Pakistan Jannah Hydropower Project

The construction scheme


Jinnah Hydropower Project The Construction Scheme

Contract No:DEC-PJHP-0008

Approval: Mr. Xie Ying

Audit: Mr. Zhong Zhaokun; Mr. Cai Shurong

Write: Mr. Luo Chunhua ; Mr. Sam Tsang

Guangdong Yuantian Engineering Co. (GYT)

Feb. 2006

Table of Contents

Section I
1 The Project.......................................................................................................3
1.1 general situation of power station............................................................3

1
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

1.2 instalation Work scope............................................................................3


2 Construction Organization structure................................................................4
2.1 Organization chart..................................................................................4
2.2 Manpower Planning................................................................................5
3. Arrangement of Work Yard, water and electricity supply, Temporary Building 6
3.1 Temporary Building .................................................................................6
3.2 Electricity and water supply...................................................................7
4. Construction equipments and facilites planing ...............................................7
4.1 Main construction equipments.................................................................7
4.2 Main test instruments & facilities...........................................................10
5. main equipments Installation technique.........................................................12
5.1Standard and regulations.......................................................................12
5.2Construction progress planing................................................................15
5.3 Loading/unloading &storing...................................................................15
5.4 Power House Overhead Bridge Crane Installation Procedure..............16
5.5 Turbine Generator Unit Installation........................................................17
5.6 Electrical Equipment Installation............................................................20
5.7 oulet and inlet Gates, Trash rack Installation........................................25
5.8 Gantry Crane Installation.......................................................................26
5.9 Transmission line installation.................................................................27
6.Turbine generator Unit test run....................................................................28
7.completion....................................................................................................29

Section Ⅱ
1. The project

2
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

1.1 general situation of the power station

The Jannah irrigation sluice lies in the Indian River downstream 5km of the Mianwali

Kalabagh, Mianwali, and Punjab, Pakistan. It is the first key project with the function of rising

water level for irrigation system of Thai founded in 1945.

The Jannah power station is a diversion type hydropower station located on the right bank of

the irrigation sluice with the river fall formed by irrigation sluice and ancillary works such as

channel and power house, in which 8 silo case turbine generator units will be installed, power

per unit is 12MW and the total capacity is 96MW. Annual output of the power house is

6.88billion Kw  h , with max flux 2800m3/s, water head 4.7m, hydro turbine speed 72.6rpm
and generator speed 750rpm connected with the speed up gear box. The electricity will be

delivered at 132v primary voltage to the local electrical fence then transferred to Mari Daud

Khel grid station with 2 loops circuit and distance 4km.

1.2 installation Works scope

1 ) The turbine and the accessorial speed governor 8units

2 ) Speed up gear box 8units

3 ) The turbine generator and the accessorial excitation appliance 8units

4 ) The house bridge crane 2units

5 ) fuel 、 air 、 water, hydraulic measurement system and pipeline 1 item

6 ) The generator voltage distribution device 1 item

7 ) 0.4KV electrical system equipment for station service 1 item

8 ) Cable works 1 item

9 ) The control , protection and measurement system 1 item

10 ) The earth system 1 item

11 ) 132KV voltage boosting transformer 1 item

12 ) 132KV switching station equipment 1 item

13 ) The primary electrical lining 1 item

14 ) 132KV transmission line 1 item


3
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

15 ) Communication system 1 item

16 ) Illumination system 1 item

17 ) Ventilating air conditioning system 1 item

18 ) Fire fighting and fire alarm system 1 item

19) Supply and drainage system in the power house 1 item

20 ) The elevator 1 item

21 ) The steel structure( including: gantry crane, inlet gauge ,tail water and the trash rack etc.)
1 item

22 ) generator unit test run 8units

23 ) all Equipment inspection 、 unloading 、 storing and the 2nd handling in site 1 item

24 ) Electrified reconstruction of the 14- water sluice gate headstock gear 1 item

25 ) The repair workshop equipment whole set

26)all permanent basic Embedded parts and pipes installation and part of built-in part manufacture
1 item

