Investigation on Grid

Connections of Wind Power


and PV Power in China
● State Electricity Regulatory Commission

Abstract: In order to fully comprehend the developing status of wind power and photovoltaic (PV)
power generation, a special investigation on the integration of wind power and PV power was launched
by the agencies of the State Electricity Regulatory Commission (SERC) throughout China during July–
October 2010. This report is completed based on the investigation along with routine supervisory and
management programs. There are totally 573 wind power projects and 94 PV power projects involved.
Existing problems in these projects are pointed out and proposals for regulation are put forward.
Keywords: wind power; PV solar power; grid integration; electricity tariff

construction, with 15 896.2 MW of wind power and


General situation 210.3 MW of PV solar power.

Development The distributions of on-grid installed capacity of wind


In recent years, wind power and PV solar power have power and PV solar power by regions are demonstrated in
been developed rapidly. The investigation shows that by figures 1 and 2, respectively.
the end of June 2010, the total installed capacity of wind
power and PV solar power completed and integrated
reached 22 136.7 MW, accounting for 2.46% of the
nationwide total generation capacity, among which the on-
grid installed capacity of wind power was 22 003.7 MW
and that of PV solar power was 133.0 MW. The installed
capacity of wind power and PV solar power already
completed but not connected to the grid added up to
765.2 MW, among which 763.6 MW was the capacity
of wind power and 1.6 MW was the capacity of PV solar
power. The scale of wind power and PV solar power
under construction reached 16 106.5 MW, accounting for Fig. 1 On-grid wind power installed capacity by
about 8.66% of the state’s total installed capacity under regions by the end of June 2010

40 ELECTRICITY 2011.3
Investment Group Corporation and Hainan Development
Holding Corporation Ltd. had reached 20 MW in capacity.
Among the projects under construction, the 20-MW on-
grid PV power demonstration project in Lin’gao, Hainan
and the 18-MW Shiliying PV power project in Jining,
Shangdong are two big ones.

Feed-in tariff and subsidy


Due to different pricing system and construction costs,
the feed-in tariffs of wind power and PV power differ in
different provinces even in different projects of the same
Fig. 2 On-grid PV power installed capacity by regions province.
by the end of June 2010
For wind power projects approved before August
Investment entities 1, 2009, some are applied with concession bidding
The investment entities of wind power and PV power tariff system while others are applied with government
are quite different. For wind power, the investment entities approved tariff system. However, for those approved after
are mainly focused on the state-owned central enterprises August 1, 2009, the newly constructed onshore projects
and the local state-owned generation investment in the four-category wind resources regions are uniformly
enterprises in regions with abundant wind resources. By applied with local wind power benchmark tariffs. So far,
the end of June 2010, there were ten generation groups the highest feed-in tariff is applied in Linhai Wind Farm
with their own on-grid installed capacity exceeding and Cangnan Wind Farm affiliated to Guodian Longyuan
500 MW, totaling 16 689.7 MW and accounting for Power Corporation Ltd., both located in Zhejiang
75.85% nationwide, among which there were three Province, hitting 1.4040 yuan/kWh.
generation groups with more than 2 000 MW on-grid
installations, i.e., China Guodian Corporation, China As a rule, the feed-in tariff for PV power is determined
Datang Corporation and China Huaneng Group. by local governments since the state has not yet
implemented uniformed feed-in tariff policy for PV
By the end of June 2010, there were seven generation power. Among the approved PV power projects, the
groups with the wind power installations under Shanghai Qianweicun PV Power Station has the highest
construction exceeding 500 MW, among which the feed-in tariff, which is 6.4436 yuan/kWh, while the lowest
capacity of China Guodian Corporation, China Datang is 1.0928 yuan/kWh for Gangsu Duanhuang PV Power
Corporation and China Huaneng Corporation all Project of China Guangdong Nuclear Power Corporation.
exceeded 1 500 MW while that of China Shenhua Group
Corporation Ltd., China Huadian Corporation, China The investigation also indicates that the implement-
Guangdong Nuclear Power Corporation and China Power ation of the subsidy policies for wind power and PV
Investment Corporation was between 500–1 000 MW. power is satisfactory; the wind power and PV power
projects in the Renewable Energy Electricity Price
At present, the PV power is still at the experimental Subsidy List jointly released by the National Development
and exploratory stage in China with small projects being and Reform Commission and the State Electricity
invested and constructed. The investment entities tend Regulatory Commission between January–June 2009 and
to be diversified. By the end of June 2010, the on-grid July–December 2009 have, by and large, received the
installed capacity of PV power of both China Energy relevant electricity price subsidy.
Conservation and Environmental Protection Group
and Jiangsu Zhongneng Silicon Industry Science and Construction of grid connection system
Technology Corporation Ltd. had all reached 20 MW. Since the implementation of the state’s subsidy
Among the on-grid PV power generation projects, policy for the construction of renewable energy power
the biggest one was the 20-MW Xuzhou Xiexin PV connecting system, which gives electricity enterprises
Power Generation Corporation Ltd. invested by Jiangsu the incentive to invest in the construction of the
Zhongneng Silicon Industry Science and Technology connecting system for wind power and PV power, the
Corporation Ltd. The PV power projects that were under scale of the connecting system in operation has rapidly
construction by both Gansu Province Electric Power increased.

