Вы находитесь на странице: 1из 32

Republic of the Philippines

Department of Health
DAVAO REGIONAL MEDICAL CENTER
Apokon, Tagum City
Tel./Fax# (084) 216-9129

BID BULLETIN NO. 1


April 13, 2017

This Bid Bulletin is being issued to modify/amend the posted Philippine Bidding Documents for the
Construction of Lead Blood Facility under IB no. 18-04-120 to be opened on April 24, 2018. This Bid
Bulletin will form an integral part of the bidding documents. Below are the modifications/amendments
to wit:
1. General Scope of Works and Technical Specification

AS POSTED AS CORRECTED
2. Demolition and Dismantling Works

• Dismantling of existing road • Dismantling of existing catwalk

5. Concrete Works/ Structural Steel Works


• Construction of concrete gutters with a OMIT
minimum width of 0.50 meter and 0.20 meter
depth

• Reinforcing bar should be deformed bars for


• Reinforcing bar should be deformed bars for all
all reinforced concrete work,use Grade 40 (
reinforced concrete work, and should have
275 MPa) for 16mm dia reinforcing bars ;
minimum yield strength of 414 N/mm2 (60000
use Grade 60 (415 MPa) for 20mm &
psi) in accordance to (ASTM A 184 and A 185).
25mm dia. Reinforcing bars in accordance
Representative samples of all steel
to (ASTM A 184 and A 185). Present
reinforcement that the contractor proposes to
samples of all steel reinforcement that the
use in the Works together with manufacture's
contractor proposes to use in the Works
certificate stating clearly for each sample, the
together with manufacture's certificate
place of manufacture expected date and size of
stating clearly for each sample, the place of
deliveries to site, and all relevant details as
manufacture expected date and size of
regards composition manufacture, strength and
deliveries to site, and all relevant details as
other qualities of the steel shall be submitted
regards composition manufacture, strength
to the Engineer for written approval
and other qualities of the steel shall be
submitted to the Engineer for written
approval

9. CEILING WORKS

Supply & Installation of 4.0mm THK. Supply & Installation of 3.5mm THK.
FIBERCEMENT BOARD CEILING SYSTEM ON 2"x2" FIBERCEMENT BOARD CEILING SYSTEM ON
METAL FURRING FRAMES IN WHITE FLAT LATEX 2’x2’ METAL FURRING FRAMES IN WHITE
PAINT FINISH for interior ceiling system. FLAT LATEX PAINT FINISH for interior ceiling
system
Supply & Installation of 4.0mm THK. ALUMINUM Supply & Installation of ALUMINUM SPANDREL
SPANDREL CEILING SYSTEM ON METAL FRAMING CEILING SYSTEM ON METAL FRAMING
including angles, furring and hangers for exterior including angles, furring and hangers for
ceiling system. exterior ceiling system.

1
AS POSTED AS CORRECTED

12. RAILINGS AND GRILLS


• Additional:
Stainless Steel Railings
18. Roofing System and Tinsmithry

Supply and installation of Ga. 26 (0.4mm thk) Supply and installation of Ga. 26 (0.4mm thk)
Pre-painted Duratile type roofing sheets (red Pre-painted Duratile type roofing sheets
color) including ridge caps, flashings and (Spanish red color) including ridge caps,
accessories. flashings and accessories.

General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)

This project shall consist of furnishing and This project shall consist of furnishing and
installation of positive air system, heating and installation of positive air system, ventilating
ventilating and air-conditioning system, and, and air-conditioning system, and, 100% air
100% air flow system particularly in operating flow system.
and infectious rooms.
Installation of equipment and its accessories and Installation of equipment and its accessories
auxiliaries shall conform to established standards. and auxiliaries shall conform to established
The project includes testing of all equipment and standards. The project includes testing of all
all other related activity needed for commissioning. equipment and all other related activity needed
The contractor shall provide maintenance program for commissioning.
for all equipment or as recommended by the
manufacturer. The types, sizes, capacities,
quantities and power characteristics of the
compressor, evaporator and condenser shall be as
specified or as shown in the plans.

B. EQUIPMENT INSTALLATION OMIT

• Installation of all air handling


equipment
• Foundation shall be provided and
shall conform to the
recommendation of the
manufacturers of the equipment.
Equipment shall be levelled on
foundation. All spaces between
equipment bases and concrete
shall be filled with cement mortar.
• For skid type equipment, anchor
the equipment to the concrete slab
(10 ins. Thick) using log screw.
Clearance around equipment base
should not be less than 12 inches

2
AS POSTED AS CORRECTED
General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)

C. REFRIGERANT TUBING/PIPES OMIT


INSTALLATION

• Installation of refrigerant
tubing/pipes and charging of
refrigerant
• Pipes shall be supplied and
installed as per established
standards. Refrigerant pipes shall
be copper tubing, type L or K black
steel pipe, schedule 40 for size of 4
inches diameter and smaller. Pipe
over 4 inches shall be black steel
pipe schedule 40
E. DUCT WORKS AND INSTALLATION OMIT

• Installation of all ducting as shown


in the drawing shall have proper
hangers and supports
• Ducts shall be galvanized sheet
steel of not less than the following
gauges:
No. 26 for 12 inches wide and
smaller
No. 24 for 14 inches wide to 30
inches wide
No. 22 for 31 inches wide to 60
inches wide
No. 20 for 61 inches wide to 89
inches wide
No. 18 for 90 inches wide to 99
inches wide

F. DUCT WORK INSULATION AND OMIT


INSTALLATION
• Installation of insulating materials to
all ducts
• Insulation material shall be rigid
board made of fibre glass or
equivalent as commonly used
material. The insulating material
should be 1 inch for internal area
and 2 inches for external

3
AS POSTED AS CORRECTED
General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)

G. DAMPER INSTALLATION OMIT

• Volume dampers should be


properly installed to its diffuser and
in accordance with ASHRAE and
SMACNA standards
• Damper shall be of same material
as duct, at least one gauge heavier
and shall have accessible location,
complete with locking device for
adjusting and locking damper in
position. Where necessary,
splitters, butterflies, and louvers
damper deflecting vanes for control
of air volume and direction and for
balancing the system shall be
provided wither or not they are
indicated in the plans

I. CONSTRUCTION REQUIREMENT

• The air conditioning system shall


be entirely automatic in operation
and shall not require the presence
of attendant except for periodic
inspection for lubrication and other
maintenance schedule. All
equipment and materials shall be
inspected upon delivery and shall
be tested after installation. Piping
shall not be buried, concealed, or
insulated until it has been
inspected, tested and approved.
Walls, floors and other parts of the
building and equipment damaged
by the contractor in the prosecution
of the work shall be replaced as
shown in the plans

GENERAL SCOPE OF WORKS & SPECIFICATIONS:


(Supply & Installation of one (1) unit Elevator)

No. of Openings: 1 @ front No. of Openings : 2 @ front and back

Floor Designation Hoistway: Ground and 2nd Floor Designation Hoistway: Ground and 2nd
Floor Floor ( Ready for 3rd Floor)

4
2. BILL OF QUANTITIES

AS POSTED AS CORRECTED

IX. CEILING WORKS


(Ground floor)
a. Supply & Installation of 4.0mm THK. a. Supply & Installation of 3.5mm THK.
FIBERCEMENT BOARD CEILING SYSTEM ON FIBERCEMENT BOARD CEILING SYSTEM
2"x2" METAL FURRING FRAMES IN WHITE FLAT ON 2"x2" METAL FURRING FRAMES IN
LATEX PAINT FINISH WHITE FLAT LATEX PAINT FINISH
(Second Floor)
a. Supply & Installation of 4.0mm THK. a. Supply & Installation of 3.5mm THK.
FIBERCEMENT BOARD CEILING SYSTEM ON FIBERCEMENT BOARD CEILING SYSTEM
2"x2" METAL FURRING FRAMES IN WHITE FLAT ON 2"x2" METAL FURRING FRAMES IN
LATEX PAINT FINISH WHITE FLAT LATEX PAINT FINISH

Material Description: (for ground and Material Description: (for ground and
second floor) second floor)
4.0mm thk. X 4' x 8' Fibercement Board Ceiling 3.5 mm thk. X 4' x 8' Fiber cement Board
System Ceiling System

3. Revised Bill of Quantities, General Scope of Works & Technical Specifications

(PLEASE SEE ATTACHED)

All other provisions of the bidding documents which are not affected shall remain in effect.

For guidance and information of all concerned.

RHODORA M. BOISER, MPA


BAC Chairperson

Received by the bidder:

_________________________
Date: ____________________

5
Project : CONSTRUCTION OF LEAD BLOOD FACILITY ( Phase 1)
Location : DRMC COMPOUND, APOKON, ATGUM CITY
ITB No. 18-04-120 PR No. 18-03-092 PhilGEPS Ref no. 5264995 (CB)

A. BILL OF QUANTITIES (REVISED)


Item Description Quantity Unit Unit Total
# Cost (Add)

I Demolition and Dismantling Works 345.942 sq.m.