27)part of installing Material procurement 1 item

2 Construction organization structure

2.1 Organization chart

According to the features of Jannah project, with the aim of carrying out further construction,

improving the work efficiency and quality, our company will set the Pakistan Jinnah

hydropower project installation works of the E/M equipment & steel structure project office

with a system of project manager responsible for whole construction; consisting of 1 project

manager; 2 deputy project managers; 1 chief project engineer; under the conduct of project
Project manager
office there are 4 managerial divisions in charge of the construction in site and arrangement

of daily life; 8 construction groups are responsible for specific construction works.
The organization chart as showing
Chief below: Deputy project
engineer manager

Planning Engineering Safety 、environment Logistics


Procurement Technique &4 quality department department
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Welding group
Engine Group

Wiring group
Piping group

Lifting group
Steel group
Elect Group

Test group

Wel
M

2.2 Manpower plan

1.Managerial staffs 18

No. DE. QU(P) No. DE QU(P)


Project manager
1 4 6 Accountant 1
department
2 Electrical engineer 2 7 Cashier 1
3 Mech. engineer 2 8 Planning control 1
4 Test engineer 2 9 Mater. & equip. 1
5 Q/C engineer 2 10 Logistics department 2
Total 18 persons

2. Annual manpower plan ( working group )

Number of staff

2006 2007 2008 2009 2010

category 1st 1st


1st 2nd 2nd 2nd
2nd semi- semi- semi- 1st semi-
semi- Semi- semi- semi-
annual annual annual annual.
annual annual. annual annual
. .
Engine
12 12 25 25 25 20 6
group
Electric.
3 4 8 20 25 25 20 6
group
5
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Piping
3 4 6 15 15 15 15 4
group
Steel
12 12
group
wiring
20 20 20
group
Welding
2 6 8 14 14 10 8 2
group
Lifting
2 4 8 10 10 10 10 4
group
Test group 2 4 4 4 4 2
Total
10 30 64 120 125 89 77 24
group
Remarks : The manpower is planning figure that will be adjusted according to the
requirement of the works. This figure is only for schedule.

3. Arrangement of Water, Electricity and Temporary Building

3.1 Temporary building

3.1 . 1 employer should provide construction site , Lodging house and office refer to the
requirements below:

a. The office: building area is 181m 2, decoration and design standard is the same
as the contractor’s: The project manager office is 26m 2;division offices 6 sets,the
standard is 3.5*5 m 2 and the total area is 105 m 2;total area of conference room and
anteroom is 44m 2;duty room is 6m 2.

b. Lodging house: building area is 577.5m 2, decoration and design standard ( with
one bedroom and one bathroom for two person ) is the same as the contractor’s, total
number is 33sets,17.5m2/set.

c. Canteen: building area is 80m 2, decoration and design standard is the same as
the contractor’s.

d. The local staffs and workers lodging house: 20 sets and 24m 2/set.

The specific arrangement of the camp will be determined together with the general
project camp layout

3.1 . 2 in nine month after starting the works, employer should supply temporary storing
yard and temporary warehouse(including temporary fence). The appliances including:
- Storing yard: Flatted with the pebble or crush, including drainage trench and fence ,the
Total area is 5000 m 2.
6
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

- Warehouse, total area is 538.5m 2, including:

a. Equipment & material store house: total area is 319m2;in which heat room takes up
60 m2;

b. Perishable material warehouse: 62m 2;

c. Chemical goods warehouse: 10 m 2

d. Workshop for working group: 5 set, 17 .5 m 2 per set, total area 87.5 m 2;

e. Opening working yard: 500m2, at least require rammed mortar or concreting surface.

f. A car shed for 4 cars, 4×15 m 2.just cover needed

The construction area is 1857 m 2; opening working yard area is 500. The temporary
construction yard should be flat, compacted, water and electricity supplied and
automobile accessed.

3.2 Electricity and water supply

Employer is responsible for the supply work and sufficient supply of electricity and water
in site. And according to the local water and electricity authority price requirement and
relevant administrative specifications, Contractor should pay employer the fee.

Employer is responsible for providing electricity and water supplying facilities, which
including two LV (0.4kv) adoption points at powerhouse and the gate dam.

