Академический Документы
Профессиональный Документы
Культура Документы
Ares(2016)6711556 - 30/11/2016
INSPUR project
Quality control protocols
WP2
D 2.5
Issue Date
Type
R – Report
Dissemination Level: PU
Leader
IMA
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
1
Quality control protocols
Table of contents
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
2
D 2.5, Quality control protocols
Executive summary
The utilization of innovative products demands the identification of the main critical issues
that derive by the application of a new technology.
The main objective of this task is to identify all the necessary controls that have to be
performed on both the two INSPUR components, in order to ensure optimal results and
considering the bi-component mixtures production process until their final application.
The quality controls mainly concern the raw materials used for the bi-components
formulation, these are followed by the controls performed on the polyols and isocyanates
formulated components until the final verification of the film reticulation during the
application phase.
After obtaining the polyurethane film, it is then possible to proceed with the final control
phase. This concerns the evaluation of the demanded physical – chemical resistance
features (light, washing, solvents, flexions…) directly on the film; these parameters must
complain with the identified standard for each article application.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
3
INSPUR Quality control protocols, introduction
To obtain optimal results using INSPUR products, it is fundamental to ensure the lowest
humidity content for the polyols mixture [Apol]. The presence of water during the two
components mixing phase will indeed determine a reaction among the isocyanate group
of (Biso) component and water thus determining the consequent withdrawal of the
isocyanate group viability from the polyol part [Apol].
Following, the reaction that occurs among the isocyanate group and the hydroxyl group
of the glycols [Apol] component:
A possible presence of water, subtracts although the viable isocyanate groups from the
reaction thus provoking the release of gas that causes bubbles in the film.
In order to avoid this effect, we have therefore focused our efforts on the evaluation of
the humidity parameters by accurately assessing the used raw materials quality (polyols
and glycols) and by issuing the two components manufacturing process within confined
anhydrous conditions (under a constant N2 flow).
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
4
Therefore, we provided to setup a reticulation control methodology based on FT-IR
spectrophotometry. This test can be performed at the end of the reticulation phase to
evaluate the possible presence of isocyanate groups directly on the film.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
5
Quality assurance for the bi-components PU
The main problem that arises during the production and manipulation of the two INSPUR
components is the avoidance of any contact from the atmospheric humidity.
After the verification of the water content in the raw materials, that must be below the
0.05%, it is necessary to ensure a production system under controlled conditions (under a
constant N2 flow). This is necessary to avoid the absorption of further external humidity.
At the end of the production process and after the final humidity control, the product
should to be packed into “two 2 caps drums”, to avoid any further absorption of external
humidity.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
6
State of art and prior knowledge in PU resins QC
The quality control for the solvent based PU resins production requires the initial inspection
of raw materials input, the process analysis and the control of finished products.
Process control:
During the production phase, and before the extension phase, the isocyanate group
inside the prepolymer is analysed while the control of reached viscosity is performed
before the closing of the reaction.
The reaction closing phase is further monitored through the control of residual -NCO peak
with FT-IR spectrophotometer.
- The aspect
- Viscosity
- Hazen colour
- Dry residue
A resin sample will be also left for 48 hours at 60°C to simulate an accelerated ageing and
in order to verify its stability. At the end of the ageing in stove, the values of viscosity and
hazens are reported; both of values have not to move above the +/- 10% compared to
the sample value.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
7
Flow diagram for PU resins production
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
8
INSPUR: QC Parameters and variable
Humidity Control
A Component:
The control phase for both raw materials and formulated polyols mixtures is aimed at
verifying that the overall water amount does not exceed the threshold of 0.05%.
The respect of this specification, that is required by the used raw materials (polyols and
glycols), and the production phase within a closed system, permits although to ensure the
respect of this parameter in the finished product (0.05%).
Pigmented pastes:
For what concerns the pigments dispersed in a polyol nature vehicle, it is not possible to
respect the limit established for the [Apol] component due the humidity already present
into the pigment powder.
Despite the precautions, to minimize the humidity absorption during the pigment
dispersions phases, the final pigmented paste shows however a humidity value higher
than the awaited one.
