Вы находитесь на странице: 1из 12

JOB SAFETY ANALYSIS

(RISK ASSESSMENT)

Area to be Access and/or Equipment Tag No. (KKS No.) : POH 2 (see attached drawings)

Work to be Done : INSTALLATION STRAUSS FOUNDATION FOR POMI COMUNITY ACADEMY BUILDING #PR148256

LOW HIGH Underwater Work Confined Space Excavation Hot Work


Risk Category Job :
Refer to Paiton Instruction : PI-05-03-01 Complex Lifting Work Working at High On Line Low & High Voltage
Work Order No. : Priority No. PAS Application No.
Work Period Date & Time Start Date & Time Finish
Operation
Applicant Health & Safety Work Parties Engineer
Supervisor

Signature :

Date : Time :

Ref. PI-05-03-01-F01 Page 1


Ref. PI-05-03-01-F01 Page 2
Work sequence Hazards Risk Control Measures

A. Prepartion
Mobilization tools,  Good manual handling practices to be used (min. 2 person
equipment and materials Manual handling Musculoskeletal injuries
lift); Use hand gloves
to the work place  Use mechanical aids where required
Improper electrical
Electrical tools/equipment Electrical Shock  Ensure all electrical equipment in good condition
tools/equipment
 Ensure all electrical equipment has been checked before use
and has valid tagging

B. Access & Ground

 Proper installation and maintenance of the piling plant,


 Toppling of plant causing injury
installed as per the piling platform design
or death to persons in the
 Piling platform to be designed by a competent person
working area
 Unstable platform  Plant to be visually inspected before work daily. Inspection to
 Damage to nearby
 Poor work area be recorded
structures/buildings
 Ramps  Avoid unnecessary tracking alongside existing structures
 Falling due to trip hazards from
Setting up plant / piling rig and trees
uneven mat causing injuries
 Refer to method statement for all must be made available
 Damage to nearby trees
throughout the works
 Auger or piling rig coming into  Live services survey to be carried out before
 Buried services contact with buried or overhead  piling commences
 Overhead services cables relating in serious injury  All live services to be clearly marked and diverted if
or death necessary

C. Unloading & Deliveries

 All person not involved in lifting/ unloading duties to be clear


 Being struck / crushed by of lifting area
moving plant possibly causing  Qualified and competent slinger only to attached and detach
 Plant movements fatalities loads
Offloading HIAB and  Lifting  Danger of slung equipment  Lifting equipment to be certified and visual inspection carried
arranging storage area  Storage become uncontrolled and out prior to use
 Manual handling injuring personnel  All plant movements on site to be supervised by slinger
 Lifting without mechanical help signaller
possibly causing serious injury  Any load that is deemed too heavy to lift shall be lifted using
attendant excavator/HIAB

Ref. PI-05-03-01-F01 Page 3


Work sequence Hazards Risk Control Measures
 Lifting to be carried out in conjunction with the Lift Plan
 If lift cannot be carried out in conjunction with the Lift Plan
 General public and site the AP is to be contacted
personnel being struck / crushed  All deliveries/concrete to be bought onto and out of site to be
Bringing deliveries /
by moving plant possibly causing accompanied by slinger signaller at all times
Concrete Wagons into and  Plant movements
fatalities
out of site  Deliveries to enter site in accordance with the traffic
 Vehicles being struck by moving management plan
plant
 Contractor to have in place traffic management plan and
gate persons if necessary

D. Riging up / de-rigging

 The piling rig must be erected as stated in the manufacturers


manual by competent persons
 An experienced and qualified piling rig operative will be the
 Failure of the piling rig or its only person permitted to operate the piling rig
components resulting in serious  12 monthly thorough inspection certificates must be checked
Erecting the Piling Rig Machinery injuries or death to ensure the test is in date
 Getting trapped in moving parts  The rig pre-start checklist and daily/weekly checklist must be
causing serious injury filled out and up to date
 Any previous defects in the rig to be amended before
commencement of work
 Banksman must be present at all times
 Safety harnesses must be used when working at height and
attached to a sturdy place
When erecting the rig, the piling  A restraint lanyard must be used to restrict the piling
operative could fall from height and
Working at height Falling from height operative coming to close to the edge of the rig
cause serious injury and endanger
others around them  Harnesses must be thoroughly inspected and checked prior
to use
 Harnesses must be of correct fit
Working from MEWP  Working from height  Risk of falling from height  MEWP must be tested every 6 months
(mobile elevating working  Falling objects causing death or serious injury  Before use, test certificates and checks shall be carried out
platform)  Toppling of plant  Dropping objects onto people recorded daily inspection/prior to use inspection
 Failure of MEWP below MEWP causing serious  All handrails shall be locked into place.
If necessary
injury  If any damage to MEWP do not use and contact supplier
 MEWP toppling causing serious  MEWP only to be used on firm level ground (piling mat area)
injury/Death and damage to  Harness to be used with fall restrain lanyard -Harness to be
plant and nearby structures used at all times and attached to the dedicated harness point