4. Construction equipments and facilities plan

4.1 The main construction equipment

No. Name Quantity. Model Remark

1 Mobile crane 1 30t

Truck 1 15t

Truck 1 5t

Lorry 2 1.5t

Jeep

Fork lifter 1 3t

Radial drilling machine 1 25mm

Winch 2 5t

7
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Hand operated fork lifter 1 1t

Chain hoist 2 10t

Chain hoist 4 5t

Chain hoist 5 3t

Chain hoist 3 1t

Rack jack 4 10t

Hydraulic jack 2 50t

Screw jack 4 50t

Screw jack 6 30t

Screw jack 4 10t

Screw jack 4 5t

AC welding machine 7 BX1-315,300A

DC welding machine 3 630A

Argon tungsten-art welding machine 3 200A

Electrode pre-heating oven 1 YHX-20

Portable insulated box 6

gas cutting tool 6

Electric angle grinder 4 150mm

Electric angle grinder 8 100mm,125mm

Abrasive wheel cutting machine 2 400mm

Portable electric air compressor 1 0.9/8

electric pipe threading machine 2 QT3-A2

Electric Hand drill 6 6-19mm

Impact drill 6 12-22mm

Magnetic drill 1 J1C2-32mm

Pneumatic spanner 2 M42

Torque spanner 2 400,750kg-m

Motor test pump 1 DSY-250

Hand operating test pump 1 400-1

Hydraulic pipe bender 2 F-18 3"

8
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Cable clamp 1

Theologize 1 J2 (T2)ANGLE

Level meter 2 S3

Ultrasonic detector 1 CTS-22

Magnetic detector 1

44 Pressure oil filter 1 100L

45 bench drill 2 13-19mm

46 coincidence level meter 1 0.01mm/m

47 Frame level 2 0.02mm/m

48 Inside micrometer 2 50-175mm

49 Inside micrometer 1 100-1400mm

50 Outside micrometer 2 0-25mm

51 Outside micrometer 1 25-50mm

52 Outside micrometer 1 50-100mm

53 Outside micrometer 1 200mm

54 Slide caliper 2 150mm

55 Slide caliper 1 300mm

56 Knife edge leveling ruler 2 250mm

57 Angle pneumatic drill 2 50mm

58 Desktop grinder 2 200 mm

Remark:
1.If giant Flat truck or large-tonnage loop wheel machine needed, it can be rented in local

place.
2.The others will be purchased from China.

4.2 Main test instrument and facility

No Name Quantity Model Remark


1 Power frequency 1set XZSB-150/35 For stator winding

resonant testing 150KVA 35KV testing


9
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

device
CQSB
2 AC/DC test transformer 1set
6KVA/50KV
PC ray medium loss DK-9001 tgδ0~30%
3 1set
testing device Cx≤60000PF
4 HV DC generator 1set ZGS 200KV 2mA
Zinc oxide arrester KDY9300
5 characteristic test 1set For testing the whole

device current and active part


Transformer DC BRT-1 10MΩ~2000Ω
6 1set
resistance test device 5A、0.2grade
Transformer ratio ZBY - Ⅲ K = 1 ~ 1000
7 1set
automatic test device 0.2grade
DDG-15/5000
8 strong current generator 1set
0~20KΩ 0.5grade
Earthing resistance test
9 1set Japanese MODEL4105
device
Chargeable HV insulate DMH2550 2500V
10 1set
gauge 0~105MΩ
ZC11D-3
11 500VMΩ meter 1
0~2000MΩ
ZC11D-4
12 1000VMΩ meter 1
0~5000MΩ
ZC11D-5
13 2500VMΩ meter 1
0~10000MΩ
Switch characteristic GKC-98H6 999.9ms Check & record
14 1set
test device 25m/s switch Charac.
Standard voltage HJ47、HJ53、
15 Set/each
transformer HJ110 0.2 grade
Standard current HL36
16 1set core
transformer 100/5--2000/5
LF-ID
17 SF6 leak detector 1set
0.01PPM—10000PPM
SF6 moisture analysis
18 1set DWS-Ⅱ 0--2000PPM
meter
19 Relay protection 1set JBY-1 0--100A 0--5A
10
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

