Department of Health
DAVAO REGIONAL MEDICAL CENTER
Apokon, Tagum City
Tel./Fax# (084) 216-9129
This Bid Bulletin is being issued to modify/amend the posted Philippine Bidding Documents for the
Construction of Lead Blood Facility under IB no. 18-04-120 to be opened on April 24, 2018. This Bid
Bulletin will form an integral part of the bidding documents. Below are the modifications/amendments
to wit:
1. General Scope of Works and Technical Specification
AS POSTED AS CORRECTED
2. Demolition and Dismantling Works
9. CEILING WORKS
Supply & Installation of 4.0mm THK. Supply & Installation of 3.5mm THK.
FIBERCEMENT BOARD CEILING SYSTEM ON 2"x2" FIBERCEMENT BOARD CEILING SYSTEM ON
METAL FURRING FRAMES IN WHITE FLAT LATEX 2’x2’ METAL FURRING FRAMES IN WHITE
PAINT FINISH for interior ceiling system. FLAT LATEX PAINT FINISH for interior ceiling
system
Supply & Installation of 4.0mm THK. ALUMINUM Supply & Installation of ALUMINUM SPANDREL
SPANDREL CEILING SYSTEM ON METAL FRAMING CEILING SYSTEM ON METAL FRAMING
including angles, furring and hangers for exterior including angles, furring and hangers for
ceiling system. exterior ceiling system.
1
AS POSTED AS CORRECTED
Supply and installation of Ga. 26 (0.4mm thk) Supply and installation of Ga. 26 (0.4mm thk)
Pre-painted Duratile type roofing sheets (red Pre-painted Duratile type roofing sheets
color) including ridge caps, flashings and (Spanish red color) including ridge caps,
accessories. flashings and accessories.
This project shall consist of furnishing and This project shall consist of furnishing and
installation of positive air system, heating and installation of positive air system, ventilating
ventilating and air-conditioning system, and, and air-conditioning system, and, 100% air
100% air flow system particularly in operating flow system.
and infectious rooms.
Installation of equipment and its accessories and Installation of equipment and its accessories
auxiliaries shall conform to established standards. and auxiliaries shall conform to established
The project includes testing of all equipment and standards. The project includes testing of all
all other related activity needed for commissioning. equipment and all other related activity needed
The contractor shall provide maintenance program for commissioning.
for all equipment or as recommended by the
manufacturer. The types, sizes, capacities,
quantities and power characteristics of the
compressor, evaporator and condenser shall be as
specified or as shown in the plans.
2
AS POSTED AS CORRECTED
General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)
• Installation of refrigerant
tubing/pipes and charging of
refrigerant
• Pipes shall be supplied and
installed as per established
standards. Refrigerant pipes shall
be copper tubing, type L or K black
steel pipe, schedule 40 for size of 4
inches diameter and smaller. Pipe
over 4 inches shall be black steel
pipe schedule 40
E. DUCT WORKS AND INSTALLATION OMIT
3
AS POSTED AS CORRECTED
General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)
I. CONSTRUCTION REQUIREMENT
Floor Designation Hoistway: Ground and 2nd Floor Designation Hoistway: Ground and 2nd
Floor Floor ( Ready for 3rd Floor)
4
2. BILL OF QUANTITIES
AS POSTED AS CORRECTED
Material Description: (for ground and Material Description: (for ground and
second floor) second floor)
4.0mm thk. X 4' x 8' Fibercement Board Ceiling 3.5 mm thk. X 4' x 8' Fiber cement Board
System Ceiling System
All other provisions of the bidding documents which are not affected shall remain in effect.