Ref. PI-05-03-01-F01 Page 4


Work sequence Hazards Risk Control Measures
 If MEWP fails when a person is stuck at height emergency
services should be called for rescue
 Failure of MEWP causing
 Competent person only to operate MEWP
toppling of plant,
 In case of MEWP failing whist carrying personnel. Somebody
 potentially crushing or trapping
must be deemed competed to lower MEWP from the controls
personnel
at ground level. If unable to do so CoreTeam must be called
to ask for fire and rescue

Ref. PI-05-03-01-F01 Page 5


Work sequence Hazards Risk Control Measures
Replacing Teeth and  All changes to auger teeth/pins to be carried out using the
inserting Pins into Auger Splinters of metal coming off Tungsten may fracture when struck following equipment; High impact eye protection, copper
Heads augers and teeth and seriously injury personnel hammers
 All PPE must be worn correctly

E. Boring of Piles

 Ensure all personnel operating the piling rig are qualified and
deemed competent
Improper operation of the piling rig  Banksman to be clearly visible to rig operative at all times
 Improper operation of piling
could cause serious damage to  Piling rig to be operated in conjunction with the operator
Operation of Rig rig
equipment and serious injury or
 Moving rig unsupervised manual
death to personnel
 Banksman to be the only person to signal the movement of
the rig
 All recently bored and concreted piles are to be covered with
 Falling down an open or recently
grates
concreted pile could cause
 Deep excavations  Personnel not involved with piling should be segregated from
Open Bores serious injury or death
 Open bores the piling mat area
 Machinery toppling over after
 Machine drivers shall back fill the open bore with hard-core
driving over an open bore
to make them safe at the end of every day
 The site will have hoarding extending the full length of the
affected area or, other methods of segregating plant from the
 Injury to the public
 Uncontrolled personnel public
 Serious damage to nearby
Piling/Boring  Working near pathways  Have splash guards in place if there is a significant risk of
equipment/structures
 Public access falling debris to nearby buildings/pathways
 Other tradesmen
 Safe systems of work to be identified in the method
statement if working next to busy roads

F. Concreting and
Reinforcing piles
Lifting reinforcement cage  Lifting of cages  Piling operatives and/or  Operatives must refer to the lift plan before any lifts take
 Proximity of nearby buildings uncontrolled personnel under place
 Uncontrolled personnel slung loads  If the lift cannot be carried out in accordance with the lift plan
 Slinging of the load  Failure of lifting gear causing the AP must be contacted
serious injury or death  Piling rig only to lift reinforcement cages
 Failure of piling rig causing  All other lifts to be carried out by attendant

Ref. PI-05-03-01-F01 Page 6


Work sequence Hazards Risk Control Measures
serious injury or death  excavator and HIAB
 Improper use of lifting gear
causing loads to fall
 Damage to nearby equipment
and structures

Ref. PI-05-03-01-F01 Page 7


Work sequence Hazards Risk Control Measures
 Consult method statement and COSHH (control of
substances hazardous to health) assessments for working
 If concrete comes into contact
with concrete to get correct PPE
with skin it can cause serious
 Concrete pump shall be checked for the inspection records
injuries
and test certificates
Pouring and pumping  Concrete burns  If a concrete pipe were to
 Concrete hoses and fittings should be visually inspected
concrete  Failure of pump/hoses burst it would cause serious
daily to check for any slices or damage to the outside
damage to property, and
 Concrete hoses to be double bagged when elevated.
could cause serious injury to
 The concrete pump shall be segregated from any persons
personnel
not dealing with the concreting works
 Vehicles shall not drive over concrete hoses where possible

G. General

 Potential run-off of harmful  Ensure the use of drip trays under all plant and materials that
chemicals used in refueling and could develop a drip/leaks of harmful materials e.g. fuel
maintenance of the piling rig and bowser, agitator, pump etc.
equipment affecting the  Make sure field bowsers are visually inspected DAILY to
surrounding ground identify any leaks or damage that could cause a leak
 Chemicals running into  Ensure all materials are kept as far away from standing
Refuelling /Greasing
watercourses resulting in water water/ flood water/ rivers as possible to reduce risk of
/Storage of harmful Gas/Oil/Fuel
course pollution contamination
materials
 Leaking fuel bowsers / COSHH  Spill kits must be in near vicinity to equipment that has the
stores resulting in harmful potential to cause a hazardous spill
pollution  COSHH assessments must be consulted and the crew
briefed before the task is undertaken
 COSHH assessments will outline the PPE required for the
task
Welding / cutting  Welding equipment  Welding equipment is extremely  Certificate welder only
 Hot works hot and can cause serious burns  Correct PPE must be Worn (Fireproof overalls/welding
 Abrasive wheels  Areas of rig being worked on can mask) along with mandatory
also become very hot and cause  PPE requirements outlined in method statement
serious burns  When carrying out cutting or welding works are must be
 Due to the nature of the work a segregated and screened off
fire could be caused resulting in  Correct fire extinguisher to be kept in the near vicinity at all
times
serious injury or death
 Gas and oxygen to be stored separately