Since this value can affect both reaction kinetics and the complete reticulation of the 2
INSPUR components, different tests have been issued to establish the percentage (%) of
the maximum acceptable humidity. The humidity threshold, that is necessary to avoid
issues on products during the application phase, is the 0.3%.
The addiction of coloured paste to the formulation is usually around 15% (maximum 30%)
and it does not significantly affect the overall humidity amount [Apol] + pigment + (BIso).
To measure the pigmentary paste humidity, it has been required the improvement of the
current system. The polyols and glycols humidity determination must be performed by
using the Karl Fischer coulometric test and by dosing directly into the titrating jar the
sample to test.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
9
This is not possible for the pigments due to the difficulty of solubilizing them in a Karl Fisher
jar, and due to the possible interference of substances present in the pigments solutions
(E.g. Oxides) with the Karl Fisher experimental protocol; these can indeed compromise the
analysis results. On purpose, it has been necessary to acquire an evaporator that allow to
dry the samples by heating.
The humidity is then conveyed directly to the colorimetric reaction jar via an anhydrous
vehicle gas to permit the quantification.
It has been indeed developed a new methodology that permits to identify the best
options of temperature and humidity stripping for the different pigment pastes.
B Component:
Since the -NCO group reacts with humidity it is fundamental that the isocyanate mixture is
produced within a closed system and under strictly controlled conditions.
At the end of the reaction, an experimental measure of the free -NCO will be issued to
understand the exact amount of reactive group within the sample; this have not to move
from the 3%(+/1) awaited value.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
10
Viscosity
A, B components
During the tuning of the formulations, the viscosity is a parameter that should be
accounted since the both 2 components require a low viscosity to be correctly dosed into
the production plant. The viscosity must then stay below the 6.000 cps at 25°C.
During the control phase, the value is measured using a Brookfield viscometer.
Density
A, B components
Pigmentary pastes
For the coloured pastes, due to their high viscosity, the density is directly measured by
weighting a known material volume.
Since viscosity is a temperature depending parameter, a density curve has been derived
to support the user during the manufacturing phase. Temperatures above 30°C are
however not taken in account. This because the temperature greater than 30°C can
affect the overall reaction kinetics and the reaction speed will be consequently
excessively high (the optimal operative condition is 25°C).
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
11
Flow diagram for 2K PU production
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
12
Current applications status
The Quality Control system provides the analysis of the raw materials, of [Apol] and (Biso)
components and the verification of the correct reaction between the two components.
Raw materials
Polyols resins
polyether, polyester and polycarbonate
A Component [Apol]
- % of humidity
- Viscosity
- Density
B Component (Biso)
To evaluate the effective reticulation, it will be performed a laboratory testing to verify the
correct catalysts dosing, the reticulation will be tested by checking on the reticulated film
and the possible presence of free -NCO groups through the FT-IR spectrophotometer.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
13
Future developments
It has been planned by IMA to implement the polyol control phase by experimentally
measuring the amount of free -OH on the sample.
The polyols resins are already provided with a related certificate of analysis that calculates
the ratio among the two components, in the future it is however planned to issue an
additional laboratory measurement as a further verification mean.
At the moment, 2 different methodologies are available, one for the polyols polyether and
the other one for polyol polyesters.
For what concerns the experimental measure of polyols [Apol], and in case of a mixed
nature (polyester / polyether) mixture, at the state of art it is not yet possible to determine
the OH value of the mixture since the available methodologies do not consider the
presence of polyols of different natures.
In this case, a theoretical calculation should be performed on the production recipe.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
14
Achieved results and conclusions
a) The controls provided during the different tuning phases of the two components,
and during the manufacturing of 2 bi-component resins, permitted to achieve the
planned project objectives concerning the development of industrial QC protocols.
In detail, the threshold limit of (<0.05%), as maximum amount of water content, has
been reached thank to the use of selected raw materials with a high-quality
standard and by pursuing a correct manipulation practice during their utilization.
Further progresses can be however achieved for what concerns the water content
within the coloured pastes. The use of pigments with a low humidity content will be
investigated and the pigmental dispersion conditions will be further improved.