checking meter 0—99999.9mS

SXY-101 0--3600
20 Digital phase meter 1
0~400V 10A
21 PC signal-generator 1set MPFC-1 1.5--99.999HZ
PC precision frequency
WP-903 0--120V
22 conversion power 1set
45—55HZ 0--0.25A
supply
23 Portable PC 1set PⅢ-450
T72-AV 0--600V
24 AC volt-ampere 4sets
0—30A 0.5grade
Japan C1102 0—1000V
25 DC volt-ampere meter 3set
0—30A 0.5grade
26 Millivoltmeter 2set C21-m V 0~100mV
27 Microampere meter 1set ZS-1 0~2000μA
28 Double bridge 1set QJ44 10-4--11Ω
29 Standard resistance box 1set ZX21 0.1--9KΩ
Photoelectric
30 1set DT-2236 0.5--9999RPM
conversion device
Digital clamp current
31 1set MODEL 2002P 2000A
meter
CFMFP03E1 Swiss
32 Standard power meter 1set
3×380V/10A 0.2grade
33 Pressure test device 1set YJY-600A 60Mpa
YB-150 YB-600

34 Pressure gauge Set/each 1Mpa、4Mpa、25MPa

0.4grade
35 Clamp phase meter 1set MG64 0~360O
POS-9020
36 Oscillograph 1set
Two trace20MHZ
37 Digital multiemeter 3sets DT840D
1000A/75mV
38 Current divider Set/each
2000A/75mV
39 Three-phase booster 1set TDGC 10KVA
40 HV insulating protection 1set HV electricity pen、

equipment insulated shoes、

11
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

glove、platform & earthing

protection、
Remark:
1. The test instrument will be newly purchased in China. In addition to those we rent at site.
2. The model and quantity of test instrument can be changed to meet the practical need.

5. Installation method & technique of main equipment

Considering complete the work on schedule and Due to the Jannah power station’s feature:

the number of generator sets needed to install is large, the time for installment is compacting

and the intercrossing work is heavy, we will carry out the construction with 2 sets of bridge

crane, 2 assembly yards (1 assembly room and 1 steel structure platform) and 2 working

faces operate in the same time. In the aim of completing the works on time we will carefully

organize and construct.

5.1 Standard & regulations

1. Acceptance regulations of the hydraulic power station capital works SDJ275-88

1. The unit work quality grade estimation standard & codes of the hydraulic power
station capital works

Turbine generator set installation works SDJ249.3-88

2. The acceptance regulations of the turbine generator unit test run

DL507-93

3. Technique specification for installation of hydraulic turbine generator unit


GB8564—88

4. Standard for acceptance test of hydraulic turbine governor and oil pressure system
GBFF9652.2—97

5. Standard for construction and acceptance of the electrical equipment installation


engineering GBJl47—90

6. Standard for handing over test of electric equipment installation engineering


12
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

GB50150—91

7. Standard for construction and acceptance of overhead power line

GBJ233—81

8. Standard for construction and acceptance of equipment in site and pipe welding
engineering GBJ236—82

9. Standard for construction and acceptance of lifting equipment installation


engineering GB50278—98

10. Code for antisepsis of hydraulic steel structure SL105-95

11. Code for manufacture, installation and acceptance of hydraulic steel structure

DL/T5018-94

12. Code for construction and acceptance of power transformer, oil compression reactor
and transformer electric equipment installation engineering
GBl48—90

13. Code for construction and acceptance of 110—500kV overhead power line GBJ233-
90

14. Code for construction technique of overhead power line SDJ266—87

15. Code for test run of hydraulic turbine generator unit DL507-93

16. Guideline for construction technique of bulb tubular turbine generator unit

DL/T5038-94

17. The primary technique of the generator GB755

18. The primary technique of the turbine generator GB7894

19. Installation and debug workmanship of the turbine thrust bearing and the guide
bearing SD288

20. The static excitation system technical requirement of the large and medium turbine
generator units SD299

21. The stator insulation test regulations of the large HV AC generator

13
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

JB3372

22. The installation and acceptance of the electrical equipment and facility

GB232

23. The basic automation facility system technical requirement of the hydraulic turbine
generator unit GB/T11805

24. the insulating pressure test regulation of large HV AC stator GB50150-91

25. electrical device installation engineering &test standard of handling electrical