_________________________
Date: ____________________
5
Project : CONSTRUCTION OF LEAD BLOOD FACILITY ( Phase 1)
Location : DRMC COMPOUND, APOKON, ATGUM CITY
ITB No. 18-04-120 PR No. 18-03-092 PhilGEPS Ref no. 5264995 (CB)
Direct Cost :
a. Material Cost
b. Labor Cost
c. Project Billboard
d. Safety and Health Program
e. Equipment Rental Cost
Sub - total II
Indirect Cost :
1. Overhead Expenses & Supervisions
2. Contingencies
3. Miscellaneous
a. Building Permits
b. Bureau of Fire Protection Permit
c. As- built Plans
4. Contractor's Profit
5. VAT 12.00%
Sub - total III
TOTAL BID COST
AMOUNT IN WORDS:
B. DETAILED ESTIMATES
I Demolition and Dismantling Works
a. Demolition, hauling and clearing of area. 335.189 sq.m.
b. Dismantling of existing road. 10.754 sq.m.
345.942 sq.m.
Heavy Equipment Description Quantity Unit Unit Cost Add Amount
Backhoe 1 unit days
Equipment Rental Cost, Php
c. Clean up & Hauling
Dump Truck, 10 T 1 unit days
Equipment Rental Cost, Php
Demolition and Dismantling Work Cost, Php
III EARTHWORKS
a. Equipment for Excavation of Column/Footing and Hauling 74.110 cu.m
b. Equipment for Excavation of Footing Tie beam & Wall Footing 28.817 cu.m
c. Equipment for Excavation of Septic Tanks 17.500 cu.m
120.427 cu.m
Heavy Equipment Description Quantity Unit Unit Cost Add Amount
Backhoe 1 unit days
Dump Truck, 10 T 1 unit days
Equipment Rental Cost, Php
V CONCRETE WORKS
a. Column/Footing 93.449 cu.m.
Material Description Quantity Unit Unit Cost Add Amount
Boulders, 6" dia. 54 cu.m
DRB, 25 mm dia x 6m 99 lengths
DRB, 20 mm dia x 6m 492 lengths
DRB, 16 mm dia x 6m 102 lengths
DRB, 10 mm dia. X 6m 233 lengths
G.I Tie Wire, # 16, 35 kgs/roll 7 rolls
Portland Cement , 40 kgs. 842 bags
Washed Sand 47 cu.m.
Washed Gravel ( class yy 3/4") 94 cu.m.
Material Cost , Php
Labor Cost
Equipment Cost , Php
Column/Footing Work Cost, Php
VI MASONRY WORKS
a. Ground Floor 416.336 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
6" CHB 4121 pcs.
4" CHB 945 pcs.
DRB, 10 mm dia. X 6m 249 lengths
G.I Tie Wire, # 16, 35 kgs/roll 2 rolls
Portland Cement , 40 kgs. 522 bags
Washed Sand 18 cu.m.
Material Cost , Php
Labor Cost
Ground Floor Cost
Second Floor :
a. Tiling of Main flooring. 319.233 sq.m.
b. Tiling of Comfort Rooms . 49.544 sq.m.
c. Tiling near at Stairs & Elevator 1.820 sq.m.
d. Tiling of Washing Counters 2.130 sq.m.
372.727 sq.m.
Material Description Quantity Unit Unit Cost Amount
600mm x 600mm HOMOGENEOUS WHITE NON-SKID FLOOR TILE
(as per sample) 893 pcs.
300mm x 300mm BEIGE CERAMIC TILES MATT/NON-SKID FINISH
(as per sample) 88 pcs.
300mm x 300mm LIGHT GREY CERAMIC WALL TILE MATT FINISH
UP TO 5 LAYERS FROM THE FLOOR FINISH & WHITE PAINT AT 473 pcs.
UPPER HALF TO CEILING (as per sample)
400mm X 400mm Ceramic Tactiles (Salt and Pepper or Gray) (as per
sample)
21 pcs.
IX CEILING WORKS
Ground Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 161.74 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
b. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (BROWN) including angles, furring and 17.88 sq.m.
hangers.
c. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (WHITE) including angles, furring and 35.27 sq.m.
hangers.
214.89 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 161.74 sq.m.
ALUMINUM SPANDREL x 10' 53.15 sq.m.
Ground Floor Works Cost, Php
Second Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 176.40 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
b. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (BROWN) including angles, furring and 16.69 sq.m.
hangers.
