm and for pedestrian it should be 100mm.

261 Select fill 600mm in height shall be used for the minimum thickness under FDS, slab on grad, spread FDS.

262 Overlap of vapor barrier should be 150mm. It should be laid upon existing ground prior to casting.

263 FBE Coated rebar shall be stored off the ground on proactive cribbing 300mm high from ground.

264 FBE coated rebar should be stored in outdoor area without protection not more than 3 month.

265 Maximum amount of damage of coating should not be more than 1% within 300mm. Bending and cutting area are
not included.

266 FBE coated rebar shall not be cut with flame and grade of rebar using in Saud Aramco is 60 grades.

267 Grade is stress and strength of rebar. There are different grades rebar’s are available in market.

268 Formwork and runway shall not be supported with reinforcement erected for any kind structure.
269 Expansion joint shall be maximum 20mm; control joint shall be 4mm and construction joint shall be 1.6mm.

270 Minimum size of anchor bolt should be 20mm or follow the drawing.

271 For road and under heavy equipment 1/90 meter square FDT, for paving 1/180 meter square and for linear trench
1 test require for each 15 meters minimum.

272 Water content of base and sub-base material should maintain plus/minus 3 of optimum moisture.

273 The prime coat of MC-70 or 250 shall be applied with 0.65 to 1.75 liters / meter square, and it should be applied
extra 300mm both sides.

274 During placement MC-70 should have temperature 50-80C and MC-250 should have 65-105C.

275 Atmospheric temperature should be 16C minimum prior to prime and tack coating application. During rain, foggy,
sand storm, application of prime coat is not allowed.

276 Minimum rate of application of tack coat shall be 0.25 liter/meter square. After tack coat within 3 days one has to
place asphalt layer.

277 RC 250 and RC 800 during application should have temperature 65C to 105C.

278 Asphalt core compaction shall be 96% marshal density and each test sample is taken from 200 ton of asphalt.

279 Without covering asphalt in truck is not accepted and asphalt placing is not allowed less than 4C air temperature.

280 Maximum thickness of asphalt layer should be 80mm and minimum it should be 50mm.

281 Any asphalt pavement touching with pipes shall be catholically protected.

282 Gypsum board metal stud spacing is 400-600 mm center. Door window and opening area to be used double stud.

283 Normal gypsum board shall be continuing minimum 50mm from ceiling. Fire rated gypsum board shall be
continue until the end of wall.

284 Fire rated gypsum board color is red, water resistance gypsum board color is green and regular gypsum board s
color is blue.

285 Minimum expansion joint length of gypsum board wall is 15 feet (4.57m).

286 Water cement ration for non-structural is 0.6, for structural water cement ratio should be 0.4 and water cement
ratio for cementious grout is 0.8.

287 Test to check TDS value and pH value (6-8)of mixing water should be carried out one within week.

288 Silica fume is used as mineral additive shall not be 7% to 8% of weight of cement as replacement.

289 Design strength of cement based non-shrink grout shall be 5000 psi after 28 days, for checking strength fill the
cube of 50x50x50. .

290 The type of anchor bolt for structural steel connector is A-325.

291 Need to conduct 4 hour hydro test on uncovered oily water sewer line, 24 hour in covered oily water sewer line.

292 There is need 150mm minimums thickness of sand bedding for pipe in trench and 300mm thickness of sand
cover from top of pipe to finish grade.

293 3 meter is the head of water for gravity test on sewer line and it shall be covered with clean sand.

294 150 psi is the working pressure of an ARAMCo fire water main line.
295 Red is the color of dye mixed in concrete for electrical and instrument duct bank and orange is the color of dye
mixed in concrete for communication duct bank.

296 Sewer pipe line in trench shall be covered with clean sand.

297 Reinforcing steel bars shall conform to SASO SSA2, hot rolled high tensile deformed steel. The bars shall be
acceptable under the ACI 318M specified limitation of 422 Mpa 60000 psi.

298 Release strength for pre-stressed concrete grout shall be 3500psi. Pre-stressing tendon shall be non coated.

299 Cement content for pre-cast concrete shall be minimum 350 and maximum 370 Kg/ meter cubic.

300 Concrete material shall be in accordance with 09 SAMSS 097 and FBE reinforcement shall be in accordance with
09 SAMSS 106.

301 Retarders are used for increasing time of initial setting, Plasticizers are used to increase workability and super
plasticizers are used to get early strength.