equipment GB50150-91

26. The acceptance technical regulations of the electrical works( pipe line )

DL5031-94

27. The acceptance technical regulations of the electrical works( welding )

SDJ151-82

28. The acceptance technical regulations of the piping line works ( Steel pipe )

GBJ235-82

29. The acceptance technical regulations of the electrical installation works

GBJ303-88

30. The safety regulations of the construction electricity supply

GB50194-93

31. The acceptance regulations of the installation of the compressor 、 fan and pump
GB50275

32. The grade estimation standard of the installation of the hydraulic mechanical
equipment SDJ249.4

33. The steel pressure vessel GB150

34. The insulation and the HV test technique of the HV transmission facility

GB311
14
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

35. The power transformer GB1094

36. The dry type power transformer GB6405

37. The AC/HV switchgear GB1984

38. The technical requirement of the AC/HV switchgear SD132

39. The technical requirement of the AC/HV insulation switch SD201

40. The voltage transformer GB1207

41. The current transformer GB1208

42. The communication technical regulations of the hydro-power works

DL/T5080-1997

43. The electrical carrier communication operation and management regulations

DL/T546-94

44. The communication power facility installation regulation YD5040-97

45. The communication power facility installation works acceptance regulations

YD5079-99

46. The electricity dispatching communication equipment technical requirement

DL/T534-93

47. The power oil and the sulfur hexafluoride inspection means

SD304~313JGJ46-88

48. The regulation of hydro-power works safety & industrial hygiene DL5061-1996

49. Safety marks GB2894-88

50. IEC standards & codes

15
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

5.2.1 Works Schedule

No. Item/description Completion Time

1 Switch Yard and transmission line delivery of current 18th Sept. 2008

2 Unit 1 synchronizing 18th Nov. 2008

3 Unit 2 synchronizing 11th Jan. 2009

4 Unit 3 synchronizing 06th Mar. 2009

5 Unit 4 synchronizing 30th Apr. 2009

6 Unit 5 synchronizing 24th Jun. 2009

7 Unit 6 synchronizing 18th Agu. 2009

8 Unit 7 synchronizing 18th Oct.2009

9 Unit 8 synchronizing 18th Dec. 2009

5.2.2 Construction Plan

The construction schedule plan is based on the time for arrival of equipment specified as the

contract and equipment installation according to the construction schedule of civil

engineering to meet the requirement of general schedule under the contract.


Attachment: The construction plan of The Pakistan Jinnah Hydropower Project

Implementation on EPC/Turnkey Basis installation works of the E/M equipment & steel

structure.

5.3 Loading/Unloading & Storing

5.3.1 Loading and Unloading

a. Use of lifting point and hoisting tool will be subject to the marking and weight on the

packing case of equipment.


b. Download the equipment within 30t in weight with the 30t mobile crane, and the equipment

with over 30t could be handled by one or two heavy duty crane rented temporarily at site.
c. Except the equipment suitable for downloading directly in the installation place, the rest
16
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

shall be disposed to the storing area and warehouse.


c. All parties concerned shall have visual check and acceptance for the packaging before

downloading the equipment. Continue further inspection and keep a written record for file if

any damage occurs.

5.3.2 Storing

a. Temporarily enclosing wall and drainage channel will be built around the storing area.

There will have secures on duty 24 hrs a day.


b. Measures shall be taken against raining and sunshine for the equipment in the open

storing place. Put crossties underneath the equipment and cover them with the waterproof

cloth and cover with asbestos tile before reinforcement. Important equipments such as the

shaft, generator and runner shall be covered with waterproof cloth before erecting the

temporary housing with asbestos tiles and relative equipment signs.


c. Adequate fire fighting apparatus shall be available in the storing place and prevention

measures shall be taken against fire.


d. Small parts and electrical equipment shall be stored in the warehouse, and precision

instruments and equipment with special requirement should be protected in the thermostatic

chamber.
e. The equipment, which stored in the warehouse must be registered and recorded. Every

case must have mark on them.

