FONCO CONSTRUCTION SDN. BHD.

FONCO

1
1. OUR HISTORY
2. STORAGE TANKS
3. SILOS
4. STEEL STRUCTURES & FACADES
5. ENERGY INDUSTRY PRODUCTS
6. ASSOCIATED SERVICES
7. SAFETY COMMITMENT
8. QUALITY ASSURANCE
OUR HISTORY

1987

1996 1997 1998 1999


Daelim GPP 5&6 Oil and Gas Flare Jacket Cone-tapered Storage BASF Complex Storage
Constructed 24 units of CS Construction of flare Tank Tanks
storage tanks of various Jacket for Seligi A Platform We were the first company A total of 23 units of
applications, with the & Riser pipe Spool with in Malaysia to have built storage tanks which
largest capacity being Monel Sheating for Bekok cone-tapered storage consists of C.S. and
9911m³. Total tonnage of C. tanks for the Pulp and SS316L materials were
the project was estimated Paper Mill owned by constructed in accordance
to be 725 MT. Malaysian Newsprint to API 650 and 620 on an
1998
Industries (MNI). A total of EPCC basis. Total tonnage
Turnkey Projects for Palm
46 SS316L tanks were built was 860 MT.
Oil Mill & Tea Processing
for MNI on an EPCC basis,
Plants
estimated weight is 750
We made advancements 1999
MT.
in the local palm oil mill Malaysian Olefins Project
industry by building the Owned by Petronas / UCC
largest plant in East 1998 JV, this was our pilot
Malaysia and also Gunawan Iron & Steel project that had used 3D
constructed several Gasholder Tank electronic matching for all
turnkey tea processing One unit of gasholder tank structural members and
plants in Malaysia. with dome roof and radiant steel panels. This
internal floating roof, was made possible by
Designed and built developing the shop
according to API 650 drawings in 3D format and
standards, our largest reassembling the
floating roof gasholder components to check for
tank ever had a diameter interference. A total of 7
of 50m, height of 25m and steel structures/platform
weighed 1,000 MT. and the radiant steel
panels for the Olefins
Cracking Furnace were
fabricated. The total
tonnage was 2,500 MT.

4
TODAY

2000 2003 2005 2010


Bechtel Chemical Tank HRSG Casing & Inlet Duct Posco Air Intake Filter Malay-Sino Chemicals
Constructed chemical A leading fabricator for the Houses Industries Tanks
storage tanks for BASF/ HRSG casing panels with Custom fabricated three Constructed four units of
Petronas Oxo-alcohol internal liner plates and Stage Air Intake Filter storage tanks which
project and for Bechtel insulation in Malaysia. We Houses for POSCO, South include a caustic tank and
butanol derivatives project. have completed these Korea. a brine clarifier tank for
The tanks were built and projects with Malay-Sino Chemicals
designed according to API commendable Industries SDN BHD, with
2006
620 or API 650 standards. achievements given by a total tonnage of 275 MT.
Pulstar Air Filter Houses
Some are floating roofs Alstom
Custom fabricated
tanks.
Pulstar Filter Modules,
2003 Clean Air Plenum, and
2000 Transition Duct. All
Mitsubishi Kakoki PVC AAF Air Intake Filter
Houses modules were exported to
Paste Plant Tank San Isidrol 2, Chile.
Constructed four units of We are strong supporter to
storage tanks for PVC the power generation
Paste Plant for Kaneka industries with our custom
Engineering (M) SDN fabrication work on Air
BHD, with a total tonnage Intake Filters Houses,
of 36 MT. Ductwork, Plenums
casing, and supporting
platforms. We have offered
2002 our expertise in the areas
Mahkota Technologies of developing the shop
Bulk Fuel Oil Tank floor detailing and unique
Constructed four units of manufacturing process to
bulk fuel oil storage tanks achieve the best quality
on an EPCC basis for ever.
Mahkota Technologies
SDN BHD with a total
tonnage of 69 MT.

5
STORAGE TANKS

STORAGE TANKS
This project consists of 2 sour water RAPID being one of the largest Petronas
tanks, 2 lean amine tanks, a liquid sulfur project in Malaysia, it is a great privilege
tank, and a fresh amine tank. Total and an honour that Fonco was chosen to
FOR RAPID tonnage was 1,810 MT. Completed in be one of the industry's players that
2018, Fonco had worked closely with the contribute to the growth of our nation.
PROJECT PKG4, main contractor and owner to meet the
stringent and necessary requirements

PENGERANG throughout the construction phase at


RAPID site.

6
TORAY PLASTICS
Completed in 2014, this dome roof tank with
19.5m diameter x 20m height, total tonnage
of 146 MT, was built in a live plant with limited
AN3 STORAGE space. We had devised a new construction
technique and incorporated automatic
TANK, PRAI welding processes that enabled us to
complete the construction within record time.

7
STORAGE TANKS & SILOS

PENFIBRE PELLET
Completed in 2014, this silo for storing pellet
with a dimension of ø4500 x 25,000mmH (25
MT) was built completely in our plant. The silo
SILO, PRAI was then transported wholly to site and
installed with a single lift. Site installation
activity was completed within a day, together
with connecting spiral staircase which was
delivered as a separate package.

8
LUBRICANT OIL
Based in Tuas, Singapore, this project
consists of 6 base oil storage tanks, 3
blending tanks, and an additive tank with
STORAGE TANKS, 50mm insulation. The base oil tanks were
constructed at the Tuas site, and the
TUAS remaining four smaller tanks were transported
in two assemblies for site assembly and
installation. Total tonnage was 250 MT,
completed in 2018.