In this way, it can be possible to lower the threshold for the maximum amount of
humidity that is currently established as the 0.3%.
b) During the tuning of both [Apol] and (Biso) components, the viscosity had to be
further accounted; this results fundamental for a good industrial application of the
product.
The raw materials have been indeed chosen also considering this parameter, and
they must not to exceed the amount of 6.000 cps at 25°C. This value has been
established as the maximum threshold for an optimal plant operability during the
production phase using INSPUR.
This has however further limited the possibility to formulate few products which the
final features were of optimal quality in terms of physical-chemical performances,
however, due to a viscosity largely higher than 6.000 cps, this implies a very
complex industrial handling.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
15
c) The -NCO/-OH ratio between the two components must be ensured by correctly
mixing the reactive groups of the two components and by providing a correct
dosing during the mixing phase.
Furthermore, in order to ensure the complete reaction between the 2 components,
it is necessary that the quantity of catalyst is present in sufficient amount.
Therefore, during the tuning of the two components, many tests have been
performed to establish the optimal amount of the catalysts, further considering that
the reticulation should be completely reached and that the reaction kinetics have
to be not too fast in order to maintain the mixture pot-life without reducing it.
The amount of dosed catalyst must be correctly dosed to obtain the optimal
compromise among the mixture reticulation and half-life.
Concluding, we can consider that during this months a reliable QC control system for the
manufacturing process of 2 bi-components resins has been tuned also providing the
control of the correct reaction after the mixing phase.
The INSPUR manufacturing QC system will be further improved considering as priority the
analysis of -OH group in polyol polyether and polyester/polycarbonates.
Considering this, it will be tried to setup a methodology that will permit to measure these
parameters in polyols mixtures of different chemical nature.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
16
Used experimental protocols for the [Acat], (Biso) and pigments QC
PROCEDURE 1. Carefully wash the electrodes of the pH meter with distilled water
and dry with soft absorbent paper;
2. Pour into a 250 [ml] clean and dry beaker:
50 [ml] of isopropyl alcohol
50 [ml] of acetone
60 [ml] of bidistilled water
3. Operate the agitation of the pHmeter, heat up to 40 [° C] and
possibly correct the pH with NaOH or HCl 0.001 [N] until you
reach pH 7.0 ± 0.1;
4. Add 27 [g] of polyol, previously melted, to the mixture under
stirring (if necessary heat on a electromagnetic hotplate);
5. The reading of the pH must be performed when the variation is
less than 0.05 pH units / min.
EXPRESSION OF THE Calculate the arithmetic mean of the two values obtained and round
RESULT to the first decimal figure.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
17
QC Method 2, determination of the polyether polyols pH
PROCEDURE 1. Wash the electrodes of the pHmeter with distilled water and dry
with soft absorbent paper;
2. Calibrate the electrode with buffer solutions at pH 4.00 and pH
7.02;
3. Pour into a dry and clean beaker of 100 [ml]:
50 ml] mixture of isopropyl alcohol / distilled water (10: 6 v /v)
4. Immerse the electrode, operate the agitation of the pHmeter, and
correct if necessary the pH with NaOH or HCl 0.001 [N] to reach
pH 7.0 ± 0.05. Do not make back-adjustments.
5. Add 10 [g] of polyol to the mixture under constant agitation (if
necessary heat on an electromagnetic hotplate);
6. The reading of the pH must be performed when the variation is
less than 0.05 pH units / min.
EXPRESSION OF THE Calculate the arithmetic mean of the two values obtained and round
RESULT at the second decimal figure.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
18
QC Method 3, determination of the pigment pastes water content using Karl Fischer
titration and ADP 611 evaporator
PURPOSE To determine the water content of the pigment pastes used in the bi-
components system.
PROCEDURE 1. Prepare the titration cell by adding the Hydranal Coulomat Oil
into the cathodic compartment and 1 vial of Hydranal Coulomat
GC into the anodic compartment
2. Turn on the ADP 611 evaporator and start the pre-titration
3. During the pre-titration position on the sample loading cell a
correctly cut aluminium foil
4. When the evaporator is in BACK PURGE mode, load 1 [gr] of
sample on the cell
5. Start the measurement
EXPRESSION OF THE The percentage value is provided directly by the automatic titrator.