193.09 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 176.40 sq.m.
ALUMINUM SPANDREL x 10' 16.69 sq.m.
Second Floor Works Cost, Php
Third Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 20.95 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 20.95 sq.m.
Third Floor Works Cost, Php
TOTAL CEILING WORK COST, PHP
X CARPENTRY WORKS 1 lot
a. Fabrication of locker, drawers, tables and cabinets. (see drawing Details)
Material Description Quantity Unit Unit Cost Add Amount
20 mm thk. x 4' x 8' Plyboard 44 shts
Hydraulic concealed hinges, pull over lay 10 pairs
Assorted Nails 1 case
Accessories 1 lot
Material Cost , Php
Labor Cost
Carpentry Works Cost, Php
a. Pebble Washout finish (BEIGE) at main entrance and ramp. 25.84 sq.m.
XV GLASS WORKS
Ground Floor: 4 sets
a. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame
b. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame w/ Frosted Film
Material Description Quantity Unit Unit Cost Add Amount
Glass Partition w/ 6mm thk. Fixed Glass
Partition #1 (4.1L x 2.55H)
Panel on Analuk Frame
1 unit
c. Plumbing Fixtures
Material Description Quantity Unit Unit Cost Add Amount
Stainless Sink w/ Complete ass. 4 units
Toilet Bowl, Flush Type 4 sets
Lavatory 4 sets
Lavatory faucet 4 pcs.
Plastic Faucet, Heavy Duty 15 pcs.
Bedit Faucet 4 sets
Gate Valves 10 pcs.
Soap Holder 4 pcs.
Tissue Holder 4 pcs.
6" x 6" Floor Drain 4 pcs.
4" x 4" Floor Drain 4 pcs.
Exhaust Fan w/ Ducting & Diffuser 4 sets
Material Cost , Php
Labor Cost , Php
Plumbing Fixture Cost
d. Drainage System
Material Description Quantity Unit Unit Cost Add Amount
RCPC, 12"Ø 58 pcs
Portland Cement , 40 kgs. 12 bags
Washed Sand 4 cu.m.
Material Cost , Php
Labor Cost
Drainage System Cost
XX PAINTING WORKS
Ground Floor Area : 1,099.90 sq.m.
a. Painting works are all solvent based.
Material Description Quantity Unit Unit Cost Amount
Liquid Tile Primer 52 gals.
Liquid Tile Gloss 75 gals.
Liquid Tile Cast 63 gals.
Liquid Tile Reducer 63 gals.
Liquid Tile Tint Color , Hansa Yellow 70 pints
Liquid Tile Tint Color , Venetian Red 40 pints
Liquid Tile Tint Color , Black 20 pints
Textured Paint Roller w/ Tray, 7", heavy duty 10 pcs
Paint Roller w/ Tray, 7", heavy duty 20 pcs
Baby Paint Roller, 4", cotton 10 pcs
Paint Brush, 4" 10 pcs
Paint Brush, 2" 10 pcs
Sand Paper, # 120 100 pcs
Sand Paper, # 60 70 pcs
Masking Tape 60 rolls
Polyster Body Filler w/ Hardener 11 gals.
Non - sag Epoxy , A & B 8 pairs
Concrete Neutralizer 8 gals.
Material Cost , Php
Labor Cost , Php
Ground Floor Area Work Cost, Php
Second Floor Area : 865.61 sq.m.
a. Painting works are all solvent based.
Material Description Quantity Unit Unit Cost Amount
Liquid Tile Primer 40 gals.
Liquid Tile Gloss 58 gals.
Liquid Tile Cast 49 gals.
Liquid Tile Reducer 49 gals.
Liquid Tile Tint Color , Hansa Yellow 50 pints
Liquid Tile Tint Color , Venetian Red 30 pints
Liquid Tile Tint Color , Black 20 pints
Textured Paint Roller w/ Tray, 7", heavy duty 10 pcs
Paint Roller w/ Tray, 7", heavy duty 10 pcs
Baby Paint Roller, 4", cotton 10 pcs
Paint Brush, 4" 15 pcs
Paint Brush, 2" 10 pcs
Sand Paper, # 120 100 pcs
Sand Paper, # 60 60 pcs
Masking Tape 70 rolls
Polyster Body Filler w/ Hardener 8 gals.