302 Inside of wall construction joint shall be provided at maximum of 6m and expansion joint shall be maximum 16m.

303 For lifting of concrete panels or cubes the bar hook should be minimum 16 mm of dia.

304 Size of course aggregates in structural concrete should be maximum 20mm and minimum 10mm.

305 Insulation of roof shall be always flexible and time to test the leakage test of roof is 24 hours.

306 Welded wire fabric shall conform to SASO – SSA 224 cold drawn wire with minimum yield strength 422 Mpa.

307 Water proofing membrane of roof shall be U/V protected, U/V water proofing shall be done in 2 coats and each
coat of U/V proofing shall be 400 micron.

308 Maximum acid soluble chloride ion in concrete shall not exceed by 0.25 by weight of cement. Maximum sulfate
(SO3) in concrete shall not exceed by weight of cement.

309 Vapor barrier to be used below the concrete shall be not less than 0.15mm and overlap should be 150mm.

310 During checking slump time for lifting the slump cone is 5 to 7 second.

311 Allowable deviation in moisture content in sub-grad is plus minus 3% of optimum moisture content.

312 Sub base shall be provided when CBR of sub-grad is 5 or less. For weak sub-grad minimum thickness of sub-
base shall be 50mm.

313 Class A sub-base: It is well graded gravel with sand and silt; it should pass 100% of 6 mm sieve and 0.00 to 15%
of sieve # 200.

314 Class B sub-base: It is uniform mixture of gravel, stone fragment with sand silt and clay, it should 100% passing
of 5mm sieve and 5 to 15% from # 200.

315 Adhesive of RTR pipes shall be stored in a closure where temperature does not exceed 38C.

316 Prior approval is required for installation for non-metallic piping under slab or similar structure.

317 Solvent of thermoplastic pipe shall be stored in air conditioned building maximum temperature 27C.

318 Gasket O rings and locking keys shall be stored flat on racks below 38C and out of direct sunlight.

319 Pipes and fittings shall be protected properly from impact especially on their end; they shall not be thrown
dropped, bumped, hit or dragged and pushed over abrasive surface.
320 Loose thermoplastic and RTR pipes shall be handled by hand or using nylon cotton strip spreader sling.

321 Bottom of trench should be dry before pipes are installed.150mm sand bedding at the bottom of pipe.

322 At the end of every work pipes end shall be capped and piping shall be anchored to prevent the floatation.

323 If we want to keep pipes in one place then height of these pipes should not be more than 1.5m without support.

324 Existing surface of concrete should be roughened and bonding agent should be sprayed prior to casting new
concrete layer.

325 In paving slab control joint should extend in to the slab of ¼ of thickness deep.

326 After pre-cast installation such as main hole, catch basin, closed drain no need to raise RFI for moisture test and
surface repairing. Because it have been done already.

327 During cable laying (instrument, electrical or communication) only sand covering backfilling and tiles placing RFI s
are raised by civil QC inspector but cable installation RFI is raised by electrical QC inspector.

328 Neoprene foam is used to wrap pipe (RTR, PVC) coming inside concrete.

329 Thermacoal and Styrofoam is same thing which are used in concrete to make space for passing pipes or other
things after placement of concrete.

330 Before pouring next layer of concrete or plastering roughing concrete surface and apply bonding agent.

331 Tolerance allowed on the spacing of rebar on installation in 50mm.

332 10-20mm size aggregates are used for micro silica concrete and less than 10mm size aggregates are be used for
screed concrete.

333 For pre-cast concrete these RFI s are raised. (1) Visual inspection before installation. (2) Positioning and
orientation. (3) Element to element sealing. (4) Protective coating.

334 In some foundation where pockets are coming there one kind wire shylock and stereo foam is used.

335 In tanks after completing foundation wall and anchor bolt. These RFIs are raised to precede work.
(1) Concrete ring wall acceptance before granular fill compaction. (2) Granular fill compaction before
another granular fill compaction. These RFIs are raised layer by layer up to the last layer. (3) Granular fill
elevation and slop check before HDPE membrane installation. (4) HDPE membrane installation before sand backfilling
over HDPE. (5) Sand backfilling over HDPE before interval backfilling completed and accepted. (6) Stabilizing
layer before bituminous layer installation. (7) Bituminous layer installation before final check.

336 There are 2 types of tests to check HDPE (1) VACUUM TEST. (2) SPARKING TEST for these tests also need to
raise RFIs.

337 During compaction of sub-base sub-grad should be kept drained.

338 Thickness of compacted layer of base course should not deviate more than 6mm.

339 Allowable deviation in optimum moisture content of base course is 1.5%.

340 Prime coat is applied on the top surface of base course and Tack coat is applied on the top surface of asphalt
binder course.