II STAKING and LAY-OUT 379.188 sq.m.
III EARTHWORKS 120.427 cu.m
IV Formworks and Scaffoldings 922.185 sq.m.
V CONCRETE WORKS
a. Column/Footing 93.449 cu.m.
b. Footing Tie Beam and Wall Footing 18.135 cu.m.
c. Slab-on fill Flooring 33.519 cu.m.
d. Stairs , 2 units 8.111 cu.m.
e. Second Floor Beams, Intermediate Beams and Cantilever
31.956 cu.m.
Beams
f. Third Floor Beams and Lintel Beams 22.160 cu.m.
g. Suspended Slab (2nd & 3rd Floor) 49.348 cu.m.
h. Concrete Canopy (2nd & 3rd Floor) 6.947 cu.m.
VI MASONRY WORKS
a. Ground Floor 416.336 sq.m.
b. Second Floor 231.526 sq.m.
c. Third Floor 108.978 sq.m.
d. Septic Tank ( 1 unit- 2m x 4m x 2m depth) 17.500 sq.m.
e. Wall Footing 74.335 sq.m.
VII TILING WORKS
Ground Floor : 389.328 sq.m.
Second Floor : 372.727 sq.m.
VIII WATER PROOFING WORKS 266.914 sq.m.
IX CEILING WORKS
Ground Floor: 214.890 sq.m.
Second Floor: 193.090 sq.m.
Third Floor: 20.950 sq.m.
X CARPENTRY WORKS 1 lot
XI STEEL WORKS 1 lot
XII Railings and Grills 1 lot
XIII DOORS & WINDOWS
Ground Floor: 8 sets
Second Floor: 4 sets
Third Floor: 1 set
XIV SPECIAL FINISHES 25.840 sq.m.
XV GLASS WORKS
Ground Floor: 4 sets
Second Floor: 3 sets
XVI CLADDING WORKS 137.668 sq.m.
XVII ROOFING SYSTEM 44.422 sq.m.
XVIII Hardwares 1 lot
XIX PLUMBING WORKS 1 lot
XX PAINTING WORKS
Ground Floor Area : 1099.897 sq.m.
Second Floor Area : 865.611 sq.m.
Third Floor Area : 263.636 sq.m.
XXI ELECTRICAL WORKS 1 lot
XXII MECHANICAL WORKS 1 lot
XXIII FIRE PROTECTION & ALARM SYSTEM 1 lot
XXIV SUPPLY & INSTALLATION OF ELEVATOR 1 lot
XXV PROJECT BILLBOARD 1 unit
XXVI SAFETY AND HEALTH PROGRAM 1 lot
Total: (Estimated Direct Cost)
BREAKDOWN OF ESTIMATED COST :
Engineering & Administrative Overhead Cost (EAO) :
a. Structural Design and Analysis 82,000.00

Sub - total I 82,000.00

Direct Cost :
a. Material Cost
b. Labor Cost
c. Project Billboard
d. Safety and Health Program
e. Equipment Rental Cost

Sub - total II
Indirect Cost :
1. Overhead Expenses & Supervisions
2. Contingencies
3. Miscellaneous
a. Building Permits
b. Bureau of Fire Protection Permit
c. As- built Plans
4. Contractor's Profit
5. VAT 12.00%
Sub - total III
TOTAL BID COST
AMOUNT IN WORDS:

B. DETAILED ESTIMATES
I Demolition and Dismantling Works
a. Demolition, hauling and clearing of area. 335.189 sq.m.
b. Dismantling of existing road. 10.754 sq.m.
345.942 sq.m.
Heavy Equipment Description Quantity Unit Unit Cost Add Amount
Backhoe 1 unit days
Equipment Rental Cost, Php
c. Clean up & Hauling
Dump Truck, 10 T 1 unit days
Equipment Rental Cost, Php
Demolition and Dismantling Work Cost, Php

II STAKING and LAY-OUT Quantity Unit


a. Installation of batterboards for layout and perimeter fence 314.388 sq.m.
b. Temporary Bunkhouse 64.800 sq.m.
379.188 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
Laminated Blue Tent, 8', 100Lm/roll 1 rolls
Fishing Nylon, 2mm dia. 7 rolls
CWN 4" , 25 kgs/box 1 boxes
Coco Lumber, 2"x 3"x10' 99 495 bdft.
Coco Lumber, 2"x 2"x10' 101 338 bdft.
Material Cost , Php
Labor Cost
STAKING and LAY-OUT Work Cost, Php

III EARTHWORKS
a. Equipment for Excavation of Column/Footing and Hauling 74.110 cu.m
b. Equipment for Excavation of Footing Tie beam & Wall Footing 28.817 cu.m
c. Equipment for Excavation of Septic Tanks 17.500 cu.m
120.427 cu.m
Heavy Equipment Description Quantity Unit Unit Cost Add Amount
Backhoe 1 unit days
Dump Truck, 10 T 1 unit days
Equipment Rental Cost, Php

d. Backfilling and Tampering (+ 25% compaction) 109.058 cu.m


Material Description Quantity Unit Unit Cost Add Amount
Good Mixed (Sand & Gravel) 110.00 cu.m
Material Cost , Php
Labor Cost
Total Eathworks Work Cost, Php

IV Formworks and Scaffoldings 922.19 sq.m.


a. Forms and Bracings for columns, beams, parapets and slabs.
Material Description Quantity Unit Unit Cost Amount
Assorted Nails 19 boxes
Coco Lumber, 2"x 4"x10' 1200 8,000.000 bdft.
Coco Lumber, 2"x 3"x10' 1100 5,500.000 bdft.
Coco Lumber, 2"x 2"x10' 1600 5,333.333 bdft.
Plywood, 1/2" Thk X 4'X 8' 380 shts.
Material Cost , Php
Labor Cost
Formworks and Scaffoldings Work Cost, Php

V CONCRETE WORKS
a. Column/Footing 93.449 cu.m.
Material Description Quantity Unit Unit Cost Add Amount
Boulders, 6" dia. 54 cu.m
DRB, 25 mm dia x 6m 99 lengths
DRB, 20 mm dia x 6m 492 lengths
DRB, 16 mm dia x 6m 102 lengths
DRB, 10 mm dia. X 6m 233 lengths
G.I Tie Wire, # 16, 35 kgs/roll 7 rolls
Portland Cement , 40 kgs. 842 bags
Washed Sand 47 cu.m.
Washed Gravel ( class yy 3/4") 94 cu.m.
Material Cost , Php
Labor Cost
Equipment Cost , Php
Column/Footing Work Cost, Php

b. Footing Tie Beam and Wall Footing 18.135 cu.m.


Material Description Quantity Unit Unit Cost Add Amount
DRB, 20 mm dia x 6m 159 lengths
DRB, 10 mm dia. X 6m 1012 lengths
G.I Tie Wire, # 16, 35 kgs/roll 5 rolls
Portland Cement , 40 kgs. 164 bags
Washed Sand 10 cu.m.
Washed Gravel ( class yy 3/4") 19 cu.m.
Material Cost , Php
Labor Cost
Equipment Cost , Php
Tie Beam and Wall Footing Work Cost, Php

c. Slab-on fill Flooring 33.519 cu.m.


Material Description Quantity Unit Unit Cost Add Amount
DRB, 10 mm dia. X 6m 280 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 303 bags
Washed Sand 18 cu.m.
Washed Gravel ( class yy 3/4") 35 cu.m.
Material Cost , Php
Labor Cost
Equipment Cost , Php
Slab-on fill Work Cost, Php

d. Stairs , 2 units 8.111 cu.m.


Material Description Quantity Unit Unit Cost Add Amount
Portland Cement , 40 kgs. 73 bags
Washed Gravel ( class yy 3/4") 8 cu.m.
Washed Sand 4 cu.m.
DRB, 16 mm dia. X 6m 64 lengths
DRB, 10 mm dia. X 6m 80 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Material Cost , Php
Labor Cost
Stairs , 2 units Work Cost, Php

e. Second Floor Beams, Intermediate Beams and Cantilever 31.956 cu.m.


Beams
Material Description Quantity Unit Unit Cost Add Amount
DRB, 25 mm dia x 6m 232 lengths
DRB, 20 mm dia x 6m 25 lengths
DRB, 16 mm dia x 6m 23 lengths
DRB, 10 mm dia. X 6m 249 lengths
G.I Tie Wire, # 16, 35 kgs/roll 2 rolls
Portland Cement , 40 kgs. 289 bags
Washed Sand 17 cu.m.
Washed Gravel ( class yy 3/4") 33 cu.m.
Material Cost , Php
Labor Cost
Second Floor Beams, Intermediate Beams
and Column Beams Work Cost, Php
f. Third Floor Beams and Lintel Beams 22.160 cu.m.
Material Description Quantity Unit Unit Cost Add Amount
DRB, 20 mm dia x 6m 162 lengths
DRB, 16 mm dia x 6m 12 lengths
DRB, 12 mm dia. X 6m 31 lengths
DRB, 10 mm dia. X 6m 223 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 199 bags
Washed Sand 11 cu.m.
Washed Gravel ( class yy 3/4") 22 cu.m.
Material Cost , Php
Labor Cost
Roof Beams and Lintel Beams Work Cost, Php

g. Suspended Slab (2nd & 3rd Floor) 49.348 cu.m.