41
2011.3 ELECTRICITY
By the end of June 2010, the line length of the wind among which that of wind power was 22.254 TWh and
power connecting system was 10 326 km with the that of PV power was 51.76 GWh (see figures 3 and 4 for
transformation capacity of 38.98 GVA (see tables 1 and 2). details).

Table 1 Line length and transformation capacity of


wind power connecting system by voltage levels
Voltage level 330 kV 220 kV 110 kV 66 kV or below

Line length (km) 666 4 202 3 733 1 725

Ratio to total length (%) 6.45 40.69 36.15 16.71

Transformation capacity
5.04 17.65 12.29 3.99
(GVA)

Ratio to total capacity (%) 12.93 45.29 31.54 10.24


Fig. 3 Feed-in wind power generation by regions
between January and June 2010
The scale of PV power connecting systems was
relatively small with the line length of 134 km and
transformation capacity of 0.22 GVA in total and the
main voltage level of 35 kV, among which the line length
and the transformation capacity invested and constructed
by generation enterprises was 109 km and 0.19 GVA,
accounting for 81.34% and 86.36%, respectively. In terms
of provinces, the scale in Ningxia, Gansu and Shandong
was relatively larger with the line length over 29 km and
the transformation capacity over 37 MVA respectively all
Fig. 4 Feed-in PV generation by regions between
in these provinces.
January and June 2010

Table 2 Line length and transformation capacity of Depending on grid security and other factors, some
wind power connecting system by entities amount of the electricity generated by the on-grid wind
power or PV power equipment might not be able to
Line be connected to the grids. Statistics on this amount of
Number Transformation
Investment entity
of projects
length
capacity (GVA)
electricity which was not acquired by the grids has been
(km) conducted by the investigation this time. Between January
and June 2010, the amount of wind power unbought was
Value 213 4 444 19.14 2.776 TWh while there was no unbought amount of PV
Grid enterprises Ratio to the
43.12 43.04 49.10 power (see Table 3). Between January 2009 and June
total (%)
2010, the unbought wind power in Hebei, Gansu and
Value 278 5 698 19.61 Helongjiang were all around 0.3 TWh.
Generation
enterprises Ratio to the
56.28 55.18 50.31
total (%)
Table 3 Unbought wind power in regions between
Value 3 184 0.23
Grid and generation January and June 2010
enterprises jointly Ratio to the
0.61 1.78 0.59
total (%) Ratio to the Comparison between
Amount
nationwide the unbought ratio
Region unbought
total unbought and the acquired
Acquisition of on-grid electricity (TWh)
amount (%) ratio (%)
In 2009, the on-grid generation amount of wind power
and PV power added up to 25.615 TWh, accounting for North China 1.588 57.20 14.64