Non - sag Epoxy , A & B 7 pairs
Concrete Neutralizer 7 gals.
Material Cost , Php
Labor Cost , Php
Second Floor Area Work Cost, Php
Total Cost
Total MECHANICAL WORK Cost, Php
Second Floor :
a. Fire Protection System
Material Description Quantity Unit Unit Cost Amount
Fire Extinguisher, HCFC 123, (10lbs); 2 unit
Fire Extinguisher, ABC Dry Chemical Content, Red (10lbs) 2 unit
Floor Control Valve 3" 1 Unit
Sight Glass 1 Unit
Ball Valve 1 1/2" 1 Unit
Water Flow switch 1 Unit
BI Pipe 3" dia Sch 40 2 length
BI Pipe 2" dia Sch 40 2 length
BI Pipe 1 1/2" dia Sch 40 2 length
BI Pipe 1" dia Sch 40 14 length
Fire Hose Cabinet 100Ft (Complete Set) 1 length
BI fittings and hangers 1 lot
Consumables 1 lot
c. Electrical Works
d.1. Supply, installation & tapping of new transformer from the nearest post to the elevator electrical panel.
d.2. Supply and installation of switches and lighting fixtures at the elevator area.
d.3. Electrical Works for Elevator are Ready for 3rd floor.
Material Description Quantity Unit Unit Cost Amount
25 KVA transformer 1 unit
Electrical Wires 1 lot
Material Cost , Php
Labor Cost
Electrical Work for Elevator Cost, Php
Prepared by:
_____________________
Contractor/ Representative
PROJECT NAME : CONSTRUCTION OF LEAD BLOOD FACILITY (P1)
APPROPRIATION : P 16,463,178.59
FUND SOURCE :
SUBJECT : GENERAL
SCOPE OF WORKS & TECHNICAL
SPECIFICATIONS- REVISED
2.1 The work shall be carried out strictly in accordance with the requirement of the
Work Orders attached as required by the Proponent.
2.2 The Project shall be carried out in all respect to the requirements of the Contract
Documents and applicable Philippine Standards, Code and Specifications.
3. Earthworks
This activity includes the following:
• Earthwork consists of excavation, back filling and disposal of
surplus material. Work of this section includes all measures and
materials required to complete the design supply, support, use,
construction, removal of earth work.
• Boulders of 6” to 8” dia. should be used as column foundation
beddings.
• Excavation of Column/Footing and Hauling
• Excavation of Footing Tie Beam & Wall Footing
• Excavation of Septic Tanks
• Backfilling and Compacting
6. Masonry Works
• This item consists of the construction of 150mm thk. CHB for perimeter
and zocalo walls, and 100mm thk. CHB for interior walls, T&B/CR walls
and concrete counter stands smooth plastered finished.
• All Concrete Hollow Blocks shall be machine-made and all CHB walls
shall be cement plastered (12mm thk.) and smooth finished and are
reinforced with 10mm dia. deformed bars with spacing of 600mm o.c. for
vertical reinforcement and every 3 layers for horizontal reinforcement.
• Mortar filler shall be Class “B” mixture while Cement Plastering shall be
Class “A” mixture;
• Construction of new toilets;
• Construction of Septic Tank using 150mm CHB (1 unit- 2m x 4m x 2m
depth).
(Please refer to Approved Detailed Plans, Drawings & Specifications)
7. Tiling Works
This activity includes the following:
• Supply and installation of 300mm x 300mm ceramic floor and wall
tiles for toilets.
• Supply and installation of 600mm x 600mm granite tiles on main
floorings (ground & second floor).
• Supply and installation of 400mm x 400mm ceramic tactiles on main
entrance (ground floor), near stairs and elevator (second floor).