Material Description Quantity Unit Unit Cost Add Amount
DRB, 10 mm dia. X 6m 575 lengths
G.I Tie Wire, # 16, 35 kgs/roll 5 rolls
Portland Cement , 40 kgs. 444 bags
Washed Sand 24 cu.m.
Washed Gravel ( class yy 3/4") 50 cu.m.
Material Cost , Php
Labor Cost
Suspended Slab Work Cost, Php

h. Concrete Canopy (2nd & 3rd Floor) 6.947 cu.m.


Material Description Quantity Unit Unit Cost Add Amount
DRB, 10 mm dia. X 6m 77 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 63 bags
Washed Sand 3 cu.m.
Washed Gravel ( class yy 3/4") 6 cu.m.
Material Cost , Php
Labor Cost
Concrete Canopy (2nd & 3rd Floor) Work Cost, Php

Total Concrete Work Cost, Php

VI MASONRY WORKS
a. Ground Floor 416.336 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
6" CHB 4121 pcs.
4" CHB 945 pcs.
DRB, 10 mm dia. X 6m 249 lengths
G.I Tie Wire, # 16, 35 kgs/roll 2 rolls
Portland Cement , 40 kgs. 522 bags
Washed Sand 18 cu.m.
Material Cost , Php
Labor Cost
Ground Floor Cost

b. Second Floor 231.53 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
6" CHB 1950 pcs.
4" CHB 781 pcs.
DRB, 10 mm dia. X 6m 134 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 281 bags
Washed Sand 10 cu.m.
Material Cost , Php
Labor Cost
Second Floor Cost

c. Third Floor 108.98 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
6" CHB 887 pcs.
4" CHB 530 pcs.
DRB, 10 mm dia. X 6m 81 lengths
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 146 bags
Washed Sand 5 cu.m.
Material Cost , Php
Labor Cost
Third Floor Cost
d. Septic Tank ( 1 unit- 2m x 4m x 2m depth) 17.500 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
4" CHB 228 pcs.
Portland Cement , 40 kgs. 42 bags
Washed Sand 3 cu.m.
DRB, 10 mm dia. X 6m 40 lengths
Material Cost , Php
Labor Cost
Septic Tank Work Cost, Php

e. Wall Footing 74.335 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
DRB, 10 mm dia. X 6m 98 lengths
4" CHB 915 pcs.
G.I Tie Wire, # 16, 35 kgs/roll 1 rolls
Portland Cement , 40 kgs. 121 bags
Washed Sand 5 cu.m.
Washed Gravel ( class yy 3/4") 4 cu.m.
Material Cost , Php
Labor Cost
Wall Footing Cost
Total Masonry Works Cost, Php

VII TILING WORKS


Ground Floor :
a. Tiling of Main Flooring. 326.469 sq.m.
b. Tiling of Comfort Rooms . 49.904 sq.m.
c. Tiling of Main Entrance 6.490 sq.m.
d. Tiling of Washing Counters 2.610 sq.m.
e. Tiling of Stairs 3.855 sq.m.
389.328 sq.m.
Material Description Quantity Unit Unit Cost Amount
600mm x 600mm HOMOGENEOUS WHITE NON-SKID FLOOR TILE
(as per sample) 912 pcs.
300mm x 300mm BEIGE CERAMIC TILES MATT/NON-SKID FINISH
(as per sample) 102 pcs.
300mm x 300mm LIGHT GREY CERAMIC WALL TILE MATT FINISH
UP TO 5 LAYERS FROM THE FLOOR FINISH & WHITE PAINT AT 463 pcs.
UPPER HALF TO CEILING (as per sample)
400mm X 400mm Ceramic Tactiles (Salt and Pepper or Gray) (as per
sample) 46 pcs.

Granite Slab, 3/4" x 2' x 8' 2 pcs.


25kg/bag ABC Tile Adhesive 60 bags
ABC Grout, 2kgs/ pack 35 packs
Washed Sand 10 cu.m.
Portland Cement, 40 kgs. 156 bags
Bronze Stair Nozing, 6m long 13 lenghts
Material Cost , Php
Labor Cost
Ground Floor Works Cost

Second Floor :
a. Tiling of Main flooring. 319.233 sq.m.
b. Tiling of Comfort Rooms . 49.544 sq.m.
c. Tiling near at Stairs & Elevator 1.820 sq.m.
d. Tiling of Washing Counters 2.130 sq.m.
372.727 sq.m.
Material Description Quantity Unit Unit Cost Amount
600mm x 600mm HOMOGENEOUS WHITE NON-SKID FLOOR TILE
(as per sample) 893 pcs.
300mm x 300mm BEIGE CERAMIC TILES MATT/NON-SKID FINISH
(as per sample) 88 pcs.
300mm x 300mm LIGHT GREY CERAMIC WALL TILE MATT FINISH
UP TO 5 LAYERS FROM THE FLOOR FINISH & WHITE PAINT AT 473 pcs.
UPPER HALF TO CEILING (as per sample)
400mm X 400mm Ceramic Tactiles (Salt and Pepper or Gray) (as per
sample)
21 pcs.

Granite Slab, 3/4" x 2' x 8' 2 pcs.


25kg/bag ABC Tile Adhesive 50 bags
ABC Grout, 2kgs/ pack 30 packs
Washed Sand 10 cu.m.
Portland Cement, 40 kgs. 151 bags
Material Cost , Php
Labor Cost
Second Floor Works Cost
Total Tiling Works Cost, Php

VIII WATER PROOFING WORKS 266.914 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
a. Supply & installation of 3mm thk. membrane water proofing. 266.914 sq.m.
Water Proofing Works Cost, Php

IX CEILING WORKS
Ground Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 161.74 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
b. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (BROWN) including angles, furring and 17.88 sq.m.
hangers.
c. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (WHITE) including angles, furring and 35.27 sq.m.
hangers.
214.89 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 161.74 sq.m.
ALUMINUM SPANDREL x 10' 53.15 sq.m.
Ground Floor Works Cost, Php

Second Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 176.40 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
b. Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING (BROWN) including angles, furring and 16.69 sq.m.
hangers.
193.09 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 176.40 sq.m.
ALUMINUM SPANDREL x 10' 16.69 sq.m.
Second Floor Works Cost, Php

Third Floor:
a. Supply & Installation of 3.5mm THK. FIBERCEMENT
BOARD CEILING SYSTEM ON 2"x2" METAL FURRING 20.95 sq.m.
FRAMES IN WHITE FLAT LATEX PAINT FINISH
Material Description Quantity Unit Unit Cost Add Amount
3.5 mm thk. X 4' x 8' Fibercement Board Ceiling System 20.95 sq.m.
Third Floor Works Cost, Php
TOTAL CEILING WORK COST, PHP
X CARPENTRY WORKS 1 lot
a. Fabrication of locker, drawers, tables and cabinets. (see drawing Details)
Material Description Quantity Unit Unit Cost Add Amount
20 mm thk. x 4' x 8' Plyboard 44 shts
Hydraulic concealed hinges, pull over lay 10 pairs
Assorted Nails 1 case
Accessories 1 lot
Material Cost , Php
Labor Cost
Carpentry Works Cost, Php

XI STEEL WORKS 1 lot


a. Fabrication and installation of Steel Grills at ACCU View
Barrier using 1/4" x 1" flat bar with ½" angle bars on tubular 2”
x 2' frame. (See Elevation)
b. Fabrication and installation of Steel Fire Exit Ladder. (See details)
Material Description Quantity Unit Unit Cost Add Amount
1/4" X 1" FLAT BAR x 20' 12 pcs
1/2" x 2" X 2' ANGLE BAR x 20' 20 pcs
1/4" x 2" X 2' ANGLE BAR x 20' 7 pcs
Welding Rod, E-6011, 1/4"Ø 2 boxes
Accessories 1 lot
Material Cost , Php
Labor Cost
Steel Works Cost, Php

XII Railings and Grills 1 lot


a. Installation of Stair & Side Railings.
Material Description Quantity Unit Unit Cost Add Amount
Stainless Pipe, mirror type 2" dia x 20' 28 lengths
Stainless Pipe, mirror type 1" dia x 20' 23 lengths
Stainless Welding Rod 10 kgs.
Material Cost , Php
Labor Cost
Railings and Grills Works Cost, Php

