CHANGEOVER TO D.O. FROM HFO. The scope of work in accordance with scope provided by client vides the enquiry.
The job will be executed by VIBSPECTRUM INTERNATIONAL DUBAI under the technical guidance as per operating instruction.
Mobilize the manpower and test equipment on board.
Consult with Chief Engineer /port engineer prior to performing the work. Prior to the start of work, contact the Chief Engineer to coordinate the Implementation of the Tag out Program for the entire performance period of the boiler. Check for evidence of overheating, and tightness of all connections in boiler panel. Check the operation of the Boiler controller as per manufacturer’s specifications. Isolate the DO/HFO valve and circuit breaker during the loop testing Perform the self-test and noted down the parameters of boiler controller. Troubleshooting the HFO and DO Interlock circuit. After completion the work and language change in controller; testing the system and witness Ship staff.