0.70% of the overall generation of the state, among which Northeast China 1.064 38.33 6.66
that of wind power was 25.610 TWh and that of PV Inner Mongolia 2.101 75.68 43.40
power was 5.6 GWh. From January to July 2010, the total
Jilin 0.260 - -
on-grid wind and PV power generation was 22.305 TWh,

42 ELECTRICITY 2011.3
The coordination between the construction of power
Existing Problems sources and power grids needs to be enhanced. Due to
the fact that the preliminary workflow for wind power
● The coordination between wind power projects is relatively simple, the approval process is fast
development and project approval needs to be further and the construction period is relatively short while the
enhanced. gird connecting system is relatively complicated in terms
of project approval, scheme making and construction, it
It is difficult to accommodate wind power in some is difficult to complete the connecting system projects
regions. In those regions with abundant wind power with the wind farms simultaneously. For example, the
resources, the planning for wind power development Phase I Project of Wulijimuren Wind Farm of Huaneng
has been focused on resources rather than delivery and Cogeneration Company, the Phase I Project of Erergetu
accommodation, leading to serious contradiction in Wind Farm and the Phase I Project of Baiyun Wind Farm
transmission and accommodation of bulk wind power. which are affiliated to Inner Mongolia Power Corporation,
The wind resources in West Inner Mongolia grid are were expected to be put into operation by the end of 2010.
abundant. By the end of June 2010, its on-grid installed However, up to now their connecting systems have not
capacity and the capacity under construction amounted to been approved, which results in the failure in transmitting
4.89 GW and 0.85 GW, respectively. Aside from being the wind power in due time. The wind power in Inner
accommodated locally, the rest of on-grid amount of Mongolia has to be transmitted to Beijing-Tianjin-
wind power has to be transmitted to the North China grid. Tangshan region through the West-to-East Electricity
However, along with the commissioning of bulk installed Transmission channels, but the capacity of the two
capacity of wind power in succession in Zhangjiakou channels now available is limited, and only a little amount
and Chengde in Hebei Province, the North China grid of wind power can be transmitted through these transfer
has to face the challenges to accommodate the local wind paths. The the third path has been planned as early as
power, which in turn makes the problem of wind power 2006, however, up to now the construction has not begun
accommodation in West Inner Mongolia grid deteriorate. yet.
By the end of June 2010, about 1-GW capacity out of the
planned 10-GW capacity of Jiuquan Wind Power Base The development of wind power and other power
in Gansu Province had been connected to grids, which sources is not balanced in a few regions. The proportion of
could not be completely accommodated by Jiuquan and heat supply units to thermal power units in the Northeast
Hexi region, but mostly has to be transmitted to Lanzhou region is high (e.g. 72% in Jilin Province). The heat
load center. By estimation the maximum dispatchable supply units are incapable of peak shaving in the winter
load within Gansu Province would be about 10 GW in heat supply season while the small and medium thermal
2010. However, the installed capacity to be completed power units for startup, shutdown or peak shaving have
by the end of 2010 would amount to around 5 GW in gradually been closed down. The construction of pumped-
Jiuquan Wind Power Base, far beyond the consumption storage hydropower stations and gas-turbine units is
demand of Jiuquan and Hexi region. It is predicted that relatively slow. Under the condition that the capability of
the power generation of Jiuquan Wind Power Base will peak shaving is severely insufficient, the dispatch system
reach about 25 TWh in 2015, which would be difficult has to restrict the output of wind power at valley load
to be accommodated in Gansu Province or even in the hours so as to ensure grid security and household heating.
Northwest power grid. Unfortunately the accommodation The installed capacity of wind power in West Inner
market and its supporting grids outside the Northwest Mongolia grid has already reached 24.52% of the grid’s
grid are still uncertain. It is similar to the situation in maximum load. In the period of heat supply in winter and
Baicheng, Jilin Province with a quite weak grid structure at valley load hours, the grid also has to restrict the output
and a limited transmission capability. As the regional load of wind power so as to ensure the secure operation of the
is rather low and the wind power could not be completely power system.
accommodated locally, the production of wind power
enterprises has been frequently restricted. For example, in ● Relevant policies and incentive mechanisms need
2009 the amount of wind power generated by Jilin Datong to be further improved.
Wind Farm under China Datang Corporation that failed
to be connected to the grid amounted to 14.88 GWh, So far, China has formulated a series of policies,
accounting for 14.7% of the total on-grid amount of the regulations and incentive mechanisms to encourage
year with the utilization hours reduced by 300 hours. the development of wind power and PV power, but the