5.4 Power House Overhead Bridge Crane Installation Procedure

5.4.1 Installation Procedure

Preliminary Work
Rail erection & Stage II Concrete
Grouting

Main Girder and End Carriage


Cleaning & Checking Travel Bogie Installation
17
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Main Girder and End Carriage Installation


Crab Erection &check

Bridge Frame Assembly

Electrical Hoist Crab Installation Travel mechanism


Installation Installation &Adjustment

Guard Rail Installation Hoisting Mechanism Adjustment

Electrical wiring
Electrical Drive-Part Wiring

Power Supply Part Winding Drum, Pulley and Wire Rope Connection
Installation

Accessories Installation
No-load Operation

Crane Load test

5.4.2 Installation Instructions

a. Use the civil construction company’s crane to lift and install most parts of the bridge crane

before powerhouse roof is covered,


b. It can be disassembly into two or more section for lifting and installation if the weight of

bridge crane is more than the lifting capacity of the crane.


c. After finishing the installation work, perform the no-load, rated load, 1.25 times rated load

static and 1.1 times rated load dynamic tests.


d. The steel bars for civil engineering can be used by Party A as test load for the bridge crane

load test.

18
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

5.5 Turbine Generator Unit Installation

5.5.1 Turbine Generator Installation Procedure

Preparatory Work

Draft Tube Installation &


Draft Tube Assembly Adjustment Draft Tube Stage II
Concrete Pouring

Stay Ring Pre-assembly and Column Welding

Stay Ring Installation& Adjustment

Stage II Concrete Pouring for


Shaft Assembly Shaft Installation Stay Ring Shaft

Gap Adjustment between Gap


Adjustment between Facade
Distributor Assembly Distributor Installation Surface and End Surface

Governor Installation
Runner Chamber and Lower Part of
Expansion Joint Positioning Temporarily
Servomotor Installation
Main Shaft Assembly &
Main Shaft Installation
Oil Head Pre-installation
Stage II Concrete Pouring

Runner Assembly Axial Line Adjustment

Runner Installation Runner Cone Installation


Runner Rotation &
Pressure Test

Runner Chamber Installation

Adjustment of Gap between


Runner and Runner Chamber

Main Shaft Seal Installation

Expansion Joints Installation Handrails & Platform


Installation
19
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Speed Increaser Check Speed Increaser Installation Lubrication Cooling


System Installation

Speed Increaser Shaft and Main


Shaft Connection

Various Tests for Generator Installation


Generator

Generator and Speed Increaser Shaft


Connection

Unit running out & Oil Head Installation


Oil,Gas and Water Measure
System Detecting System
Installation
Unit Dry Debug

Water Flushing Test

Unit Start-up & Trial Run

5.5.2 Turbine Generator Unit Installation Instructions

1. Assemble the tail tube into a whole in the powerhouse and lift down section by section to

the erection position.


2. Assemble the stay ring into a whole in the installation position; adjust the center, elevation,

verticality and plane, then fix it after checking; no change after rechecking and then pour

concrete.
3. Assemble the access shaft steel case section-by-section in the erection place or on the

steel platform, then lift down to the erection position for adjustment and centering and put

them together with stay ring before pouring concrete.


4. Assemble the wicket gate mechanism into a whole in the erection place, then lift it to the

installation place after turning over and connected with the ring seat and adjust it accordingly.
5. Assemble the main shaft and guide bearing in the installation place and lift to position and

adjust the axial line


6.After dissembling, cleaning、assembling, blade installing and pressure test the runner in
20
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

the erection place, turn it over and lift to position in connection with the main shaft with

special tools.
7.Install the runner chamber and adjust the gap between the runner and runner chamber.
8. Inspect the speed increaser gearbox in the powerhouse, clean it with the lubrication oil;

and then check its rotation flexibility. Lift it down to the assembly place for installation after

checking.
9. Check the bearing and insulation of electrical parts of generator in the powerhouse and

perform insulation pressure test. Lift it down to the assembly place for installation after

checking.
10 . Before connecting the shaft of speed increaser gearbox and turbine shaft with

generator shaft and speed increaser gearbox, check and adjust the axis deviation to

qualification by jigger. Check rotating part with jigger after their connection.
11.Centering, adjust and fix the oil head according to its actual position.