342 Atmospheric temperature at the time of asphalt placement should not increase plus/minus 4C. Asphalt
temperature in truck at placing spot shall be 139 – 163C.
343 If surface of concrete subject to coating is chemically contaminated the wash it with water and longtime
contaminated surface of coating shall be neutralized by soaking 24 hours and pH values for neutralization should be 6 to
8.

344 If water cement ratio is 4 or less for cement based grout then keep it water curing minimum for 7 days.

345 Design strength of epoxy grout after 7 days should be 14000 psi and cementitious grout design strength is 500psi.

346 If grout is 100mm or deeper then install rebar in that.

347 Working time for epoxy grout for machinery support is 50 mm @ 32C. The corner of mounting plates on epoxy
grout shall be rounded for at least 50mm radius.

348 No load bearing CMU shall be used for non-load bearing partitioned not for exterior wall.

349 Foundation shall be found on either undisturbed soil or compacted fill at least 600mm below the existing of finish
grad.

350 Foundation support steel base top of concrete shall be minimum 150mm above the finished grad and foundation
shall not be placed above the underground piping telecommunication or electrical items.

352 Foundation including pipe line anchor block constructed near the slope should ensure that a 45 degree plane
extending downward from the bottom edge of the foundation does not intersect the slope face.

353 150 mm of any area to receive fill foundation, pavement are area to be used support structural shall be scarified.

354 Fill or backfill adjacent to structural such as a retaining wall pit and basement and with heavy equipment and
within 1.2 meter use only hand operated equipment.

355 For wet mix concrete batched in central plant and transported in truck mixer. The volumes of concrete shall not
exceed 80% the rated volumes of mixer truck drum.

356 Dry batched truck mixed concrete total shall not exceed 63% of total volumes of mixing truck s drum or container.

357 Micro silica is added to concrete to protect concrete structure from chemical attack this substitute for cement
having range 7-10% by weight of cement.

358 The raw material for concrete is water, cement, micro silica, aggregates, fine aggregates and admixtures.

359 Water required for aggregates washing should not exceed TDS by 3500pp.

360 Anchor bolt tolerance for installation. (1) Should be equal to or less than 3mm between centre adjacent anchor
bolts with in anchor bolt group. (2) Should be equal or less than 6mm between the centres of adjacent bolt groups.
(3) Shall be plus minus 13mm in elevation of the top of bolts. (4) Deviation in plumpness should not more than 1.5%.

361 For surface preparation prior to coating. (1) Sand blasting. (2) Grinding to medium grit. (3) Repair crack whole &
other surface irregularities.

362 Following tests are required prior to coating. (1) Humidity should be 85% or less. (2) Surface temperature should
be between10 to 80C. (3) Moisture test with 450x450 polyethylene sheet of 0.15mm thickness after 16 hour moisture
should not be more than 4%. Dew point should not be less than 3C.

363 After 12 hours side formwork of footing, wall and columns can be removed.

364 For bolt projection = thickness of grout + thickness of plat + 2.5 x diameter of bolt (it is for double nut bolt). (2)
Thickness of grout + thickness of plate x 1.5 x diameter of bolt (it is used for single nut bolt ).

365 The height of slumping measuring is 300mm and cylinders of concrete have also same height.
366 Allowable time gape in concrete pouring after discontinue is 20 to 30 minutes.

367 Fire proofing is commonly used in Aramco project to delay the main structure by being affected by fire for (1-2)
hours delay.

368 Pouring height for grouting of CMU (concrete masonry unit) should be able 1.220meter.

369 For 3 meter length of the tolerance of gap of tiles is 6mm. For retaining wall s minimum thickness should be
300mm.

370 Vibrator in concrete should be implementing after 500mm to 600mm distance and one place it should work 30
second.

371 Minimum thickness of reinforced concrete for paving in area that subject to spill, wash and side walk should be
100mm.

372 Water used for compaction should have TDS 10000 ppm maximum, and for aggregates washing it should be
3500 ppm.

373 There are 3 type of lab ASTM soil density test and their minimum required density values are these.
(1) Standard Proctor Test. (2) Modify Proctor. (3) Relative Density.

374 The most important elements of soil classification are following: (1) Type of soil. (2) Atterberg limits (liquid limits,
plastic limits, and plasticity index).

375 Project s conditions and factors that control compaction are following: (1) Proper moisture content. (2)
Compaction equipment used and the number of rolls. (3) Type of soil. (4) Confinement of soil.

376 For inspection of formwork the following things are main concerns: Position, length, width, height, stability,
plumpness, cleanness, oil coating, chamfer in corner, distance from existing buildings and bonding agent on existing
concrete prior to start another concrete work.