(Ceramic Tactiles)
• Supply and installation of 600mm x 600mm granite tiles on stairs
with bronze stair nosing at edge.
• Supply and installation of Granite Slab, 3/4" x 2' x 8' at concrete
counters and mop wash.
• Sample of tiles should be presented to the agency’s representative
for approval prior to installation.
9. Ceiling Works
• Supply & Installation of 3.5mm THK. FIBERCEMENT BOARD
CEILING SYSTEM ON 2’x2’ METAL FURRING FRAMES IN WHITE
FLAT LATEX PAINT FINISH for interior ceiling system.
• Supply & Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING including angles, furring and hangers for
exterior ceiling system.
13. Doors
DOORS: Fabrication and Installation
• Supply and installation of double swing glass door using 12mm thk
Annealed Glass Panel
• Supply and installation of sliding glass door using 12mm thk
Annealed Glass Panel on Analuk frame.
• Supply and installation of swing glass door using 12mm thk
Annealed Glass Panel on Analuk frame.
• Supply and installation of single swing PVC door on white standard
PVC Panel with louvers at bottom.
14. Windows
WINDOWS: Supply and Installation
• Supply and installation of 6mm thk fixed glass window using Fixed
Glass Panel on Analuk Frame.
• Supply and installation of 6mm thk awning glass window and Fixed
Glass Panel on Analuk Frame.
• Supply and installation of 6mm thk sliding glass window and Fixed
Glass Panel on Analuk Frame.
• Supply and installation of transaction window with 6mm thk. Fixed
Glass Panel on Analuk Frame with sliding glass below.
This project shall consist of furnishing and installation of positive air system,
heating and ventilating and air-conditioning system, and, 100% air flow system.
This includes necessary electrical connections, pipes and condensate drains and
all other necessary accessories and auxiliaries, ready for service in accordance
with the plans and specifications.
A. SUPPLY OF EQUIPMENT
• ACU: 1 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 1.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 2 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 2.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• Exhaust Fan, ceiling mounted, 230V, 1 phase
B. PIPE INSULATION INSTALLATION
C. ELECTRICAL WORKS
D. STANDARDS
This project shall consist of furnishing and installation of Fire Sprinkler System. Provide
necessary isolating fixtures such as Gate Valves and Check. System testing shall be
done in the presence of the hospital chief, project engineer and DOH representative.
• Buried pipes shall be provided with bituminous material wrapped around its
circumferential
• Exposed pipes shall be applied with epoxy primer AB for two coatings
• Exposed pipes shall be applied with fire red paint for two coatings after
application of epoxy primer
H. CONSTRUCTION REQUIREMENT
I. CONTRACTOR REQUIREMENT
• The contractor shall have ample experience on fire fighting system specially
on stand pipe system
J. OPERATING TEST
•
The piping system shall be hydro tested 1.5 times the operating pressure or
as per recommended in the NFPA standards. Test shall be within 3 hours
without dropping of pressure.
• All leak/s or suspected leak/s shall be eliminated/repaired before acceptance
K. METHOD OF MEASUREMENT
• The work under this item shall be measured either by set, piece, length,
square foot actually placed and installed as shown in the plans
• FHC shall be measured by set; valves by piece, pipe/tubing by length
L. MISCELLANEOUS
• The owner shall be provided with three (3) bound copies “ AS BUILT “
diagram, shop drawings, parts lists, serial number and inventory of equipment
including manufacturers and maintenance manuals
M. STANDARDS
LIFT LOBBY
Landing Door Panel Finishes ( Main Floors) Hairline Stainless Steel
Landing Door Panel Finishes ( Typical Floors) Hairline Stainless Steel
SPECIAL FEATURES
Arrival Gong on Car
Intercom system, 3 way
Attendant control
Out -of -service Switch
ADDITIONAL FEATURES
Emergency Landing Device- UPS must be
provided in case of power failure.
Management Key Switch
Training for four (4) in-house elevator
maintenance and operators.
Warranty : Two (2) years, parts and service