5.6 Electrical Equipment Installation

The main electrical equipment consist of HV system, LV system, control system, lighting
system, communication system.

5.6.1 Electrical Installation Procedure

Preparatory Work

Working Place Check-up

Foundation & Embedded Parts Installation

Embedded Parts Acceptance

Equipment Base Assembly

Equipment Acceptance & Test Equipment Installation

21
Check and Test
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Trial Run

Acceptance & Document Hand-over

a. Preparation
Be familiar with the design drawing, construction norms and the technical document and

prepare installation schedule before construction.


b. Working Face Check
Check whether the reserved hydraulic structure holes and equipment basis meet design
requirement and the equipment installation site complies with equipment installation
conditions according to the design drawing and equipment installation document.
c. Foundation and Embedded Part Installation
Based on the design drawing, equipment installation document, notice of design modification
and supervision, measurement can be made by the theodolite, level meter and tape to
release point positioning for foundation and embedded part installation and pursuant to the
requirement of regulations with records correspondingly.
d. Acceptance of Embedded Parts
After finishing the embedded part work and passing test by the unit, such shall be submitted
to the supervision engineer for acceptance, after which will be handed over to the civil
construction company for concreting.
e. Installation of Equipment Foundation
Installation of electrical equipment is the foundation installation for Stage 2 concrete grouting,
such as installation of main transformer foundation and basis steel of HV/LV switchgear
cabinet etc, the installation procedure of which is the same as that under Clause3.
f. Equipment Acceptance and Test
All equipments should be checked carefully in accordance with design requirement, order
inventory, package list, equipment instructions and norms after their arrival on site.
Equipment to be tested shall be exceeded according to standards and requirements for
product.
g. Installation
Carry out installation according to the requirement of design and relevant standard with on
time and quality assurance.
h. Check and Test
After equipment installation, carry out test according to design requirement and relevant

22
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

standard. Proceed with other tests and simulation tests according to relevant specifications
prior to passing the test.
i. Trial Operation
After the acceptance of installed equipment, trial operation with power should be preceded
with available start conditions in any other ways.
j., Document Hand-over for Completion
Hand over all relevant documents within one month after the trial operation to facilitate the
client for equipment operation management and maximum efficiency thereof.

5.6.2 Electrical equipment installation

1. Procedure for HV/LV electrical equipment installation of power house

Preparatory Work

Foundation & Embedded Parts Embed Equipment Acceptance & Storage


&
Box
LV Switchgear Installation

HV Switchgear Installation

Communication System
Cable Holder & Bridge

Station Transformer
Frame Installation

Cabinet

Installation
Installation
Distribution
Installation
Control

Cable Laying, Cable Termination Production, Jointing and Wiring

Electrical Line Checking Test Trial Run

2. Procedure for equipment installation of switch-yard

Grounding Network Equipment Base


Embed Installation
Transformer Installation
HV Circuit Breaker
HV Isolation Switch
Lightning Arrester

Main Transformer
Switchinstallation

Current& Voltage
Installation

Installation
Installation

Installation

23
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Electrical Equipment Test

One-time Wiring Installation


Switch StationAcceptance

3. Illumination installation procedure


Preparatory work

Cable & Wire Pipeline Embedded Lighting Foundation Embed

Distribution Cabinet Installation

Pipeline Wiring

Lamps Installation

Lighting Switch Debug

Hand-over & Acceptance

5.6.3 The main electrical equipment installation


5.6.3.1 HV/LV switchgear, control cubicle, distribution box and control box installation

Basic Steel Embedded

Cabinet Acceptance & Transport

Cabinet Installation

Line Checking & Instrument Testing


Line Checking & Instrument Testing

Cabinet Wiring

24
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Check & Test

Acceptance

a. Production of the foundation steel should base on the design drawing. The relative

elevation between the foundation steel and ground after completion shall meet the

requirement of design.
b. The equipment should be transported in good weather. Apply manual-handled forklift for

load & unload and short-distance transport. During handling process, use firmly-tied ropes to

ensure stable against collision and damage the equipment.


c. During and after installation, measures should be taken for the screen counter and power

distribution control cabinet regarding anticorrosion, dustproof, damp-proof, and anti-

accidental damage and vandalism.