XIII DOORS & WINDOWS


Ground Floor: 8 sets
a. Using Yacal Lumber as Door Jambs (8 units)
b. Using Lauan Lumber as Doors ( 8 units)
c. Supply & Installation of Double Swing Glass Door w/ 12mm thk. Annealed Glass Panel
d. Supply & Installation of Sliding Glass Door w/ 12mm thk. Annealed Glass Panel on Analuk Frame
Material Description Quantity Unit Unit Cost Add Amount
Pre-fabricated 2" x 6" Kiln-Dry Door Jamb 8 sets
Pre-fabricated HCFD 0.80 x 2.10m high 8 sets
D1(1.6 L X 2.55H) double swing glass door 1 unit
D7(1.6 L X 2.15H) double swing glass door 1 unit
D9(.8 L X 2.1H) sliding glass door 3 unit
Material Cost , Php
Labor Cost , Php
Door Cost, Php
e. Supply & Installation of Fixed Glass Window w/ 6mm thk. Fixed Glass Panel on Analuk Frame
f. Supply & Installation of Frameless Awning Window 1/4".thk. Brown glass w/ Analuk Frame & brown Mosquito screen
g. Supply & Installation of Sliding Gass Window 1/4" thk Brown Glass w/ Analuk Frame & brown mosquito Screen
h. Supply & Installation of Transaction Window w/ 6mm thk. Fixed Glass Panel on Analuk Frame w/ Sliding Glass below
Material Description Quantity Unit Unit Cost Add Amount
W1(5.7L X 2.15H) fixed glass window 1 unit
W2(1.7L X 2H) awning glass window 1 unit
W3(.9L X 2.45H) awning glass window 1 unit
W4(3.24L X 1.25H) sliding glass window 2 unit
W5(1.92L X 1.25H) sliding glass window 2 unit
W6(1.88L X .7H) awning glass window 1 unit
W7(1.3L X .7H) awning glass window 2 unit
W9(2.78L X .7H) awning glass window 2 unit
W15(1.35L X 1.25H) fixed glass window 1 unit
W16(2.53L X 1.25H) transaction window 1 unit
W18(2.10L X 1.25H) transaction window 1 unit
W19(1.09L X 1.25H) fixed glass window 2 unit
W20(1.34L X 1.25H) fixed glass window 2 unit
Window Cost, Php
Doors & Windows Cost, Php

Second Floor: 4 sets


a. Using Yacal Lumber as Door Jambs (4 units)
b. Using Lauan Lumber as Doors ( 4 units)
c. Supply & Installation of Double Swing Glass Door w/ 12mm thk. Annealed Glass Panel
d. Supply & Installation of Swing Glass Door w/ 12mm thk. Annealed Glass Panel on Analuk Frame
e. Supply & Installation of Single Swing PVC Door w/ White Standard PVC Panel w/ Louvers at bottom
Material Description Quantity Unit Unit Cost Add Amount
Pre-fabricated 2" x 6" Kiln-Dry Door Jamb 4 sets
Pre-fabricated HCFD 0.80 x 2.10m high 4 sets
D1(1.6 L X 2.55H) double swing glass door 1 unit
D10(.72 L X 2.1H) swing glass door 1 unit
D11(.7 L X 2.1H)-cr single swing pvc door 2 unit
Material Cost , Php
Labor Cost , Php
Door Cost, Php
f. Supply & Installation of Fixed Glass Window w/ 6mm thk. Fixed Glass Panel on Analuk Frame
g. Supply & Installation of Frameless Awning Window 1/4".thk. Brown glass w/ Analuk Frame & brown Mosquito screen
h. Supply & Installation of Sliding Gass Window 1/4" thk Brown Glass w/ Analuk Frame & brown mosquito Screen
i. Supply & Installation of Transaction Window w/ 6mm thk. Fixed Glass Panel on Analuk Frame w/ Sliding Glass below
Material Description Quantity Unit Unit Cost Add Amount
W3(.9L X 2.45H) awning glass window 1 unit
W4(3.24L X 1.25H) sliding glass window 2 unit
W7(1.3L X .7H) awning glass window 2 unit
W8(5.5L X .7H) awning glass window 2 unit
W9(2.78L X .7H) awning glass window 4 unit
W10(1.65L X 1.25H) sliding glass window 1 unit
W11(1.98L X 1.25H) fixed glass window 1 unit
W12(2.47L X 1.25H) fixed glass window 2 unit
W13(2.32L X 1.25H) fixed glass window 1 unit
W14(1.85L X 1.25H) fixed glass window 1 unit
W15(1.35L X 1.25H) fixed glass window 1 unit
Window Cost, Php
Doors & Windows Cost, Php

Third Floor: 1 set


a. Using Yacal Lumber as Door Jambs (1 unit)
b. Using Lauan Lumber as Doors ( 1 unit)
Material Description Quantity Unit Unit Cost Add Amount
Pre-fabricated 2" x 6" Kiln-Dry Door Jamb 1 set
Pre-fabricated HCFD 0.80 x 2.10m high 1 set
Material Cost , Php
Labor Cost , Php
Door Cost, Php
c. Supply & Installation of Frameless Awning Window 1/4".thk. Brown glass w/ Analuk Frame & brown Mosquito screen
Material Description Quantity Unit Unit Cost Add Amount
W9(2.78L X .7H) awning glass window 2 unit
Window Cost, Php
Doors & Windows Cost, Php
Total Doors & Windows Cost, Php

XIV SPECIAL FINISHES 25.84 sq.m.


Material Description Quantity Unit Unit Cost Add Amount

a. Pebble Washout finish (BEIGE) at main entrance and ramp. 25.84 sq.m.

Special Finishes Work Cost, Php

XV GLASS WORKS
Ground Floor: 4 sets
a. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame
b. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame w/ Frosted Film
Material Description Quantity Unit Unit Cost Add Amount
Glass Partition w/ 6mm thk. Fixed Glass
Partition #1 (4.1L x 2.55H)
Panel on Analuk Frame
1 unit

Glass Partition w/ 6mm thk. Fixed Glass


Partition #2 (.9L x 2.1H)
Panel on Analuk Frame w/ Frosted Film
2 unit

Glass Partition w/ 6mm thk. Fixed Glass


Partition #3 (2L x 2.1H)
Panel on Analuk Frame w/ Frosted Film
1 unit

Supply & Installation Cost, Php

Second Floor: 3 sets


a. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame
b. Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass Panel on Analuk Frame w/ Frosted Film
Material Description Quantity Unit Unit Cost Add Amount
Glass Partition w/ 6mm thk. Fixed Glass
Partition #1 (4.1L x 2.55H) Panel on Analuk Frame 1 unit
Glass Partition w/ 6mm thk. Fixed Glass
Partition #4 (5.70L x 2.15H) Panel on Analuk Frame w/ Frosted Film 1 unit

Glass Partition w/ 6mm thk. Fixed Glass


Partition #4a (.9L x 2.15H) Panel on Analuk Frame w/ Frosted Film 1 unit

Supply & Installation Cost, Php


TOTAL GLASS WORK COST, PHP

XVI CLADDING WORKS 137.67 sq.m.


a. Supply & Installation of Red Aluminum Composite Pannel on 4mm PVDF w/ no Sealant Exposed ( see Detail )
w/ Aluminum Frames T-Runner
Material Description Quantity Unit Unit Cost Add Amount
4mm.thk. PVDF Composite Pannel 137.67 sq.m.
Supply & Installation Cost, Php

XVII ROOFING SYSTEM


a. Roof Framing System : 44.42 sq.m.
Material Description Quantity Unit Unit Cost Add Amount
Cee Purlins, 1.60mm thk x 2"x 6"x 20' 25 length
Steel Plate, 1/2" thk x 4' x 8' 1 shts.
Acetylene 1 tank
Industrial Oxygen 1 tank
Primer Red Oxide 1 gal
Welding Rod 6011, 20kg/box, good quality 1 box
Material Cost , Php
Labor Cost
Roofing System Cost

b. Roofing Sheets : 44.42 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
Duratile Roofing, 0.4mmthk x 1.005 m eff. Width x 6.34m. H 19 shts.
Pre-painted Spanish Gutter, 0.4mm x 0.914m x 3.34m 4 pcs
Pre-painted End Flashing, 0.4mm x 0.610 x 3.34m 2 pcs
Pre-painted Ridge Roll, 0.4mm x 0.610 x 3.34m 2 pcs
Tekscrew # 2" 300 pcs
3/16" dia. X 3/4" Blind Rivets 2 boxes
Roof Thermal Insulation, 10mm thk x 1m x 50meters/roll 1 rolls
Material Cost , Php
Labor Cost , Php
Roof Sheets Cost
Total Roofing System Cost, Php

XVIII Hardwares 1 lot


Material Description Quantity Unit Unit Cost Add Amount
Finishing Nails 1 1/2" , 25 kgs/box 1 boxes
Finishing Nails 2",25 kgs/box 1 boxes
Cylindrical Door Knob, US 13 sets
4-Heavy Duty Butt Hinges 15 pairs
36mm diam.x 1.2mL Stainless Steel Door Handle 6 pcs
Stainless Steel Door Lock Handle (Lever Type) 4 pcs
Hacksaw Blade, heavy duty 50 pcs
Welding Rod, E-6011, 1/4"Ø 3 box
Chalk Stone 20 pcs
Material Cost , Php
Labor Cost
Roof Sheets Cost

XIX PLUMBING WORKS 1 lot


a. Supply and Installation of Water Lines
Material Description Quantity Unit Unit Cost Add Amount
PPR Pipe PN-25 1/2" 69 lengths
Accessories 1 lot
Material Cost , Php
Labor Cost , Php
Waterline Cost
b. Sanitary Line, downspouts
Material Description Quantity Unit Unit Cost Add Amount
4" dia x 10' PVC Pipe, s 1000 25 pcs.
4" dia PVC Wye 20 pcs.
4" dia x 2" PVC Wye 20 pcs.
4" dia x 90 PVC elbow 50 pcs.
4" dia x 45 PVC elbow 25 pcs.
4" dia PVC cleanout 25 pcs.
4" dia PVC p-trap 25 pcs.
2" dia x 10' PVC Pipe, s 1000 50 pcs.
2" dia PVC elbow 75 pcs.
Material Cost , Php
Labor Cost , Php
Sanitary Line Cost

c. Plumbing Fixtures
Material Description Quantity Unit Unit Cost Add Amount
Stainless Sink w/ Complete ass. 4 units
Toilet Bowl, Flush Type 4 sets
Lavatory 4 sets
Lavatory faucet 4 pcs.
Plastic Faucet, Heavy Duty 15 pcs.
Bedit Faucet 4 sets
Gate Valves 10 pcs.
Soap Holder 4 pcs.
Tissue Holder 4 pcs.
6" x 6" Floor Drain 4 pcs.
4" x 4" Floor Drain 4 pcs.
Exhaust Fan w/ Ducting & Diffuser 4 sets
Material Cost , Php
Labor Cost , Php
Plumbing Fixture Cost
d. Drainage System
Material Description Quantity Unit Unit Cost Add Amount
RCPC, 12"Ø 58 pcs
Portland Cement , 40 kgs. 12 bags
Washed Sand 4 cu.m.
Material Cost , Php
Labor Cost
Drainage System Cost

e. Catch Basin (9 units) 3.888 sq.m.