43
2011.3 ELECTRICITY
completeness of the system and the coordination between price subsidy provided in the Provisional Measures of
relevant policies still need to be enhanced. Allocating the Additional Income of Renewable Energy
Electricity Price, which increases enterprises’ operation
The supporting policies for PV power need to be burden. For example, the Chongming, Nanhui and
improved. Up to now no feed-in tariff about PV power or Fengxian Gulf wind farms in Shanghai and the Linhai
detailed implementation rules concerning the construction and Cangnan wind farms in Zhejiang Province were all
of PV power have ever been enacted at the state level, put into operation before 2006 with high feed-in tariff.
which restricts the bulk development of PV power They are not eligible to obtain the compensation from
industry. What is more, there is no supporting policies renewable energy additional funds, therefore, their
with regard to distributed PV power connecting to electricity purchase cost for grid enterprises increases.
distribution network (user’s side), one of the major types
of the PV power in the future such that the incentives ● The management of integration and operation
to investment in small PV power projects are greatly needs to be further regulated and improved.
undermined.
There are two problems existing in the current grid
National provisions for the investment, operation and connecting systems of wind power or PV power.
maintenance of connecting systems for renewable energy
power need to be improved. The insufficient subsidy The lack of clear definition of wind power connecting
to some of the connecting systems has undermined the system leads to different understanding from different
investment incentives of grid enterprises. As wind power parties. Some argue that it includes the step-up substation
projects are usually located in areas far away from load of wind farms and the line from the step-up substation to
centers, the construction workload and investment amount the first base tower of incoming feeder on the grid side;
of their supporting connecting systems are huge while the some argue that it is the line from the first base tower of
line utilization ratio is low. The current subsidy standard the outgoing feeder of wind farms to the first base tower
for the connecting system cannot meet the requirements of incoming feeder on the grid side; others argue that it
of some projects in terms of the investment, operation is the line from the first base tower of outgoing feeder
and maintenance of grids. For example, the Shanghai of wind farms to the first base tower of incoming feeder
Electricity Corporation invested 65.28 million yuan on the grid side and the incoming feeder spacing on the
in constructing the connecting system for the East Sea grid side. Different understanding would easily result
Bridge Offshore Wind Power Project, which will take in different opinions in the process of construction and
32 years to recoup the static investment according to the different statistical approaches.
current electricity price subsidy policy. The investigation
shows that all or part of the connecting system projects Standards and regulations regarding grid connection
in Helongjiang, Shandong, Zhejiang, Inner Mongolia, and dispatch management of wind power or PV power
Liaoning and Xinjiang are invested by generation need to be further regulated and improved in light of the
enterprises and some generation enterprises are even features of wind power and PV power. At present, there is
responsible for the operation and maintenance of these no national standard for the integration of wind farm. For
projects, which is not good for the security management the purpose of addressing the problems of LVRT, reactive
of the projects. power absorption, power system security and stability, the
Technical Rules for Wind Farm Integration formulated
Electricity price was not subsidized in time. The by the State Grid has come into force, which requires that
subsidy for the electricity price of wind power or PV wind farms connect to power networks after they meet
power was usually granted far behind the time when relevant technical standards and have carried out technical
the power was connected to the grid. Consequently, the innovation. With this rule, wind farm integration has
generation enterprises couldn’t obtain the subsidy in been regulated to some extent. However, it is a rule of an
time and their economic benefits have been affected. enterprise rather than of the state, which may easily bring
Some small generation enterprises may even suffer the the grids into conflicts with wind farms.
difficulties in the cash flow.
● Impacts of bulk development on the secure and
A few historical issues need to be addressed. Wind stable operation of grids have been increasing.
power and other renewable energy projects approved
before 2006 are not eligible for obtaining the electricity Both wind and PV solar power generation have the