377 For reinforcement following things should be performed. Space of rebar, concrete cover, lap splice, development
length, Bending and tie bar, rebar number and size, coating touch up and anchor bolt should not touch rebar.

378 There are 2 types of pre-stressed concrete. (1) Pre-tensioned concrete. (2) Post tensioned concrete.

379 Effect of sea water on concrete is the following. (1) It increases the risk of corrosion of rebar. (2) It weakens the
strength of concrete. (3) Crack occurs due to the crystallization of salt in concrete mix.

380 Reason behind crack: Poor curing, poor design, poor vibration, less rebar covering, poor quality of concrete.

381 Rebar splicing should be staggered / wire for tie rebar should be double or butterfly type.

382 Span in between two columns should not have any splicing in the middle area of ¼ of whole length.

383 There are some densities: (1) Rebar density = 7850 kg/m3. (2) Concrete density = 2400-2600 kg/m3.
(3) Aggregate density = 2800. (4) Water density = 1000 kg/m3. (5) Asphalt density = 2400-2600 kg/m3.

384 Maximum temperature of concrete that can be poured in to structure shall be 32C and within 90 minutes and prior
to 300 revolution concrete should be discharge.

385 Plant scale shall be calibrated 3 times per year and shall be certified by independent laboratory.

386 Drop vibrator under its own weight and vibrator tip must penetrate 10mm in to previous layer.

387 Maximum slop of chute in pouring concrete is 1:2 and minimum slope is 1:3 (vertically too horizontally).
388 Minimum length of splicing for rebar is 57-65x diameter of rebar. If splicing is done on different size of rebar adapt
bigger.

389 We can apply concrete curing after initial setting. Initial setting start after 35 to 40 minutes.

390 maximum time of stationary or central batching plant for concrete mixing is 50 to 90 minutes.

391 Bend of rebar D=diameter of bend, d=diameter of rebar. D=6d for 22mm diameter rebar or less. D=8d for 24-
28mm diameter rebar. D=10d for 30mm diameter rebar or above.

392 California bearing ratio is laboratory value that determine the soil bearing capacity and classifying soil. It is design
parameter. CBR value should be 20% for feeder and 25% for highway roads minimum.

393 If the top most layer of sub-grad was compacted and tested one month back and next layer is to be backfilled it
should be cleaned spray water and re-compact until compaction is attained.

394 SPT: Standard penetration test usually mad to evaluate the bearing capacity of soil.

395 The maximum size of rock use in rock fill shall not be more than 600mm.

396 Minimum distance of borrow pit from structure should be downstream 200m and from road way the toe of
embankment is 30m.

397 Tolerance requirement of sub-grad prior to asphalt placing should be 6mm longitudinally/3metre, for sub-base it is
4mm longitudinally/3metre and for finished asphalt surface it shall be 3mm longitudinally/3metre.

398 MC 1 smell like kerosene and looks dull and thicker and RC 1 smell like benzene and look shiny and thinner.

399 Determining the grade of rebar on site by its longitudinally mark. (1) Grade 40= No marking between longitudinally
strip. (2) Grade 60 = 1 line between the ribs of steel. (3) Grad 75= 2 line between the ribs of steel.

400 ASTM DD 1557 for backfilling. ASTM D 2922 for soil testing. 09 SAMSS 09 for concrete material. 09 SAMSS 106
for FBE coated rebar, ACI 305R for hot weather concrete.

401 A 114-Excavation and backfilling. 409 H 003-Coating requirements for concrete surface.

402 H 101-Aproved proactive coating system. 411 N 130-Installation of fire clay bricks.

403 M 009-Structural design criteria for blast resisting structure.

404 Q 001-Cretirea for design and construction of concrete structure.

405 Q 005-Concrete foundation. 415 Q 006-Asphalte concrete paving.

406 Q-007-Foundation and supporting structure for heavy machinery.

407 Q 009-Concrete retaining wall. 418 Q 010-Cement based no shrink grout.

408 Q 011-Epoxy grout for machinery support. 420 S 010-Santry and sewers.

409 S 070-Installation of utility piping system.

410 Q 012-Criteria for design and construction of pre-cast and pre-stressed concrete.

411 Inspection Test Plan it is mandatory item in quality plan that guide and assure quality in specific type of work
in specific sequence of QC activity steps.

412 These reference shall be found in ITP 1- SA Standards. 2- Code references. 3-Procedure.
4-Specifications.
413 These types of inspection action are found in ITP 1- Witness. 2-Hold. 3-Surveillance.
4-Review.

414 Quality System An organizational structure procedure process and resource needed to fulfill quality
management.

Вам также может понравиться