Material Description Quantity Unit Unit Cost Add Amount
Portland Cement , 40 kgs. 13 bags
4" CHB 65 pcs.
DRB, 10 mm dia. X 6m 10 lengths
Washed Sand 4 cu.m.
Washed Gravel ( class yy 3/4") 2 cu.m.
Material Cost , Php
Labor Cost
Catch Basin Cost
Total Plumbing Work Cost, Php

XX PAINTING WORKS
Ground Floor Area : 1,099.90 sq.m.
a. Painting works are all solvent based.
Material Description Quantity Unit Unit Cost Amount
Liquid Tile Primer 52 gals.
Liquid Tile Gloss 75 gals.
Liquid Tile Cast 63 gals.
Liquid Tile Reducer 63 gals.
Liquid Tile Tint Color , Hansa Yellow 70 pints
Liquid Tile Tint Color , Venetian Red 40 pints
Liquid Tile Tint Color , Black 20 pints
Textured Paint Roller w/ Tray, 7", heavy duty 10 pcs
Paint Roller w/ Tray, 7", heavy duty 20 pcs
Baby Paint Roller, 4", cotton 10 pcs
Paint Brush, 4" 10 pcs
Paint Brush, 2" 10 pcs
Sand Paper, # 120 100 pcs
Sand Paper, # 60 70 pcs
Masking Tape 60 rolls
Polyster Body Filler w/ Hardener 11 gals.
Non - sag Epoxy , A & B 8 pairs
Concrete Neutralizer 8 gals.
Material Cost , Php
Labor Cost , Php
Ground Floor Area Work Cost, Php
Second Floor Area : 865.61 sq.m.
a. Painting works are all solvent based.
Material Description Quantity Unit Unit Cost Amount
Liquid Tile Primer 40 gals.
Liquid Tile Gloss 58 gals.
Liquid Tile Cast 49 gals.
Liquid Tile Reducer 49 gals.
Liquid Tile Tint Color , Hansa Yellow 50 pints
Liquid Tile Tint Color , Venetian Red 30 pints
Liquid Tile Tint Color , Black 20 pints
Textured Paint Roller w/ Tray, 7", heavy duty 10 pcs
Paint Roller w/ Tray, 7", heavy duty 10 pcs
Baby Paint Roller, 4", cotton 10 pcs
Paint Brush, 4" 15 pcs
Paint Brush, 2" 10 pcs
Sand Paper, # 120 100 pcs
Sand Paper, # 60 60 pcs
Masking Tape 70 rolls
Polyster Body Filler w/ Hardener 8 gals.
Non - sag Epoxy , A & B 7 pairs
Concrete Neutralizer 7 gals.
Material Cost , Php
Labor Cost , Php
Second Floor Area Work Cost, Php

Third Floor Area : 263.64 sq.m.


a. Painting works are all solvent based.
Material Description Quantity Unit Unit Cost Amount
Liquid Tile Primer 13 gals.
Liquid Tile Gloss 19 gals.
Liquid Tile Cast 16 gals.
Liquid Tile Reducer 16 gals.
Liquid Tile Tint Color , Hansa Yellow 30 pints
Liquid Tile Tint Color , Venetian Red 20 pints
Liquid Tile Tint Color , Black 20 pints
Textured Paint Roller w/ Tray, 7", heavy duty 10 pcs
Paint Roller w/ Tray, 7", heavy duty 15 pcs
Baby Paint Roller, 4", cotton 10 pcs
Paint Brush, 4" 10 pcs
Paint Brush, 2" 10 pcs
Sand Paper, # 120 80 pcs
Sand Paper, # 60 70 pcs
Masking Tape 60 rolls
Polyster Body Filler w/ Hardener 5 gals.
Non - sag Epoxy , A & B 9 pairs
Concrete Neutralizer 8 gals.
Material Cost , Php
Labor Cost , Php
Third Floor Area Work Cost, Php
Total Painting Works Cost, Php

XXI ELECTRICAL WORKS 1 lot


a. Supply and installation of electrical materials
b. Supply and installation of Data and Voice provisions (roughing-ins of pipes and utility boxes)

Item Material Description Quantity UOM Unit Cost Total Cost


Data and voice outlet, 2-gang 12 sets
20mm dia.uPVC Pipe 180 lengths
25mm dia.uPVC Pipe 8 lengths
32mm dia.uPVC Pipe 2 lengths
63mm dia.uPVC Pipe 3 lengths
75mm dia.uPVC Pipe 2 lengths
110mm dia.uPVC Pipe 20 lengths
63mm dia.uPVC elbow 2 pcs
75mm dia.uPVC elbow 2 pcs
110mm dia.uPVC elbow 5 pcs
20mm dia PVC male adaptor w/ locknut 150 sets
25mm dia PVC male adaptor w/ locknut 5 sets
63mm dia PVC male adaptor w/ locknut 2 sets
75mm dia PVC male adaptor w/ locknut 2 sets
110mm dia PVC male adaptor w/ locknut 4 sets
110mm dia entrance cap 1 pc
1/2" dia. PVC moldflex 19 rolls
3/4" dia. PVC moldflex 1 rolls
8" x 8" x 4" metal Pull Box w/ cover 5 pcs.
12" x 12" x 6" metal Pull Box w/ cover 5 pcs.
4" x4" uPVC Junction Box 200 pcs.
2" x 4 " uPVC Utility Box 132 pcs.
4" x 4 " uPVC Square Box 25 pcs.
Flush Type Switch (1-gang)w/ plate 15 sets
Flush Type Switch (2-gang)w/ plate 9 sets
Flush Type Switch (3-gang)w/ plate 7 sets
Flush Type Switch (1-gang, 3-way) w/ plate 1 sets
1-gang universal outlet, 3-prong w/ plate (wide series) 20 sets
2-gang universal outlet, 3-prong w/ plate (wide series) 65 sets
2-gang universal outlet, 3-prong w/ weather proof cover (wide
1 set
series)
G.I. tie wire #16 30 kilos
Electrical Tape, big, 3M 150 pcs.
Rubber Tape 5 pcs.
LED emergency light (2 bulbs in one housing) 20 pcs.
100mm dia circular recessed type housing w/ 9Watts, E27, 100-
52 sets
277V, LED, downlight
150mm dia circular surface type housing w/ 12Watts, E27, 100-
28 sets
277V, LED, downlight
2x23W T8, 100-277V, LED tube light in 1200mm Recesed
57 sets
luminaire w/ acrylic diffuser
14W T5, 100-277V, LED tube light w/ base 8 sets
150 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
150 mtrs
600V, Copper Wire , Stranded
60 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
27 mtrs
600V, Copper Wire , Stranded
50 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
36 mtrs
600V, Copper Wire , Stranded
30 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
81 mtrs
600V, Copper Wire , Stranded
14 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
175 mtrs
600V, Copper Wire , Stranded
5.5 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
5 rolls
600V, Copper Wire , Stranded
3.5 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
20 rolls
600V, Copper Wire , Stranded
2.0 sq.mm. THHN/THWN-2 Building Wire 90°C both Wet/Dry
7 rolls
600V, Copper Wire , Stranded
Copper clad ground rod w/ accessories 1 pc
Wire way and gutters 1 lot
Consumables 1 lot
Main: 2 - 300AT/630AF, 3P, 240V, 36kAIC, Molded-case ckt
breaker w/ adjustable trip unit, manual transfer switch w/
mechanical interlock
Branches:
1 - 175AT, 160AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type w/ adjustable trip unit
1 - 150AT, 160AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type w/ adjustable trip unit
1 - 100AT, 160AF, 3P, 240V, 25kAIC, Molded-case ckt breaker, 1 assembly
bolt-on type w/ adjustable trip unit
1 - 60AT, 160AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type w/ adjustable trip unit
SPACE - 2
Complete w/ Busbar, hardware, lugs, accessories, and
grounding bus
Enclosure Specs: Nema 1, surface mounted, B.I. Ga#16,
chemically treated,powder coated