44 ELECTRICITY 2011.3
characteristics of intermittence and randomness, and system. To develop the resources in areas around load
wind power has another feature of anti-peak shaving as centers, distributed power sources shall be constructed and
well, which presents new challenges to the power flow connected to the nearby distribution network according to
control in the power system, ancillary service dispatch, local conditions and from the aspects favorable to energy
short-circuit current control and electricity quality, etc. At conservation, emission reduction and the enhancement
present, grid enterprises are unable to make out day-ahead of electricity supply. Meanwhile, the approval and
plans according to the wind power prediction because the regulatory mechanism for wind power projects shall be
wind power prediction system is imperfect, and there is straightened out between the central government and local
a lack of fundamental and accurate data. Therefore, there governments to regularize the development and utilization
are strong uncertainties in the arrangement of operation of wind power, rationalize the distribution of wind power
approaches. Located in the northwest of Gansu Province and avoid disorderly and casual development.
and at the end of Gansu grid, the Jiuquan grid with bulk
wind power integrated has seen various kinds of stability ● Policies on price, finance and taxation as well
issues such as transient stability and difficulties in peak as the incentive mechanism for wind power and PV
regulation in actual operation. In 2009, the maximum power shall be improved.
load difference between peak and valley in Fujian grid
reached 6.36 GW with the peak regulation capability of As the technologies for wind power and PV power are
some large thermal units reaching about 60% in actual still under development, their construction costs are rather
operation, which is close to or approaches the regulation high with weak economic competitiveness in the market.
limits of the units. Along with more wind power to be put Therefore, it is necessary to keep on strengthening the
into operation during the National Twelfth Five-Year Plan policy support to promote their continuous and healthy
period, the demanding for peak regulation of the system development. First, studies on levying energy tax or
will be even higher, which exerts greater pressure on the carbon tax shall be carried out to establish the funding
peak regulation capability for power grids. sources for the subsidy to the stable and sustainable
development of wind power and PV power. Second,
Recommendations for regulation studies on the financial and taxation policies with regard
to supporting the development of wind power and PV
● Scientific planning shall be enhanced to promote power shall be enhanced to combine the development of
the coordinative and orderly development of wind wind power or PV power with the development of local
power and PV power. economy so as to establish competitive industries that
could promote regional economic development. Third,
In light of the national renewable energy development the compensation mechanism for electricity price shall
strategy and the Medium- and Long-Term Program be improved to increase the timeliness of the subsidy
for Renewable Energy Development, according to to wind power and PV power prices and scientifically
the characteristics of wind power and PV power make out the compensation standard for the construction
combined with the factors such as energy resources, of connecting systems. Fourth, pricing policies for PV
power source infrastructure, electricity consumption power generation shall be improved and the scientific and
market, transmission corridor, grid construction and reasonable police for feed-in price shall be put forward.
grid operation, the local wind power or PV power Fifth, the innovation on commercial model shall be
development plan shall be improved to develop wind encouraged to support enterprises to enter markets and
power and other renewable energies on the basis of local create innovative commercial models.
conditions and realize the harmonious development
between power sources and resources, between power ● Integration and operation shall be well managed
sources and grids, between power sources and power to meet the requirements for the bulk development of
sources, as well as between power sources and users. wind power and PV power.
To build large power generation bases in areas rich in
wind power or solar power resources, the grid frame First, studies on the grid connection and operation
and accommodation capability shall be taken into full security of wind power and PV power shall be carried out
consideration, the connection of wind power or PV such that relevant technical standards can be established
power to grids shall be well planned so as to promote the and the adverse impacts of wind power or PV power
coordinative development of wind power or PV power on the security and stability of the power system can be
and maintain the secure and stable operation of the power reduced.

