SECTION 01200
PROJECT MEETINGS
01200-1 GENERAL
1.1 Summary
1. Pre-construction meeting.
2. Pre-installation meeting.
3. Progress meeting
B. Related Sections:
A. Pre-construction meeting shall be held within 14 days after the Commencement Date.
Attendees should include authorized representatives of Employer, and their
consultants; Contractor and its superintendent; major subcontractors, manufacturers;
Suppliers; and other concerned parties. Participants shall be familiar with Project and
authorized to conclude matters relating to the works.
B. Agenda for this meeting will include but not be limited to:
9. Procedures for safety and first aid, security, quality control, etc,
10. Procedures for reporting and monitoring progress, cost materials, labour and
equipment.
A. Within four (4) weeks of the Commencement Date of the Works the Contractor and
the Employer’s Representative will agree a program schedule for weekly progress
meetings covering the six (6) months of the Works The Contractor shall make
himself available for any other meetings called for by the Employer’s Representative
outside the schedule.
B. Job site progress meetings will be held to review Contractor’s construction schedule
and to discuss work progress and site co-ordination issues. Attendees at this meeting
shall include the Employer’s Representative, Contractor, subcontractors and other
concerned parties.
C. The job site progress meeting shall be convened as directed by the Employer’s
Representative. Additional meetings required by Contractor to comply with his
obligations under Section 01040-Co-ordination, shall be requested in writing by him
to the Employer’s Representative with full details of agenda and names of other
Direct Contractors who are required to attend. Such meetings will be chaired by the
Employer’s Representative or his Delegate or Assistant.
D. Pre-Meeting Submittals: Three days before each site meeting, submit the following
information, but not necessary limited to, the Employer’s Representative’s or his
Delegate or Assistant.
5. A list of activities that the Contractor plans to start during the following
period.
iv. Discuss whether schedule revisions are required to insure that current
v. Review present and future needs of each entity present, including the
following:
. Interface requirements.
. Schedule.
. Sequences.
. Status of submittals.
. Deliveries.
. Access.
. Site utilization.
. Hours of work.
. Housekeeping.
. Change Orders.
F. Reporting: No later than 3 days after each meeting, distribute minutes of meeting to
each party present and to parties who should have been present. Include brief
summary, in narrative form, of progress since previous meeting and report.
C. Agenda: The agenda shall include the review of progress of other construction
activities and preparations for particular activity under consideration at each pre-
installation conference, including requirements for the following:
1. Contract documents.
2. Options.
3. Purchases.
4. Deliveries.
6. Review of mock-ups.
7. Possible conflicts.
8. Compatibility problems.
17. Safety.
21. Protection.
D. Reporting
A. The proceedings of all meetings shall be recorded and minutes distributed to all
parties present or concerned by not later than the beginning of the next such meeting.
Such minutes, when accepted, shall be binding upon all parties.
END OF SECTION