Main: 60AT/160AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,


bolt-on type w/ adjustable trip unit
Branches:
18 - 20AT, 63AF, 2P, 240V, 10kAIC, Miniature ckt breaker, bolt-
on type 1 assembly
Complete w/ Busbar, hardware, lugs, accessories, and
grounding bus
Enclosure Specs: Nema 1, surface mounted, B.I. Ga#16,
chemically treated,powder coated

Main: 175AT/250AF, 3P, 240V, 25kAIC, Molded-case ckt


breaker, bolt-on type w/ adjustable trip unit
Branches:
2 - 60AT, 100AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type 1 - 40AT,
100AF, 3P, 240V, 25kAIC, Molded-case ckt breaker, bolt-on
type 1 - 30AT,
100AF, 3P, 240V, 25kAIC, Molded-case ckt breaker, bolt-on
1 assembly
type 9 - 30AT,
100AF, 2P, 240V, 10kAIC, Miniature ckt breaker, bolt-on type
11 - 20AT, 63AF, 2P, 240V, 10kAIC, Miniature ckt breaker, bolt-
on type
Complete w/ Busbar, hardware, lugs, accessories, and
grounding bus
Enclosure Specs: Nema 1, surface mounted, B.I. Ga#16,
chemically treated,powder coated
Main: 150AT/250AF, 3P, 240V, 25kAIC, Molded-case ckt
breaker, bolt-on type w/ adjustable trip unit
Branches:
1 - 60AT, 100AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type 1 - 40AT,
100AF, 3P, 240V, 25kAIC, Molded-case ckt breaker, bolt-on
type 2 - 30AT, 100AF, 3P,
240V, 25kAIC, Molded-case ckt breaker, bolt-on type 1 assembly
8 - 30AT, 100AF, 2P, 240V, 10kAIC, Miniature ckt breaker, bolt-
on type 12 - 20AT, 63AF,
2P, 240V, 10kAIC, Miniature ckt breaker, bolt-on type
Complete w/ Busbar, hardware, lugs, accessories, and
grounding bus
Enclosure Specs: Nema 1, surface mounted, B.I. Ga#16,
chemically treated,powder coated

Main - 60AT/100AF, 3P, 240V, 25kAIC, Molded-case ckt


breaker, bolt-on type w/ adjustable trip unit
Branches:
1 - 40AT, 63AF, 3P, 240V, 25kAIC, Molded-case ckt breaker,
bolt-on type 1 - 30AT,
63AF, 3P, 240V, 25kAIC, Molded-case ckt breaker, bolt-on type
1 - 30AT, 63AF, 2P, 240V, 10kAIC, Miniature ckt breaker, bolt- 3 assembly
on type 3 - 20AT, 63AF,
2P, 240V, 10kAIC, Miniature ckt breaker, bolt-on type
Complete w/ Busbar, hardware, lugs, accessories, and
grounding bus
Enclosure Specs: Nema 1, surface mounted, B.I. Ga#16,
chemically treated,powder coated

Digital check meter, 3-phase w/ CT, PT, and accessories 1 set


Material Cost, Php
Labor Cost, Php
Total Electrical Work Cost, Php

XXII MECHANICAL WORKS 1 lot


a. Supply and Installation of complete new Airconditioning Units including water-proof service breaker and compatible magnetic
switch w/ free copper tube within 10ft and additional cost per ft for the excess copper tube (inclusive of copper tube, rubber
insulation, PE tape, PVC pipe for drain, wiring from condenser and to evaporator and fabrication of painted wall-hang bracket for
condenser)
b. Supply and installation of Exhaust Fans including ducting and diffusers.
ITEM DESCRIPTION QTY UOM UNIT COST TOTAL COST
A. GROUND FLOOR
1 1 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 4 sets
2 2 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 3 sets

3 2.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 4 sets

4 Exhaust Fan, ceiling mounted, 230V, 1 phase 8 sets


Total Cost
B. SECOND FLOOR

1 1.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 2 sets

2 2 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 2 sets


3 2.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz 4 sets

Total Cost
Total MECHANICAL WORK Cost, Php

XXIII FIRE PROTECTION & ALARM SYSTEM 1 lot


Ground Floor :
a. Fire Protection System
Material Description Quantity Unit Unit Cost Amount
Fire Extinguisher, HCFC 123, (10lbs); 2 unit
Fire Extinguisher, ABC Dry Chemical Content, Red (10lbs) 3 unit
Floor Control Valve 3" 1 Unit
Sight Glass 1 Unit
Ball Valve 1 1/2" 1 Unit
Water Flow switch 1 Unit
BI Pipe 3" dia Sch 40 6 length
BI Pipe 2" dia Sch 40 2 length
BI Pipe 1 1/2" dia Sch 40 2 length
BI Pipe 1" dia Sch 40 15 length
Fire Hose Cabinet 100Ft (Complete Set) 2 length
BI fittings and hangers 1 lot
Consumables 1 lot

b. Fire Alarm System


Fire Alarm Control Panel Conventional Type 4 Zones 1 set
Smoke Detector 15 pc
Fire Alarm Bell 2 pc
Manual Pull Station 2 pc
TF wire #16 10 roll
uPVC Pipe 12.5mm 70 length
Other accessories and consumables 1 lot
Material Cost, Php
Labor Cost, Php
Ground Floor Cost, Php

Second Floor :
a. Fire Protection System
Material Description Quantity Unit Unit Cost Amount
Fire Extinguisher, HCFC 123, (10lbs); 2 unit
Fire Extinguisher, ABC Dry Chemical Content, Red (10lbs) 2 unit
Floor Control Valve 3" 1 Unit
Sight Glass 1 Unit
Ball Valve 1 1/2" 1 Unit
Water Flow switch 1 Unit
BI Pipe 3" dia Sch 40 2 length
BI Pipe 2" dia Sch 40 2 length
BI Pipe 1 1/2" dia Sch 40 2 length
BI Pipe 1" dia Sch 40 14 length
Fire Hose Cabinet 100Ft (Complete Set) 1 length
BI fittings and hangers 1 lot
Consumables 1 lot

b. Fire Alarm System


Smoke Detector 14 pc
Fire Alarm Bell 2 pc
Manual Pull Station 2 pc
TF wire #16 9 roll
uPVC Pipe 12.5mm 66 length
Other accessories and consumables 1 lot
Material Cost, Php
Labor Cost, Php
Second Floor Cost, Php
FIRE PROTECTION & ALARM SYSTEM Cost, Php

XXIV SUPPLY & INSTALLATION OF ELEVATOR 1 lot


a. Steel Works
b. Installation of Top Roofing for Elevator (see Sample Design)
Material Description Quantity Unit Unit Cost Amount
WF 10 x 49 Beam 6 lengths
MS Plate 1/2" thk 2 shts
Angle Bar 6mm x 2" x 2"x 20' 8 lengths
Acetylene & Oxygen 7 sets
Welding Rod 5 boxes
Material Cost , Php
Labor Cost
Steel Works & Roofing Work Cost, Php

c. Electrical Works
d.1. Supply, installation & tapping of new transformer from the nearest post to the elevator electrical panel.
d.2. Supply and installation of switches and lighting fixtures at the elevator area.
d.3. Electrical Works for Elevator are Ready for 3rd floor.
Material Description Quantity Unit Unit Cost Amount
25 KVA transformer 1 unit
Electrical Wires 1 lot
Material Cost , Php
Labor Cost
Electrical Work for Elevator Cost, Php

d. ELEVATOR UNIT 1 lot


Elevator Cost, Php
Total SUPPLY & INSTALLATION OF
ELEVATOR Cost, Php

XXV PROJECT BILLBOARD


Material Description Quantity Unit Unit Cost Amount
Billboards 8' x 8' 1 unit
Suppy & Installation Cost, Php

XXVI SAFETY AND HEALTH PROGRAM


a. Supply and implementation of PPE's and safety and health programs.
b. Installation of signages, barricades and protections.
Material Description Quantity Unit Unit Cost Amount
Safety and Health Program 1 lot
SAFETY AND HEALTH PROGRAM COST

A - ESTIMATED BREAKDOWN OF EXPENDITURES :

I - ENGINEERING & ADMINISTRATIVE OVERHEAD (EAO) :


a. Structural Design and Analysis Sub - total I 82,000.00

II - ESTIMATED DIRECT COST (EDC) :


a. Material Cost
b. Labor Cost
c. Project Billboard
d. Safety and Health Program
e. Equipment Rental Cost
Sub - total II
III - INDIRECT COST (IC) :
1. Overhead Expenses & Supervisions
2. Contingencies
3. Miscellaneous
a. Building Permits
b. Bureau of Fire Protection Permit
c. As- built Plans
4. Contractor's Profit
5. VAT 12.00%
Sub - total III
TOTAL BID COST , Php
AMOUNT IN WORDS:

Prepared by:

_____________________
Contractor/ Representative
PROJECT NAME : CONSTRUCTION OF LEAD BLOOD FACILITY (P1)

LOCATION : DRMC Compound, Apokon, Tagum City

APPROPRIATION : P 16,463,178.59

FUND SOURCE :

SUBJECT : GENERAL
SCOPE OF WORKS & TECHNICAL
SPECIFICATIONS- REVISED

1.0 PROJECT SUMMARY:

1.1 This project requires the following activity:


CONSTRUCTION OF LEAD BLOOD FACILITY (P1)
1.2 The work requires the furnishing of all labor, supervision, administration and
management, supply of equipment, tools and services necessary for the
satisfactory and expeditious completion of the Project.