45
2011.3 ELECTRICITY
Second, the security assessment on wind power or PV up the upgrading of grids, improve the grid structure,
power integration , the management on the compensation and perform feasibility studies on connecting system
for ancillary services and the management on wind project to select the connection plan on merit order. By
power or PV power dispatch shall be carried out in order proactively providing grid connection services for the
to systematically improve the regulation on the grid wind power or PV power, the grid enterprises can hence
connection and operation of wind power and PV power. ensure the timely on-grid operation of the generation
project. In addition, on the premise that the power system
The cooperation between generation enterprises and security and stability is ensured, grid enterprises shall
grid enterprises in wind power and PV power integration strictly comply with the requirements of the Renewable
and accommodation shall be strengthened. The generation Energy Act and other laws and regulations to purchase
enterprises shall actively collaborate with grid enterprises the on-grid electricity at the feed-in price approved by the
by putting forward feasible delivery and accommodation state’s relevant department of price administration. They
schemes and submitting them to the authorized also have to strictly implement the price policy for feed-
departments of the government for confirmation. On the in tariff for wind power and PV power, do a better job in
other hand, when the grid enterprises start to process the distribution of additional electricity price and achieve
the application for grid connection from a wind power sufficient and timely electricity settlement.
or a PV power project, they shall prepare carefully the
transmission line, grid structure and terminal for the
project according to the requirements of grid development Translated by Zhang Sufang
plans and wind power or PV power project plans, speed Edited by Zhang Yan

(Continued from P39) of the cold air into the pulverizer could be under 3% or
air heater which can play a role of the steam-air heater even be zero and the exhaust gas temperature of the boiler
or the hot air recirculation system, shortening the startup drops successfully.
period for the steam-air heater or the hot air recirculation
system consequently and improving the economics of the 2) The hot primary air heater could be used to adjust
unit. the exhaust gas temperature of the boiler. Though the hot
primary air heater cannot replace the steam-air heater or
The temperature of the hot primary air can be raised the hot air recirculation system completely because of the
by reducing the flow rate of the cooling medium passing limited adjustment, it could effectively shorten the starting
through the hot primary air heater if the exhaust gas period of the steam-air heater or the hot air recirculation
temperature drops under the dew-point temperature for system.
the running unit with some cold air being mixed into the
pulverized coal system in such case, which could rise the 3) The hot primary air heater could be a high-pressure
exhaust gas temperature to a certain extent. Although the heater, a low-pressure heater or just an economizer. Each
maximum rise of the exhaust gas temperature is less than type has its own advantages and disadvantages and will be
20 ℃, it is enough to keep the exhaust gas temperature suitable for some certain external conditions. Therefore,
over the dew-point temperature when the atmospheric its application depends on the practical situation when
temperature and the unit load change, which could reconstructing a certain boiler. The technologies and
shorten the startup period for the steam-air heater or the economics should be compared and analyzed for making
hot air recirculation system. This application is a unique the best choice.
advantage of the hot primary air heater to drop the exhaust
gas temperature. Reference
[1] Wang C C. The instruction leaflet of the patent on hot
Conclusions primary air heater and its related system for coal-fired
boiler in power plant [R]. Shaanxi: Xi’an Thermal
1) The hot primary air heater is developed to reduce Power Research Institute Co., Ltd., 2009.
the amount of the cold air into the pulverized coal system.
It can lower the temperature of the hot primary air at the
inlet of the pulverizer effectively and recover some heat Translated by Zhu Xianran
from the hot primary air. Consequently, the proportion Edited by Zhang Yan

46 ELECTRICITY 2011.3