9
STEEL STRUCTURES & FAÇADES

TABUNG HAJI
A unique design with three dimensional
varying axis was effortlessly captured in our
3D CAD drawing. With sophisticated
BUILDING ARCHES, electronic marking capabilities coupled with
shop drawings design to offer simplicity in the
PUTRAJAYA erection or installation process, this project
was realized and built with utmost precision
within a short time frame. All structural
members had architectural finishes with all
weld seams and joints ground flush. Fonco
was responsible for building the Block A, B
and D arches totaling 700 MT.

10
GUIDEWAY STEEL
Spanning 55m in length and 9m in width, the
280 MT guideway was fully constructed in our
factory in 5 segments and delivered to site for
STRUCTURE, installation. Splice joints at the ends of each
segment were fabricated with laser precision
SUBANG JAYA joint alignment.

11
ENERGY INDUSTRY PRODUCTS
SILENCERS
We are a strong supporter of the power generation industries with
our custom fabrication works of steam vent silencers, flue gas
silencers, and casings. At peak season, we are able to produce
110 units of silencers in a month. These silencers are exported
world wide.

PLENUM DUCT
This is a Central Electricity Board Mauritius project, with the scope
of fabricating a plenum duct. Leveraging our in-house 3D modelling
capability, we were able to convert our client’s CAD model, and
incorporated with our proprietary marking technology to speed up
our fabrication period. Trial fit activity was conducted in factory,
before exporting to Mauritius.

DIVERTERS
This is a diverter built for Gelugor Power Station, owned by Tenaga
Nasional Berhad. This 40 MT diverter were fabricated at shop, with
over 2000 units of internal insulation studs welded at precise
locations within a 4.6m x 4.6m x 4.6m volume surface area for the
installation of internal stainless steel panels.

STACK DAMPERS
This is a PT Alstom Power Energy Systems Indonesia project with
the scope of stack damper fabrication. It is a 7.5m diameter by
0.5m width damper with four rotating dampening blade. Working
closely with our client’s designer, we have conducted a trial fit in
factory to ensure all mechanical features were functional as per
requirement before delivery.

12
ASSOCIATED SERVICES
ENGINEERING
& 3D MODELLING
Our expertise lies in storage tanks design to API 620 or API 650
standards. Shop detailing for various categories such as structural
steelwork, panel work, storage tanks, pressure vessels, piping &
isometric, and 3D assembly and erection drawings can be
produced from General Arrangement drawings.

CNC PLASMA CUTTING


Our CNC High Definition Plasma machine is able to integrate
seamlessly with our 3D modelling capabilities, allowing the
machine to mark and cut at a high precision level, minimizing
human interference in our daily operations.

SPECIAL WELDING
Our welding specifications are to ASME and AWS code. Welding
processes include SAW, SMAW, MIG, TIG, and FCAW, aided by
semiautomatic machines to achieve consistent quality. We pride
ourselves in tailoring our welding activities to fulfill the specific
requirements of our clients.

PAINTING SERVICE
Sandblasting and painting is part and parcel of our services. We
are equipped with automatic grit blasting as well as manual
blasting facilities together with an indoor painting area. Our
knowledgeable workers are able to deliver a superior painting
quality.

13
SAFETY COMMITMENT

IT IS IMPERATIVE TO HAVE Our employees weld, fabricate, machine, By involving all personnel at every level of
COMPREHENSIVE SAFETY blast and paint in workshops, on client the company, we ensure that all staff are
PROTOCOLS IN PLACE TO sites, at height, and in confined spaces. aware of health and safety policies.
ENSURE OUR EMPLOYEES, Our main aim is to complete each job to Investing time and energy into workforce
the clients’ satisfaction and return home training is a priority within our company to
ASSETS, AND REPUTATION,
safely. Committed to our workforce, we ensure our and our clients’ needs are
ARE NOT COMPROMISED AT
continually monitor and audit our met. With committed and dedicated
ALL TIME.
systems, methods and employee welfare. management personnel and the
We ensure our workplaces are safe by cooperation and involvement of the
maintaining robust systems and workforce, we are able to deliver quality
protocols. products and services to the industry
without compromising safety.

SAFETY FIRST, DO IT THE RIGHT WAY FROM THE START

14
QUALITY ASSURANCE

AIMS QUALITY CONTROL DOCUMENTATION


We are committed to the pursuit of The quality of our product is vital to the We produce Manufacturing Data Record
Excellence in Quality with a vision to be success of our client. Inspection and volumes routinely for all projects.
the market leader, specializing in the core testing of our product are executed
activities in Engineering Design & the according to client’s requirement,
Fabrication of metallic products by international design codes and statutory
providing premium quality services to our inspection checks. Our team of
customers that exceeds mutually agreed experienced QC personnel assist our
requirements. production team to ensure that all quality
requirements are consistently met.

COMMITTED TO PRODUCING QUALITY SOLUTIONS

15
FONCO CONSTRUCTION SDN BHD (166914W)
Lot 84, Jalan Johan ½, Kawasan Perindustrian Pengkalan 2, 31500 Pusing, Perak, Malaysia.
Tel (05)-3663118, 3664113, 3663525 | Fax (05)-3667116 | Email: contactus@foncoeng.com

www.foncoeng.com

Вам также может понравиться