RESULT
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
19
QC Method 4, determination of the polyols and glicole water content using the Karl
Fisher titration
PURPOSE To determine the water content inside the polyols part of a bi-
component system
PROCEDURE 1. Prepare the titration cell by adding the Hydranal Coulomat Oil
into the cathodic compartment and 1 vial of Hydranal Coulomat
GC into the anodic compartment
2. Condition the syringe
3. Weight about 1 [ml] of product with the syringe
4. Wait 1 minute
5. Introduce the product into the cathodic compartment of titration
the cell
6. Follow the instructions provided by the automatic titrator
EXPRESSION OF THE The percentage value is provided directly by the automatic titrator.
RESULT
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
20
QC Method 5, INSPUR / bi-component system density determination
REAGENTS None
EXPRESSION OF THE Calculate the arithmetic average of the two obtained values and
RESULT round the obtained numbers to the third decimal
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
21
QC Method 6, determining the reticulation of INSPUR made products
PROCEDURE 1. Weight in a small jar the amount of polyol part, determined by the
using ratio. The overall amount of the two compounds must be at
least 50 [gr]
2. Weight in the same jar of 1. the isocyanate part, that is
determined by the using ratio
3. Shake the bicomponent using a stirrer at 350 rpm/min for 50 sec
4. Spread 0.1 [mm] of mixture using the spreading frame
5. Reticulate the bi-components using the oven according the
specific temperatures and times of the formulation
6. Measure the initial transmittance data at 2260cm-1 using the FT-
IR spectrophotometer in different sample zones. Proceed as
follow:
Clean the ATR ground plan
Issue the background reading
Position the film on the ATR ground plan and acquire the
spectrum
Verify that the baseline falls at 100% of transmittance
Evaluate the possible presence of an absorbance peak at
2260-2270 cm-1, typic of -NCO functional group: if present
read the % transmittance value
If the value results ≥ 98.5%, we can suppose a correct
reticulation
If the value results < 98.5%, the film is not completely
reticulated and is not compliant
In case of a good reticulation, repeat the same measure in
the following days to monitor the residual peak decreasing
time
It is advised the acquisition of IR spectrum from different
zones of the sample.
EXPRESSION OF THE It is the transmittance percentage value red by the FT-IT instrument
RESULT and the -NCO peak annihilation time
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
22
TEST REPORT The test report must contain:
- All the elements necessary for the complete identification of the
sample
- The initial transmittance percentage measured at 2260 cm-1
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
23
QC Method 7, Brookfield viscosity determination in bi-components systems
REAGENTS None
PROCEDURE 1. Pour into the 300 [ml] jar about 200 [g] of the sample to examine
2. Close the jar and submerge it into the thermostatically-controlled
water bath for the amount of time necessary to reach the test
temperature (25°C)
3. Put the instrument on the ground
4. Immerse the spindle in the sample to examine and perform the
test at the desired rotation speed
5. The test ends when the instrument output is stable
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
24
QC Method 8, determination of free isocyanate in urethane pre-polymers
4. Shake flask with the magnetic stirrer until the complete sample
solubilisation
5. Add 25 [ml] of N-Butylbutan-1-amine and wait 15 minutes
6. Add 50 [ml] of Isopropyl alcohol
7. Add 0.8 [ml] of Bromocresol green
8. Titrate samples with HCl [1N] until the equivalence point
9. Issue 3 blank tests using the same procedure but without
prepolymer sample
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
25
(V Vc ) N 42,02
% NCO b 200
M 1000
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
26
QC Method 8, kinetic determination of a bi-component system (INSPUR)
EXPRESSION OF THE They are viscosity values (expressed as [cPs]) measured by the
RESULT viscometer and temperature (expressed as [°C]) measured by
thermocouple.
This project is implemented through the HORIZON 2020 SME Instrument, Phase-2 (GA 711591)
27