Вы находитесь на странице: 1из 1

• PRODUCTION PROCESS PROCEDURES

• Note: Item to check before operation: CONTROL PANEL AND LABELS


• a. check raw water tank if empty. Machine should not be run without raw water.
• b. check all closed ball or gate valves. Be sure that all valve set at the std. position.

• 1. Turn “ON” the main switch or breaker (R).


• 2. Turn “ON” the Raw Motor switch (A). V.) U.) AUTO WASTE S.) U.V.
MEMBRANE DISPOSAL TIMER T.) R.O. PRESSURE BALLAST
• 3. Raw motor will stop after about 5sec. then Turn “ON” the R.O. ADJUSTER VALVE
/HOUSING
motor switch (B). R.) MAIN
• 4. Set the R.O. pressure gauge’s pointer (P) on the std. machine POWER
operating pressure: (100~150psi) A.) RAW SWITCH /
MOTOR
• 1. Turn the R.O. pressure adjuster valve (T) clockwise “tighten- BREAKER
SWITCH
up to increase the pressure” while monitoring the movement of the
R.O. pressure gauge (P). Q.) U.V.
• 2. Adjust the R.O. adjuster valve until the R.O. pressure gauge B.) R.O. (Ultra Violet )
reading will rise up to desirable operating pressures. (90~150 psi) MOTOR LAMP
SWITCH
• Note: To prevent the machine from water leaks, the R.O. pressure P.) R.O.
setting must not exceed the max operating pressure of 250psi. C.) PRESSURE
• Important : PRODUCT GAUGE
MOTOR
• * You should replace or clean your membrane when your R.O. pressure is already SWITCH
set at 150psi but your product rate readings on the flow meter is less than 1gpm. O.)
D.) U.V. LIGHT SYSTEM
• * If you hear unfamiliar loud noise or sounds coming from your Procon pump, then SWITCH PRESSUR
you should immediately stop your mach. and check your system. (loud noise
usually heard when your procon pump cannot received sufficient water from the E GAUGE
pre-filtration system). N.) WASTE
E.) PRODUCT
• WARNING: Clogged membrane and insufficient water supply at your R.O. WATER FLOW
FLOW METER
process may damaged your procon. METER
M.)
F.) R.O. MOTOR CARBON
• WATER REFILLING PROCEDURES SOL. VALVE FILTER
• Note:
• a. Be sure that you have enough product water from the product tank. L.) SEDIMENT
G.) / OTHER
• b. Always disposed at least 5gals of water in the 1st refill in the morning. PROCON
• 1. Turn “ON” the product motor switch (C) PUMP
• 2. Turn “ON” the U.V. Lamp switch (D) K.) SEDIMENT
• 3. Put the cleaned empty containers under the faucets and open H.) PRODUCT i.) R.O. J.) RAW FILTER
the faucet valve to start the refilling process. Close faucet valve to MOTOR MOTOR MOTOR
stop re-fill process.

Note: some parts / label may have difference in position or location. Pls. check your
machine model.

Copyright Equizone Enterprise 2009 ver. 1.3, revision Date: 05-20-09