2.0 PROJECT DESCRIPTION:

2.1 The work shall be carried out strictly in accordance with the requirement of the
Work Orders attached as required by the Proponent.
2.2 The Project shall be carried out in all respect to the requirements of the Contract
Documents and applicable Philippine Standards, Code and Specifications.

3.0 GENERAL SCOPE OF WORK:


3.1 Verification of Dimension:
Authorized Contractor’s personnel shall visit the project location of the above
mentioned Work Orders to familiarize themselves with all details of the work and
working conditions and to verify all the stated Project requirements with the
Proponent. Contractor shall advise DAVAO REGIONAL MEDICAL CENTER
project representative of any perceived discrepancy before performing any work

3.2 Work Order and Work Description


3.2. A. CONSTRUCTION OF LEAD BLOOD FACILITY (P1)
1. Staking and Lay-out
This activity includes the following:
• Installation of batter boards for lay-out and perimeter fence.
• Installation of Temporary facility.

2. Demolition and Dismantling Works


The Contractor shall demolish, dismantle and/or remove any miscellaneous
existing structures, buildings or parts thereof which occupy or obstruct the
Permanent Works, all as shown on the Drawings. Unsuitable materials from
demolishing and dismantling remain the property of the Contractor and shall
be disposed of in a manner and at a location to the approval of the Engineer.
Where partial demolition of structures is required, the Contractor shall take
the utmost care not to damage any part of the structure which is to remain in
place. If any such damage may occur the Contractor shall repair and make
good the damage at his own expense.
• Demolition, hauling and clearing of area affected by the lay-out.
• Demolition of concrete pavements and structures which are affected
by the construction works.
• Dismantling of existing (road) catwalk.
• Dismantling and turn-over of the dismantled materials to the agency.

3. Earthworks
This activity includes the following:
• Earthwork consists of excavation, back filling and disposal of
surplus material. Work of this section includes all measures and
materials required to complete the design supply, support, use,
construction, removal of earth work.
• Boulders of 6” to 8” dia. should be used as column foundation
beddings.
• Excavation of Column/Footing and Hauling
• Excavation of Footing Tie Beam & Wall Footing
• Excavation of Septic Tanks
• Backfilling and Compacting

4. Formworks and Scaffoldings


This item consist of:
• Installation of Forms and Bracings for columns, beams, parapets and
slabs.

5. Concrete Works/ Structural Steel Works


• Concrete work shall consist of mixing, conveying, placing of concrete
and reinforcement Work, (it is inclusive of all measures and materials
required removal of concrete forms and reinforcement).
• Construction of concrete columns, footings, tie beams and zoccalos
with a minimum of 3,000 psi concrete strength in 28 days;
• Reinforcing bar should be deformed bars for all reinforced concrete
work,use Grade 40 ( 275 MPa) for 16mm dia reinforcing bars ; use
Grade 60 (415 MPa) for 20mm & 25mm dia. Reinforcing bars in
accordance to (ASTM A 184 and A 185). Present samples of all steel
reinforcement that the contractor proposes to use in the Works
together with manufacture's certificate stating clearly for each
sample, the place of manufacture expected date and size of
deliveries to site, and all relevant details as regards composition
manufacture, strength and other qualities of the steel shall be
submitted to the Engineer for written approval
• Test of Concrete -Work cylinder test shall be made on concrete
sampled during the works. Samples shall be taken for each new
3
grade concrete, from each 100 m of concrete when the same grade
is being used continuously, except for lean concrete and other non
load bearing concrete. The number of specimens taken shall not less
than 3 for each compressive strength test. All tests shall be
performed in accordance with ASTM C. 39, B.S, 1881 and shall be
carried out in an authorized laboratory at the contractor's own
expense. If the results of the 28 days test are unsatisfactory, all
concrete work shall be stopped at contractor's expense and shall not
proceed further without the written permission of the Engineer.
Should the test prove that the concrete is not satisfactory or the
Engineer Judge any section to be defective the condemned concrete
shall be cut out, removed and replaced by the contractor;
• Concreting of suspended slabs and on-fill flooring, second floor
beams, column beams, parapets and roof beams.
• Construction of concrete stairs.
• Construction of concrete canopy

6. Masonry Works
• This item consists of the construction of 150mm thk. CHB for perimeter
and zocalo walls, and 100mm thk. CHB for interior walls, T&B/CR walls
and concrete counter stands smooth plastered finished.
• All Concrete Hollow Blocks shall be machine-made and all CHB walls
shall be cement plastered (12mm thk.) and smooth finished and are
reinforced with 10mm dia. deformed bars with spacing of 600mm o.c. for
vertical reinforcement and every 3 layers for horizontal reinforcement.
• Mortar filler shall be Class “B” mixture while Cement Plastering shall be
Class “A” mixture;
• Construction of new toilets;
• Construction of Septic Tank using 150mm CHB (1 unit- 2m x 4m x 2m
depth).
(Please refer to Approved Detailed Plans, Drawings & Specifications)

7. Tiling Works
This activity includes the following:
• Supply and installation of 300mm x 300mm ceramic floor and wall
tiles for toilets.
• Supply and installation of 600mm x 600mm granite tiles on main
floorings (ground & second floor).
• Supply and installation of 400mm x 400mm ceramic tactiles on main
entrance (ground floor), near stairs and elevator (second floor).

(Ceramic Tactiles)
• Supply and installation of 600mm x 600mm granite tiles on stairs
with bronze stair nosing at edge.
• Supply and installation of Granite Slab, 3/4" x 2' x 8' at concrete
counters and mop wash.
• Sample of tiles should be presented to the agency’s representative
for approval prior to installation.

8. Water Proofing Works


This item consist of:
• Supply & installation of membrane water proofing.

9. Ceiling Works
• Supply & Installation of 3.5mm THK. FIBERCEMENT BOARD
CEILING SYSTEM ON 2’x2’ METAL FURRING FRAMES IN WHITE
FLAT LATEX PAINT FINISH for interior ceiling system.
• Supply & Installation of ALUMINUM SPANDREL CEILING SYSTEM
ON METAL FRAMING including angles, furring and hangers for
exterior ceiling system.

10. Carpentry Works


This item consist of:
• Fabrication of locker, drawers, tables and cabinets. (see drawing
Details)

11. Steel Works


This activity includes the following:
• Fabrication and installation of Steel View Barrier using 1/4" x 1" flat
bar with ½" angle bars on tubular 2” x 2' frame. (See Elevation)
• Fabrication and installation of Steel Fire Exit Ladder. (See details)

12. Railings and Grills


This item consist of:
• Installation of Stair & Side Railings.
• Stainless Steel Railings

13. Doors
DOORS: Fabrication and Installation
• Supply and installation of double swing glass door using 12mm thk
Annealed Glass Panel
• Supply and installation of sliding glass door using 12mm thk
Annealed Glass Panel on Analuk frame.
• Supply and installation of swing glass door using 12mm thk
Annealed Glass Panel on Analuk frame.
• Supply and installation of single swing PVC door on white standard
PVC Panel with louvers at bottom.

Pre-fabricated 2” x 6” Kiln-Dry Door Jambs using Yacal Lumber.


Pre-fabricated HCFD 0.80 x 2.10m high.

14. Windows
WINDOWS: Supply and Installation
• Supply and installation of 6mm thk fixed glass window using Fixed
Glass Panel on Analuk Frame.
• Supply and installation of 6mm thk awning glass window and Fixed
Glass Panel on Analuk Frame.
• Supply and installation of 6mm thk sliding glass window and Fixed
Glass Panel on Analuk Frame.
• Supply and installation of transaction window with 6mm thk. Fixed
Glass Panel on Analuk Frame with sliding glass below.

15. Special Finishes


This item consist of:
• Supply and installation of Pebble Washout finish (BEIGE) at main
entrance and ramp. (see detailed drawings)

16. Glass Works


This activity includes the following:
• Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass
Panel on Analuk Frame.
• Supply & Installation of Glass Partition w/ 6mm thk. Fixed Glass
Panel on Analuk Frame w/ Frosted Film.
17. Cladding Works
This item consist of:
• Supply & Installation of Red Aluminum Composite Pannel on 4mm
PVDF w/ no Sealant Exposed w/ Aluminum Frames T-Runner ( see
Detail )

18. Roofing System and Tinsmithry


This activity includes the following:
• Supply, fabrication and installation of roof framings using 2.0mm x 2”
x 6” Cee Purlins and ¼” thk. Angle Bars (see details).
• Supply and installation of 10 mm thk. double aluminum thermal roof
insulator;
• Supply and installation of Ga. 26 (0.4mm thk) Pre-painted Duratile
type roofing sheets (Spanish red color) including ridge caps,
flashings and accessories.

19. Plumbing and Fixtures


This activity comprises the following:
• Installation of new set of plumbing fixtures, water lines (PPR) and
sanitary lines (s1000).
• Supply and installation of plumbing fixtures.
• Supply and installation of wall hang lavatories for hand washing at
toilets;
• Tapping of water and sanitary lines to existing water system.
• Supply and installation of downspouts, catch basins and 12” dia.
(Reinforced Concrete Pipe Culvert) drainage canals connecting the
existing drainage system.
• Supply and installation of 9 units catch basins.