Ref. PI-05-03-01-F01 Page 8


Work sequence Hazards Risk Control Measures
 Mounting of abrasive wheels by
untrained persons causing wheel  Trained operatives only to use abrasive wheels
to detach  Ensure equipment is properly maintained
 Wheel guards being damaged or  and fit for purpose
removed causing serious injury

Ref. PI-05-03-01-F01 Page 9


Work sequence Hazards Risk Control Measures
 Noise  Noise of machinery can cause  Hearing protection must be worn when in the specified
 Working hours serious damage to hearing vicinity of the rigs (specified by noise assessments)
 Noise in a sensitive community  Working hours to be agreed with site management
can cause disruption among
local neighbours
Enviroment
Security of equipment and plant  Unauthorized use of piling  Tools must be stored away properly when not in use and
equipment while on breaks
 Tools left unattended could be
picked up and used by
unauthorized personnel
 Untidy work area  An untidy area can cause slips  The work area should be cleared of obstructions and trip
 Manual handling trips and falls resulting in serious hazards
 Sharp edges injury  Collect excessive tying wire
 Lifting heavy loads can cause  Steel fixing tressels should be laid on firm level ground
Steel fixing
injuries  Stack reinforcement in agreed lay down areas
 Cuts and lacerations can be  Use barriers to segregate from other works
obtained from shard or  Use mechanical aids to lift steel bundles and heavy cages
protruding steel
 Plant movement  Plant movement in the vicinity  Ensure yourself and your personnel are in clear view and out
 Untidy work areas could seriously injure or cause a of the route of moving plant
 Spray markers fatality  Make plant operators aware that you are working in the area
 Slips trips and falls could occur if  Keep work area tidy at all times
Setting out
area is untidy  -Refer to COSHH for working with spray paint
 Fumes released from spray paint
could cause headaches and
sickness
H. Foot plate foundation
and pedestal
Excavate as deep as 1,0  Ensure working tools in good condition and knowing how to
meter (dimension 1,9 x 1,9 Beaten by working tools Personal injury
use properly
meter)  Provide adequate barriers, signs and warning lights to
Unauthorised access Personal injury
prevent unauthorized person entering the site
Type of soil benching :
 Identify confined space and deal with them inaccordance
types of ground collapse Confined space Trapped inside the excavation
with the confined space procedur erfer to PP-05-03
risk control depending on
how deep can be Spoil Storage Overturning  Make sure spoil storage areas must be clearly identified
(minimum 2 meter away from the excavation)

Ref. PI-05-03-01-F01 Page 10


Work sequence Hazards Risk Control Measures
excavate. If the deep is
more than ankle used
benching and shoring Access/Egress Fall inside the excavation  Access to excavation must be by suitably safe method
(multiplex 20mm and
struts)
Sharp edge. Cut from reinforcement bar end or  Rebar end and tie wire must turned down into reinforcement
Bar bending and tie wire cage
arragement rebar  Sufficient rest periode between jobs and avoid repetitious
Bending rebar Stains and sprains twisting
 Provide adequate shoring to hold wet concrete when pouring
Install formwork for Collapse formwork cause by
Struck down, wedge  Design formwork must be based on calculation from
pedestal (400 x 400 mm) improper shoring /stager
engineering
 Wearing rubber safety shoes; avoid walking backwards and
Wet concrete cover
Slip, fall, trip or twist ankle or knee make sure steel reinforcement not sags/give way because
reinforcement bar
Placing concrete not enough ties
 Worm eye protection and prepare water source near work
Wet concrete splashes in eyes Eyes injury
area to flush concrete from eye/s

Additional Note :
1. Electrical isolation.
2.
3.
4.
5.

Ref. PI-05-03-01-F01 Page 11


The following test are required to assess the atmospheric conditions in the nominated space :
TEST REQUIRED
TEST FOR Permissible Exposure Limit (PEL)
YES NO
Ammonia Less than 25 ppm √
Carbon Dioxide Less than 5000 ppm   √
Carbon Monoxide Less than 25 ppm   √
Chlorine Less than 0.5 ppm   √
Hydrogen Sulfide Less than 10 ppm   √
Oxygen Greater than 19.5% & Less than 23.5%   √
Ozone Less than 0.1 ppm   √
Sulphur Dioxide Less than 2 ppm   √
Hydrogen LEL = 4% & UEL = 75.6%   √
LEL Less than/ ≤ 4% √
Note :
1. Reference (OSHA PEL – 2013)
2. For clarification on the test required to be carried out refer PI-05-03-02 (Testing of Confined Space)

Ref. PI-05-03-01-F01 Page 12

Вам также может понравиться