5.6.3.2 Main transformer installation

Preparatory work

Transformer Appearance Check

Insulation Oil
Filtering and Pressure Body Check

M.T. Body Check


Accessories Cleaning &Radiator
Pressure Test
Installation On-site

Accessories Installation

Oil Filling

Check & Test

Trail Run
25
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

a. For main transformer installation, gantry crane, bridge crane or truck-crane can be used

for unloading on site. And the transformer rail or the trailer could be used to transport the

equipment to the erection place.


b. For main transformer body check, use gantry crane or bridge crane lift the cover; check

the core, winding, voltage switch, lead line etc. Check all bolts tight and carry out the

electrical test. After the body check, apply qualified transformer oil for washing and then fill

qualified transformer oil before putting back the bell cover.


c. Line voltage shall be applied for the voltage impact test after the installation of main

transformer.

5.7 Hydraulic Gates & Trash Removal System Installation

1.Embedded Parts Installation

Gate Groove Check & Cleaning

Installation Control Point & Line Positioning

Embedded Parts Rechecking & Distortion Treatment before Installation

Embedded Parts Lifting, Adjustment and Reinforcement

Stage II Concrete Grouting

Cleaning & Remeasureing


2.Stop log slot installation

Preparatory Work

Gate Shape and Size Check

26
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

Gate Groove Cleaning & Check

Single Section Transport & Lifting

Assemble into Work Unit

Water Sealing Installation & Seal Checking

Dry test

5.8 Gantry Crane Installation Procedure

Preparatory Work

Rail Installation & Stage II Concrete Pouring

Gantry Cleaning, Check and Assembly


Traveling Mechanism Installation
安装

Set Wiring of Electrical


Trolley Assembly & Check Gate Frame & End Parts
Carriage Installation

Electric Hoist Installation Trolley Lifting Travel Mechanism Installation


& Adjustment

Handrails Installation Hoisting Mechanism Installation & Adjustment


扶梯等附件安装

Power Supply Part Installation Electrical-Driven Part Wiring

Auxiliary Equipment Installation


Pulley, Wire Rope and Drum Connection

Crane Test

1. Lifting and erection the main parts of the gantry with the civil engineering’s crane or mobile
27
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

crane.
2. If the load weight of trolley exceeds the lifting capacity of crane, some parts can be

dismantled and hoisted separately for lifting and erection.


3. Give adequate consideration to the weather and the circumstance during lift and erection

outdoor.
3. After finishing the installation, perform trial run, rated load and 1.25 times load tests, the

load of which can be made by Party A with steel bars for civil engineering.

5.9 Transmission Line Installation

Preparatory Work

Over-head Wiring Work

Tower Pole Erection

Tower installation

Overhead Line Work

Earthing Work

Test

Acceptance

1.Check the dimension of the parts and clean the base before working.
2. A complete construction scheme shall be available for the tower unit and preventive

measures shall be taken to avoid part deformation & damage.


3.Line arrangement includes: letting off、connecting 、tight and accessory parts installation

etc.
4 . Connection between the earthing line and tower should be contacted well to facilitate

opening the interface for measuring the grounding resistance.

28
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

6.Unit Commissioning

Dry test

Flushing Water Test

Manual Start-up

Bearing Run Test

Unit Over-speed Test

Governor Test

Generator Short-circuit Test


Automatic Start & Shutdown Test

Generator Pressure Build-up Test


Main Transformer Impact Test

Protection System Commissioning


Synchronizing Test

Load & Load-rejection Test

72-hour Continuous Operation

30-day Operation for Reliability

7.Acceptance of Works

The reliability of 30days for operation of 8 turbine generator units is over for the completion of
works as specified in the contract. The contractor shall hand over the units 、 spare
parts 、special installation tools and documentations to the client as the requirement of the
contract.
After the finishing the clean of working area and withdrawal of construction equipment and
staff, then the installation of mechanical and electrical and metal construction is fully
complete.
29
Guangdong Yuantian Engineering Co. (GYT)
Jinnah Hydropower Project The Construction Scheme

30
Guangdong Yuantian Engineering Co. (GYT)