20. Painting Works


This activity involves the following:
• Surface preparation and painting of ceiling and partitions with solvent
base paints.
• Surface preparation and painting of CHB walls and partitions with
solvent base paints.
• Exterior painting finishes- textured type.
• Surface preparation and painting of hollow core flush doors with
solvent base paints.

21. Electrical Works


This item consist of:
• Supply and installation of electrical materials.
• Supply and installation of Data and Voice provisions (roughing-ins of
pipes and utility boxes)

General Scope of Work: (MECHANICAL WORKS – HVAC SYSTEM)

This project shall consist of furnishing and installation of positive air system,
heating and ventilating and air-conditioning system, and, 100% air flow system.
This includes necessary electrical connections, pipes and condensate drains and
all other necessary accessories and auxiliaries, ready for service in accordance
with the plans and specifications.

Installation of equipment and its accessories and auxiliaries shall conform to


established standards. The project includes testing of all equipment and all other
related activity needed for commissioning.
Detailed Scope of Work:

A. SUPPLY OF EQUIPMENT
• ACU: 1 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 1.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 2 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• ACU: 2.5 HP, Split-type, Inverter, wall-mounted, 230V/1ph/60Hz
• Exhaust Fan, ceiling mounted, 230V, 1 phase
B. PIPE INSULATION INSTALLATION

• Installation of 1 inch thick fibre glass insulating material to all tubing/pipes


• Insulation shall be pre-formed fibre glass or its equivalent. The insulating
materials shall be covered with 4 inches x ½ inch thick poly ethylene film,
which shall be overlapped not less than 2 inches. Pipe insulation shall be
adequately protected at point of support by means of suitable metal shield to
avoid damage from compression. Insulated pipes, valves and fittings located
outdoors shall be provided with metal jacket

C. ELECTRICAL WORKS

• Provision of electrical supply cables necessary to all equipment


• Power supply shall be provided by the contractor at the pull box installed
inside the machine room and shall furnish and install the main circuit breaker
and starter with suitable ratings and capacities, conduits, wiring, fittings,
devices and all other equipment and electrical connections needed to
complete the electrical installation of the system. All electrical works shall
comply with the latest edition of the electrical code, with the applicable
ordinance of the local government and all the rules and requirements of the
local power company

D. STANDARDS

• DOH Air-conditioning specifications and standards


• SMACNA
• ASHRAE
• NFP

General Scope of Work: FIRE FIGHTING (STAND PIPE) SYSTEM

This project shall consist of furnishing and installation of Fire Sprinkler System. Provide
necessary isolating fixtures such as Gate Valves and Check. System testing shall be
done in the presence of the hospital chief, project engineer and DOH representative.

Detailed Scope of Work:

E. SUPPLY OF EQUIPMENT AND INSTALLATION OF PIPES, VALVES, FHC


• Supply and installation of 10 lbs. ABC dry type chemical fire extinguisher.
• Supply and installation sch. 40 seamless welded or threaded BI pipe
including its fittings. Size of pipe shall be in accordance with the NFPA
standards
• Supply and installation of Bronze Gate Valve 150 psi WOG
• Supply and installation of Bronze Swing Check Valves 150 psi WOG

F. INSTALLATION OF HANGERS , SUPPORTS, AND FITTINGS

• Installation of pipe hangers and supports. Support shall be ¼”X2”X2” angle


bar, hangers and pipe clamps shall not be less than ½” dia. threaded with nut
or as per drawing and specification. Pipe support shall be wall mounted
unless specified in the drawing
• Valves and check valves shall be threaded and in conformance with ASTM
standards
G. PIPE PROTECTION

• Buried pipes shall be provided with bituminous material wrapped around its
circumferential
• Exposed pipes shall be applied with epoxy primer AB for two coatings
• Exposed pipes shall be applied with fire red paint for two coatings after
application of epoxy primer

H. CONSTRUCTION REQUIREMENT

• The fire fighting system shall be entirely semi-automatic in operation by just


assuring that all main gate valves are permanently open in nature (Main Gate
Valves means valves at supply and fire department sides)and shall be
connected to elevated tank
• The system shall be in conformance with NFPA standards
• The system shall have end drain for line removal of dirt and flow testing
• All materials shall be inspected upon delivery and shall be tested after
installation. Piping shall not be buried, concealed, or insulated until it has
been inspected, tested and approved. Walls, floors and other parts of the
building and equipment damaged by the contractor in the prosecution of the
work shall be replaced as shown in the plans

I. CONTRACTOR REQUIREMENT

• The contractor shall have ample experience on fire fighting system specially
on stand pipe system

J. OPERATING TEST


The piping system shall be hydro tested 1.5 times the operating pressure or
as per recommended in the NFPA standards. Test shall be within 3 hours
without dropping of pressure.
• All leak/s or suspected leak/s shall be eliminated/repaired before acceptance
K. METHOD OF MEASUREMENT

• The work under this item shall be measured either by set, piece, length,
square foot actually placed and installed as shown in the plans
• FHC shall be measured by set; valves by piece, pipe/tubing by length

L. MISCELLANEOUS

• The owner shall be provided with three (3) bound copies “ AS BUILT “
diagram, shop drawings, parts lists, serial number and inventory of equipment
including manufacturers and maintenance manuals

M. STANDARDS

• UNIFORM PLUMBING CODE


• NFPA
GENERAL SCOPE OF WORKS & SPECIFICATIONS:

(Supply & Installation of one (1) unit Elevator)

General Specifications One ( 1 ) Lift


Quantity 1
Type Stretcher Lift ( Single Direct acting
hydraulic cylinder )
No. of Stops 2
No. of Openings 2 @ front and back
Travel Height 6.70 m
Speed (m/s) 30 mtrs./ min. (minimum)
Fireman's Lift Homing
Capacity ( kg) 1000 kg. (Minimum)
Floor Designation Ground and 2nd Floor ( Ready for
Hoistway 3rd Floor)
Shaft Size ( W x D ) at least
Shaft Size 1900mm x 2900mm
Lift Arrangement maximum requirement
Over Travel (mm) single
Pit Depth (mm) 4300mm ( Min. Req.)
Drive System 1600mm
Control System Permanent Magnet Gearless
Operation VVVF
Machine Room Location SIMPLEX
Counterweight Safety Gear Inside the hoistway /shaft
LIFT CAR Not required
Car Size (W x D x H ) Structural
Door Type 1400mm x 2400 mm x 2350 mm
Door Size ( W x H ) 2- panel Side Opening
Door Panel 1200 mm x 2100 mm( minimum)
Door Sill Hairline Stainless Steel
Front Wall Finishes Aluminum
Rear Wall Finishes Hairline Stainless Steel
Side Wall Finishes
Handrails

Car Operation Panel (COP) Buttons


No. of Cop's Location
Cop Facelate
Platform Decoration Hairline Stainless Steel
Hairline Stainless Steel
Double Round Stainless Steel
@ rear wall, left & right walls
Manufacturer's Standard
1- right front wall
Hairline Stainless Steel
Tango Granite
Car Ceiling Std. Stainless Steel

LIFT LOBBY
Landing Door Panel Finishes ( Main Floors) Hairline Stainless Steel
Landing Door Panel Finishes ( Typical Floors) Hairline Stainless Steel

Landing Door Jamb Wide Jamb w/ Transom Panel at


ground Floor, other doors narrow
jamb
Landing Operation Panel (LOP) Buttons Manufacturer's Standard
Lop Facelate Stainless ,Hairline

CAR & LANDING POSITION


INDICATORS
Car Position Indicator Manufacturer's Standard
Landing Position Indicator ( Main Floor ) Manufacturer's Standard
Landing Position Indicator ( Typical Floor ) LED Dot Matrix w/
Direction Arrows
ELECTRIC POWER REQUIREMENT
( SUPPLIED ,INSTALLED AND TAPPED BY THE CONTRACTOR)

Power Supply ( Main) 230VAC, 3PH, 60 HZ


Power Supply Lighting 220 VAC, 1 PH, 60 HZ
Transformer Capacity 25 KVA
Earthwire 6 square mm
Power Feeder 10 square mm

STANDARD CONTROL FEATURES


Alarm
Anti-Nuisance
Car Fan / Light Automatic Off
Door Final Timer
Timer
Door Pre- opening
Light Curtain
Emergency Light in COP
Full Load Bypass
Overload Measuring w/ load contacts

SPECIAL FEATURES
Arrival Gong on Car
Intercom system, 3 way
Attendant control
Out -of -service Switch

ADDITIONAL FEATURES
Emergency Landing Device- UPS must be
provided in case of power failure.
Management Key Switch
Training for four (4) in-house elevator
maintenance and operators.
Warranty : Two (2) years, parts and service

22. Project Billboard


This item consist of:
• Supply and Installation of Billboards 8' x 8'

23. Safety and Health Program


This activity includes the following:
• Supply and implementation of PPE's and safety and health
programs.
• Installation of signages, barricades and protections.

Вам также может понравиться